Access Control Delay Demonstration- Hotel - MEP - Ground FLoor - Shop Dwgs - RFI's - WI's with Hotel Ground Floor As-built (taken from the MEP Inspection Records)
Excel A3 Summary Sheet
M200 M240 M290 M330 M390 M450 M510   M850   M910   M930
02/12/09
02/04/10
01/09/10
01/03/11
30/09/11
30/03/12
27/09/12
30/03/13
30/09/13
30/11/13
Dur % Dur % Dur % Dur % Dur % Dur % Dur % Dur % Dur % Dur %
30 37 54 73 100 100 100 100 100 100
37 39 43 63 85 90 90 99 99 100
0 0 0 0 0 5 90 99 99 100
Ground Floor Hotel ‐ Actual Hand Over 
‐ TOC on 31 January 2014. Therefore 
GF MEP Scheduled date for 
completion Rev 6 Baseline 
‐ 19 Aug 10
Critical Delay to Ground Floor MEP 
Completion ‐ 1261 Days
% Complete from actual Start to 30 November 2013 in 
approx 6 month intervals taken from the Updated 
Progressed Programmes ffor Hotel GF MEP Activities
As‐planned (Rev 6 Baseline) showing Hotel GF Hotel MEP Activities the 
include Access Controls. Programme Data Date: 11 May 08 
(Commencement)
As‐built (taken from the last progressed updated programme Data 
Date: 15 May 14) showing Hotel GF MEP Activities the include Access 
Controls 
As‐built (taken from the last progressed updated programme Data Date: 
15 May 14)  showing the As‐built Testing and Commissioning activities 
for the Elelctrical ELV System that includes Access Controls
Table E ‐ on the Excel Spreadheet titled: "Access Control DD ‐ 12 May 2015 ‐ MEP ‐ GF Shop Dwgs ‐ RFI's & GF As‐built" 
Table E identfies the entire MEP as‐built record from the inspection request procedure for the Hotel GF. This is the Sub‐
total of each MEP trade shown as a time line for the as‐built  of the Hotel GF MEP. 
Table F ‐ on the Excel Spreadheet titled: "Access Control DD ‐ 12 May 2015 ‐ MEP ‐ GF Shop Dwgs ‐ RFI's & GF As‐built" 
Table F identfies the entire MEP as‐built record shop dwgs, RFI's and IFC dwgs associated with the Hotel GF. This is the Sub‐
total of each Shop Dwg, RFI and IFC submitted and/or received shown as a time line for the Hotel GF MEP 
Table B ‐ is taken from the spreadsheet titled: "Access Control DD ‐ 12 May 2015 ‐ MEP ‐ GF Shop Dwgs ‐ RFI's & GF As‐built" . Table F 
identifies all the Work Instructions that were issued for and associated with the Fire Strategy which encompassed the Access Control. The 
WI's with direct reference to Access Control are coloured in yellow. 
Table A ‐ is taken from the spreadsheet titled: "Access Control DD ‐ 12 May 2015 ‐ MEP ‐ GF Shop Dwgs ‐ RFI's & GF As‐built". Table A 
identifies the shop drawings issued that concerned Access Controls for the Hotel GF (Rev 01 and Rev 02 dates need to be entered.
Table F ‐ ‐ is taken from the spreadsheet titled: "Access Control DD ‐ 12 May 2015 ‐ MEP ‐ GF Shop Dwgs ‐ RFI's & GF As‐built". Table F has been 
filtered to only show the shop drawing and RFI's submitted and returned for the Access Control requirements for the the Hotel Ground Floor 
MEP. 

More Related Content

PPTX
Abila MIP Tax Reporting Overview
PDF
Solicitud inmofianza aprobada bucaramanga
DOCX
Carryforward with posting in SAP
PDF
BE benchmark project cost allocation
DOC
Caddata warehousing
PDF
pp2 Final account-1
PDF
Comprehensive Maintenance Contract for Air Conditioners (Window Type) & (Split).
Abila MIP Tax Reporting Overview
Solicitud inmofianza aprobada bucaramanga
Carryforward with posting in SAP
BE benchmark project cost allocation
Caddata warehousing
pp2 Final account-1
Comprehensive Maintenance Contract for Air Conditioners (Window Type) & (Split).

More from Jeremy Fearnsides (7)

PDF
BLOCK5 - Programme with updates superimposed one with all sorts - Critical Path
PDF
Full time line for causes that drive the critical delays on a single activity...
PDF
Time Line Demonstration
PDF
Float Mapping Notes
PDF
Concurrent and Parallel Competing Critical Delay Demonstration Float Map A
PDF
Fearnsides & Associates Company Profile
PDF
Apportionment the netting off approach c
BLOCK5 - Programme with updates superimposed one with all sorts - Critical Path
Full time line for causes that drive the critical delays on a single activity...
Time Line Demonstration
Float Mapping Notes
Concurrent and Parallel Competing Critical Delay Demonstration Float Map A
Fearnsides & Associates Company Profile
Apportionment the netting off approach c
Ad

MEP EXCEL P6 PDF GF MEP A3 Access Control Delay Demonstration Summary Sheet

  • 1. Access Control Delay Demonstration- Hotel - MEP - Ground FLoor - Shop Dwgs - RFI's - WI's with Hotel Ground Floor As-built (taken from the MEP Inspection Records) Excel A3 Summary Sheet M200 M240 M290 M330 M390 M450 M510   M850   M910   M930 02/12/09 02/04/10 01/09/10 01/03/11 30/09/11 30/03/12 27/09/12 30/03/13 30/09/13 30/11/13 Dur % Dur % Dur % Dur % Dur % Dur % Dur % Dur % Dur % Dur % 30 37 54 73 100 100 100 100 100 100 37 39 43 63 85 90 90 99 99 100 0 0 0 0 0 5 90 99 99 100 Ground Floor Hotel ‐ Actual Hand Over  ‐ TOC on 31 January 2014. Therefore  GF MEP Scheduled date for  completion Rev 6 Baseline  ‐ 19 Aug 10 Critical Delay to Ground Floor MEP  Completion ‐ 1261 Days % Complete from actual Start to 30 November 2013 in  approx 6 month intervals taken from the Updated  Progressed Programmes ffor Hotel GF MEP Activities As‐planned (Rev 6 Baseline) showing Hotel GF Hotel MEP Activities the  include Access Controls. Programme Data Date: 11 May 08  (Commencement) As‐built (taken from the last progressed updated programme Data  Date: 15 May 14) showing Hotel GF MEP Activities the include Access  Controls  As‐built (taken from the last progressed updated programme Data Date:  15 May 14)  showing the As‐built Testing and Commissioning activities  for the Elelctrical ELV System that includes Access Controls Table E ‐ on the Excel Spreadheet titled: "Access Control DD ‐ 12 May 2015 ‐ MEP ‐ GF Shop Dwgs ‐ RFI's & GF As‐built"  Table E identfies the entire MEP as‐built record from the inspection request procedure for the Hotel GF. This is the Sub‐ total of each MEP trade shown as a time line for the as‐built  of the Hotel GF MEP.  Table F ‐ on the Excel Spreadheet titled: "Access Control DD ‐ 12 May 2015 ‐ MEP ‐ GF Shop Dwgs ‐ RFI's & GF As‐built"  Table F identfies the entire MEP as‐built record shop dwgs, RFI's and IFC dwgs associated with the Hotel GF. This is the Sub‐ total of each Shop Dwg, RFI and IFC submitted and/or received shown as a time line for the Hotel GF MEP  Table B ‐ is taken from the spreadsheet titled: "Access Control DD ‐ 12 May 2015 ‐ MEP ‐ GF Shop Dwgs ‐ RFI's & GF As‐built" . Table F  identifies all the Work Instructions that were issued for and associated with the Fire Strategy which encompassed the Access Control. The  WI's with direct reference to Access Control are coloured in yellow.  Table A ‐ is taken from the spreadsheet titled: "Access Control DD ‐ 12 May 2015 ‐ MEP ‐ GF Shop Dwgs ‐ RFI's & GF As‐built". Table A  identifies the shop drawings issued that concerned Access Controls for the Hotel GF (Rev 01 and Rev 02 dates need to be entered. Table F ‐ ‐ is taken from the spreadsheet titled: "Access Control DD ‐ 12 May 2015 ‐ MEP ‐ GF Shop Dwgs ‐ RFI's & GF As‐built". Table F has been  filtered to only show the shop drawing and RFI's submitted and returned for the Access Control requirements for the the Hotel Ground Floor  MEP.