SlideShare a Scribd company logo
Spatial Planning for Disaster Risk
Reduction
Dr. Estuning Tyas Wulan Mei
Faculty of Géography, Universitas Gadjah Mada, Indonesia
estu.mei@gmail.com / estu.mei@ugm.ac.id
• Estuning Tyas Wulan Mei
• Lecturer at the Faculty of Geography, Universitas Gadjah
Mada, Indonesia
• 2013 – PhD Géographie, Université Paris 1 Panthéon – Sorbonne (Dir. :
Pr. Franck Lavigne)
• Sujet : Gestion des évacuations lors des crises volcaniques. Etude de cas du
volcan Merapi, Java, Indonésie
• 2008 – Master Geo-Information for Spatial Planning and Risk
Management, Double Degree M.Sc Programme between Universitas
Gadjah Mada, Indonesia and University of Twente, the Netherlands
• 2006 – Undergraduate/Bachelor, Regional Development Program
Study, Faculty of Geography, Universitas Gadjah Mada, Indonesia
https://scholar.google.ca/citations?user=ZvZdZIQAAAAJ&hl=en
https://www.scopus.com/authid/detail.uri?authorId=55018646400
https://orcid.org/0000-0003-3814-9014
Planning or plan?
Planning
• Process of thinking and
organizing the activities to
achieve a goal.
• Planning refers to the
process of deciding what to
do and how to do it
Plan
• Results or products of a
certain planning activity.
Planner(s)
Planners do not make decisions themselves; rather, they support decision-makers
(managers, public officials, citizens) by coordinating information and activities.
Their role is to create a logical, systematic decision-making process that results in the
best action
Planning
• Peter Hall (1992):
• ….'is concerned with deliberately achieving some
objectives, and it proceeds by assembling actions into
some orderly sequence’.
• Ernest R. Alexander (1986):
• “Planning is the deliberate social or organizational
activity of developing an optimal strategy of future
action to achieve a desired set of goals, for solving novel
problems in complex contexts, and attended by the
power and intention to commit recourses and to act as
necessary to implement the chosen strategy”
Planning
• Diana Conyers and Peter Hills (1984):
“…is a continues process which involves decisions, or
choices, about alternative ways of using available
resources, with the aims of achieving particular goals at
some time in the future”.
• 4 main elements of planning:
• Decisions or choices
• Resource allocations
• Goal(s) achievement
• For the future
Aspects of Planning
Planning: Role
and place in
public
decision
making
Planning steps
Spatial levels
Planning
spheres
Operational
fields
Administration
Time horizons
Styles of planning
Centrally-planned economies
Market-based economies
Mixed economies
Project planning
Sectoral planning
Macro-economic planning
Integrated area planning
Short-term planning
Medium-term planning
Long-term planning
Conception
Preparation
Realization
Evaluation
1. Blueprint planning
2. Process planning
3. Comprehensive planning
4. Jointed Vs. Disjointed Incrementalism
5. Functional planning
6. Normative planning
Planning Principles
• Good planning requires a methodical process that clearly
defines the steps that lead to optimal solutions.
(Preston, 2012)
Plan-
ning
Compre-
hensive
Efficient
Inclusive
Inform-
ative
Inte-
grated
Logical
Trans-
parent
all significant options and
impacts are considered
the process should not
waste time or money
people affected by
the plan have
opportunities to be
involved
individual, short-term decisions should
support strategic, long-term goals
results are understood by
stakeholders (people
affected by a decision)
each step leads to the next
everybody involved understands
how the process operates
Spatial Planning
• A strategic direction for the development of a given geographic
area, states the policies, priorities, programmes and land
allocations that will implement the strategic direction and
influences the distribution of people and activities in spaces of
various scales.
• Spatial planning systems refer to the methods and approaches
used by the public and private sector to influence the
distribution of people and activities in spaces of various scales.
• Spatial plans may be developed for urban planning, regional
planning, environmental planning, landscape planning, national
spatial plans, or spatial planning at the Union level. (noted:
some countries used the term urban planning, regional
planning, land use planning).
Lecture 8: Spatial Planning for Disaster Risk Reduction
Spatial Structure
Urban System
Transportation
System
Energy System
Telecommunica
tions System
Water
Resources
System
the arrangement of public and private space in cities and
the degree of connectivity and accessibility
Structure
Spatial Pattern
Protected Area
• area that provides protection for
subordinate areas : protected forests,
peatlands, water catchments
• local protection area : borders of
beaches & rivers, around lakes /
reservoirs, urban green open spaces
• conservation areas: nature reserves,
nature conservation, hunting parks,
coastal conservation and small
islands
• geological protected area : geological
nature reserve, groundwater
protection
• other protected areas : biosphere
reserves, ramsar, cultural heritage,
germplasm, animal refuge,
mangroves
Cultivated Area
• production forest allocation area;
• forest reserve area;
• agricultural allocation area;
• fisheries allocation area;
• mining allocation area;
• industrial allocation area;
• tourism allocation area;
• residential area; and / or
• other allocation areas.
Disaster and Spatial Planning
Picture: PU
Picture: LePost
Disasters are different
Eachdisasterisunique
http://studioprotector.org/
(Tilling, 2008)
Uncertainty
However,whenthereisaction,casualties
and/ordamagesmightbereduced
DISASTER
« Disaster Management »
Disaster risk
management
Crisis
management
Post-crisis
management
Pre Syn Post
SPACE
TIME
Response
Reconstructi
on
Rehabilitatio
n
Mitigation
Preparednes
s
Concept of DRR
NATURALEVENT
No harm to
humans
HAZARD(H) The
probability
of
occurrence
of certain
natural
disaster
VULNERABILITY(V)
The degree
of loss for
each
element in
the event of
disaster
RISIKO(R)
Potential
losses
caused by
disaster
Before we discuss about the relation between Disaster
management and Spatial Planning….
1
(UNDRO, 1992)
Risk = Hazard x Vulnerability
Capacity
Planning
CYCLE
Disaster
Planning= cycle
Disaster = cycle
Planning = cycle
PLAN OF SPACE USE OF SPACE
CONTROL OF SPACE USE
SPATIAL PLANNING (INDONESIAN TERM)
SchemeofSpatialPlanDocumentStages
Sumber: Schramm, et al.(1991)
Spatial Plan & Disaster Management
• Law No. 26 of 2007
The physical condition of the NKRI area is vulnerable to disasters,
therefore disaster mitigation-based spatial planning is needed
• Law No. 26 of 2007
Disaster mitigation is a series of efforts to reduce disaster risk, both
through physical development (structural mitigation) and awareness
and capacity building in the face of disaster threats
Spatial planning = disaster risk reduction
< Risk
Capacity
(ies)>
Hazard (s)
<
Vulnerability
(ies)<
Indonesian Spatial Planning
Law
• No. 26 of 2007
• No. 1 of 2018
Ministrial
Regulation
• Public Work Ministrial Regulation No. 21 of 2007
• Disaster prone areas of volcanic eruptions and earthquakes
Ministrial
Regulation
• PU No 22 2007
• Disaster prone area of landslide
Plan
UseControl
Including the HAZARD elements (KRB) with the aim of reducing RISK
Unfortunately….
• Indonesia
Sumber: Small, et al., 2001
: volcano
Indonésie
5.120 km (3.181 mi) from East to West
1,760 km (1,094 mi) from North to South
Area: 1,916,862 km2 (741,052 mil2).
Coastal area: 54,716 km (33,999 mil)
16,056 islands
- / + 261 890 900 inhabitants
Population growth: 1.4%
Density of population: 9 - 15,624 inhabitants / km2
Several time zones
Lecture 8: Spatial Planning for Disaster Risk Reduction
Geomorphology
Volcanic Structural
Denudational Karstic
Glacial Aeolin
Fluvial Coastal
Océan Indien
Plaque Indo-australienne
Volcanic risk
 120 active volcanoes including:
 1 in high surveillance (level 4)
 4 to level 3
 15 at level 2
https://magma.vsi.esdm.go.id
Volcanic risk
Volcanoes in Indonesia
Subduction phenomena
Earthquake risk
Earthquake risk
Faults and earthquakes
Tsunami risk
1) Plan of space
• HAZARD kawasan rawan bencana
• Too many bureau/institutions/agencies  different methods,
different maps
• BNPB,
• Kemen PU,
• Kemen ESDM,
• Bakosurtanal
• Universities
• NGOs
• Etc.
BNPB
Event map, danger: Floods, tsunamis, earthquakes, cyclones, forest fires, etc.
74 Kabupaten/Kota belum punya BPBD (Data Maret 2015 – Saat Rakornas BNPB)
52 kabupaten dan 22 kota
Ministry of Public Works
Disaster Information Map: Hurricanes, floods, tidal waves, earthquakes, eruptions, droughts, conflicts,
landslides
Geological Agency
Map of Geological Disaster Areas: Volcanoes, Earthquakes and Tsunamis, Movement of land.
Geospatial Information Agency
Disaster Index Map: Floods, earthquakes, eruptions
Meteorology, Climatology, and Geophysical
Agency
Potential maps and / or events: floods, tsunamis, earthquakes, cyclones, forest fires, etc.
How about the spatial planning maker?
• Do they have any hazard map(s)?
• How they may get the maps?
1. ‘Primary’ data  how they create the maps?
• Preliminary report?
• Data and analysis report?
• Final report?
2. Secondary data 
• Which map(s) they use?
Preliminary Report Data and Analysis Report Final Report
Preliminary Preliminary Preliminary
Method and Work
Plan
General Area Description Potential, Problem, and Area
Development
Profile Area Preview Spatial Plan Evaluation Strategic and Policy
Schedule
Implementation
Policy Development and
Sectoral
Spatial Structure Planning
Schedule
Mobilization
Analysis Pattern Structure Planning
Reporting Determining Strategic Area
Referrals space utilization
Provision of spatial Control
Right, Duty, and community
involvement
Closing
Spatial Planning Report Content
1) Plan of space
• HAZARD kawasan rawan bencana
• Sync and valid
• Reduce the uncertainty of spatial problem
• Reduce the misinterpretation of KRB
• KRB classes are different, but similar
• Volcanoes  only 51 volcanoes having “published” KRB map
• Another classes (PVMBG):
• Type A volcano: minimum one recorded eruption since 1600
• Type B volcano: no eruption recorded since 1600
• Type C volcano: no information
Hazard level Ministry of Public Work Volcanological Agency
High Tipe C KRB III
Medium Tipe B KRB II
Low Tipe A KRB I
Plan of space
• One map policy  to be used by all institutions
• Horizontal and vertical coordination (national, regional,
local).
• Hazard map is primordial, but it has to be valid and sycn.
• Hazard map must be used as a basis to analyze every
aspects in spatial planning process (the latest law in spatial
planning).
Consideration of aspects of threats (disaster-prone areas) in
spatial planning is very important to determine spatial planning
and disaster mitigation devices.
2) Use of space
• The problem of “land/spatial use” is closely related to the
“spatial plan/planning”.
• Single basic reference reduce misinterpretation 
reduce problem on land/spatial use
2) Use of space
• Example: Merapi Volcano
• Volcanic Hazard Map
• Clearly states that: Highest Hazard Zone or KRB III (Legend) is not
allowed to be used as settlement.
“….Oleh karena tingkat kerawanan yang tinggi, kawasan (KRB
III) ini tidak diperkenankan untuk hunian tetap…”
“….Due to its high vulnerability, permanent settlement in
Hazard Zone III is not allowed….”
• PerDa Sleman No 12 2012 RTRW
“Kawasan rawan bencana Merapi III adalah kawasan yang letaknya dekat dengan sumber
bahaya yang sering terlanda awanpanas, aliran lava, guguran batu, lontaran batu (pijar)
dan hujan abu lebat. Oleh karena tingkat kerawanan yang tinggi, kawasan ini tidak
diperkenankan untuk hunian tetap.”
"Merapi III disaster-prone areas are areas that are located near sources of danger that are
often hit by pyroclastic flows, lava, rock avalanches, bombs, lapilis and heavy ash rain.
Due to its high level of vulnerability, this area is not permitted for permanent occupancy. "
Volcanic geomorphology
(BPPTK, 2006)
Photo: NatGeo
Lecture 8: Spatial Planning for Disaster Risk Reduction
Hazard Map Merapi 2006
Hazard Map Merapi 2010
• Peraturan ini sepertinya tidak mudah ditegakkan
Different scale 
difficulty of the
law application
Use of space
• The use of disaster-prone areas must be carried
out together with measures to reduce the level of
vulnerability of the population.
To reduce risk, if a threat already exists, it is necessary
to reduce vulnerability and increase capacity
3) Control of space use
• Control of potential disaster space use is carried out by looking at
the consistency between the use of space and the regional spatial
plan
• Some problems:
• Conflict of interest
• i.e. Highest hazard zone 
• Settlement or non-settlement
• Evacuation routes and zones vs. Sand mining routes
• Clearly stated in the Regional Law (Perda Sleman No. 12
year 2012 act 73)
• Activities that have the potential to damage supporting
infrastructure and facilities on the disaster evacuation
routes and spaces are not permitted
• Different points of view
• Philosophie of Living in Harmony  with nature or with
disaster?
Reluctant to relocate:
Engagement with the land of birth
There is no evidence of pyroclastic flows (only ash rains)
(Suroto - Kalitengah Lor, Desa Glagaharjo, Kecamatan Cangkringan)
(Harian Jogja, 2 September 2013, ZONA BAHAYA MERAPI Pilih Bertahan, 1.000 Warga KRB III Minta Fasilitas )
Kawasan Ra di-Bantu
KRB = Kawasan Rawan Bencana
(Hazard Zone)
Local population change this term into
Kawasan Ra di-Bantu (Not
assisten/helped area)
Sumber: KRJogja, Nov 2013
Local newspaper KR (10/11/2013)
stated that in 2013, 41 billions IDR
were given to maintain the
evacuation routes, while in 2014,
30 billions IDR were also given for
the same reason in Klaten
Regency.
PLAN OF SPACE
USE OF SPACE
CONTROL OF SPACE USE
Identification of Hazards
H 
V  C ↑
Increasing Capacity
Minimizing Vulnerability
R 
Disaster risk
Disaster aspects, be they hazards, vulnerabilities, capacities or risks, have their
respective roles that are interrelated in disaster-based spatial planning.
What did we learn from the past
experiences?
Lecture 8: Spatial Planning for Disaster Risk Reduction
Lecture 8: Spatial Planning for Disaster Risk Reduction
Earthquake, Lombok
29 juillet
6,4 SR
5 août 6,9
SR
9 août 5,9
SR
9 août 6,0
SR (11.10)
9 août 7,0
SR (21.56)
25 août
5,5 SR
> 585 secousses signalées
A series of earthquake in Lombok
• > 550 personnes décédées
• > 7.000 personnes blessées
• > 400.000 personnes déplacées
• > 70.000 bâtiments détruits
Spatial plan: tourism sector
• The tourism sector accounts for 60%
of the district's total initial revenue
(PAD) à West Nusa Tenggara (NTB)
(+/- 275.000 euros)
Photo: Tempo (2018)
Masse evacuation in a port of an island of Lombok (Gili
Trawangan)
 Relief is not well organized
 Lack of transportation
 The panic of tourists
(summer vacation period)
 Hundreds of mountaineers
were trapped in the
caldera of Rinjani volcano
 Those who stay are mostly
residents and expatriates
 Tourism Crisis Center
established by the
Indonesian Government
• Sulawesi
• Kasih peta Indonesia, lalu zoom ke Sulawesi
Max Carl Wilhelm Weber
(zoologist)
Siboga expedition
Diversity of Indonesian fauna
Diversity of indonesian plants
Earthquake, tsunami and liquifaction in
Sulawesi
Source: Natawidjaja & Daryono (2015)
19 tsunami have been
recorded since 1900
Central Sulawesi
(Sopaheluwakan et al , 1995)
City of Palu
• The capital of Central
Sulawesi Province.
• > 342,000 inhabitants
• The Sultanate of Gowa (XIII
- XVII centuries), then the
Kingdom of Palu (XVII -
XIX centuries)
• The city began to develop
after the Second World
War
• More and more
immigration from Java
(transmigration in the
years 1970-1980)
Le pont jaune (symbole de la ville)
Earthquake on 28 september 2019
Earthquake
Tsunami
Liquifaction
Bilan:
• > 2.100 dead people
• > 4,500 people injured
• > 250,000 displaced people
• > 60,000 buildings destroyed
Le week-end d’un grand événement
régional: Festival Pesona Palu Nomoni
Source: BNPB (2018)
Séisme
Source: BNPB
Source: ZonaSultra (2018)
Séisme
Tsunami
Complexe de résidence (Balaroa) construit dans
les années 1980 (le premier complexe de
résidence financé par l’Etat)
Tsunamidanslecentreville
Source: BNPB
Tsunami vu du ciel
Source: BNPB
Liquifaction
Source: BNPB
Toponymy - local wisdom for DRR
• The name of the city (Palu) carries a
definition of the land raised -
Topalu'e (Kaili language)
• Bombatalu (three destructive ocean
waves)
• Linu (the earthquake)
• Nalodo (buried under the mud)
that describes the liquefaction
event
Balaroa and Petobo events leave us
important notes: methods of
disaster mitigation and regional
space management.
Balaroa avant et après le tsunami
• Kembali lagi ke Java
Lecture 8: Spatial Planning for Disaster Risk Reduction
• Large eruptions
of the years 416
or 535 and 1883
(> 36,000
deaths).
• The archipelago
is part of the
Ujung Kulon
National Park
(UNESCO World
Heritage Site)
Krakatau (and Anak Krakatau) Volcano(es)
Foto: tempo (2018)
Krakatau: volcanic eruption & tsunami
Foto: BNPB(2018)
Événement du tsunami
Source: BNPB(2018)
End of year; School vacation; in a tourist area that attract a lot of local tourists from big cities
around (Jakarta, Bandung, etc.)
Source: BNPB
Lecture 8: Spatial Planning for Disaster Risk Reduction
• Ash Falls
• Pyroclastic Flows and Surges
• Debris Avalanches
• Lava Flows
• Lahars
• Geothermal Eruptions
Volcanic hazard map for Mount Taranaki
Traditional
Knowledge
Monitoring of
Volcanic Hazards
Warning Systems
for Volcanic
Hazards
Lecture 8: Spatial Planning for Disaster Risk Reduction
Land use zoning map for areas around Mount Usu (adapted
from Nakao, 2005).
Volcanic hazard map of the Okataina Volcanic Centre (in Nairn,
2002 and adapted from Scott & Nairn, 1998).
Lecture 8: Spatial Planning for Disaster Risk Reduction
Lecture 8: Spatial Planning for Disaster Risk Reduction
Specific options that could be applied by land use planners
within plans and policy statements include:
• Avoiding new development in high volcanic risk areas, especially in localities that are not
already developed. This concept is reflected in the Mt. Usu case study, where development in
the most destructive volcanic hazard areas has been prohibited. Additionally certain types of
development (e.g., essential or hazardous facilities and covered assemblies) have been
prohibited in lahar and pyroclastic flow zones in Pierce County;
• Restricting development or permitting only low density development in already developed
hazardous areas to minimise the number of people residing in volcanic hazard areas. Pierce
County’s standards reflect this concept, whereby development is required to be low-density in
certain lahar hazard areas;
• Using volcanic hazard-specific criteria for assessing consents in volcanic hazard areas. For
example, a local authority may require that for a consent to be granted in a rural area subject
to volcanic hazards, the water supply must be able to be covered in the event of ash fall.
• Siting and where necessary relocating key facilities and critical infrastructure out of hazardous
areas;
• Incorporating specific urban design measures to mitigate volcanic impacts, for example, the
effects of ash falls, as seen in the urban design example from Kagoshima;
• Taking proactive steps to ascertain how to dispose of volcanic debris after an eruption
(Johnston et al., 2009); and
• Planning for other land use recovery aspects. In a general sense this requires considering
what the effects of an eruption might be, how the use of land could be improved after an
event, and what steps might be taken before an event to ensure such improvements can be
made (Becker et al., 2006).
Disaster aspects, be they hazards, vulnerabilities, capacities
or risks, have their respective roles that are interrelated in
disaster-based spatial planning (plan of space, use of space,
control of space use)
Even though Indonesia has continuously experienced
different natural disasters, each event brings a lesson
learned  used to improve risk and crisis management in
Indonesia or around the world
Conclusion
Thank you for your attention…

More Related Content

PPTX
Aim and objectives of Professional Institutions of Planning.
PPTX
Applications of RS and GIS in Urban Planning by Rakshith m murthy
PPTX
Lecture 3 rup 218 planng theories
PDF
Rancang kota yang baik
PPTX
103 Planning Theory i
PPTX
Urban & Regional Planning - Issues & Challenges
PPTX
Lectures 6 rup 2185 new directions in planning
PDF
REGIONAL PLAN: A CASE OF MUMBAI METROPOLITAN REGION
Aim and objectives of Professional Institutions of Planning.
Applications of RS and GIS in Urban Planning by Rakshith m murthy
Lecture 3 rup 218 planng theories
Rancang kota yang baik
103 Planning Theory i
Urban & Regional Planning - Issues & Challenges
Lectures 6 rup 2185 new directions in planning
REGIONAL PLAN: A CASE OF MUMBAI METROPOLITAN REGION

What's hot (20)

PPTX
Growth foci concept
PPT
Spatial planning india
PDF
Town planning theories concept and models
PPTX
Regional planning ppt
PPTX
Land Pooling Models in India.pptx
PDF
Growth pole theory
PDF
Unit 1 ppt
PDF
Indian Urban Policies & Programmes
PPTX
Lectures 5 rup 2185 roles of planners
PDF
Evolution of planning legislation in india
PDF
Application of Remote Sensing and GIS in Urban Planning
PPT
Settlement planning process
PPTX
District planning in India
PPTX
Planning Surveys
PDF
Sectorial planning
PPTX
Land use and land value theory ppt
PPTX
Regional Planning- Theories of explaining the emergence of towns
PDF
Planning techniques
PPTX
Strategies for metropolitan planning
PDF
Part 3 - Urban planning history, theories, and concepts
Growth foci concept
Spatial planning india
Town planning theories concept and models
Regional planning ppt
Land Pooling Models in India.pptx
Growth pole theory
Unit 1 ppt
Indian Urban Policies & Programmes
Lectures 5 rup 2185 roles of planners
Evolution of planning legislation in india
Application of Remote Sensing and GIS in Urban Planning
Settlement planning process
District planning in India
Planning Surveys
Sectorial planning
Land use and land value theory ppt
Regional Planning- Theories of explaining the emergence of towns
Planning techniques
Strategies for metropolitan planning
Part 3 - Urban planning history, theories, and concepts
Ad

Similar to Lecture 8: Spatial Planning for Disaster Risk Reduction (20)

PPTX
Environmental movements in India and geospatial technology and environmental ...
PPTX
Application of Geo-informatics in Environmental Management
PPT
Clean energy for basic community needs in south asia
PPTX
GEOLAND Landscape Policy Case Study: Greece
PPTX
Integrated_Coastal_Zone_Management.pptx
PPTX
Disaster Risk Preparedness & Sustainable Housing
PDF
Integrated coastal zone management md. yousuf gazi
PPTX
Decision support system for Local Level Agencies and Communities Disaster Ris...
PDF
Dr. Kwame Emmanuel Build Better Jamaica Presentation at Caribbean School of A...
PPTX
Photo documentation bogor workshop 14 november 2014
PDF
ppt - Mumbai DRR and flood risk mitigation.pdf
PPTX
Beyond protected areas: Landscape approaches to reconcile conservation and d...
PPTX
disaster management in Nepal with application of Remote Sensing
PDF
Joint GWP CEE/DMCSEE training: Overview of existing plans in the region by Ta...
PPTX
Natural disasters in afghanistan2
PDF
M melchiorri unece_know4_drr_red
PPTX
Regional planning concept in tourism planning.pptx
PDF
King Tirana Disaster Risk final - Introduction to Risk Management: Concepts, ...
PDF
Imagery Interpretation for Coastal and Marine Spatial Planning
PPTX
Qingdao coastal risks - Rebecca Nadin
Environmental movements in India and geospatial technology and environmental ...
Application of Geo-informatics in Environmental Management
Clean energy for basic community needs in south asia
GEOLAND Landscape Policy Case Study: Greece
Integrated_Coastal_Zone_Management.pptx
Disaster Risk Preparedness & Sustainable Housing
Integrated coastal zone management md. yousuf gazi
Decision support system for Local Level Agencies and Communities Disaster Ris...
Dr. Kwame Emmanuel Build Better Jamaica Presentation at Caribbean School of A...
Photo documentation bogor workshop 14 november 2014
ppt - Mumbai DRR and flood risk mitigation.pdf
Beyond protected areas: Landscape approaches to reconcile conservation and d...
disaster management in Nepal with application of Remote Sensing
Joint GWP CEE/DMCSEE training: Overview of existing plans in the region by Ta...
Natural disasters in afghanistan2
M melchiorri unece_know4_drr_red
Regional planning concept in tourism planning.pptx
King Tirana Disaster Risk final - Introduction to Risk Management: Concepts, ...
Imagery Interpretation for Coastal and Marine Spatial Planning
Qingdao coastal risks - Rebecca Nadin
Ad

More from ESD UNU-IAS (20)

PDF
FACTORIA 4.7 - Ibero-American Platform On Education For Sustainable Development
PDF
Proyecto Boost - Promoting Environmental Education For Sustainability in the ...
PDF
Aprendiztegi
PDF
Educational Community In Exile Without Institutional Support
PDF
Vemo-nos no Monte (See You in the Forest)
PDF
RCE South Poland
PDF
How Do We Build A Movement For Change
PDF
The Role of the Human Dimension in Promoting Education for Sustainable Develo...
PDF
Araban Zu Zero – Climate Footprint Calculator
PDF
Pedagogy Of Hope
PDF
The 15 Critical Uncertainties Taken Into Consideration
PDF
How Can We Support Education Professionals in (Re)Designing Education for Sus...
PDF
Monitoring and Evaluating Education for Sustainable Development
PDF
Inner Development Goals (IDGs)
PDF
Role of Youth in Climate Action: Creating a Multistakeholdership in Japan
PPTX
Intersectional Approach to Uplift the Vulnerable
PPTX
Stakeholder Identification in Net Zero Initiatives
PDF
Result Based Project Design
PPTX
Zeroing MY Foodprint - Transitioning the Carbon Loop of Food Waste to Net Zero
PPTX
Towards Jakarta Net Zero by 2050
FACTORIA 4.7 - Ibero-American Platform On Education For Sustainable Development
Proyecto Boost - Promoting Environmental Education For Sustainability in the ...
Aprendiztegi
Educational Community In Exile Without Institutional Support
Vemo-nos no Monte (See You in the Forest)
RCE South Poland
How Do We Build A Movement For Change
The Role of the Human Dimension in Promoting Education for Sustainable Develo...
Araban Zu Zero – Climate Footprint Calculator
Pedagogy Of Hope
The 15 Critical Uncertainties Taken Into Consideration
How Can We Support Education Professionals in (Re)Designing Education for Sus...
Monitoring and Evaluating Education for Sustainable Development
Inner Development Goals (IDGs)
Role of Youth in Climate Action: Creating a Multistakeholdership in Japan
Intersectional Approach to Uplift the Vulnerable
Stakeholder Identification in Net Zero Initiatives
Result Based Project Design
Zeroing MY Foodprint - Transitioning the Carbon Loop of Food Waste to Net Zero
Towards Jakarta Net Zero by 2050

Recently uploaded (20)

PPTX
Biodiversity.udfnfndrijfreniufrnsiufnriufrenfuiernfuire
PDF
Global Natural Disasters in H1 2025 by Beinsure
PPTX
Biodiversity of nature in environmental studies.pptx
DOCX
Epoxy Coated Steel Bolted Tanks for Farm Digesters Supports On-Farm Organic W...
PPTX
Delivery census may 2025.pptxMNNN HJTDV U
PDF
Effects of rice-husk biochar and aluminum sulfate application on rice grain q...
DOCX
Epoxy Coated Steel Bolted Tanks for Leachate Storage Securely Contain Landfil...
PPTX
Green and Cream Aesthetic Group Project Presentation.pptx
PPTX
FIRE SAFETY SEMINAR SAMPLE FOR EVERYONE.pptx
PPTX
structure and components of Environment.pptx
PPT
Compliance Monitoring report CMR presentation.ppt
PPTX
Concept of Safe and Wholesome Water.pptx
DOCX
D-360 ESG Series: Sustainable Hospitality Strategies for a Greener Future
PDF
Tree Biomechanics, a concise presentation
PDF
Weather-Patterns-Analysis-and-Prediction.pdf
PPT
Environmental pollution for educational study
PPTX
Importance of good air quality and different pollutants.
PDF
Urban Hub 50: Spirits of Place - & the Souls' of Places
PPTX
sustainable-development in tech-ppt[1].pptx
PDF
Insitu conservation seminar , national park ,enthobotanical significance
Biodiversity.udfnfndrijfreniufrnsiufnriufrenfuiernfuire
Global Natural Disasters in H1 2025 by Beinsure
Biodiversity of nature in environmental studies.pptx
Epoxy Coated Steel Bolted Tanks for Farm Digesters Supports On-Farm Organic W...
Delivery census may 2025.pptxMNNN HJTDV U
Effects of rice-husk biochar and aluminum sulfate application on rice grain q...
Epoxy Coated Steel Bolted Tanks for Leachate Storage Securely Contain Landfil...
Green and Cream Aesthetic Group Project Presentation.pptx
FIRE SAFETY SEMINAR SAMPLE FOR EVERYONE.pptx
structure and components of Environment.pptx
Compliance Monitoring report CMR presentation.ppt
Concept of Safe and Wholesome Water.pptx
D-360 ESG Series: Sustainable Hospitality Strategies for a Greener Future
Tree Biomechanics, a concise presentation
Weather-Patterns-Analysis-and-Prediction.pdf
Environmental pollution for educational study
Importance of good air quality and different pollutants.
Urban Hub 50: Spirits of Place - & the Souls' of Places
sustainable-development in tech-ppt[1].pptx
Insitu conservation seminar , national park ,enthobotanical significance

Lecture 8: Spatial Planning for Disaster Risk Reduction

  • 1. Spatial Planning for Disaster Risk Reduction Dr. Estuning Tyas Wulan Mei Faculty of Géography, Universitas Gadjah Mada, Indonesia estu.mei@gmail.com / estu.mei@ugm.ac.id
  • 2. • Estuning Tyas Wulan Mei • Lecturer at the Faculty of Geography, Universitas Gadjah Mada, Indonesia • 2013 – PhD Géographie, Université Paris 1 Panthéon – Sorbonne (Dir. : Pr. Franck Lavigne) • Sujet : Gestion des évacuations lors des crises volcaniques. Etude de cas du volcan Merapi, Java, Indonésie • 2008 – Master Geo-Information for Spatial Planning and Risk Management, Double Degree M.Sc Programme between Universitas Gadjah Mada, Indonesia and University of Twente, the Netherlands • 2006 – Undergraduate/Bachelor, Regional Development Program Study, Faculty of Geography, Universitas Gadjah Mada, Indonesia https://scholar.google.ca/citations?user=ZvZdZIQAAAAJ&hl=en https://www.scopus.com/authid/detail.uri?authorId=55018646400 https://orcid.org/0000-0003-3814-9014
  • 3. Planning or plan? Planning • Process of thinking and organizing the activities to achieve a goal. • Planning refers to the process of deciding what to do and how to do it Plan • Results or products of a certain planning activity. Planner(s) Planners do not make decisions themselves; rather, they support decision-makers (managers, public officials, citizens) by coordinating information and activities. Their role is to create a logical, systematic decision-making process that results in the best action
  • 4. Planning • Peter Hall (1992): • ….'is concerned with deliberately achieving some objectives, and it proceeds by assembling actions into some orderly sequence’. • Ernest R. Alexander (1986): • “Planning is the deliberate social or organizational activity of developing an optimal strategy of future action to achieve a desired set of goals, for solving novel problems in complex contexts, and attended by the power and intention to commit recourses and to act as necessary to implement the chosen strategy”
  • 5. Planning • Diana Conyers and Peter Hills (1984): “…is a continues process which involves decisions, or choices, about alternative ways of using available resources, with the aims of achieving particular goals at some time in the future”. • 4 main elements of planning: • Decisions or choices • Resource allocations • Goal(s) achievement • For the future
  • 6. Aspects of Planning Planning: Role and place in public decision making Planning steps Spatial levels Planning spheres Operational fields Administration Time horizons Styles of planning Centrally-planned economies Market-based economies Mixed economies Project planning Sectoral planning Macro-economic planning Integrated area planning Short-term planning Medium-term planning Long-term planning Conception Preparation Realization Evaluation 1. Blueprint planning 2. Process planning 3. Comprehensive planning 4. Jointed Vs. Disjointed Incrementalism 5. Functional planning 6. Normative planning
  • 7. Planning Principles • Good planning requires a methodical process that clearly defines the steps that lead to optimal solutions. (Preston, 2012) Plan- ning Compre- hensive Efficient Inclusive Inform- ative Inte- grated Logical Trans- parent all significant options and impacts are considered the process should not waste time or money people affected by the plan have opportunities to be involved individual, short-term decisions should support strategic, long-term goals results are understood by stakeholders (people affected by a decision) each step leads to the next everybody involved understands how the process operates
  • 8. Spatial Planning • A strategic direction for the development of a given geographic area, states the policies, priorities, programmes and land allocations that will implement the strategic direction and influences the distribution of people and activities in spaces of various scales. • Spatial planning systems refer to the methods and approaches used by the public and private sector to influence the distribution of people and activities in spaces of various scales. • Spatial plans may be developed for urban planning, regional planning, environmental planning, landscape planning, national spatial plans, or spatial planning at the Union level. (noted: some countries used the term urban planning, regional planning, land use planning).
  • 10. Spatial Structure Urban System Transportation System Energy System Telecommunica tions System Water Resources System the arrangement of public and private space in cities and the degree of connectivity and accessibility
  • 12. Spatial Pattern Protected Area • area that provides protection for subordinate areas : protected forests, peatlands, water catchments • local protection area : borders of beaches & rivers, around lakes / reservoirs, urban green open spaces • conservation areas: nature reserves, nature conservation, hunting parks, coastal conservation and small islands • geological protected area : geological nature reserve, groundwater protection • other protected areas : biosphere reserves, ramsar, cultural heritage, germplasm, animal refuge, mangroves Cultivated Area • production forest allocation area; • forest reserve area; • agricultural allocation area; • fisheries allocation area; • mining allocation area; • industrial allocation area; • tourism allocation area; • residential area; and / or • other allocation areas.
  • 13. Disaster and Spatial Planning Picture: PU Picture: LePost
  • 16. However,whenthereisaction,casualties and/ordamagesmightbereduced DISASTER « Disaster Management » Disaster risk management Crisis management Post-crisis management Pre Syn Post SPACE TIME Response Reconstructi on Rehabilitatio n Mitigation Preparednes s
  • 17. Concept of DRR NATURALEVENT No harm to humans HAZARD(H) The probability of occurrence of certain natural disaster VULNERABILITY(V) The degree of loss for each element in the event of disaster RISIKO(R) Potential losses caused by disaster Before we discuss about the relation between Disaster management and Spatial Planning…. 1 (UNDRO, 1992) Risk = Hazard x Vulnerability Capacity
  • 19. PLAN OF SPACE USE OF SPACE CONTROL OF SPACE USE SPATIAL PLANNING (INDONESIAN TERM)
  • 21. Sumber: Schramm, et al.(1991)
  • 22. Spatial Plan & Disaster Management • Law No. 26 of 2007 The physical condition of the NKRI area is vulnerable to disasters, therefore disaster mitigation-based spatial planning is needed • Law No. 26 of 2007 Disaster mitigation is a series of efforts to reduce disaster risk, both through physical development (structural mitigation) and awareness and capacity building in the face of disaster threats
  • 23. Spatial planning = disaster risk reduction < Risk Capacity (ies)> Hazard (s) < Vulnerability (ies)<
  • 24. Indonesian Spatial Planning Law • No. 26 of 2007 • No. 1 of 2018 Ministrial Regulation • Public Work Ministrial Regulation No. 21 of 2007 • Disaster prone areas of volcanic eruptions and earthquakes Ministrial Regulation • PU No 22 2007 • Disaster prone area of landslide Plan UseControl Including the HAZARD elements (KRB) with the aim of reducing RISK
  • 26. Indonésie 5.120 km (3.181 mi) from East to West 1,760 km (1,094 mi) from North to South Area: 1,916,862 km2 (741,052 mil2). Coastal area: 54,716 km (33,999 mil) 16,056 islands - / + 261 890 900 inhabitants Population growth: 1.4% Density of population: 9 - 15,624 inhabitants / km2
  • 31. Volcanic risk  120 active volcanoes including:  1 in high surveillance (level 4)  4 to level 3  15 at level 2 https://magma.vsi.esdm.go.id
  • 38. 1) Plan of space • HAZARD kawasan rawan bencana • Too many bureau/institutions/agencies  different methods, different maps • BNPB, • Kemen PU, • Kemen ESDM, • Bakosurtanal • Universities • NGOs • Etc.
  • 39. BNPB Event map, danger: Floods, tsunamis, earthquakes, cyclones, forest fires, etc. 74 Kabupaten/Kota belum punya BPBD (Data Maret 2015 – Saat Rakornas BNPB) 52 kabupaten dan 22 kota
  • 40. Ministry of Public Works Disaster Information Map: Hurricanes, floods, tidal waves, earthquakes, eruptions, droughts, conflicts, landslides
  • 41. Geological Agency Map of Geological Disaster Areas: Volcanoes, Earthquakes and Tsunamis, Movement of land.
  • 42. Geospatial Information Agency Disaster Index Map: Floods, earthquakes, eruptions
  • 43. Meteorology, Climatology, and Geophysical Agency Potential maps and / or events: floods, tsunamis, earthquakes, cyclones, forest fires, etc.
  • 44. How about the spatial planning maker? • Do they have any hazard map(s)? • How they may get the maps? 1. ‘Primary’ data  how they create the maps? • Preliminary report? • Data and analysis report? • Final report? 2. Secondary data  • Which map(s) they use?
  • 45. Preliminary Report Data and Analysis Report Final Report Preliminary Preliminary Preliminary Method and Work Plan General Area Description Potential, Problem, and Area Development Profile Area Preview Spatial Plan Evaluation Strategic and Policy Schedule Implementation Policy Development and Sectoral Spatial Structure Planning Schedule Mobilization Analysis Pattern Structure Planning Reporting Determining Strategic Area Referrals space utilization Provision of spatial Control Right, Duty, and community involvement Closing Spatial Planning Report Content
  • 46. 1) Plan of space • HAZARD kawasan rawan bencana • Sync and valid • Reduce the uncertainty of spatial problem • Reduce the misinterpretation of KRB • KRB classes are different, but similar • Volcanoes  only 51 volcanoes having “published” KRB map • Another classes (PVMBG): • Type A volcano: minimum one recorded eruption since 1600 • Type B volcano: no eruption recorded since 1600 • Type C volcano: no information Hazard level Ministry of Public Work Volcanological Agency High Tipe C KRB III Medium Tipe B KRB II Low Tipe A KRB I
  • 47. Plan of space • One map policy  to be used by all institutions • Horizontal and vertical coordination (national, regional, local). • Hazard map is primordial, but it has to be valid and sycn. • Hazard map must be used as a basis to analyze every aspects in spatial planning process (the latest law in spatial planning). Consideration of aspects of threats (disaster-prone areas) in spatial planning is very important to determine spatial planning and disaster mitigation devices.
  • 48. 2) Use of space • The problem of “land/spatial use” is closely related to the “spatial plan/planning”. • Single basic reference reduce misinterpretation  reduce problem on land/spatial use
  • 49. 2) Use of space • Example: Merapi Volcano • Volcanic Hazard Map • Clearly states that: Highest Hazard Zone or KRB III (Legend) is not allowed to be used as settlement. “….Oleh karena tingkat kerawanan yang tinggi, kawasan (KRB III) ini tidak diperkenankan untuk hunian tetap…” “….Due to its high vulnerability, permanent settlement in Hazard Zone III is not allowed….” • PerDa Sleman No 12 2012 RTRW “Kawasan rawan bencana Merapi III adalah kawasan yang letaknya dekat dengan sumber bahaya yang sering terlanda awanpanas, aliran lava, guguran batu, lontaran batu (pijar) dan hujan abu lebat. Oleh karena tingkat kerawanan yang tinggi, kawasan ini tidak diperkenankan untuk hunian tetap.” "Merapi III disaster-prone areas are areas that are located near sources of danger that are often hit by pyroclastic flows, lava, rock avalanches, bombs, lapilis and heavy ash rain. Due to its high level of vulnerability, this area is not permitted for permanent occupancy. "
  • 54. • Peraturan ini sepertinya tidak mudah ditegakkan Different scale  difficulty of the law application
  • 55. Use of space • The use of disaster-prone areas must be carried out together with measures to reduce the level of vulnerability of the population. To reduce risk, if a threat already exists, it is necessary to reduce vulnerability and increase capacity
  • 56. 3) Control of space use • Control of potential disaster space use is carried out by looking at the consistency between the use of space and the regional spatial plan • Some problems: • Conflict of interest • i.e. Highest hazard zone  • Settlement or non-settlement • Evacuation routes and zones vs. Sand mining routes • Clearly stated in the Regional Law (Perda Sleman No. 12 year 2012 act 73) • Activities that have the potential to damage supporting infrastructure and facilities on the disaster evacuation routes and spaces are not permitted • Different points of view • Philosophie of Living in Harmony  with nature or with disaster?
  • 57. Reluctant to relocate: Engagement with the land of birth There is no evidence of pyroclastic flows (only ash rains) (Suroto - Kalitengah Lor, Desa Glagaharjo, Kecamatan Cangkringan) (Harian Jogja, 2 September 2013, ZONA BAHAYA MERAPI Pilih Bertahan, 1.000 Warga KRB III Minta Fasilitas ) Kawasan Ra di-Bantu KRB = Kawasan Rawan Bencana (Hazard Zone) Local population change this term into Kawasan Ra di-Bantu (Not assisten/helped area)
  • 58. Sumber: KRJogja, Nov 2013 Local newspaper KR (10/11/2013) stated that in 2013, 41 billions IDR were given to maintain the evacuation routes, while in 2014, 30 billions IDR were also given for the same reason in Klaten Regency.
  • 59. PLAN OF SPACE USE OF SPACE CONTROL OF SPACE USE Identification of Hazards H  V  C ↑ Increasing Capacity Minimizing Vulnerability R  Disaster risk Disaster aspects, be they hazards, vulnerabilities, capacities or risks, have their respective roles that are interrelated in disaster-based spatial planning.
  • 60. What did we learn from the past experiences?
  • 64. 29 juillet 6,4 SR 5 août 6,9 SR 9 août 5,9 SR 9 août 6,0 SR (11.10) 9 août 7,0 SR (21.56) 25 août 5,5 SR > 585 secousses signalées A series of earthquake in Lombok • > 550 personnes décédées • > 7.000 personnes blessées • > 400.000 personnes déplacées • > 70.000 bâtiments détruits
  • 65. Spatial plan: tourism sector • The tourism sector accounts for 60% of the district's total initial revenue (PAD) à West Nusa Tenggara (NTB) (+/- 275.000 euros) Photo: Tempo (2018) Masse evacuation in a port of an island of Lombok (Gili Trawangan)  Relief is not well organized  Lack of transportation  The panic of tourists (summer vacation period)  Hundreds of mountaineers were trapped in the caldera of Rinjani volcano  Those who stay are mostly residents and expatriates  Tourism Crisis Center established by the Indonesian Government
  • 66. • Sulawesi • Kasih peta Indonesia, lalu zoom ke Sulawesi
  • 67. Max Carl Wilhelm Weber (zoologist) Siboga expedition
  • 70. Earthquake, tsunami and liquifaction in Sulawesi Source: Natawidjaja & Daryono (2015) 19 tsunami have been recorded since 1900
  • 72. City of Palu • The capital of Central Sulawesi Province. • > 342,000 inhabitants • The Sultanate of Gowa (XIII - XVII centuries), then the Kingdom of Palu (XVII - XIX centuries) • The city began to develop after the Second World War • More and more immigration from Java (transmigration in the years 1970-1980) Le pont jaune (symbole de la ville)
  • 73. Earthquake on 28 september 2019 Earthquake Tsunami Liquifaction Bilan: • > 2.100 dead people • > 4,500 people injured • > 250,000 displaced people • > 60,000 buildings destroyed Le week-end d’un grand événement régional: Festival Pesona Palu Nomoni Source: BNPB (2018)
  • 75. Source: ZonaSultra (2018) Séisme Tsunami Complexe de résidence (Balaroa) construit dans les années 1980 (le premier complexe de résidence financé par l’Etat)
  • 77. Tsunami vu du ciel Source: BNPB
  • 79. Toponymy - local wisdom for DRR • The name of the city (Palu) carries a definition of the land raised - Topalu'e (Kaili language) • Bombatalu (three destructive ocean waves) • Linu (the earthquake) • Nalodo (buried under the mud) that describes the liquefaction event Balaroa and Petobo events leave us important notes: methods of disaster mitigation and regional space management. Balaroa avant et après le tsunami
  • 80. • Kembali lagi ke Java
  • 82. • Large eruptions of the years 416 or 535 and 1883 (> 36,000 deaths). • The archipelago is part of the Ujung Kulon National Park (UNESCO World Heritage Site) Krakatau (and Anak Krakatau) Volcano(es) Foto: tempo (2018)
  • 85. Événement du tsunami Source: BNPB(2018) End of year; School vacation; in a tourist area that attract a lot of local tourists from big cities around (Jakarta, Bandung, etc.)
  • 88. • Ash Falls • Pyroclastic Flows and Surges • Debris Avalanches • Lava Flows • Lahars • Geothermal Eruptions
  • 89. Volcanic hazard map for Mount Taranaki Traditional Knowledge Monitoring of Volcanic Hazards Warning Systems for Volcanic Hazards
  • 91. Land use zoning map for areas around Mount Usu (adapted from Nakao, 2005).
  • 92. Volcanic hazard map of the Okataina Volcanic Centre (in Nairn, 2002 and adapted from Scott & Nairn, 1998).
  • 95. Specific options that could be applied by land use planners within plans and policy statements include: • Avoiding new development in high volcanic risk areas, especially in localities that are not already developed. This concept is reflected in the Mt. Usu case study, where development in the most destructive volcanic hazard areas has been prohibited. Additionally certain types of development (e.g., essential or hazardous facilities and covered assemblies) have been prohibited in lahar and pyroclastic flow zones in Pierce County; • Restricting development or permitting only low density development in already developed hazardous areas to minimise the number of people residing in volcanic hazard areas. Pierce County’s standards reflect this concept, whereby development is required to be low-density in certain lahar hazard areas; • Using volcanic hazard-specific criteria for assessing consents in volcanic hazard areas. For example, a local authority may require that for a consent to be granted in a rural area subject to volcanic hazards, the water supply must be able to be covered in the event of ash fall. • Siting and where necessary relocating key facilities and critical infrastructure out of hazardous areas; • Incorporating specific urban design measures to mitigate volcanic impacts, for example, the effects of ash falls, as seen in the urban design example from Kagoshima; • Taking proactive steps to ascertain how to dispose of volcanic debris after an eruption (Johnston et al., 2009); and • Planning for other land use recovery aspects. In a general sense this requires considering what the effects of an eruption might be, how the use of land could be improved after an event, and what steps might be taken before an event to ensure such improvements can be made (Becker et al., 2006).
  • 96. Disaster aspects, be they hazards, vulnerabilities, capacities or risks, have their respective roles that are interrelated in disaster-based spatial planning (plan of space, use of space, control of space use) Even though Indonesia has continuously experienced different natural disasters, each event brings a lesson learned  used to improve risk and crisis management in Indonesia or around the world Conclusion
  • 97. Thank you for your attention…