Parallel Machines

In this section we consider scheduling problems in which more than one machine
is available for processing the jobs. It does not matter which machine a job is
assigned to, but it cannot be processed on more than one machine at the same time.
Such machines are known as parallel processors.

tj,k is the time required of machine k by job j. If tj,k1 = tj,k2 = tj for all machines k1 and
k2, then they are said to be identical processors. If there exists a constant 0 < Rk ≤ 1
associated with each machine k such that tj,k = tj / Rk for all jobs j, then the
machines are known as uniform processors. If no such processing rate can be
associated with each machine, the machines are known as independent processors.
The rest of this section will consider the special case of parallel identical
processors, in which all Rk = 1.

Minimizing Makespan

Makespan is the total time required to process a set of jobs. In the single machine
model, this was simply the sum of all processing and idle time, while in the
multiple machine model it is the maximum value of this quantity over all
machines.
As a job can be processed on at most one machine at a time, we have that




M ≥ M1 = max{tj : ∀ jobs j},




M ≥ M2 = ∑{tj/m : ∀ jobs j}.




If preempt-resume is allowed, the following, known as McNaughton's Algorithm
[McNaughton, R. Scheduling with deadlines and loss functions. Management
Science 6.1(1959)] constructs a schedule which achieves one of these bounds and
thus is optimal.

Determine M = max{M1 , M2}.
Arrange the jobs in any arbitrary order.
Assign the first M units of time to machine 1, the next M units to machine 2, and
so on until all jobs are scheduled.

Note that if the division occurs part of the way through a job, then that job is
assigned to two machines, its time being preempted on the larger numbered
machine and resumed on the other.
The algorithm may be proven by showing that the resulting schedule is feasible
(i.e. no job is scheduled on two machines at the same time, which is guaranteed by
M1) and that its makespan is no greater than the larger of M1 and M2 (which is
guaranteed by M2).

If jobs may not be preempted, no simple algorithm to find an optimal schedule is
known. However, the following heuristic LPT dispatching rule may be used to find
a reasonable but not necessarily optimal schedule.

Whenever a machine is available, schedule a job requiring the greatest amount of
time.

Minimizing Mean Flowtime

Let nk be the number of jobs assigned to machine k, and let tj,k be the time required
of machine k by job j. Assuming all jobs are initially available, the mean flowtime




of the schedule is ∑∑{tj,k (nk+1−j)/n : ∀ jobs j, ∀ machines k},




The following algorithm may be used to schedule a set of n jobs on m parallel
identical processors, minimizing the mean flowtime.

If n ≤ m, schedule all jobs on different machines. Otherwise schedule the smallest
n−m jobs optimally followed by the largest m jobs all on different machines.
we know that in an optimal schedule the jobs on each machine must be in SPT
order, a condition clearly satisfied by this algorithm. Now suppose some schedule
does not have the largest m jobs on different machines. Then one machine, say m1,
has none of the largest m jobs, while another machine, say m2, has at least two of
them, say j1 and j2. If i is the last job scheduled on m1, then ti < tj1 ≤ tj2. If we
interchange the scheduled positions of i and j1, then the total flowtime on m1 is
increased by tj1 − ti, while the total flowtime on m2 is decreased by 2 (tj1 − ti) as
both i and j2 finish that much earlier. Thus there is a net decrease in the total
flowtime and the original schedule must not be optimal, thus proving that any
optimal schedule must have the largest m jobs on different machines. Now suppose
the last job on each of two different machines are interchanged. The change in total
flowtime on one machine will be equal and opposite to that on the other machine,
and so it does not matter in which order the largest m jobs are assigned to different
machines.

As there is no restriction as to which machines the jobs must be placed on, this
algorithm can be used to generate many (in fact all) optimal schedules. The
following SPT dispatching rule may also be used to find some, but not all, optimal
schedules.Whenever a machine is available, schedule a job requiring the smallest
amount of time.Notice that this is the exact opposite of the heuristic for minimizing
makespan.

Minimizing Makespan with Precedence Constraints

No efficient algorithm is known for the general problem of minimizing makespan
with precedence constraints, although some are known for special cases.
If all processing times are constant, say 1, and the precedence constraints form an
assembly forest, then the following, known as Hu's algorithm [Hu, T.C. Parallel
sequencing and assembly line problems. Operations Research 9.6(1961)] will
produce an optimal schedule.

Assign a label Xj to each node j such that
  Xj = 1 if j is a terminal job, or
  Xj = 1 + Xi where i is the direct successor of j.
Until all jobs are scheduled, if there are fewer than m jobs with no unscheduled
predecessors then schedule the remaining machines with one unit of idle time each,
otherwise schedule the m jobs with largest labels and no unscheduled predecessors
to different machines.

If preemption is allowed, the following, known as the Muntz-Coffman algorithm
[Muntz, R.R.; Coffman, E. Optimal preemptive scheduling on two-processor
systems. IEEE Transactions on Computers 18.11(1969)] may be used with
arbitrary precedence constraints, although the solution may be suboptimal for the
case of more than two machines.

Assign a label Xj to each job j such that
 Xj = 1 if j has no successors, and
 Xj = 1 + max{ Xi : i ← j }.
Let K = max{ Xj }.
Let Sk = { Xj : Xj = k }.
For k = K, K−1, K−2, ... ,1 if |Sk| <m, try to complete Sk by adding jobs without
unscheduled predecessors, choosing those with largest labels first.
Schedule Sk using McNaughton's algorithm.
The previous two algorithms may also be used to schedule jobs with unequal
processing times if preemption is allowed and if the processing times are
commensurable, by simply subdividing each job j into a string of tj jobs each with
unit processing time. The resulting set of jobs may be quite large however.

If processor sharing is allowed, and the precedence constraints form an assembly
tree, then the following modified version of the Muntz-Coffman algorithm [Muntz,
R.R.; Coffman, E. Preemptive scheduling of real-time tasks on multiprocessor
systems. JACM 17.2(1970)] may be used to minimize makespan of a set of jobs
with arbitrary processing times on any number of machines.

Assign a label Xj to each job j such that
 Xj = tj if j has no successors, and
 Xj = tj + max{ Xi : i ← j }.
Until all jobs are completed, use the following dispatching rule, the first decision
point being the availability of all m machines.
 Set all Rj = 0.
 Set m' = m, the number of available machines.
 While m' > 0,




   Let S = { j : Xj ≥ Xi ∀ jobs i }.
Set Rj = min{ 1, m'/|S| } ∀ j ∈ S.


   Reduce m' by |S|.



Update the labels on each job by reducing Xj by Rj for each unit of scheduled time,
until either some job is completed in which case it is removed from further
consideration, or until there are two jobs i and j such that Ri < Rj and Xi ≥ Xj.

The resulting schedule may be converted into a schedule with identical makespan
but without processor sharing by applying McNaughton's algorithm to each time
interval delimited by changes in the set of jobs with positive R.

More Related Content

PDF
Presentation_Parallel GRASP algorithm for job shop scheduling
PDF
Approximation Algorithms Part Two: More Constant factor approximations
PPT
Control position for servo motor
PPTX
INTERRUPT LATENCY AND RESPONSE OF THE TASK
PDF
Round Robin Algorithm in Operating System
PPTX
QUANTUM COMP 22
PDF
The Use of Markov Model in Continuous Time for Prediction of Rainfall for Cro...
PDF
Quantum Computing and Quantum Supremacy at Google
Presentation_Parallel GRASP algorithm for job shop scheduling
Approximation Algorithms Part Two: More Constant factor approximations
Control position for servo motor
INTERRUPT LATENCY AND RESPONSE OF THE TASK
Round Robin Algorithm in Operating System
QUANTUM COMP 22
The Use of Markov Model in Continuous Time for Prediction of Rainfall for Cro...
Quantum Computing and Quantum Supremacy at Google

What's hot (11)

PDF
R0260950100
PPTX
Quantum Computing
PPTX
Introduction to Quantum Computing with Qiskit
PPTX
Shor’s algorithm the ppt
PPT
Randomizing quicksort algorith with example
PPTX
Comparing Different Job Scheduling Heuristics
PPTX
Quantum Computing Fundamentals via OO
PDF
Introsort or introspective sort
ODP
Beyond TrueTime
PPTX
Quantum Machine Learning for IBM AI
PDF
Quantum computation: past-now-future - 2021-06-19
R0260950100
Quantum Computing
Introduction to Quantum Computing with Qiskit
Shor’s algorithm the ppt
Randomizing quicksort algorith with example
Comparing Different Job Scheduling Heuristics
Quantum Computing Fundamentals via OO
Introsort or introspective sort
Beyond TrueTime
Quantum Machine Learning for IBM AI
Quantum computation: past-now-future - 2021-06-19
Ad

Viewers also liked (7)

PPT
PPTX
Priority queuing
PPTX
ScaleJoin: a Deterministic, Disjoint-Parallel and Skew-Resilient Stream Join
PPTX
Event Scheduling
PPTX
Scheduling Algorithms
PDF
Oleksandr Frei and Murat Apishev - Parallel Non-blocking Deterministic Algori...
PPT
Parallel computing
Priority queuing
ScaleJoin: a Deterministic, Disjoint-Parallel and Skew-Resilient Stream Join
Event Scheduling
Scheduling Algorithms
Oleksandr Frei and Murat Apishev - Parallel Non-blocking Deterministic Algori...
Parallel computing
Ad

Similar to Parallel machines (20)

PPTX
Multiprocessor Real-Time Scheduling.pptx
PPTX
Flowshop scheduling
PDF
SWARM INTELLIGENCE SCHEDULING OF SOFT REAL-TIME TASKS IN HETEROGENEOUS MULTIP...
PDF
An efficient simulated annealing algorithm for a No-Wait Two Stage Flexible F...
PDF
An efficient simulated annealing algorithm for a No-Wait Two Stage Flexible F...
PPTX
Sequencing and shedulding problems for Operations management
PDF
Bounded ant colony algorithm for task Allocation on a network of homogeneous ...
PDF
Eliiyi working time
PDF
11.bicriteria in constrained n x 0003www.iiste.org call for paper flow shop t...
PDF
Bicriteria in constrained n x 3 flow shop to minimize the rental cost, setup ...
PPT
multiprocessor real_ time scheduling.ppt
PDF
AN ANT COLONY OPTIMIZATION ALGORITHM FOR JOB SHOP SCHEDULING PROBLEM
PDF
AN APPROXIMATION ALGORITHM FOR THE GENERALIZED ASSIGNMENT PROBLEM
PDF
N job m machine.pdf OR job Sequencing problems
PDF
Bicriteria in n x 3 flow shop scheduling under specified rental policy
PDF
Exam100412
PDF
Exam100118
PDF
Sequencing model
PDF
C017611624
PDF
A Hybrid Evolutionary Optimization Model for Solving Job Shop Scheduling Prob...
Multiprocessor Real-Time Scheduling.pptx
Flowshop scheduling
SWARM INTELLIGENCE SCHEDULING OF SOFT REAL-TIME TASKS IN HETEROGENEOUS MULTIP...
An efficient simulated annealing algorithm for a No-Wait Two Stage Flexible F...
An efficient simulated annealing algorithm for a No-Wait Two Stage Flexible F...
Sequencing and shedulding problems for Operations management
Bounded ant colony algorithm for task Allocation on a network of homogeneous ...
Eliiyi working time
11.bicriteria in constrained n x 0003www.iiste.org call for paper flow shop t...
Bicriteria in constrained n x 3 flow shop to minimize the rental cost, setup ...
multiprocessor real_ time scheduling.ppt
AN ANT COLONY OPTIMIZATION ALGORITHM FOR JOB SHOP SCHEDULING PROBLEM
AN APPROXIMATION ALGORITHM FOR THE GENERALIZED ASSIGNMENT PROBLEM
N job m machine.pdf OR job Sequencing problems
Bicriteria in n x 3 flow shop scheduling under specified rental policy
Exam100412
Exam100118
Sequencing model
C017611624
A Hybrid Evolutionary Optimization Model for Solving Job Shop Scheduling Prob...

Recently uploaded (20)

PPTX
Job-opportunities lecture about it skills
PPTX
ESD MODULE-5hdbdhbdbdbdbbdbdbbdndbdbdbdbbdbd
PPTX
Your Guide to a Winning Interview Aug 2025.
PPT
APPROACH TO DEVELOPMENTALlllllllllllllllll
PPTX
Prokaryotes v Eukaryotes PowerPoint.pptx
PDF
Daisia Frank: Strategy-Driven Real Estate with Heart.pdf
PPTX
OnePlus 13R – ⚡ All-Rounder King Performance: Snapdragon 8 Gen 3 – same as iQ...
DOC
field study for teachers graduating samplr
PPTX
cse couse aefrfrqewrbqwrgbqgvq2w3vqbvq23rbgw3rnw345
PPTX
DPT-MAY24.pptx for review and ucploading
PPTX
chapter 3_bem.pptxKLJLKJLKJLKJKJKLJKJKJKHJH
PDF
Understanding the Rhetorical Situation Presentation in Blue Orange Muted Il_2...
PPT
Gsisgdkddkvdgjsjdvdbdbdbdghjkhgcvvkkfcxxfg
PPTX
Definition and Relation of Food Science( Lecture1).pptx
PDF
MCQ Practice CBT OL Official Language 1.pptx.pdf
PPTX
Principles of Inheritance and variation class 12.pptx
PPTX
Overview Planner of Soft Skills in a single ppt
PPTX
PE3-WEEK-3sdsadsadasdadadwadwdsdddddd.pptx
PDF
Prostaglandin E2.pdf orthoodontics op kharbanda
PPTX
_+✅+JANUARY+2025+MONTHLY+CA.pptx current affairs
Job-opportunities lecture about it skills
ESD MODULE-5hdbdhbdbdbdbbdbdbbdndbdbdbdbbdbd
Your Guide to a Winning Interview Aug 2025.
APPROACH TO DEVELOPMENTALlllllllllllllllll
Prokaryotes v Eukaryotes PowerPoint.pptx
Daisia Frank: Strategy-Driven Real Estate with Heart.pdf
OnePlus 13R – ⚡ All-Rounder King Performance: Snapdragon 8 Gen 3 – same as iQ...
field study for teachers graduating samplr
cse couse aefrfrqewrbqwrgbqgvq2w3vqbvq23rbgw3rnw345
DPT-MAY24.pptx for review and ucploading
chapter 3_bem.pptxKLJLKJLKJLKJKJKLJKJKJKHJH
Understanding the Rhetorical Situation Presentation in Blue Orange Muted Il_2...
Gsisgdkddkvdgjsjdvdbdbdbdghjkhgcvvkkfcxxfg
Definition and Relation of Food Science( Lecture1).pptx
MCQ Practice CBT OL Official Language 1.pptx.pdf
Principles of Inheritance and variation class 12.pptx
Overview Planner of Soft Skills in a single ppt
PE3-WEEK-3sdsadsadasdadadwadwdsdddddd.pptx
Prostaglandin E2.pdf orthoodontics op kharbanda
_+✅+JANUARY+2025+MONTHLY+CA.pptx current affairs

Parallel machines

  • 1. Parallel Machines In this section we consider scheduling problems in which more than one machine is available for processing the jobs. It does not matter which machine a job is assigned to, but it cannot be processed on more than one machine at the same time. Such machines are known as parallel processors. tj,k is the time required of machine k by job j. If tj,k1 = tj,k2 = tj for all machines k1 and k2, then they are said to be identical processors. If there exists a constant 0 < Rk ≤ 1 associated with each machine k such that tj,k = tj / Rk for all jobs j, then the machines are known as uniform processors. If no such processing rate can be associated with each machine, the machines are known as independent processors. The rest of this section will consider the special case of parallel identical processors, in which all Rk = 1. Minimizing Makespan Makespan is the total time required to process a set of jobs. In the single machine model, this was simply the sum of all processing and idle time, while in the multiple machine model it is the maximum value of this quantity over all machines.
  • 2. As a job can be processed on at most one machine at a time, we have that M ≥ M1 = max{tj : ∀ jobs j}, M ≥ M2 = ∑{tj/m : ∀ jobs j}. If preempt-resume is allowed, the following, known as McNaughton's Algorithm [McNaughton, R. Scheduling with deadlines and loss functions. Management Science 6.1(1959)] constructs a schedule which achieves one of these bounds and thus is optimal. Determine M = max{M1 , M2}. Arrange the jobs in any arbitrary order. Assign the first M units of time to machine 1, the next M units to machine 2, and so on until all jobs are scheduled. Note that if the division occurs part of the way through a job, then that job is assigned to two machines, its time being preempted on the larger numbered machine and resumed on the other.
  • 3. The algorithm may be proven by showing that the resulting schedule is feasible (i.e. no job is scheduled on two machines at the same time, which is guaranteed by M1) and that its makespan is no greater than the larger of M1 and M2 (which is guaranteed by M2). If jobs may not be preempted, no simple algorithm to find an optimal schedule is known. However, the following heuristic LPT dispatching rule may be used to find a reasonable but not necessarily optimal schedule. Whenever a machine is available, schedule a job requiring the greatest amount of time. Minimizing Mean Flowtime Let nk be the number of jobs assigned to machine k, and let tj,k be the time required of machine k by job j. Assuming all jobs are initially available, the mean flowtime of the schedule is ∑∑{tj,k (nk+1−j)/n : ∀ jobs j, ∀ machines k}, The following algorithm may be used to schedule a set of n jobs on m parallel identical processors, minimizing the mean flowtime. If n ≤ m, schedule all jobs on different machines. Otherwise schedule the smallest n−m jobs optimally followed by the largest m jobs all on different machines.
  • 4. we know that in an optimal schedule the jobs on each machine must be in SPT order, a condition clearly satisfied by this algorithm. Now suppose some schedule does not have the largest m jobs on different machines. Then one machine, say m1, has none of the largest m jobs, while another machine, say m2, has at least two of them, say j1 and j2. If i is the last job scheduled on m1, then ti < tj1 ≤ tj2. If we interchange the scheduled positions of i and j1, then the total flowtime on m1 is increased by tj1 − ti, while the total flowtime on m2 is decreased by 2 (tj1 − ti) as both i and j2 finish that much earlier. Thus there is a net decrease in the total flowtime and the original schedule must not be optimal, thus proving that any optimal schedule must have the largest m jobs on different machines. Now suppose the last job on each of two different machines are interchanged. The change in total flowtime on one machine will be equal and opposite to that on the other machine, and so it does not matter in which order the largest m jobs are assigned to different machines. As there is no restriction as to which machines the jobs must be placed on, this algorithm can be used to generate many (in fact all) optimal schedules. The following SPT dispatching rule may also be used to find some, but not all, optimal schedules.Whenever a machine is available, schedule a job requiring the smallest amount of time.Notice that this is the exact opposite of the heuristic for minimizing makespan. Minimizing Makespan with Precedence Constraints No efficient algorithm is known for the general problem of minimizing makespan with precedence constraints, although some are known for special cases.
  • 5. If all processing times are constant, say 1, and the precedence constraints form an assembly forest, then the following, known as Hu's algorithm [Hu, T.C. Parallel sequencing and assembly line problems. Operations Research 9.6(1961)] will produce an optimal schedule. Assign a label Xj to each node j such that Xj = 1 if j is a terminal job, or Xj = 1 + Xi where i is the direct successor of j. Until all jobs are scheduled, if there are fewer than m jobs with no unscheduled predecessors then schedule the remaining machines with one unit of idle time each, otherwise schedule the m jobs with largest labels and no unscheduled predecessors to different machines. If preemption is allowed, the following, known as the Muntz-Coffman algorithm [Muntz, R.R.; Coffman, E. Optimal preemptive scheduling on two-processor systems. IEEE Transactions on Computers 18.11(1969)] may be used with arbitrary precedence constraints, although the solution may be suboptimal for the case of more than two machines. Assign a label Xj to each job j such that Xj = 1 if j has no successors, and Xj = 1 + max{ Xi : i ← j }. Let K = max{ Xj }. Let Sk = { Xj : Xj = k }. For k = K, K−1, K−2, ... ,1 if |Sk| <m, try to complete Sk by adding jobs without unscheduled predecessors, choosing those with largest labels first. Schedule Sk using McNaughton's algorithm.
  • 6. The previous two algorithms may also be used to schedule jobs with unequal processing times if preemption is allowed and if the processing times are commensurable, by simply subdividing each job j into a string of tj jobs each with unit processing time. The resulting set of jobs may be quite large however. If processor sharing is allowed, and the precedence constraints form an assembly tree, then the following modified version of the Muntz-Coffman algorithm [Muntz, R.R.; Coffman, E. Preemptive scheduling of real-time tasks on multiprocessor systems. JACM 17.2(1970)] may be used to minimize makespan of a set of jobs with arbitrary processing times on any number of machines. Assign a label Xj to each job j such that Xj = tj if j has no successors, and Xj = tj + max{ Xi : i ← j }. Until all jobs are completed, use the following dispatching rule, the first decision point being the availability of all m machines. Set all Rj = 0. Set m' = m, the number of available machines. While m' > 0, Let S = { j : Xj ≥ Xi ∀ jobs i }.
  • 7. Set Rj = min{ 1, m'/|S| } ∀ j ∈ S. Reduce m' by |S|. Update the labels on each job by reducing Xj by Rj for each unit of scheduled time, until either some job is completed in which case it is removed from further consideration, or until there are two jobs i and j such that Ri < Rj and Xi ≥ Xj. The resulting schedule may be converted into a schedule with identical makespan but without processor sharing by applying McNaughton's algorithm to each time interval delimited by changes in the set of jobs with positive R.