Multitasking Exercise - switching cost
• The three projects are as follows:
Project 1—Write the letters A to J in the first column.
Project 2—Write the numbers 1 to 10 in the middle column.
Project 3—Write the Roman Numerals I to X in the third column.
The end result is three columns filled like this:
A | 1 | I
B | 2 | II
Etc.
• Exercise:
• Do these projects by multitasking (1 row at a time)
• Do these projects by not multitasking (1 column at a time)
http://www.stickyminds.com/eNewsletters/Iterations/Default.aspx?eNewsletter=200805#powerbookreview
Clarke.Ching@ge.com
Multitasking Exercise - switching cost is only a tiny bit of
the problem
Clarke.Ching@ge.com
Multi-tasking is evil - Eliminate Multitasking
A BP1 C D E F G H I J
P2
P3
A B C D E F G H I J
A B C D E F G H I J
20 weeks
20 weeks
20 weeks
£ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £
£ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £
£ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £
Cash Flow:
Three projects - no sharing
Each task takes 2 weeks to complete
x3 x3 x3Resources:
Clarke.Ching@ge.com
When resources are shared across projects?
• Too many projects
• too many priorities
• Too many bosses
• Therefore:
• Staff must switch between projects
• i.e. multitask
x1 x1 x1Resources:
Clarke.Ching@ge.com
Scenario: multitasking
A
x1 x1 x1
B
Resources:
P1 C D E F G H I J
P2
P3
A B C D E F G H I J
A B C D E F G H I J
48 weeks
50 weeks
52 weeks
£ £ £ £ £ £ £ £ £
£ £ £ £ £ £ £ £
£ £ £ £ £ £ £
Cash Flow:
Clarke.Ching@ge.com
Scenario: not multitasking
A
x1 x1 x1
B
Resources:
P1 C D E F G H I J
P2
P3
A B C D E F G H I J
A B C D E F G H I J
20 weeks
28 weeks
36 weeks
£ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £
£ £ £ £ £ £ £ £ £ £ £ £ £ £ £
£ £ £ £ £ £ £ £ £ £ £ £
Cash Flow:
Clarke.Ching@ge.com
Compare
• Each project is shorter
• All projects finished sooner => capacity increased
• Cash flow earlier; faster 2 market, profits up, up, up
• Organisation evolves faster
A BP1 C D E F G H I J
P2
P3
A B C D E F G H I J
A B C D E F G H I J
20 weeks
28 weeks
36 weeks
A BP1 C D E F G H I J
P2
P3
A B C D E F G H I J
A B C D E F G H I J
48 weeks
50 weeks
52 weeks
Multitasking
No Multitasking

More Related Content

PDF
Does reporting takes lots of time
PPTX
The Power of the Junior
PPT
Multitasking - The Good The Bad and The Ugly
PDF
Project Cage Match: Multitasking vs Critical Chain
PDF
What is the actual meaning of
PPT
Time Management
PPTX
Allocating resources
PDF
Limiting WIP - Global Scrum Gathering Denver 2022
Does reporting takes lots of time
The Power of the Junior
Multitasking - The Good The Bad and The Ugly
Project Cage Match: Multitasking vs Critical Chain
What is the actual meaning of
Time Management
Allocating resources
Limiting WIP - Global Scrum Gathering Denver 2022

Similar to Multitasking is evil (20)

PDF
Limiting WIP @ SM Summit_5.17.22
PPTX
Multitasking group ppt
PPTX
OB presentation on Multitasking from the concept of Motivation
PPTX
Multiple project management By shehzad khan yousafzai
PPTX
Management, Multitasking, Efficiency
PDF
Limiting WIP: Doing Less to Do More
DOCX
Finding Technological Balance in International Education
PPTX
Toughest Things First & Normative Multi-Tasking - Aditya Yadav
PPT
Resource-Allocation.ppt
PPTX
Skills matter agile multitasking 2010
PPTX
Managing Multiple Priorities
PDF
Download my FREE Time Management Presentation
PDF
Shady Hollow Tasks
PPTX
TIME MANAGEMENT.pptx
PPTX
Symphony flow - The Effective Engineer
PDF
Week12 slides
PPT
Software project management
PPTX
Multi tasking rev 1
PPT
Navigating the Chaos - Personal Effectiveness [NSW STATECON 2014]
Limiting WIP @ SM Summit_5.17.22
Multitasking group ppt
OB presentation on Multitasking from the concept of Motivation
Multiple project management By shehzad khan yousafzai
Management, Multitasking, Efficiency
Limiting WIP: Doing Less to Do More
Finding Technological Balance in International Education
Toughest Things First & Normative Multi-Tasking - Aditya Yadav
Resource-Allocation.ppt
Skills matter agile multitasking 2010
Managing Multiple Priorities
Download my FREE Time Management Presentation
Shady Hollow Tasks
TIME MANAGEMENT.pptx
Symphony flow - The Effective Engineer
Week12 slides
Software project management
Multi tasking rev 1
Navigating the Chaos - Personal Effectiveness [NSW STATECON 2014]
Ad

Multitasking is evil

  • 1. Clarke.Ching@ge.com Multitasking Exercise - switching cost • The three projects are as follows: Project 1—Write the letters A to J in the first column. Project 2—Write the numbers 1 to 10 in the middle column. Project 3—Write the Roman Numerals I to X in the third column. The end result is three columns filled like this: A | 1 | I B | 2 | II Etc. • Exercise: • Do these projects by multitasking (1 row at a time) • Do these projects by not multitasking (1 column at a time) http://www.stickyminds.com/eNewsletters/Iterations/Default.aspx?eNewsletter=200805#powerbookreview
  • 2. Clarke.Ching@ge.com Multitasking Exercise - switching cost is only a tiny bit of the problem
  • 3. Clarke.Ching@ge.com Multi-tasking is evil - Eliminate Multitasking A BP1 C D E F G H I J P2 P3 A B C D E F G H I J A B C D E F G H I J 20 weeks 20 weeks 20 weeks £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ Cash Flow: Three projects - no sharing Each task takes 2 weeks to complete x3 x3 x3Resources:
  • 4. Clarke.Ching@ge.com When resources are shared across projects? • Too many projects • too many priorities • Too many bosses • Therefore: • Staff must switch between projects • i.e. multitask x1 x1 x1Resources:
  • 5. Clarke.Ching@ge.com Scenario: multitasking A x1 x1 x1 B Resources: P1 C D E F G H I J P2 P3 A B C D E F G H I J A B C D E F G H I J 48 weeks 50 weeks 52 weeks £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ Cash Flow:
  • 6. Clarke.Ching@ge.com Scenario: not multitasking A x1 x1 x1 B Resources: P1 C D E F G H I J P2 P3 A B C D E F G H I J A B C D E F G H I J 20 weeks 28 weeks 36 weeks £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ Cash Flow:
  • 7. Clarke.Ching@ge.com Compare • Each project is shorter • All projects finished sooner => capacity increased • Cash flow earlier; faster 2 market, profits up, up, up • Organisation evolves faster A BP1 C D E F G H I J P2 P3 A B C D E F G H I J A B C D E F G H I J 20 weeks 28 weeks 36 weeks A BP1 C D E F G H I J P2 P3 A B C D E F G H I J A B C D E F G H I J 48 weeks 50 weeks 52 weeks Multitasking No Multitasking