SlideShare a Scribd company logo
www.fullertonengineering.com
Engineer Training Series – SST Towers
Part 2
Objective: Understand, Confirm, and Explore ... Past and Most Unique Practices
(1) Monopole
(2) Self Supporter
(3) Guyed Tower
The following information is presented in a 3 part series that
cover the Parts, Foundations, Erection, and Maintenance
efforts for each of the following structure types:
Fred Teichman 03/2014
www.fullertonengineering.com
Part 2 – SST Typical Use
Increased Height, Requires more Ground space,
Good loading Capacity & Mainly in Suburban areas
www.fullertonengineering.com
Part Two – Why use a Self Supporting Tower (SST) ?
Self Supporting
Self-supporting towers, sometimes referred to as “free standing antenna
towers” or “wireless communication towers” are the most popular and
versatile type of structure used today in the wireless industry.
Self Support towers have a larger footprint than monopoles, but a much
smaller one than Guyeded towers.
3 legged triangular base pattern are the most common. Angle or Pipe
(tubular and solid) for the legs, assembled in sections with a lattice work of
cross braces bolted and designed for medium to heavy loads. The wider the
base, the larger the acceptable antenna load.
As the industry matures - 4 legged structures are becoming more obsolete
due to the additional capital and construction costs and the ongoing change
in technology.
www.fullertonengineering.com
Part Two – What & How ... SST
Self Supporting
• Typical Parts & Pieces
(Structure & Accessories)
• Manufactures
• Foundations
• Assembly and Erection
• Installation & Maintenance
65% of the photos used in this material are from actual projects and referenced by customer & site.
Project drawings and costs information is available upon request. FredTeichmanHTH@gmail.com
www.fullertonengineering.com
SST - Typical Parts
The Tower Section
www.fullertonengineering.com
SST two basic Types – Bolted
Bolted sections – before Hot dip Galv
Based on the manufacture, it could be an All Bolted construction, All Welded or a
combination of the two.
Bolt-together Structures
X-brace designs are available in face sizes
up to 27'. K-brace designs are available up
to 40', and truss leg designs are available
for larger face sizes. The designs
accommodate a wide range of tower
requirements up to 900' in height.
www.fullertonengineering.com
SST Types – Welded – less common
All Welded sections
Based on the manufacture, it could be an All Bolted construction, All Welded or a
combination of the two.
Weld-together Structures
Designed in face widths from 12" to 72".
Straight and tapered sections, with designs
ranging up to 220'.
PiRod Sleeved flange
www.fullertonengineering.com
SST - Typical Parts
The Tower Legs
www.fullertonengineering.com
SST - Typical Parts – Legs
Tubular /Pipe/ Round - Solid and Hollow Leg
Angle Leg
Small Towers sections as legs
Or
Or
www.fullertonengineering.com
SST - Typical Parts
Bracing Designs
K X Z
www.fullertonengineering.com
SST - Typical Designs
“X” Bracing“K” Bracing “Z” Bracing
www.fullertonengineering.com
SST - Typical Parts
The Connection
www.fullertonengineering.com
SST #1 Common Connection – Flange
SST types continued
Circular Flange on Solid Leg
Hexagon Flange on Hollow Leg
Square Flange
there is also
Triangle shape
PiRod’s Sleeved &
special 2 bolt
flange (old school)
www.fullertonengineering.com
SST 2nd Most Common Connections – Plate
Plate Flange used on
on 3 and 4 angle leg
towers
www.fullertonengineering.com
SST - By Who
Manufacture
www.fullertonengineering.com
SST – Manufactures: Who and Where
Is now
Valley NE
Sioux City IA
South Bend IN
Ft Worth TX
Peoria IL
Plymouth IN
Newburg IN
Fremont IN
www.fullertonengineering.com
SST Typical Parts
Accessories
&
Mounts
www.fullertonengineering.com
SST Basic Parts & Accessories – How to climb?
A. Ladder (inside, outside or leg)
or
B. Step Bolts (leg)
Interior climbing
Tower leg is the ladderSafety climb
system
Step bolts - angle
or round tower
leg
This tower has both – step bolts and ladder
www.fullertonengineering.com
SST Typical Parts
1. Mounts
A. Three-sectored mounting frame
B. Side Arm mounts
C.Pipe mounts
2. Cable Support System
A. waveguide ladder
B. T or Cluster Brackets
3. Lighting system (structures 200’ or more)
A. Red Flash
B. White Strobe
www.fullertonengineering.com
SST – #1 Mounts
Source: Comscope & SitePro
Stand off
Arms for
Omni
antennas
M/W pipe
mounts
Universal Sector Frame
(capable of additional vertical
pipes)
Universal Adjustable Slope
Pipe Mount
Mounts are single leg , or across the face leg
to leg mounted
Stand-Off bracket
Face mount
www.fullertonengineering.com
SST – #2 Cable Support Systems
Tee Brackets
Cable Ladder (most common)
Cluster Bracket
Or combination of everything ...
www.fullertonengineering.com
SST – #3 Lighting Systems – Reference
FAA Marking for structures over 200’ or near Airport zone.
Red light flashing requires FAA Orange White paint bands
Strobe requires lights only (day night operations)
www.fullertonengineering.com
SST – #3 Lighting Systems
Old style - 2 bulb Red flashing beacon
*New LED Red beacon and side light
Medium Intensity
White Strobe
Old style - single
side lights
Dual System
Red flashing
and White
Strobe
www.fullertonengineering.com
Monopole Foundations
Foundations
www.fullertonengineering.com
SST FND Types – Pad & Pier and Drilled Caisson
Drilled CaissonPad & Pier
State of WI Genoa WI
X 3
www.fullertonengineering.com
SST Foundations – Pad and Pier
State - Genoa WI
The Pad & Pier requires more area & schedule
but clearly is a more costs effective approach.
34’ x 34’ x 2’3”pad with 7.5’ pier
Anchor Bolts and template plate
www.fullertonengineering.com
SST Foundations – Pad and Pier
The pad is poured continuous and vibrated
to remove air pockets and allow proper flow
in, around and thru rebar.
State - Genoa WI
www.fullertonengineering.com
SST Foundations – Pad and Pier
Once the pad is poured out and cured for
12 to 18 hours , the piers are formed using
Sonotube and poured with the anchor
bolts in place and secured by the template
plate and angles
The pad is then backfilled to
proper site grade
www.fullertonengineering.com
SST Foundations – Drilled Caisson
Drilled Caissons can be installed year round
Typical sizes 4-6’ diameter with depths ranging
from 18 – 28’ +
Rebar cages are
tied prior to
drilling
www.fullertonengineering.com
SST Foundations – Drilled Caisson
MNDOT – Blue Earth MN
One of the Three caissons
Note: the Drill
Rig is used for,
drilling removing
spoils, and lifting
the required
material used in
the foundation
Rebar cage is
lifted into hole
and secured
prior to
pouring
concrete.
www.fullertonengineering.com
SST Foundations – Drilled Caisson finished
Template angles and plates
position the anchor bolts for
proper fit with the bottom
tower section
Leveling jacks, C-Clamps and
proper forming material result in
quality caisson installation
Finished grade and
removed steel caisson
casing on two of the 3
piers
MNDOT – Blue Earth MN
www.fullertonengineering.com
SST Foundation – upside down P&P? – No
MNDOT – Wykoff MN
Drilled caisson shortened in length to
reduce costs, then added an
engineered pad ! This approach
allowed us to be low bidder on 5
additional site
One of three tower legs – the costs to drill
the extra 13’ per twr leg was more
expensive than installing this pad on each
of the three tower legs
www.fullertonengineering.com
SST New Caisson Foundation that is modified
Engineered approach in turning a costly
Drilled caisson into a semi inverted pad
and pier construction. This approach
was presented and state approved on 5
tower sites – MNDOT
MNDOT – Wykoff MN
Once the shortened Caisson was
drilled & cured the excavation,
rebar doweling and pad was
poured added only 5 days to the
schedule.
www.fullertonengineering.com
SST – Offload, Assembly & Erection
Offload
Assembly & Erection
www.fullertonengineering.com
SST Tower Assembly and Erection
What a 330’ SST solid leg heavily loaded tower looks like before it goes vertical
MNDOT – Bicay & Baxter MN
Everything that can be assembled on the ground is completed prior and during erection
www.fullertonengineering.com
SST Tower Assembly and Erection
K & X
sections
are pre
assembled
Antenna
mounts
Boom truck or
small crane is
used to set
lower sections
and assist in
assembly
www.fullertonengineering.com
SST Tower - Erection with Large Crane 90 - 270 ton
2 – 3 tower
workers
are on the
tower to
receive, pin
and bolts
sections
Sections being set prior to jib
needed
Jib extension added to boom
www.fullertonengineering.com
SST Tower Erection
With
sections pre
assembled
and material
properly
staged, the
time
required for
the crane to
be on site
can be
controlled $$
Topping out !
Weight
is less of
an issue
than
height
www.fullertonengineering.com
SST Tower Assembly and Erection
Gin Pole and Skid Winch – note the pivot action of the pole to center the load
Crane costs,
availability,
capability,
contractor skill,
weather, and
schedule all play a
role in the decision
to use of a gin pole
vs crane to stack
the tower.
www.fullertonengineering.com
Tower Erection – Winch & Gin Pole process
Double block
to lift the load
and jump the
pole
Double drum
winch allows
dual function
required with
using a gin
pole – raising
the tower
section then
jumping the
pole higher for
the next
section
Gin pole basic use for SST
and Guyeded structures
www.fullertonengineering.com
SST – What goes on
Installing Equipment
www.fullertonengineering.com
Installing Equipment on SST Towers
Once the tower is stack , next is to
Install the equipment. Since the
hourly rate for crane is expensive, the Crew
breaks down the crane (removes jib),
and gets the crane off the project to
stop the billable clock.
Then a block is used at the top or mid point of
the structure and the tower is now part of
the lifting equipment - here shown is a mini
gin pole used to set the m/w antenna
Capstan winch
with foot switch
Single drum
winch with
Rope capstone on
the side
www.fullertonengineering.com
Most Common Equipment – Support Hardware
Here are a few of the most common equipment accessories (support hardware)
used to secure the equipment to tower, on the mounts and into the equipment
enclosure:
Angle Adapter
Round Member Adapter
(with standoff)
Hoisting Grip
Snap-in and Standard hanger
www.fullertonengineering.com
SST Tower for Multiple use – M/W, Cellular, etc
WSDOT – Sumas Mtn
Here shown top view for raising 10’ m/w HP dish.
Note a tag line is used to keep the dish safely away
from the tower as it is raised
www.fullertonengineering.com
Installing & Alignment on SST
AAT – Antenna
Alignment Tool
Digital Level
LTE, PCS, Cellular, M/W
antennas jumpers, etc all need
to be secured and protected
from high winds & extreme
weather conditions
Tools used to Align
the antennas
Important point – 99% of the
antennas are mounted to the
tapered legs of the SST
resulting in consistent effort to
make sure the vertical pipe on
the antenna mount are plumb
Sample mount that adjusts to
the slope of the tower leg
Pendulum
M/W path
gear
www.fullertonengineering.com
SST Typical Service
Maintenance
Up and Down
www.fullertonengineering.com
SST Tower Maintenance – 3 areas
Basic maintenance covers 3 areas:
1. Tower Surface condition (Galvanizing)
2. FAA marking (Paint and lights) if required
3. Confirm no lose bolts (tight)
Most towers are marked
with an identity tag/plate
that references ownership,
manufacture and drawings
Sample
tower
plates
#1 product used in the
field for repairing
damaged galvanizing
www.fullertonengineering.com
SST Tower Maintenance – FAA Marking (Painting)
The FAA has strict guidelines for marking structures over
200’. When specific zoning requirements prevent a tower
owners from using strobe lights, painting the Orange & White
bands on the tower become required. Repainting is a natural
occurrence every 5 – 7 years .
Fade chart is used to determine
if paint condition is compliant
Most Common
www.fullertonengineering.com
SST – Summary & Key Points
• Most Common for Telecom
• Requires More Area
• Taller Heights
• Low Maintenance
• FAA Marking over 200’
• Construct with Crane under 300’(+-)
then gin pole for more !
• Drilled Caisson & Spread footing both
common – costs, customer and skill
www.fullertonengineering.com
Specialized Suppliers & Resources
www.sabretowersandpoles.com
www.valmont.com/valmont-
structures/products/wireless-communication
www.wirelesscomponents.com
Specialty Manufacturing LLC
www.ep-ind.com Fred Teichman
www.linkedin.com/in/fredteichman
www.engend.com
www.primuselectronics.com
www.us-instrument.com
www.wirelessestimator.com

More Related Content

PPTX
Part 4 Mods - Tower and Foundation Modifications on vertical structures
PPTX
Part 3 Guy Tower Structure
PPTX
Part 1 Monopole Tower Structures
PPTX
analysis and design of telecommunication tower
PPTX
Telecommunication Tower
PPT
telecommunication Towers
PDF
Construction of telecommunication towers
PPTX
Transmission tower
Part 4 Mods - Tower and Foundation Modifications on vertical structures
Part 3 Guy Tower Structure
Part 1 Monopole Tower Structures
analysis and design of telecommunication tower
Telecommunication Tower
telecommunication Towers
Construction of telecommunication towers
Transmission tower

What's hot (20)

PPT
DESIGN OF STEEL STRUCTURE
PPT
Transmission Line Towers and details
PDF
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
PDF
Machine Foundation Design
PPT
Microwave Tower Presentation.ppt
PDF
Comparative study of four legged self supported angular telecommunication tow...
PPT
Design of footing as per IS 456-2000
PPTX
Circular-Slabs.pptx
PPT
Wind load calculation
PPT
Deck slab bridge
PPTX
Overhead transmission lines_ Foundation.pptx
PPTX
DESIGN OF CONNECTIONS IN STEEL STRUCTURE
PPT
Peb structures
PPTX
Design of t beam bridge using wsm(2)
PDF
ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)
PPTX
A mini project on the transmission tower
PPTX
EC3 design
PPTX
Wind loading
PPTX
Monopole
DESIGN OF STEEL STRUCTURE
Transmission Line Towers and details
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Machine Foundation Design
Microwave Tower Presentation.ppt
Comparative study of four legged self supported angular telecommunication tow...
Design of footing as per IS 456-2000
Circular-Slabs.pptx
Wind load calculation
Deck slab bridge
Overhead transmission lines_ Foundation.pptx
DESIGN OF CONNECTIONS IN STEEL STRUCTURE
Peb structures
Design of t beam bridge using wsm(2)
ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)
A mini project on the transmission tower
EC3 design
Wind loading
Monopole
Ad

Similar to Part 2 Self Supporting tower structures (20)

PPT
Field Services: Problem Resolution
PPT
Pipe Support Field Examples & Case Studies
PPT
Metode Konstruksi Offshore Platform_2016_2_18.ppt
PPT
Pipe Support & EJ Field Examples & Case Studies
DOCX
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
PPTX
PRE-CAST-CONSTRUCTION.pptx
PPTX
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
PPT
Scaffolding
PPT
Scaffolding
PPT
Scaffolding
PDF
Company profile
PPT
Field Service: Problem Resolution - Feb. 2010
PPT
Segmental Lining Design Presentation
PPT
Pre Bid Conference
PDF
305913027-Design-owwwwwwwwwf-Steel-Tower.pdf
PPT
Design of Steel Tower calculation presentaton i
PDF
REBARRING REPRORT A1 SIZE (BUILDING CONSTRUCTION)
TXT
115659118 pre-engineered-buildings (1)
TXT
115659118 pre-engineered-buildings
PDF
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Field Services: Problem Resolution
Pipe Support Field Examples & Case Studies
Metode Konstruksi Offshore Platform_2016_2_18.ppt
Pipe Support & EJ Field Examples & Case Studies
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
Scaffolding
Scaffolding
Scaffolding
Company profile
Field Service: Problem Resolution - Feb. 2010
Segmental Lining Design Presentation
Pre Bid Conference
305913027-Design-owwwwwwwwwf-Steel-Tower.pdf
Design of Steel Tower calculation presentaton i
REBARRING REPRORT A1 SIZE (BUILDING CONSTRUCTION)
115659118 pre-engineered-buildings (1)
115659118 pre-engineered-buildings
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Ad

Recently uploaded (20)

PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PDF
composite construction of structures.pdf
PDF
PPT on Performance Review to get promotions
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PPTX
additive manufacturing of ss316l using mig welding
PPT
Mechanical Engineering MATERIALS Selection
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
Well-logging-methods_new................
PPT
Project quality management in manufacturing
PPTX
Sustainable Sites - Green Building Construction
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PPTX
Geodesy 1.pptx...............................................
PPTX
Internet of Things (IOT) - A guide to understanding
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPTX
CH1 Production IntroductoryConcepts.pptx
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
composite construction of structures.pdf
PPT on Performance Review to get promotions
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
additive manufacturing of ss316l using mig welding
Mechanical Engineering MATERIALS Selection
CYBER-CRIMES AND SECURITY A guide to understanding
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Well-logging-methods_new................
Project quality management in manufacturing
Sustainable Sites - Green Building Construction
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Geodesy 1.pptx...............................................
Internet of Things (IOT) - A guide to understanding
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
CH1 Production IntroductoryConcepts.pptx
Operating System & Kernel Study Guide-1 - converted.pdf
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx

Part 2 Self Supporting tower structures

  • 1. www.fullertonengineering.com Engineer Training Series – SST Towers Part 2 Objective: Understand, Confirm, and Explore ... Past and Most Unique Practices (1) Monopole (2) Self Supporter (3) Guyed Tower The following information is presented in a 3 part series that cover the Parts, Foundations, Erection, and Maintenance efforts for each of the following structure types: Fred Teichman 03/2014
  • 2. www.fullertonengineering.com Part 2 – SST Typical Use Increased Height, Requires more Ground space, Good loading Capacity & Mainly in Suburban areas
  • 3. www.fullertonengineering.com Part Two – Why use a Self Supporting Tower (SST) ? Self Supporting Self-supporting towers, sometimes referred to as “free standing antenna towers” or “wireless communication towers” are the most popular and versatile type of structure used today in the wireless industry. Self Support towers have a larger footprint than monopoles, but a much smaller one than Guyeded towers. 3 legged triangular base pattern are the most common. Angle or Pipe (tubular and solid) for the legs, assembled in sections with a lattice work of cross braces bolted and designed for medium to heavy loads. The wider the base, the larger the acceptable antenna load. As the industry matures - 4 legged structures are becoming more obsolete due to the additional capital and construction costs and the ongoing change in technology.
  • 4. www.fullertonengineering.com Part Two – What & How ... SST Self Supporting • Typical Parts & Pieces (Structure & Accessories) • Manufactures • Foundations • Assembly and Erection • Installation & Maintenance 65% of the photos used in this material are from actual projects and referenced by customer & site. Project drawings and costs information is available upon request. FredTeichmanHTH@gmail.com
  • 6. www.fullertonengineering.com SST two basic Types – Bolted Bolted sections – before Hot dip Galv Based on the manufacture, it could be an All Bolted construction, All Welded or a combination of the two. Bolt-together Structures X-brace designs are available in face sizes up to 27'. K-brace designs are available up to 40', and truss leg designs are available for larger face sizes. The designs accommodate a wide range of tower requirements up to 900' in height.
  • 7. www.fullertonengineering.com SST Types – Welded – less common All Welded sections Based on the manufacture, it could be an All Bolted construction, All Welded or a combination of the two. Weld-together Structures Designed in face widths from 12" to 72". Straight and tapered sections, with designs ranging up to 220'. PiRod Sleeved flange
  • 9. www.fullertonengineering.com SST - Typical Parts – Legs Tubular /Pipe/ Round - Solid and Hollow Leg Angle Leg Small Towers sections as legs Or Or
  • 10. www.fullertonengineering.com SST - Typical Parts Bracing Designs K X Z
  • 11. www.fullertonengineering.com SST - Typical Designs “X” Bracing“K” Bracing “Z” Bracing
  • 13. www.fullertonengineering.com SST #1 Common Connection – Flange SST types continued Circular Flange on Solid Leg Hexagon Flange on Hollow Leg Square Flange there is also Triangle shape PiRod’s Sleeved & special 2 bolt flange (old school)
  • 14. www.fullertonengineering.com SST 2nd Most Common Connections – Plate Plate Flange used on on 3 and 4 angle leg towers
  • 16. www.fullertonengineering.com SST – Manufactures: Who and Where Is now Valley NE Sioux City IA South Bend IN Ft Worth TX Peoria IL Plymouth IN Newburg IN Fremont IN
  • 18. www.fullertonengineering.com SST Basic Parts & Accessories – How to climb? A. Ladder (inside, outside or leg) or B. Step Bolts (leg) Interior climbing Tower leg is the ladderSafety climb system Step bolts - angle or round tower leg This tower has both – step bolts and ladder
  • 19. www.fullertonengineering.com SST Typical Parts 1. Mounts A. Three-sectored mounting frame B. Side Arm mounts C.Pipe mounts 2. Cable Support System A. waveguide ladder B. T or Cluster Brackets 3. Lighting system (structures 200’ or more) A. Red Flash B. White Strobe
  • 20. www.fullertonengineering.com SST – #1 Mounts Source: Comscope & SitePro Stand off Arms for Omni antennas M/W pipe mounts Universal Sector Frame (capable of additional vertical pipes) Universal Adjustable Slope Pipe Mount Mounts are single leg , or across the face leg to leg mounted Stand-Off bracket Face mount
  • 21. www.fullertonengineering.com SST – #2 Cable Support Systems Tee Brackets Cable Ladder (most common) Cluster Bracket Or combination of everything ...
  • 22. www.fullertonengineering.com SST – #3 Lighting Systems – Reference FAA Marking for structures over 200’ or near Airport zone. Red light flashing requires FAA Orange White paint bands Strobe requires lights only (day night operations)
  • 23. www.fullertonengineering.com SST – #3 Lighting Systems Old style - 2 bulb Red flashing beacon *New LED Red beacon and side light Medium Intensity White Strobe Old style - single side lights Dual System Red flashing and White Strobe
  • 25. www.fullertonengineering.com SST FND Types – Pad & Pier and Drilled Caisson Drilled CaissonPad & Pier State of WI Genoa WI X 3
  • 26. www.fullertonengineering.com SST Foundations – Pad and Pier State - Genoa WI The Pad & Pier requires more area & schedule but clearly is a more costs effective approach. 34’ x 34’ x 2’3”pad with 7.5’ pier Anchor Bolts and template plate
  • 27. www.fullertonengineering.com SST Foundations – Pad and Pier The pad is poured continuous and vibrated to remove air pockets and allow proper flow in, around and thru rebar. State - Genoa WI
  • 28. www.fullertonengineering.com SST Foundations – Pad and Pier Once the pad is poured out and cured for 12 to 18 hours , the piers are formed using Sonotube and poured with the anchor bolts in place and secured by the template plate and angles The pad is then backfilled to proper site grade
  • 29. www.fullertonengineering.com SST Foundations – Drilled Caisson Drilled Caissons can be installed year round Typical sizes 4-6’ diameter with depths ranging from 18 – 28’ + Rebar cages are tied prior to drilling
  • 30. www.fullertonengineering.com SST Foundations – Drilled Caisson MNDOT – Blue Earth MN One of the Three caissons Note: the Drill Rig is used for, drilling removing spoils, and lifting the required material used in the foundation Rebar cage is lifted into hole and secured prior to pouring concrete.
  • 31. www.fullertonengineering.com SST Foundations – Drilled Caisson finished Template angles and plates position the anchor bolts for proper fit with the bottom tower section Leveling jacks, C-Clamps and proper forming material result in quality caisson installation Finished grade and removed steel caisson casing on two of the 3 piers MNDOT – Blue Earth MN
  • 32. www.fullertonengineering.com SST Foundation – upside down P&P? – No MNDOT – Wykoff MN Drilled caisson shortened in length to reduce costs, then added an engineered pad ! This approach allowed us to be low bidder on 5 additional site One of three tower legs – the costs to drill the extra 13’ per twr leg was more expensive than installing this pad on each of the three tower legs
  • 33. www.fullertonengineering.com SST New Caisson Foundation that is modified Engineered approach in turning a costly Drilled caisson into a semi inverted pad and pier construction. This approach was presented and state approved on 5 tower sites – MNDOT MNDOT – Wykoff MN Once the shortened Caisson was drilled & cured the excavation, rebar doweling and pad was poured added only 5 days to the schedule.
  • 34. www.fullertonengineering.com SST – Offload, Assembly & Erection Offload Assembly & Erection
  • 35. www.fullertonengineering.com SST Tower Assembly and Erection What a 330’ SST solid leg heavily loaded tower looks like before it goes vertical MNDOT – Bicay & Baxter MN Everything that can be assembled on the ground is completed prior and during erection
  • 36. www.fullertonengineering.com SST Tower Assembly and Erection K & X sections are pre assembled Antenna mounts Boom truck or small crane is used to set lower sections and assist in assembly
  • 37. www.fullertonengineering.com SST Tower - Erection with Large Crane 90 - 270 ton 2 – 3 tower workers are on the tower to receive, pin and bolts sections Sections being set prior to jib needed Jib extension added to boom
  • 38. www.fullertonengineering.com SST Tower Erection With sections pre assembled and material properly staged, the time required for the crane to be on site can be controlled $$ Topping out ! Weight is less of an issue than height
  • 39. www.fullertonengineering.com SST Tower Assembly and Erection Gin Pole and Skid Winch – note the pivot action of the pole to center the load Crane costs, availability, capability, contractor skill, weather, and schedule all play a role in the decision to use of a gin pole vs crane to stack the tower.
  • 40. www.fullertonengineering.com Tower Erection – Winch & Gin Pole process Double block to lift the load and jump the pole Double drum winch allows dual function required with using a gin pole – raising the tower section then jumping the pole higher for the next section Gin pole basic use for SST and Guyeded structures
  • 41. www.fullertonengineering.com SST – What goes on Installing Equipment
  • 42. www.fullertonengineering.com Installing Equipment on SST Towers Once the tower is stack , next is to Install the equipment. Since the hourly rate for crane is expensive, the Crew breaks down the crane (removes jib), and gets the crane off the project to stop the billable clock. Then a block is used at the top or mid point of the structure and the tower is now part of the lifting equipment - here shown is a mini gin pole used to set the m/w antenna Capstan winch with foot switch Single drum winch with Rope capstone on the side
  • 43. www.fullertonengineering.com Most Common Equipment – Support Hardware Here are a few of the most common equipment accessories (support hardware) used to secure the equipment to tower, on the mounts and into the equipment enclosure: Angle Adapter Round Member Adapter (with standoff) Hoisting Grip Snap-in and Standard hanger
  • 44. www.fullertonengineering.com SST Tower for Multiple use – M/W, Cellular, etc WSDOT – Sumas Mtn Here shown top view for raising 10’ m/w HP dish. Note a tag line is used to keep the dish safely away from the tower as it is raised
  • 45. www.fullertonengineering.com Installing & Alignment on SST AAT – Antenna Alignment Tool Digital Level LTE, PCS, Cellular, M/W antennas jumpers, etc all need to be secured and protected from high winds & extreme weather conditions Tools used to Align the antennas Important point – 99% of the antennas are mounted to the tapered legs of the SST resulting in consistent effort to make sure the vertical pipe on the antenna mount are plumb Sample mount that adjusts to the slope of the tower leg Pendulum M/W path gear
  • 47. www.fullertonengineering.com SST Tower Maintenance – 3 areas Basic maintenance covers 3 areas: 1. Tower Surface condition (Galvanizing) 2. FAA marking (Paint and lights) if required 3. Confirm no lose bolts (tight) Most towers are marked with an identity tag/plate that references ownership, manufacture and drawings Sample tower plates #1 product used in the field for repairing damaged galvanizing
  • 48. www.fullertonengineering.com SST Tower Maintenance – FAA Marking (Painting) The FAA has strict guidelines for marking structures over 200’. When specific zoning requirements prevent a tower owners from using strobe lights, painting the Orange & White bands on the tower become required. Repainting is a natural occurrence every 5 – 7 years . Fade chart is used to determine if paint condition is compliant Most Common
  • 49. www.fullertonengineering.com SST – Summary & Key Points • Most Common for Telecom • Requires More Area • Taller Heights • Low Maintenance • FAA Marking over 200’ • Construct with Crane under 300’(+-) then gin pole for more ! • Drilled Caisson & Spread footing both common – costs, customer and skill
  • 50. www.fullertonengineering.com Specialized Suppliers & Resources www.sabretowersandpoles.com www.valmont.com/valmont- structures/products/wireless-communication www.wirelesscomponents.com Specialty Manufacturing LLC www.ep-ind.com Fred Teichman www.linkedin.com/in/fredteichman www.engend.com www.primuselectronics.com www.us-instrument.com www.wirelessestimator.com