Driving Contractor Delivery with Forecasting
and Improved Decision-Making
#BIG5GLOBAL
/@big5global
Mohamed Maged Hegazy
Associate Planning Director, Red Sea Global
#BIG5GLOBAL
/@big5global
• Master in Construction Law – Salford University, UK
• Master of Business Administration – UoPeople, US
• B.Sc. Civil Engineering – Ain Shams University, Egypt
• Consultant – Saudi Council of Engineers
• MRICS, Chartered Project Management Surveyor – RICS
• CCP, Certified Cost Professional – AACE
• PMP, Project Management Professional – PMI
• P3O, Portfolio, Programme and Projects Offices – AXELOS, UK
• FIDIC Contracts Consultant, AIA (Brussels) Fellow
• Author of 50 Planning fundamentals & Fundamentals of Construction Contracts
• Experience more than 21 years in mega-projects (Buildings, Infrastructure & Roads)
Content
1. Introduction to performance management
2. Performance measurement systems
3. KPIs, Root cause analysis and forecasting
4. Proposing appropriate mitigation strategies
5. Monitoring and evaluating the effectiveness of the actions
6. Deciding the way forward for performance enhancement
7. Conclusion and closing notes
1- Introduction to Performance Management
Master and High-Level Programmes
Levels of detail, Scope priorities, Milestones, Rolling wave planning & Critical path/Calendars
WBS vs Levels of
Detail
Rolling Wave
Planning
Critical/Longest
Path
WBS Decomposition and Consistency
Phases of construction/work, Zoning, Vertical levels, Trades and Logical dependencies
Work Phase
Const. Phase
Building
Trade
Floor/ Level
Area/ Zone
• The best approach to decompose the WBS is to keep the dependent activities/paths as
close as possible for better monitoring and control.
• One you establish a decomposition approach, be consistent in all phases as much as
possible.
Performance Management, Forecasting and Improved Decision-Making
2- Performance Measurement Systems
PMS Basis (Consuming Time vs Cost vs Effort)
Mobilization, Engineering, Procurement, Construction and Close-out duration/cost/manhours
Duration Weights:
- Timewise, activity takes
more time deserves more
proportional weight.
But:
- An activity can take
long duration without
much cost or resources
required as a shorter
activity may need.
Cost Weights:
- Resources are loaded as
per payments because
cash flow is key in
progress.
But:
- An expensive activity
may reflect a sudden
high progress while the
project is not ahead of
schedule.
Manhours Weights:
Manhours address the
required effort to execute
any activity and it’s more
indicative for progress
While this neglects the
other resources & the
difference between
payments and progress
makes confusion.
Rules of Credit – Incremental Milestones
Standard methods of measure for construction vary widely depending on the nature of
the work and the number of steps.
The following describes five common
physical progress methods for
measuring the extent of completion of
the scope of a work package:
1. Units Completed
2. Incremental Milestone
3. Weighted or Equivalent Units
Completed
4. Resource Expenditure (Level of Effort)
5. Judgment
Applying Weightages on the Programme with Rules of Credit
Org. Maturity in PM and Quantity based activities vs Engineering and procurement progress
Phase Weight
Mobilization 2%
Engineering
Submission/Approval 60/40%
10%
Procurement 3%
Prequalification 10%
Material Submission/Approval 20%
PO 20%
Delivery 50%
Construction 80%
Close-Out 5%
Example for a Construction Project JIT:
Break down between physical Mobilization and Early submissions
Break down by no. between all types of submissions and approvals (resubmission issue)
Does this includes the manufacturing and how will it be measured or to split for long-lead items
Break down based on the productivity sheet and manhours assigned to each activity (Qty credit)
Break down between physical demobilization, snag/de-snagging and documents submissions
0/100 activities based on the issuance of the purchase orders
Break down between submissions and approval 60/40% (resubmission issue= e.g. 20%)
Appropriateness for Control and Forecasting
Progress %s/layouts, Remaining works, LOB and Practicality of look-ahead schedules
P6 calculates the planned (schedule)% and actual
(performance EV)% only if the programme is cost loaded
(Budget cost).
Therefore, we may load the weightage in units with cost (rate $1)
either equal to the project total cost or 1M … as aforementioned.
Otherwise, the resource units can be used for reporting.
This may contradict with the cash flow or other resource
reporting.
Visualizing the progress is important via progress layout/4D.
Forecasting of the remaining work is also crucial for project
control.
3- KPIs, Root cause analysis and forecasting
Programme Updating and EVM
Performance vs Schedule% (Baseline early/late, changed logic & revised %s), Reporting details and KPIs
- Are you reporting against the early planned or late planned or
something in between? And why?
- If you allows for fixing the out of sequence using a change log, do you
keep reporting the delays against the original baseline either? And why?
- After having a revised/recovery programme, do you keep the planned% of
the original baseline in your reports as well? And why?
AACE MARCH/APRIL 2020
Performance Management, Forecasting and Improved Decision-Making
Reporting Details and KPIs
Forecasting Challenges - Practicality of look-ahead schedules
Primavera filters are not
always useful. It may be not
achievable or less than
required or not practical on
site.
Therefore, manual preparation
of the look-ahead schedules
can be helpful with reference
to the planned %s, dates,
critical paths as required.
Delay Quantification Approaches including LOB and Trend Analysis
Baseline (TF=0) Update TF=0 while
Performance%>Scheduled%
Data
Date
Data
Date
Line Of Balance
http://www.cpmtutor.com/c02/img/gif_22a.gif
Data Date
Delay: 1W
Ahead:
4D
Dealy:
9D
(Forecast)
-Magnify the cost
variance.
-Maintain the variance
till end.
-More accurate.
-Time (SV) affect he cost
as well as (CV).
Var.
now
VAC
CPI
CPI
SPI
Planned Value vs Earned Value = Schedule% vs Performance %
(for PMS regardless Actual Cost and Cost Control)
Planned Manhours vs Earned Manhours (for PMS regardless Efficiency)
Planned Units vs Earned Units (for PMS regardless Changes in Quantities)
Earned Value Forecasting/Units according to Budget Cost/Units
22
(earned value)
(Invoices)
(planned value)
Cost baseline
3- SV= -1,067$
Daily
planned
budget=
266.67
$ / day
1- TF= -15 Days
5- Trend analysis
delay= -35 days
% Complete = 26.7%
= - 4 days
Example of
multiple
approaches
ETC: time schedule update
4- ES, Var= -6 Days
4- Proposing appropriate mitigation strategies
Resources Issues
- Shortage in Manpower: Extra crews and labors
- Overtime (temp) or double shifts
- Idle Equipment: Ensure maintenance and sufficient operators
- Nonproductive Resources: Supervision and training
- Lumpsum work with incentives program
- Delay in engineering works: Technical team increase/support
- Material takes long for installation: Check alternatives
Cash-flow Issues
- Cash flow enhancement by
expediting payment process
- Improve the review/payment time of
IPCs
- Advanced payment increase
- Pay material on site
- Payment to subcontractors and
suppliers directly
Management Issues
- Methodology of application
- Training and adding more skilled labors
- Enhance Supervision workforce or skills
- Get the site ready early to decrease time losses
- Sequence and logistics solutions
- Management Rearrangement
- Site layout and choosing weather suitable
working hours
5- Monitoring and evaluating the effectiveness of the
actions
Reporting of Performance
• Performance is improving and recovering delays
• Improvement is not sufficient, and more actions are
required
• Plan B/C/D – Apply the effective solution
• Recovery is not enough: Acceleration is required
Acceleration
• Recovery is not enough: Acceleration is
required
• Where the contract does not provide for acceleration
instruction but the Contractor and the Employer agree
that accelerative measures should be undertaken, the
basis of payment should be agreed before the
acceleration is commenced.
• SCL 16.5: The Contractor should provide notice.
6- Deciding the way forward for performance
enhancement
Potential Decisions:
- Micromanagement of contractor
resources
- Direct payment/management of
subcontractors
- Descope based on the capacity of the contractor or type of
work
- Termination after grace periods and re-award to another
contractor
7- Conclusion and closing notes
Recommendations
- Plan with consideration of the completion/close out
activities and the risk mitigation plans to be prepared
- Check the root causes of delays or poor performance to
effectively recover/mitigate them
- Focus on the project success with win-win situation to
work in a collaboration with all parties
Schedule levels,
critical path and
control basis
Performance
measurement
systems
KPIs, Root cause
analysis and
forecasting
Proposing
appropriate
mitigation
strategies
Monitoring and
evaluating the
effectiveness of
the actions
Deciding the way
forward for
performance
enhancement
Thank you
#BIG5GLOBAL
/@big5global
Mohamed Maged Hegazy
mm.hegazy@ppmconference.net
mobile : 00966-580264968

More Related Content

PDF
المحاضرة رقم 208 مهندس / محمد ماجد حجازي عنوان المحاضرة Performance Measur...
PDF
Performance Measurement and Weightage Systems
PDF
50 Planning Fundamentals V5.0 - procedures only
PPTX
Kpi Lister Sto 061411
PDF
Project Schedule Management
PPTX
AWIN presentation it's only logical-a scheduling overview
PPTX
RICS Project Controls 240415-final 12 May
PDF
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
المحاضرة رقم 208 مهندس / محمد ماجد حجازي عنوان المحاضرة Performance Measur...
Performance Measurement and Weightage Systems
50 Planning Fundamentals V5.0 - procedures only
Kpi Lister Sto 061411
Project Schedule Management
AWIN presentation it's only logical-a scheduling overview
RICS Project Controls 240415-final 12 May
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...

Similar to Performance Management, Forecasting and Improved Decision-Making (20)

PPTX
day 3 PMP.pptx
PPTX
MARKS IN YOUR POCKET PMP for PMP Preparation
PPT
5 Key Chart Project Management (TM) Methodology
PDF
PMP PMBOK 5TH Ch 6 time management
PPTX
pm--basic.pptx
PDF
Scheduling by Primavera - Training
PPTX
Progress and Preformance Measurement and Evaluation.pptx
PPTX
PMP-Schedule Management area
PPTX
TIME MANAGEMENT chapter(6), PMBOK5
PDF
P6 brief
PPTX
Kanban for Fixed Price Projects
PDF
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
PPT
Project Management for the resource-challenged
PPT
Project Management
PPTX
00 project control tools
PDF
BioPharma Projects: Essentials in Project Controls
PPSX
Information Technology Project Management
PPT
121905000-KM-04- Presentation0000001.ppt
PPTX
2.06 time management 1
PPTX
day 3-1 PMP.pptx
day 3 PMP.pptx
MARKS IN YOUR POCKET PMP for PMP Preparation
5 Key Chart Project Management (TM) Methodology
PMP PMBOK 5TH Ch 6 time management
pm--basic.pptx
Scheduling by Primavera - Training
Progress and Preformance Measurement and Evaluation.pptx
PMP-Schedule Management area
TIME MANAGEMENT chapter(6), PMBOK5
P6 brief
Kanban for Fixed Price Projects
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
Project Management for the resource-challenged
Project Management
00 project control tools
BioPharma Projects: Essentials in Project Controls
Information Technology Project Management
121905000-KM-04- Presentation0000001.ppt
2.06 time management 1
day 3-1 PMP.pptx
Ad

More from M Maged Hegazy, LLM, MBA, CCP, P3O (20)

PDF
Enhancing project management and control by levering visualization and 4D sch...
PDF
Mastering the Critical Path and Mitigation Actions
PDF
Concurrent Delay in Construction - NCMA 2024
PDF
Variation Orders – Types, Permission and Consequences
PDF
Roadmap to Membership of RICS - Pathways and Routes
PDF
Concurrent Delay in Construction
PDF
Essentials of EOT Claims
PDF
CCP Course - Introduction.pdf
PDF
International Delay Analysis Approaches
PDF
Delay Analysis and Concurrent Delay
PDF
Fundamentals of Construction Contracts - English, ver. 2021
PDF
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
PDF
Performing against the wall - SPI after completion
PDF
CCP Technical Paper and Application
PDF
مقدمة عن إدارة التكاليف والشهادات الاحترافية
PDF
Missing and modern necessary skills
PDF
Standard Forms of Construction Contracts
PDF
Introduction to construction contracts fundamentals
PDF
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
PDF
Procurement negotiation tips and phases
Enhancing project management and control by levering visualization and 4D sch...
Mastering the Critical Path and Mitigation Actions
Concurrent Delay in Construction - NCMA 2024
Variation Orders – Types, Permission and Consequences
Roadmap to Membership of RICS - Pathways and Routes
Concurrent Delay in Construction
Essentials of EOT Claims
CCP Course - Introduction.pdf
International Delay Analysis Approaches
Delay Analysis and Concurrent Delay
Fundamentals of Construction Contracts - English, ver. 2021
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
Performing against the wall - SPI after completion
CCP Technical Paper and Application
مقدمة عن إدارة التكاليف والشهادات الاحترافية
Missing and modern necessary skills
Standard Forms of Construction Contracts
Introduction to construction contracts fundamentals
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
Procurement negotiation tips and phases
Ad

Recently uploaded (20)

PDF
Arduino robotics embedded978-1-4302-3184-4.pdf
PPT
Project quality management in manufacturing
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PDF
PPT on Performance Review to get promotions
PDF
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PPTX
Strings in CPP - Strings in C++ are sequences of characters used to store and...
PDF
Digital Logic Computer Design lecture notes
PPTX
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PPTX
Lecture Notes Electrical Wiring System Components
PPTX
web development for engineering and engineering
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
Internet of Things (IOT) - A guide to understanding
PPTX
Sustainable Sites - Green Building Construction
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Arduino robotics embedded978-1-4302-3184-4.pdf
Project quality management in manufacturing
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPT on Performance Review to get promotions
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
Strings in CPP - Strings in C++ are sequences of characters used to store and...
Digital Logic Computer Design lecture notes
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
CYBER-CRIMES AND SECURITY A guide to understanding
Model Code of Practice - Construction Work - 21102022 .pdf
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
Lecture Notes Electrical Wiring System Components
web development for engineering and engineering
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
Internet of Things (IOT) - A guide to understanding
Sustainable Sites - Green Building Construction
UNIT-1 - COAL BASED THERMAL POWER PLANTS

Performance Management, Forecasting and Improved Decision-Making

  • 1. Mohamed Maged Hegazy Associate Planning Director, Red Sea Global Driving Contractor Delivery with Forecasting and Improved Decision-Making #BIG5GLOBAL /@big5global
  • 2. Mohamed Maged Hegazy Associate Planning Director, Red Sea Global #BIG5GLOBAL /@big5global • Master in Construction Law – Salford University, UK • Master of Business Administration – UoPeople, US • B.Sc. Civil Engineering – Ain Shams University, Egypt • Consultant – Saudi Council of Engineers • MRICS, Chartered Project Management Surveyor – RICS • CCP, Certified Cost Professional – AACE • PMP, Project Management Professional – PMI • P3O, Portfolio, Programme and Projects Offices – AXELOS, UK • FIDIC Contracts Consultant, AIA (Brussels) Fellow • Author of 50 Planning fundamentals & Fundamentals of Construction Contracts • Experience more than 21 years in mega-projects (Buildings, Infrastructure & Roads)
  • 3. Content 1. Introduction to performance management 2. Performance measurement systems 3. KPIs, Root cause analysis and forecasting 4. Proposing appropriate mitigation strategies 5. Monitoring and evaluating the effectiveness of the actions 6. Deciding the way forward for performance enhancement 7. Conclusion and closing notes
  • 4. 1- Introduction to Performance Management
  • 5. Master and High-Level Programmes Levels of detail, Scope priorities, Milestones, Rolling wave planning & Critical path/Calendars WBS vs Levels of Detail Rolling Wave Planning Critical/Longest Path
  • 6. WBS Decomposition and Consistency Phases of construction/work, Zoning, Vertical levels, Trades and Logical dependencies Work Phase Const. Phase Building Trade Floor/ Level Area/ Zone • The best approach to decompose the WBS is to keep the dependent activities/paths as close as possible for better monitoring and control. • One you establish a decomposition approach, be consistent in all phases as much as possible.
  • 9. PMS Basis (Consuming Time vs Cost vs Effort) Mobilization, Engineering, Procurement, Construction and Close-out duration/cost/manhours Duration Weights: - Timewise, activity takes more time deserves more proportional weight. But: - An activity can take long duration without much cost or resources required as a shorter activity may need. Cost Weights: - Resources are loaded as per payments because cash flow is key in progress. But: - An expensive activity may reflect a sudden high progress while the project is not ahead of schedule. Manhours Weights: Manhours address the required effort to execute any activity and it’s more indicative for progress While this neglects the other resources & the difference between payments and progress makes confusion.
  • 10. Rules of Credit – Incremental Milestones Standard methods of measure for construction vary widely depending on the nature of the work and the number of steps. The following describes five common physical progress methods for measuring the extent of completion of the scope of a work package: 1. Units Completed 2. Incremental Milestone 3. Weighted or Equivalent Units Completed 4. Resource Expenditure (Level of Effort) 5. Judgment
  • 11. Applying Weightages on the Programme with Rules of Credit Org. Maturity in PM and Quantity based activities vs Engineering and procurement progress Phase Weight Mobilization 2% Engineering Submission/Approval 60/40% 10% Procurement 3% Prequalification 10% Material Submission/Approval 20% PO 20% Delivery 50% Construction 80% Close-Out 5% Example for a Construction Project JIT: Break down between physical Mobilization and Early submissions Break down by no. between all types of submissions and approvals (resubmission issue) Does this includes the manufacturing and how will it be measured or to split for long-lead items Break down based on the productivity sheet and manhours assigned to each activity (Qty credit) Break down between physical demobilization, snag/de-snagging and documents submissions 0/100 activities based on the issuance of the purchase orders Break down between submissions and approval 60/40% (resubmission issue= e.g. 20%)
  • 12. Appropriateness for Control and Forecasting Progress %s/layouts, Remaining works, LOB and Practicality of look-ahead schedules P6 calculates the planned (schedule)% and actual (performance EV)% only if the programme is cost loaded (Budget cost). Therefore, we may load the weightage in units with cost (rate $1) either equal to the project total cost or 1M … as aforementioned. Otherwise, the resource units can be used for reporting. This may contradict with the cash flow or other resource reporting. Visualizing the progress is important via progress layout/4D. Forecasting of the remaining work is also crucial for project control.
  • 13. 3- KPIs, Root cause analysis and forecasting
  • 14. Programme Updating and EVM Performance vs Schedule% (Baseline early/late, changed logic & revised %s), Reporting details and KPIs - Are you reporting against the early planned or late planned or something in between? And why? - If you allows for fixing the out of sequence using a change log, do you keep reporting the delays against the original baseline either? And why? - After having a revised/recovery programme, do you keep the planned% of the original baseline in your reports as well? And why? AACE MARCH/APRIL 2020
  • 17. Forecasting Challenges - Practicality of look-ahead schedules Primavera filters are not always useful. It may be not achievable or less than required or not practical on site. Therefore, manual preparation of the look-ahead schedules can be helpful with reference to the planned %s, dates, critical paths as required.
  • 18. Delay Quantification Approaches including LOB and Trend Analysis
  • 19. Baseline (TF=0) Update TF=0 while Performance%>Scheduled% Data Date Data Date
  • 21. (Forecast) -Magnify the cost variance. -Maintain the variance till end. -More accurate. -Time (SV) affect he cost as well as (CV). Var. now VAC CPI CPI SPI Planned Value vs Earned Value = Schedule% vs Performance % (for PMS regardless Actual Cost and Cost Control) Planned Manhours vs Earned Manhours (for PMS regardless Efficiency) Planned Units vs Earned Units (for PMS regardless Changes in Quantities) Earned Value Forecasting/Units according to Budget Cost/Units
  • 22. 22 (earned value) (Invoices) (planned value) Cost baseline 3- SV= -1,067$ Daily planned budget= 266.67 $ / day 1- TF= -15 Days 5- Trend analysis delay= -35 days % Complete = 26.7% = - 4 days Example of multiple approaches ETC: time schedule update 4- ES, Var= -6 Days
  • 23. 4- Proposing appropriate mitigation strategies
  • 24. Resources Issues - Shortage in Manpower: Extra crews and labors - Overtime (temp) or double shifts - Idle Equipment: Ensure maintenance and sufficient operators - Nonproductive Resources: Supervision and training - Lumpsum work with incentives program - Delay in engineering works: Technical team increase/support - Material takes long for installation: Check alternatives
  • 25. Cash-flow Issues - Cash flow enhancement by expediting payment process - Improve the review/payment time of IPCs - Advanced payment increase - Pay material on site - Payment to subcontractors and suppliers directly
  • 26. Management Issues - Methodology of application - Training and adding more skilled labors - Enhance Supervision workforce or skills - Get the site ready early to decrease time losses - Sequence and logistics solutions - Management Rearrangement - Site layout and choosing weather suitable working hours
  • 27. 5- Monitoring and evaluating the effectiveness of the actions
  • 28. Reporting of Performance • Performance is improving and recovering delays • Improvement is not sufficient, and more actions are required • Plan B/C/D – Apply the effective solution • Recovery is not enough: Acceleration is required
  • 29. Acceleration • Recovery is not enough: Acceleration is required • Where the contract does not provide for acceleration instruction but the Contractor and the Employer agree that accelerative measures should be undertaken, the basis of payment should be agreed before the acceleration is commenced. • SCL 16.5: The Contractor should provide notice.
  • 30. 6- Deciding the way forward for performance enhancement
  • 31. Potential Decisions: - Micromanagement of contractor resources - Direct payment/management of subcontractors - Descope based on the capacity of the contractor or type of work - Termination after grace periods and re-award to another contractor
  • 32. 7- Conclusion and closing notes
  • 33. Recommendations - Plan with consideration of the completion/close out activities and the risk mitigation plans to be prepared - Check the root causes of delays or poor performance to effectively recover/mitigate them - Focus on the project success with win-win situation to work in a collaboration with all parties
  • 34. Schedule levels, critical path and control basis Performance measurement systems KPIs, Root cause analysis and forecasting Proposing appropriate mitigation strategies Monitoring and evaluating the effectiveness of the actions Deciding the way forward for performance enhancement
  • 35. Thank you #BIG5GLOBAL /@big5global Mohamed Maged Hegazy mm.hegazy@ppmconference.net mobile : 00966-580264968