OPEN CIRCUIT & SHORT CIRCUIT 
TEST ON TRANSFORMER 
PREPAIRED BY: 
MANAVAR MILAN
INTRODUCTION 
• Necessity of testing 
• Open circuit test 
• Short circuit test 
• Advantages 
• Application
NECESSITY OF TESTING 
• In transformer and other equipment have 
input and output. Hence how to we find the 
performance of transformer and other 
equipment…..? 
• We have a solution even we will find the loss 
of transformer so we can easily find the all 
parameters of transformer like, we can find 
iron loss, cu loss, impedance, no load current, 
short circuit current and efficiency.
OPEN CIRCUIT TEST
HOW TO MEASURE O.C. TEST 
1. To connect Wattmeter in primary side. 
2. To connect Ammeter in series of phase. 
3. To connect Voltmeter in parallel of primary 
side. 
4. We will open the Secondary side. 
5. We will give the supply primary side for the 
measurement of iron losses.
• The purpose of this test is to find the no-load loss 
or core loss. 
• A wattmeter, voltmeter and an ammeter are 
connected in low voltage side. 
• Secondary side of transformer we will keep open. 
• We give the normal voltage applied to the 
primary, normal flux will be set up in the core, 
hence normal iron losses will occur which are 
recorded by the wattmeter.
• As the primary no-load current is measured 
by ammeter and its value is small, Cu-loss is 
negligibly small in primary and nil in 
secondary (it being open). 
• Hence, the wattmeter reading represents 
practically the CORE LOSS under no-load 
condition.
• Sometimes a high resistance voltmeter is 
connected across the secondary. The reading 
of the voltmeter gives the induced e.m.f. in 
the secondary winding.
SHORT CIRCUIT TEST
HOW TO MEASURE S.C. TEST 
1. To connect the wattmeter primary side 
2. To connect the Ammeter in series of primary 
side 
3. To connect the Voltmeter in parallel of 
primary side 
4. Short the secondary side using thick 
conductor 
5. Now give the small voltage supply for the 
measurement of Cu-losses.
• A wattmeter, voltmeter and an ammeter are 
connected in high voltage side. 
• The low voltage side of transformer is short 
circuited. 
• The applied voltage is a small percentage of the 
normal voltage. 
• Hence the core losses are very small with the 
result of the wattmeter reading represent the 
full-load CU-LOSS or loss for the whole 
transformer .
ADVANTAGES 
• No require for extra load 
• This test are very economical and convenient, 
because they furnish the required information 
without actually loading the transformer.
APPLICATION 
• By using open circuit test we can measure the 
loss of no-load losses means that iron losses. 
• By using short circuit test we can measure the 
loss of full-load losses means that Cu-losses. 
• We can find the efficiency by using of iron 
losses and cu-losses.
THANK YOU

More Related Content

PPT
32.open circuit and short circuit test .ppt
PPT
Sc and oc test on transformer
PPTX
Transformer ppt.
PPTX
Open circuit and Short circuit test on transformer
PPT
Power transformer
PDF
Presentation on Transformer,it's working principle
PPT
Auto transformer
PPTX
Transformer
32.open circuit and short circuit test .ppt
Sc and oc test on transformer
Transformer ppt.
Open circuit and Short circuit test on transformer
Power transformer
Presentation on Transformer,it's working principle
Auto transformer
Transformer

What's hot (20)

PDF
Three phase-circuits
PPT
Testing of dc motor
PPTX
Armature windings
PDF
Three phase Induction Motor (Construction and working Principle)
PPTX
electrical machines
PDF
Power electronics Phase Controlled Rectifiers - SCR
PPTX
Synchronous machines
PPTX
synchronous motor for presentation
PPT
Single phase induction motor
PPTX
Dc machines (Generator & Motor)
PDF
3 ph induction motor ppt
PPTX
PPTX
Motor Test (Induction motor)
PPTX
Induction motor
PPTX
Presentation on induction motor
PPTX
PDF
DC MOTORS-UNIT-II.pdf
PDF
Power Electronics Chopper (dc – dc converter)
PDF
Transformer single phase and three phase
PDF
Moving iron (MI) instruments
Three phase-circuits
Testing of dc motor
Armature windings
Three phase Induction Motor (Construction and working Principle)
electrical machines
Power electronics Phase Controlled Rectifiers - SCR
Synchronous machines
synchronous motor for presentation
Single phase induction motor
Dc machines (Generator & Motor)
3 ph induction motor ppt
Motor Test (Induction motor)
Induction motor
Presentation on induction motor
DC MOTORS-UNIT-II.pdf
Power Electronics Chopper (dc – dc converter)
Transformer single phase and three phase
Moving iron (MI) instruments
Ad

Viewers also liked (8)

PPT
Lecture 8 bjt_1
PPT
EE201 -Chapter 6
PDF
Testing of transformer
PPT
EE201 - Chapter 3 (BJT)
PPT
EE201 -Chapter 4
PPT
TRANSISTORS
PPT
3.bipolar junction transistor (bjt)
PPTX
Transistors ppt by behin
Lecture 8 bjt_1
EE201 -Chapter 6
Testing of transformer
EE201 - Chapter 3 (BJT)
EE201 -Chapter 4
TRANSISTORS
3.bipolar junction transistor (bjt)
Transistors ppt by behin
Ad

Similar to open circuit and short circuit test on transformer (20)

PPTX
VIKAS short circuit AND OC TEST PPT.pptx
PPTX
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
PPTX
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
PDF
Transformer 2
PDF
Transformer 2
PPTX
Akshay kumar
DOCX
PPTX
open circuit and short circuit test on transformers.pptx
DOCX
Electrical Machines
DOC
Ac machines-lab-manual
PPTX
Transformer: Open Circuit and Short Circuit Test
PPTX
Transformers.pptx
PDF
Transformer Course Lab.pdf
PDF
EN_lab1.pdf
PDF
PPTX
Open circuit and Short circuit Test Presentaion
PPT
6. Factory Acceptance Tests transformer.ppt
PPTX
Single and 3 phase transformer
PPTX
A brief presentation on Electrical Machines
VIKAS short circuit AND OC TEST PPT.pptx
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
Transformer 2
Transformer 2
Akshay kumar
open circuit and short circuit test on transformers.pptx
Electrical Machines
Ac machines-lab-manual
Transformer: Open Circuit and Short Circuit Test
Transformers.pptx
Transformer Course Lab.pdf
EN_lab1.pdf
Open circuit and Short circuit Test Presentaion
6. Factory Acceptance Tests transformer.ppt
Single and 3 phase transformer
A brief presentation on Electrical Machines

Recently uploaded (20)

PDF
Well-logging-methods_new................
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PDF
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
PDF
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
DOCX
573137875-Attendance-Management-System-original
PPTX
Welding lecture in detail for understanding
PPTX
Lecture Notes Electrical Wiring System Components
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPT
Mechanical Engineering MATERIALS Selection
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PPTX
additive manufacturing of ss316l using mig welding
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PPTX
web development for engineering and engineering
PPTX
Sustainable Sites - Green Building Construction
PPTX
Internet of Things (IOT) - A guide to understanding
PPTX
Construction Project Organization Group 2.pptx
Well-logging-methods_new................
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
573137875-Attendance-Management-System-original
Welding lecture in detail for understanding
Lecture Notes Electrical Wiring System Components
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
Automation-in-Manufacturing-Chapter-Introduction.pdf
Mechanical Engineering MATERIALS Selection
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
additive manufacturing of ss316l using mig welding
CYBER-CRIMES AND SECURITY A guide to understanding
web development for engineering and engineering
Sustainable Sites - Green Building Construction
Internet of Things (IOT) - A guide to understanding
Construction Project Organization Group 2.pptx

open circuit and short circuit test on transformer

  • 1. OPEN CIRCUIT & SHORT CIRCUIT TEST ON TRANSFORMER PREPAIRED BY: MANAVAR MILAN
  • 2. INTRODUCTION • Necessity of testing • Open circuit test • Short circuit test • Advantages • Application
  • 3. NECESSITY OF TESTING • In transformer and other equipment have input and output. Hence how to we find the performance of transformer and other equipment…..? • We have a solution even we will find the loss of transformer so we can easily find the all parameters of transformer like, we can find iron loss, cu loss, impedance, no load current, short circuit current and efficiency.
  • 5. HOW TO MEASURE O.C. TEST 1. To connect Wattmeter in primary side. 2. To connect Ammeter in series of phase. 3. To connect Voltmeter in parallel of primary side. 4. We will open the Secondary side. 5. We will give the supply primary side for the measurement of iron losses.
  • 6. • The purpose of this test is to find the no-load loss or core loss. • A wattmeter, voltmeter and an ammeter are connected in low voltage side. • Secondary side of transformer we will keep open. • We give the normal voltage applied to the primary, normal flux will be set up in the core, hence normal iron losses will occur which are recorded by the wattmeter.
  • 7. • As the primary no-load current is measured by ammeter and its value is small, Cu-loss is negligibly small in primary and nil in secondary (it being open). • Hence, the wattmeter reading represents practically the CORE LOSS under no-load condition.
  • 8. • Sometimes a high resistance voltmeter is connected across the secondary. The reading of the voltmeter gives the induced e.m.f. in the secondary winding.
  • 10. HOW TO MEASURE S.C. TEST 1. To connect the wattmeter primary side 2. To connect the Ammeter in series of primary side 3. To connect the Voltmeter in parallel of primary side 4. Short the secondary side using thick conductor 5. Now give the small voltage supply for the measurement of Cu-losses.
  • 11. • A wattmeter, voltmeter and an ammeter are connected in high voltage side. • The low voltage side of transformer is short circuited. • The applied voltage is a small percentage of the normal voltage. • Hence the core losses are very small with the result of the wattmeter reading represent the full-load CU-LOSS or loss for the whole transformer .
  • 12. ADVANTAGES • No require for extra load • This test are very economical and convenient, because they furnish the required information without actually loading the transformer.
  • 13. APPLICATION • By using open circuit test we can measure the loss of no-load losses means that iron losses. • By using short circuit test we can measure the loss of full-load losses means that Cu-losses. • We can find the efficiency by using of iron losses and cu-losses.