SlideShare a Scribd company logo
8
Most read
9
Most read
12
Most read
MRP
Shakhawat Hossain
MRP
Material Requirements Planning (MRP)---a computerized information system developed
specifically to aid in managing dependent demand and scheduling replenishment
orders.
2
Other
sources
of demand
Inventory
transactions
Inventory
records
Bills of
materials
Engineering
and process
designs
Material
requirements
plan
MRP
explosion
Authorized
master production
schedule
MRP Input & Output
3
Data Files
Purchasing data
BOM
Lead times
(Item master file)
Inventory data
Master
production schedule
Material
requirement
planning
programs
(computer and
software)
Output Reports
MRP by period report
MRP by date report
Planned order report
Purchase advice
Exception reportsi
Order early or late or not
needed
Order quantity too small or
too large
Master Production Schedule (MPS)
■ Specifies what is to be made and when
■ The MPS is the result of the production planning process
■ MPS is established in terms of specific products
■ The MPS is quite often fixed or frozen in the near term part of the
plan
■ The MPS is a statement of what is to be produced.
4
Inventory record
■ Accurate inventory records are absolutely required for MRP
(or any dependent demand system) to operate correctly
■ Generally MRP systems require 99% accuracy
■ Outstanding purchase orders must accurately reflect
quantities and scheduled receipts
5
Lead time
■ The time required to purchase, produce, or assemble an
item
■ For production – the sum of the order, wait, move, setup,
store, and run times
■ For purchased items – the time between the recognition of
a need and the availability of the item for production
6
Bill of Material (BOM)
■ List of components, ingredients, and materials needed to
make a product
– Provides product structure
– items above a given level are called parents
– items below a given level are called children
– items may be both a parent and a child
7
Pictorial example of a ladder back chair BOM
Seat cushion
Seat-frame boards
Front legs
A
Ladder-back
chair
Back legs
Leg supports
Back slats
8
Product structure example of the same
item
C (1)
Seat
subassembly
D (2)
Front
legs
B (1)
Ladder-back
subassembly
E (4)
Leg
supports
I (1)
Seat cushion
H (1)
Seat frame
G (4)
Back slats
F (2)
Back legs
J (4)
Seat-frame boards
A Ladder-back
chair
9
Block diagram of general example
Item A
B (2) C (3)
D (2) E (2) E (2) F (2)
D (2) G (1)
10
The MRP process begins by determining gross
requirements
– The production schedule for the end item – 50 units of Item A in
week 8
– Using the lead time for the item, determine the week in which the
order should be released – a 1 week lead time means the order
for 50 units should be released in week 7
– This step is often called “lead time offset” or “time phasing”
11
Gross Requirements Plan
12
Week
1 2 3 4 5 6 7 8
Lead Time
A. Required date 50
Order release date 50 1
week
B. Required date 100
Order release date 100 2
weeks
C. Required date 150
Order release date 150 1
week
E. Required date 200 300
Order release date 200 300 2
weeks
F. Required date 300
Order release date 300 3
weeks
G. Required date 600 200
Order release date 600 200 1
week
Gross Requirements Plan
13
Week
1 2 3 4 5 6 7 8
Lead Time
A. Required date 50
Order release date 50 1
week
B. Required date 100
Order release date 100 2
weeks
C. Required date 150
Order release date 150 1
week
E. Required date 200 300
Order release date 200 300 2
weeks
F. Required date 300
Order release date 300 3
weeks
G. Required date 600 200
Order release date 600 200 1
week
G. Required date 300
Gross Requirements Plan
14
Week
1 2 3 4 5 6 7 8
Lead Time
A. Required date 50
Order release date 50 1
week
B. Required date 100
Order release date 100 2
weeks
C. Required date 150
Order release date 150 1
week
E. Required date 200 300
Order release date 200 300 2
weeks
F. Required date 300
Order release date 300 3
weeks
G. Required date 600 200
Order release date 600 200 1
week
G. Required date 300
Order release date 300 2
Net Requirements Plan
15
Net Requirements Plan
16
Net Requirements Plan Continues
17
MRP Management
■ MRP is a dynamic system
■ Facilitates re-planning when changes occur
■ System nervousness can result from too many changes
■ Time fences put limits on re-planning
■ Pegging links each item to its parent allowing effective
analysis of changes
■ Adequate staffing and accurate records are pre-requisites
to operational success
18

More Related Content

PPTX
Operations Management Classroom Presentation
PPT
Session 5
PPT
Chapter 5_OM
PPT
Heizer 14
PPTX
MATERIAL REQUIREMENTS PLANNING (MRP)
PPTX
MRP and ERP
PPT
08. 444444444444444444444444444444MRP.ppt
PDF
Scps -materials_requirements_planning
Operations Management Classroom Presentation
Session 5
Chapter 5_OM
Heizer 14
MATERIAL REQUIREMENTS PLANNING (MRP)
MRP and ERP
08. 444444444444444444444444444444MRP.ppt
Scps -materials_requirements_planning

Similar to MRP Basics and calculation of MRP explotions (20)

PDF
Module11. Material requirement plan..pdf
PPT
Ch16 mrp
PPT
Operations Management Material Requirements Planning (MRP)
PPTX
Managing productions across Supply Chain
PPT
Material requirement planning
PPTX
Managing production across supply chain
PPT
Material Requisite Planning
PPT
PPTX
Session 6-7-8 MRP.pptx PPC MBA Sem IV IB
PPT
Material Resource Planning
PPTX
Production planning and control
PPT
Sales & operations planning
PPTX
Production Planning.pptx
PPT
Methods Defense - Philcan Industrial Corporation
PPTX
Material requirement planning (mrp1)
PDF
Production planning and control - Basic concepts
PPTX
OM Unit_ IV.pptxucoxpuxofupupf Fuppfoufuflhlchjllh lh
PPTX
Inventory management
PDF
Module11. Material requirement plan..pdf
Ch16 mrp
Operations Management Material Requirements Planning (MRP)
Managing productions across Supply Chain
Material requirement planning
Managing production across supply chain
Material Requisite Planning
Session 6-7-8 MRP.pptx PPC MBA Sem IV IB
Material Resource Planning
Production planning and control
Sales & operations planning
Production Planning.pptx
Methods Defense - Philcan Industrial Corporation
Material requirement planning (mrp1)
Production planning and control - Basic concepts
OM Unit_ IV.pptxucoxpuxofupupf Fuppfoufuflhlchjllh lh
Inventory management
Ad

Recently uploaded (20)

PPTX
Five S Training Program - Principles of 5S
PPTX
Principles & Theories of Mgt-Master in PM.pptx
PDF
Maintaining a Quality Culture - Performance Metrics, Best Practices and QMS E...
PDF
Human resources management is a best management
PPTX
Course Overview of the Course Titled.pptx
PPTX
Organisational behaviour_ managerial applications of perception
PDF
The Plan: Save the Palestinian Nation Now
PPTX
Human Resource Management | Introduction,Meaning and Definition
PPTX
Chapter-3.pptx project life cycle presentation
PDF
The Sustainable Site: Boosting Productivity in Construction – Pipe Dream or P...
PDF
CISSP Domain 6: Security Assessment and Testing
PPTX
Basics of Project Management for development of leadership skills in practice
PDF
Equity at the Helm_ Guiding Schools Through Inclusive Leadership by Dr.pdf
PPTX
The Sustainable Site: Boosting Productivity in Construction – Pipe Dream or P...
PDF
The Untold Story of Swami Vijay Kumar Durai: Building PRS International
PPTX
Chapter Three for international political
PPTX
Human resources management -job perception concept
PPT
Project Management - Scope Management.ppt
PPTX
FSC Building Trust in LGs august 8 2025.pptx
PDF
CISSP - Domain 7: Security Operations - InfoSec Institute
Five S Training Program - Principles of 5S
Principles & Theories of Mgt-Master in PM.pptx
Maintaining a Quality Culture - Performance Metrics, Best Practices and QMS E...
Human resources management is a best management
Course Overview of the Course Titled.pptx
Organisational behaviour_ managerial applications of perception
The Plan: Save the Palestinian Nation Now
Human Resource Management | Introduction,Meaning and Definition
Chapter-3.pptx project life cycle presentation
The Sustainable Site: Boosting Productivity in Construction – Pipe Dream or P...
CISSP Domain 6: Security Assessment and Testing
Basics of Project Management for development of leadership skills in practice
Equity at the Helm_ Guiding Schools Through Inclusive Leadership by Dr.pdf
The Sustainable Site: Boosting Productivity in Construction – Pipe Dream or P...
The Untold Story of Swami Vijay Kumar Durai: Building PRS International
Chapter Three for international political
Human resources management -job perception concept
Project Management - Scope Management.ppt
FSC Building Trust in LGs august 8 2025.pptx
CISSP - Domain 7: Security Operations - InfoSec Institute
Ad

MRP Basics and calculation of MRP explotions

  • 2. MRP Material Requirements Planning (MRP)---a computerized information system developed specifically to aid in managing dependent demand and scheduling replenishment orders. 2 Other sources of demand Inventory transactions Inventory records Bills of materials Engineering and process designs Material requirements plan MRP explosion Authorized master production schedule
  • 3. MRP Input & Output 3 Data Files Purchasing data BOM Lead times (Item master file) Inventory data Master production schedule Material requirement planning programs (computer and software) Output Reports MRP by period report MRP by date report Planned order report Purchase advice Exception reportsi Order early or late or not needed Order quantity too small or too large
  • 4. Master Production Schedule (MPS) ■ Specifies what is to be made and when ■ The MPS is the result of the production planning process ■ MPS is established in terms of specific products ■ The MPS is quite often fixed or frozen in the near term part of the plan ■ The MPS is a statement of what is to be produced. 4
  • 5. Inventory record ■ Accurate inventory records are absolutely required for MRP (or any dependent demand system) to operate correctly ■ Generally MRP systems require 99% accuracy ■ Outstanding purchase orders must accurately reflect quantities and scheduled receipts 5
  • 6. Lead time ■ The time required to purchase, produce, or assemble an item ■ For production – the sum of the order, wait, move, setup, store, and run times ■ For purchased items – the time between the recognition of a need and the availability of the item for production 6
  • 7. Bill of Material (BOM) ■ List of components, ingredients, and materials needed to make a product – Provides product structure – items above a given level are called parents – items below a given level are called children – items may be both a parent and a child 7
  • 8. Pictorial example of a ladder back chair BOM Seat cushion Seat-frame boards Front legs A Ladder-back chair Back legs Leg supports Back slats 8
  • 9. Product structure example of the same item C (1) Seat subassembly D (2) Front legs B (1) Ladder-back subassembly E (4) Leg supports I (1) Seat cushion H (1) Seat frame G (4) Back slats F (2) Back legs J (4) Seat-frame boards A Ladder-back chair 9
  • 10. Block diagram of general example Item A B (2) C (3) D (2) E (2) E (2) F (2) D (2) G (1) 10
  • 11. The MRP process begins by determining gross requirements – The production schedule for the end item – 50 units of Item A in week 8 – Using the lead time for the item, determine the week in which the order should be released – a 1 week lead time means the order for 50 units should be released in week 7 – This step is often called “lead time offset” or “time phasing” 11
  • 12. Gross Requirements Plan 12 Week 1 2 3 4 5 6 7 8 Lead Time A. Required date 50 Order release date 50 1 week B. Required date 100 Order release date 100 2 weeks C. Required date 150 Order release date 150 1 week E. Required date 200 300 Order release date 200 300 2 weeks F. Required date 300 Order release date 300 3 weeks G. Required date 600 200 Order release date 600 200 1 week
  • 13. Gross Requirements Plan 13 Week 1 2 3 4 5 6 7 8 Lead Time A. Required date 50 Order release date 50 1 week B. Required date 100 Order release date 100 2 weeks C. Required date 150 Order release date 150 1 week E. Required date 200 300 Order release date 200 300 2 weeks F. Required date 300 Order release date 300 3 weeks G. Required date 600 200 Order release date 600 200 1 week G. Required date 300
  • 14. Gross Requirements Plan 14 Week 1 2 3 4 5 6 7 8 Lead Time A. Required date 50 Order release date 50 1 week B. Required date 100 Order release date 100 2 weeks C. Required date 150 Order release date 150 1 week E. Required date 200 300 Order release date 200 300 2 weeks F. Required date 300 Order release date 300 3 weeks G. Required date 600 200 Order release date 600 200 1 week G. Required date 300 Order release date 300 2
  • 17. Net Requirements Plan Continues 17
  • 18. MRP Management ■ MRP is a dynamic system ■ Facilitates re-planning when changes occur ■ System nervousness can result from too many changes ■ Time fences put limits on re-planning ■ Pegging links each item to its parent allowing effective analysis of changes ■ Adequate staffing and accurate records are pre-requisites to operational success 18

Editor's Notes

  • #18: FPO – Firm Planned Orders also help control re-planning, as well as allowing intentional over-rides.