SlideShare a Scribd company logo
12
Most read
14
Most read
16
Most read
UNIT-II
SEWER DESIGN
SATHYAN S
DEPARTMENT OF CIVIL ENGINEERING
KIOT,SALEM.
LAYING
 Starting from outfall end to starting end
 Manholes are required to be constructed
 Laying is done between two man holes
Detailed map study
 Map showing all roads, cable lines, lanes etc., is prepared.
 Pipe line with size and length is marked.
 The position of existing pipe lines, curb lines, water lines will also be marked .
CENTER LINE AND OFFSET LINE MARKING.
 Center line of the sewer is marked by drawing an offset line on the ground parallel
to the center line at suitable fixed horizontal distance(2-3m).
 OFFSET DISTANCE = ( 0.5 x trench width) +0.6m.
 This offset line should be drawn on that side of the trench which is not likely to be
disturbed by the piling of the excavated earth
 Offset is used to find the center line by offsetting the fixed distance from offset
line.
 Temporary bench marks along this offset line ,at intervals of 200-300m should also
be established by carrying the levels from G.T.S bench mark.
Laying and Testing of sewer
TRENCHES
 The Road pavements may have to be first of all ,removed . (Softer pavements –pick
axes by manual labour ) and (hard concrete pavements –pneumatic drills or
spades).
 The inner portion is remover either by pick axes or power shovels, boom and
bucket excavator …
 Min. width of the trench = 15cm more than the dia of sewer
 For smaller dia pipes =60-75cm
 Pipes in firm ground no need of embedding of concrete and the bottom half
portion of the trench is excavated as the shape of the pipe .
 Pipes in softer or ordinary grounds need embedding of concrete.
 A recess is also excavated at required intervals for accommodation of joints and
caulking at the bottom .
Laying and Testing of sewer
TIMBERING
 It is used when the excavation is more than 2m and It is used to resist soil from
falling into the trench.
 The sheeting or sheeting boards are the wooden planks which are placed in
actual contact with the trench sides, either horizontally or vertically.
 The braces are the cross wooden pieces extending from one side of the trench to
the other side, and may also be called struts.
 The ranger are waless are the timber planks which transfer the transfer the loads
from the sheeting boards to the cross braces by jointing the sheeting boards
together.
 The softer soil require more elaborate and closer timbering than that of harder
soils.
 In case of extremely soft and water logged soil or in places where timber is not
available steel sheeting(water tight and durable) are used.
Laying and Testing of sewer
DEWATERING
 Dewatering is require if the w.t is high or if the sewer happens to be laid very deep.
 Its removed by open jointed drain constructed below the sewer trench ,which
discharges into an independent water course either by gravity or pumping.
 Its removed by pumping out the water from the sump constructed in the trench. It
should be operated for 24 hours if the water keeps on flowing int the trench.
 Dewatering in sandy soils become enormous, because if the water flow is large and
the sub soil is sandy , quicksand is caused.so it is done by well pointing system.
NO. of well points are installed by water jetting method along the sides of the
trench at suitable intervals of 1.5m . All these well points are connecter to a
common header pipe which is connected to a pump.
Laying and Testing of sewer
SHAPING THE TRENCH AT THE BOTTOM
TO THE CORRECT LEVEL
 it should be excavated equal to the bottom of the embedding concrete or to the invert level of
the sewer.
 The bottom most portion of the trench should be excavated carefully so as not to dug more than
require.
 Two vertical posts are first of all driven along the sides of the trench at the interval of 10m at all
junction and change points.
 A horizontal board spanning the entire width is now fixed on that post by means of nails is called
sight rail.
 A vertical pencil line is marked on the wooden board and a needle is fixed on that line.
 A string is stretched between the needle and produce a line in space and used to measure the
depth of foundation ,invert level and embedded concrete.
 A boning rod or traveler is used to measure levels at the bottom oh the trench .
Laying and Testing of sewer
LAYING
 After the bedding concrete has been laid in the required alignment and levels, the
sewer pipes are lowered down into the trenches.
 Smaller pipes less than 40cm dia can be directly handled by masons and their
helpers.
 Larger pipes can be lowered by passing ropes around each end of the pipe length.
For very large pipes machines have to be used.
 The sewer pipe lengths are usually laid from the lowest point with their socket end
facing upstream so that the spigot end can easily be jointed.
 After joints are jointed ,the jointing is done with lead caulking or cement mortar as
required.
 During jointing care should be taken to see that the pipe lengths remains in true
level and alignment, and do not get disturbed till the jointing material hardens.
Laying and Testing of sewer
TESTING
TEST FOR LEAKAGE OR WATER TEST:-
 Sewers are tested to ensure no leakage in
their joints.
 They are tested between manhole to manhole
under a test pressure of 1.5m of water head.
 Lower end is plugged and the water is allowed
to flow through the upper end .
 Depth of water in the manhole is maintained
to the testing head of about 1.5m.
 The sewer line is watched by moving along
the trench and the joints which leak or sweat,
are repaired.
 TEST FOR STRAIGHTNESS OF
ALIGNMENT OR OBSTRUCTION:-
 IT is tested by placing a mirror at one end and
the lamp at the other end.
 If the pipe line is straight full circle of light will
be observed .
 If the pipe is not straight it would be apparent
and the mirror will also indicate any
obstruction in pipe.
 Obstruction in the pipe is tested by inserting a
smooth ball of dia 13mm less than the
internal dia of sewer at the upper end of the
sewer .
 If no obstruction is their the ball rolled down
to the lower end.
Backfilling
 While backfilling the excavated earth it should be laid equally on either side of the
sewer and it should filled up in layers of 15cm thick.
 Each layer should be properly watered, tamped and rammed.
 Earth filling above the crown of the sewer should be carefully carried out.
 After few months of exposure , when the top layer gets fully settled, the road
pavements, may be constructed . This will prevent the subsidence and cracking.
Laying and Testing of sewer
Laying and Testing of sewer

More Related Content

PPTX
Construction and testing of sewer line
PPTX
Sewer Appurtanances
DOCX
SEWER DESIGN:
PPTX
Design and Construction of Sewers And Sewer Appurtenances
PPTX
Laying, jointing and testing of pipes
PPTX
Sewer appurtenances
PPTX
Sewer appurtenances [recovered]
PDF
materials of sewer
Construction and testing of sewer line
Sewer Appurtanances
SEWER DESIGN:
Design and Construction of Sewers And Sewer Appurtenances
Laying, jointing and testing of pipes
Sewer appurtenances
Sewer appurtenances [recovered]
materials of sewer

What's hot (20)

PPTX
Plain sedimentation
PPTX
Design of sewers
PPTX
energy dissipator in hydraulic structure
PPTX
Sewage Conveyance and Pumping
PPT
Sinking of well foundation
PPTX
Collection and estimation of sewage
PPTX
Hydraulic design of sewer
PDF
Canal regulation works. m4pptx
PPT
Sludge digestion process
PPT
SOIL EXPLORATION
PPTX
water supply scheme
PPT
Dry weather flow
PPTX
Intake structures
PPTX
Sewer Appurtenances
PPTX
02 water demand
PPTX
Tunnel engineering
PPTX
SEWERAGE SYSTEMS ppt by mayank oza
PPTX
Types of joints in rigid pavement
PPTX
WATER & WASTE WATER ENGINEERING - water treatment process & units
Plain sedimentation
Design of sewers
energy dissipator in hydraulic structure
Sewage Conveyance and Pumping
Sinking of well foundation
Collection and estimation of sewage
Hydraulic design of sewer
Canal regulation works. m4pptx
Sludge digestion process
SOIL EXPLORATION
water supply scheme
Dry weather flow
Intake structures
Sewer Appurtenances
02 water demand
Tunnel engineering
SEWERAGE SYSTEMS ppt by mayank oza
Types of joints in rigid pavement
WATER & WASTE WATER ENGINEERING - water treatment process & units
Ad

Similar to Laying and Testing of sewer (20)

PPTX
Lecture 02.pptx Lecture 02.pptxLecture 02.pptx
PPTX
Hydraulicdesignofsewer
PPTX
10-Construction of Sewers AND WATER SUPPLY04.pptx
PPTX
Laying of Sewer Line
PDF
sewage layy out lec
PPTX
Drains and sewer
PDF
construction of drain and seers
DOCX
216631544 Ntuli S.I EXP I.docx
PPTX
CH3-2-Design of sewer system.power point
PPT
Trenchless technology
PPTX
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
PDF
Drainage system and Equipment 5, BST200-new.pdf
PPT
TRIC Trenchless LA building & safety
PPTX
Krishna Gopal Samanta- Design of Sub Surface Drainage System.pptx
PPTX
Introduction to Sewerage and Wastewater .pptx
DOCX
IVRCL REPORT Atishay TYagi (UPES)
PPTX
Subsurface drainage
PDF
Trench less Technology
PPTX
PIPE LAYING
Lecture 02.pptx Lecture 02.pptxLecture 02.pptx
Hydraulicdesignofsewer
10-Construction of Sewers AND WATER SUPPLY04.pptx
Laying of Sewer Line
sewage layy out lec
Drains and sewer
construction of drain and seers
216631544 Ntuli S.I EXP I.docx
CH3-2-Design of sewer system.power point
Trenchless technology
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Drainage system and Equipment 5, BST200-new.pdf
TRIC Trenchless LA building & safety
Krishna Gopal Samanta- Design of Sub Surface Drainage System.pptx
Introduction to Sewerage and Wastewater .pptx
IVRCL REPORT Atishay TYagi (UPES)
Subsurface drainage
Trench less Technology
PIPE LAYING
Ad

More from sathyan s (7)

PPTX
ADVANCED WATER TREATMENT PROCESS
PPTX
Disposal of sewage and sludge management
PPTX
Disaster management
PPTX
Chain surveying
PPTX
Geosynthetics and fibre textile
PPTX
elements of seismology
PPTX
Top 6 hardest languages to learn
ADVANCED WATER TREATMENT PROCESS
Disposal of sewage and sludge management
Disaster management
Chain surveying
Geosynthetics and fibre textile
elements of seismology
Top 6 hardest languages to learn

Recently uploaded (20)

PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PDF
composite construction of structures.pdf
PDF
Well-logging-methods_new................
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
DOCX
573137875-Attendance-Management-System-original
PPTX
Sustainable Sites - Green Building Construction
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PPTX
Lesson 3_Tessellation.pptx finite Mathematics
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PDF
PPT on Performance Review to get promotions
PPTX
OOP with Java - Java Introduction (Basics)
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPTX
Strings in CPP - Strings in C++ are sequences of characters used to store and...
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPTX
UNIT 4 Total Quality Management .pptx
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PPTX
Construction Project Organization Group 2.pptx
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
composite construction of structures.pdf
Well-logging-methods_new................
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
573137875-Attendance-Management-System-original
Sustainable Sites - Green Building Construction
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
Lesson 3_Tessellation.pptx finite Mathematics
Model Code of Practice - Construction Work - 21102022 .pdf
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPT on Performance Review to get promotions
OOP with Java - Java Introduction (Basics)
Foundation to blockchain - A guide to Blockchain Tech
Strings in CPP - Strings in C++ are sequences of characters used to store and...
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
UNIT 4 Total Quality Management .pptx
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
Construction Project Organization Group 2.pptx

Laying and Testing of sewer

  • 1. UNIT-II SEWER DESIGN SATHYAN S DEPARTMENT OF CIVIL ENGINEERING KIOT,SALEM.
  • 2. LAYING  Starting from outfall end to starting end  Manholes are required to be constructed  Laying is done between two man holes
  • 3. Detailed map study  Map showing all roads, cable lines, lanes etc., is prepared.  Pipe line with size and length is marked.  The position of existing pipe lines, curb lines, water lines will also be marked .
  • 4. CENTER LINE AND OFFSET LINE MARKING.  Center line of the sewer is marked by drawing an offset line on the ground parallel to the center line at suitable fixed horizontal distance(2-3m).  OFFSET DISTANCE = ( 0.5 x trench width) +0.6m.  This offset line should be drawn on that side of the trench which is not likely to be disturbed by the piling of the excavated earth  Offset is used to find the center line by offsetting the fixed distance from offset line.  Temporary bench marks along this offset line ,at intervals of 200-300m should also be established by carrying the levels from G.T.S bench mark.
  • 6. TRENCHES  The Road pavements may have to be first of all ,removed . (Softer pavements –pick axes by manual labour ) and (hard concrete pavements –pneumatic drills or spades).  The inner portion is remover either by pick axes or power shovels, boom and bucket excavator …  Min. width of the trench = 15cm more than the dia of sewer  For smaller dia pipes =60-75cm  Pipes in firm ground no need of embedding of concrete and the bottom half portion of the trench is excavated as the shape of the pipe .  Pipes in softer or ordinary grounds need embedding of concrete.  A recess is also excavated at required intervals for accommodation of joints and caulking at the bottom .
  • 8. TIMBERING  It is used when the excavation is more than 2m and It is used to resist soil from falling into the trench.  The sheeting or sheeting boards are the wooden planks which are placed in actual contact with the trench sides, either horizontally or vertically.  The braces are the cross wooden pieces extending from one side of the trench to the other side, and may also be called struts.  The ranger are waless are the timber planks which transfer the transfer the loads from the sheeting boards to the cross braces by jointing the sheeting boards together.  The softer soil require more elaborate and closer timbering than that of harder soils.  In case of extremely soft and water logged soil or in places where timber is not available steel sheeting(water tight and durable) are used.
  • 10. DEWATERING  Dewatering is require if the w.t is high or if the sewer happens to be laid very deep.  Its removed by open jointed drain constructed below the sewer trench ,which discharges into an independent water course either by gravity or pumping.  Its removed by pumping out the water from the sump constructed in the trench. It should be operated for 24 hours if the water keeps on flowing int the trench.  Dewatering in sandy soils become enormous, because if the water flow is large and the sub soil is sandy , quicksand is caused.so it is done by well pointing system. NO. of well points are installed by water jetting method along the sides of the trench at suitable intervals of 1.5m . All these well points are connecter to a common header pipe which is connected to a pump.
  • 12. SHAPING THE TRENCH AT THE BOTTOM TO THE CORRECT LEVEL  it should be excavated equal to the bottom of the embedding concrete or to the invert level of the sewer.  The bottom most portion of the trench should be excavated carefully so as not to dug more than require.  Two vertical posts are first of all driven along the sides of the trench at the interval of 10m at all junction and change points.  A horizontal board spanning the entire width is now fixed on that post by means of nails is called sight rail.  A vertical pencil line is marked on the wooden board and a needle is fixed on that line.  A string is stretched between the needle and produce a line in space and used to measure the depth of foundation ,invert level and embedded concrete.  A boning rod or traveler is used to measure levels at the bottom oh the trench .
  • 14. LAYING  After the bedding concrete has been laid in the required alignment and levels, the sewer pipes are lowered down into the trenches.  Smaller pipes less than 40cm dia can be directly handled by masons and their helpers.  Larger pipes can be lowered by passing ropes around each end of the pipe length. For very large pipes machines have to be used.  The sewer pipe lengths are usually laid from the lowest point with their socket end facing upstream so that the spigot end can easily be jointed.  After joints are jointed ,the jointing is done with lead caulking or cement mortar as required.  During jointing care should be taken to see that the pipe lengths remains in true level and alignment, and do not get disturbed till the jointing material hardens.
  • 16. TESTING TEST FOR LEAKAGE OR WATER TEST:-  Sewers are tested to ensure no leakage in their joints.  They are tested between manhole to manhole under a test pressure of 1.5m of water head.  Lower end is plugged and the water is allowed to flow through the upper end .  Depth of water in the manhole is maintained to the testing head of about 1.5m.  The sewer line is watched by moving along the trench and the joints which leak or sweat, are repaired.  TEST FOR STRAIGHTNESS OF ALIGNMENT OR OBSTRUCTION:-  IT is tested by placing a mirror at one end and the lamp at the other end.  If the pipe line is straight full circle of light will be observed .  If the pipe is not straight it would be apparent and the mirror will also indicate any obstruction in pipe.  Obstruction in the pipe is tested by inserting a smooth ball of dia 13mm less than the internal dia of sewer at the upper end of the sewer .  If no obstruction is their the ball rolled down to the lower end.
  • 17. Backfilling  While backfilling the excavated earth it should be laid equally on either side of the sewer and it should filled up in layers of 15cm thick.  Each layer should be properly watered, tamped and rammed.  Earth filling above the crown of the sewer should be carefully carried out.  After few months of exposure , when the top layer gets fully settled, the road pavements, may be constructed . This will prevent the subsidence and cracking.