Training Seminar
On
“ Shri Karsna Sudharshan Urja pvt. Ltd.”
This training seminar is submitted for partial fulfilment of the degree of
Bachler of Technology
Submitted to Submitted By
Mr. Jitendra Singh Yuvraj Singh
(Assistant Professor) 14EGCEE037
GLOBAL COLLEGE OF TECHNOLOGY, JAIPUR
TRANSFORMER
TRANSFORMER INTRODUCTION
An A.C. device used to change high voltage low current
A.C. into low voltage high current A.C. and vice-versa
without changing the frequency
1. Transfers electric power from one circuit to another
2. It does so without a change of frequency
3. It accomplishes this by electromagnetic induction
4. Where the two electric circuits are in mutual inductive influence
of each other.
PRINCIPLE OF OPERATION
 It is based on
principle of
MUTUAL
INDUCTION.
 According to which
an e.m.f. is induced
in a coil when
current in the
neighboring coil
changes.
 CONSTRUCTIONAL DETAIL :
SHELL TYPE-
• Windings are wrapped around the center leg of a
laminated core.
CORE TYPE-
• Windings are wrapped around two sides of a laminated square
core.
 SECTIONALVIEW OF TRANSFORMERS
Note:
High voltage conductors are smaller cross section conductors
than the low voltage coils
Fig- Coil and laminations of core type transformer
Fig: Shell type windings
 TRANSFORMER WITH CONSERVATOR AND
BREATHER
WORKING OF A TRANSFORMER
1. When current in the primary coil
changes being alternating in nature,
a changing magnetic field is
produced
2. This changing magnetic field gets
associated with the secondary
through the soft iron core
3. Hence magnetic flux linked with
the secondary coil changes.
4. Which induces e.m.f. in the
secondary.
SINGLE PHASE TRANSFORMER
• SINGLE PHASE TRANSFORMER
Two or more winding coupled by a common Magnetic
Core
 IDEAL TRANSFORMERS
• Zero leakage flux:
• Fluxes produced by the primary and secondary currents are
confined within the core
• The windings have no resistance:
• Induced voltages equal applied voltages
• The core has infinite permeability
• Reluctance of the core is zero
• Negligible current is required to establish magnetic flux
• Loss-less magnetic core
• No hysteresis or eddy currents
TRANSFORMER EFFICIENCY
 Transformer efficiency is defined as (applies to motors, generators and
transformers):
%100×=
in
out
P
P
η %100×
+
=
lossout
out
PP
P
η
 Types of losses incurred in a transformer:
Copper I2
R losses
Hysteresis losses
Eddy current losses
VOLTAGE REGULATION
voltageload-no
voltageload-fullvoltageload-no
regulationVoltage
−
=






=
1
2
12
N
N
VV
p
s
p
s
N
N
V
V
=recall
Secondary voltage on no-load
V2 is a secondary terminal voltage on full load






−





=
1
2
1
2
1
2
1
regulationVoltage
N
N
V
V
N
N
V
Substitute we have
 CORE BUILDING
MACHINE
NAME-UNICORE
• This machine uses iron sheet roll for making
the core of the transformer.
• Using thickness :-0.23mm-0.27mm
• It consists sensors to reduce the tension
CORES ARE BAKING
To reduce tension and to make it hard of further
treatment.
For 5 hours at 160 degree centigrade.
CORE ARE READY FOR
WINDING
• For single phase transformer .
• L.VTurns=56
• H.VTurns=1482
• So the turns ratio for this transformer is 26.42
• Turns Ratio=H.VTurns
L.VTurns
MAKING OF OUTER SHELL FOR
TRANSFORMER
• It is made by the metal sheets which is having the
thickness of 20 mm.
• It is prepared by using sheet cutting machine and welding
machine.
TRANSFORMER TESTS
MeggerTest :-For Insulation testing
RatioTest:-ForTurns OF L.V & H.V
DVDF:-DoubleVoltage Double Frequency Test
No LoadTest/ Open Ckt Test:Iron Loss
Short Ckt Test/ LoadTest:-Copper Loss
3KVTest :-For L.V Side (InsulationTest)
BreakdownVoltage:-For Oil Test
THANK YOU

More Related Content

PPTX
Transformers
PPTX
Transformer construction,types and working
PPTX
TRANSFORMER PPT
PPTX
PLC AND SCADA
PPT
Transformer ppt download
PPTX
Alternator
PPSX
Laws of illuminations
PDF
Training at 132 kv substation
Transformers
Transformer construction,types and working
TRANSFORMER PPT
PLC AND SCADA
Transformer ppt download
Alternator
Laws of illuminations
Training at 132 kv substation

What's hot (20)

PDF
Transformer basics
PPTX
Transformer
PPTX
Thyristor family
PPT
Silicon control rectifier
PPTX
Series & shunt compensation and FACTs Devices
PPTX
transformer ppt
PPTX
PDF
Power Electronics - Power Semi – Conductor Devices
PPTX
single phase energy meter.pptx
PPTX
PPTX
Transformers
PPTX
Three phase transformer
PPTX
Presentation about transformer and its types
PPT
Current Transformer and Potential Transformer
PPTX
TRANSFORMERS and LOSSES
PPTX
PPTX
Transformer
PPT
Ups
PPTX
transformer slide prsentation
PPTX
Scr firing circuits
Transformer basics
Transformer
Thyristor family
Silicon control rectifier
Series & shunt compensation and FACTs Devices
transformer ppt
Power Electronics - Power Semi – Conductor Devices
single phase energy meter.pptx
Transformers
Three phase transformer
Presentation about transformer and its types
Current Transformer and Potential Transformer
TRANSFORMERS and LOSSES
Transformer
Ups
transformer slide prsentation
Scr firing circuits
Ad

Similar to ppt on the Transformer (20)

PDF
Full transformer
PPT
Transformer
PDF
transformer
PPTX
Transformer
PDF
Transformer
PPTX
lec 8 and 9 single phase transformer.pptx
PDF
BEEE machines
PPTX
Single Phase Transformer Transformer-1_L3.pptx
PDF
DC MOTORS-UNIT-II.pdf
PPTX
ae-1.pptx
PPTX
INVERTER BY PANKAJ CHAUDHARY
PPT
Abb power transformer detail presentation.ppt
PPTX
Transformer by pankaj chaudhary
PPTX
H06 elo g
PPTX
Static Power Conversion Course -Converters DC-DC Flyback.pptx
PPTX
Transformer
 
PPT
DC Generator.ppt
PDF
DC generator construction and operations
PDF
transformer class 12 all -210216004858.pdf
PPTX
Transformer
Full transformer
Transformer
transformer
Transformer
Transformer
lec 8 and 9 single phase transformer.pptx
BEEE machines
Single Phase Transformer Transformer-1_L3.pptx
DC MOTORS-UNIT-II.pdf
ae-1.pptx
INVERTER BY PANKAJ CHAUDHARY
Abb power transformer detail presentation.ppt
Transformer by pankaj chaudhary
H06 elo g
Static Power Conversion Course -Converters DC-DC Flyback.pptx
Transformer
 
DC Generator.ppt
DC generator construction and operations
transformer class 12 all -210216004858.pdf
Transformer
Ad

More from Yuvraj Singh (20)

PDF
Spring Board Academy Book - Geography .pdf
PDF
Book hindi grammar for Competitions.pdf
PDF
Book Hindi Grammar for Competitions.pdf
PDF
Pinnacle TCS GK Hindi for Competitions.pdf
PDF
Book हिन्दी व्याकरण RBSE 9th to 12th.pdf
PDF
Book English Grammar Rule and Shortcuts.pdf
PDF
Book Paramount English Grammar for Competitions.pdf
PDF
Rajasthan-New-Map-2023-Rajasthan-New-50-District-List-2023.pdf
PDF
Kiran Guide Saamaany Hindi Book For MP SI.pdf
PDF
Hindu calander 2020
PDF
Computer notes
PDF
Corona ppt in hindi
PDF
report on the West central railway
PDF
report on the Techno india network
PDF
report on the GOVERNING CONTROL AND EXCITATION CONTROL FOR STABILITY OF POWER...
PDF
report on the Governing control and excitation control for stability of power...
PDF
report on the GOVERNING CONTROL AND EXCITATION CONTROL FOR STABILITY OF POWER...
PDF
report on the Study Of Technology System Of Self-Healing Control In Smart Dis...
PDF
report on automatic tracking solar power system
PDF
Report on the IMPROVING THE EFFICIENCY OF SOLAR PHOTOVOLTAIC POWER GENERATION...
Spring Board Academy Book - Geography .pdf
Book hindi grammar for Competitions.pdf
Book Hindi Grammar for Competitions.pdf
Pinnacle TCS GK Hindi for Competitions.pdf
Book हिन्दी व्याकरण RBSE 9th to 12th.pdf
Book English Grammar Rule and Shortcuts.pdf
Book Paramount English Grammar for Competitions.pdf
Rajasthan-New-Map-2023-Rajasthan-New-50-District-List-2023.pdf
Kiran Guide Saamaany Hindi Book For MP SI.pdf
Hindu calander 2020
Computer notes
Corona ppt in hindi
report on the West central railway
report on the Techno india network
report on the GOVERNING CONTROL AND EXCITATION CONTROL FOR STABILITY OF POWER...
report on the Governing control and excitation control for stability of power...
report on the GOVERNING CONTROL AND EXCITATION CONTROL FOR STABILITY OF POWER...
report on the Study Of Technology System Of Self-Healing Control In Smart Dis...
report on automatic tracking solar power system
Report on the IMPROVING THE EFFICIENCY OF SOLAR PHOTOVOLTAIC POWER GENERATION...

Recently uploaded (20)

PPTX
human mycosis Human fungal infections are called human mycosis..pptx
PDF
Business Ethics Teaching Materials for college
PDF
BÀI TẬP BỔ TRỢ 4 KỸ NĂNG TIẾNG ANH 9 GLOBAL SUCCESS - CẢ NĂM - BÁM SÁT FORM Đ...
PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PDF
Microbial disease of the cardiovascular and lymphatic systems
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PDF
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PPTX
Renaissance Architecture: A Journey from Faith to Humanism
PPTX
Week 4 Term 3 Study Techniques revisited.pptx
PPTX
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
PDF
O7-L3 Supply Chain Operations - ICLT Program
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
RMMM.pdf make it easy to upload and study
PDF
Anesthesia in Laparoscopic Surgery in India
PDF
FourierSeries-QuestionsWithAnswers(Part-A).pdf
PDF
Insiders guide to clinical Medicine.pdf
PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PPTX
Introduction to Child Health Nursing – Unit I | Child Health Nursing I | B.Sc...
PDF
VCE English Exam - Section C Student Revision Booklet
human mycosis Human fungal infections are called human mycosis..pptx
Business Ethics Teaching Materials for college
BÀI TẬP BỔ TRỢ 4 KỸ NĂNG TIẾNG ANH 9 GLOBAL SUCCESS - CẢ NĂM - BÁM SÁT FORM Đ...
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
Microbial disease of the cardiovascular and lymphatic systems
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
Supply Chain Operations Speaking Notes -ICLT Program
Renaissance Architecture: A Journey from Faith to Humanism
Week 4 Term 3 Study Techniques revisited.pptx
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
O7-L3 Supply Chain Operations - ICLT Program
Final Presentation General Medicine 03-08-2024.pptx
RMMM.pdf make it easy to upload and study
Anesthesia in Laparoscopic Surgery in India
FourierSeries-QuestionsWithAnswers(Part-A).pdf
Insiders guide to clinical Medicine.pdf
Module 4: Burden of Disease Tutorial Slides S2 2025
Introduction to Child Health Nursing – Unit I | Child Health Nursing I | B.Sc...
VCE English Exam - Section C Student Revision Booklet

ppt on the Transformer

  • 1. A Training Seminar On “ Shri Karsna Sudharshan Urja pvt. Ltd.” This training seminar is submitted for partial fulfilment of the degree of Bachler of Technology Submitted to Submitted By Mr. Jitendra Singh Yuvraj Singh (Assistant Professor) 14EGCEE037 GLOBAL COLLEGE OF TECHNOLOGY, JAIPUR
  • 3. TRANSFORMER INTRODUCTION An A.C. device used to change high voltage low current A.C. into low voltage high current A.C. and vice-versa without changing the frequency 1. Transfers electric power from one circuit to another 2. It does so without a change of frequency 3. It accomplishes this by electromagnetic induction 4. Where the two electric circuits are in mutual inductive influence of each other.
  • 4. PRINCIPLE OF OPERATION  It is based on principle of MUTUAL INDUCTION.  According to which an e.m.f. is induced in a coil when current in the neighboring coil changes.
  • 5.  CONSTRUCTIONAL DETAIL : SHELL TYPE- • Windings are wrapped around the center leg of a laminated core.
  • 6. CORE TYPE- • Windings are wrapped around two sides of a laminated square core.
  • 7.  SECTIONALVIEW OF TRANSFORMERS Note: High voltage conductors are smaller cross section conductors than the low voltage coils
  • 8. Fig- Coil and laminations of core type transformer
  • 9. Fig: Shell type windings
  • 10.  TRANSFORMER WITH CONSERVATOR AND BREATHER
  • 11. WORKING OF A TRANSFORMER 1. When current in the primary coil changes being alternating in nature, a changing magnetic field is produced 2. This changing magnetic field gets associated with the secondary through the soft iron core 3. Hence magnetic flux linked with the secondary coil changes. 4. Which induces e.m.f. in the secondary.
  • 12. SINGLE PHASE TRANSFORMER • SINGLE PHASE TRANSFORMER Two or more winding coupled by a common Magnetic Core
  • 13.  IDEAL TRANSFORMERS • Zero leakage flux: • Fluxes produced by the primary and secondary currents are confined within the core • The windings have no resistance: • Induced voltages equal applied voltages • The core has infinite permeability • Reluctance of the core is zero • Negligible current is required to establish magnetic flux • Loss-less magnetic core • No hysteresis or eddy currents
  • 14. TRANSFORMER EFFICIENCY  Transformer efficiency is defined as (applies to motors, generators and transformers): %100×= in out P P η %100× + = lossout out PP P η  Types of losses incurred in a transformer: Copper I2 R losses Hysteresis losses Eddy current losses
  • 15. VOLTAGE REGULATION voltageload-no voltageload-fullvoltageload-no regulationVoltage − =       = 1 2 12 N N VV p s p s N N V V =recall Secondary voltage on no-load V2 is a secondary terminal voltage on full load       −      = 1 2 1 2 1 2 1 regulationVoltage N N V V N N V Substitute we have
  • 16.  CORE BUILDING MACHINE NAME-UNICORE • This machine uses iron sheet roll for making the core of the transformer. • Using thickness :-0.23mm-0.27mm • It consists sensors to reduce the tension
  • 17. CORES ARE BAKING To reduce tension and to make it hard of further treatment. For 5 hours at 160 degree centigrade.
  • 18. CORE ARE READY FOR WINDING • For single phase transformer . • L.VTurns=56 • H.VTurns=1482 • So the turns ratio for this transformer is 26.42 • Turns Ratio=H.VTurns L.VTurns
  • 19. MAKING OF OUTER SHELL FOR TRANSFORMER • It is made by the metal sheets which is having the thickness of 20 mm. • It is prepared by using sheet cutting machine and welding machine.
  • 20. TRANSFORMER TESTS MeggerTest :-For Insulation testing RatioTest:-ForTurns OF L.V & H.V DVDF:-DoubleVoltage Double Frequency Test No LoadTest/ Open Ckt Test:Iron Loss Short Ckt Test/ LoadTest:-Copper Loss 3KVTest :-For L.V Side (InsulationTest) BreakdownVoltage:-For Oil Test