OBJECTIVES
On completion of this period, you would be
able to know
• Procedure of Earthing different line supports for LT,
11Kv, 33Kv lines
• Maximum earth resistance values with the size of pipe
or plate used for Earthing.
EE504.32 3
RECAP
We have discussed in the last class about
• Conductor spacing and ground clearance
EE504.32 4
PROCEDURE OF EARTHING DIFFERENT LINE
SUPPORTS FOR
LT, 11KV AND 33 KV LINES FOR SAFETY
1. Metal supports
• Every fifth pole shall be earthed.
• All supports provided with mass or block concrete
foundation shall be earthed.
2. RCC poles
• metal cross arms and insulator pins shall be bonded
together and earthed
• At every pole for HT lines
• At every fifth pole for LT lines.
EE504.32 5
• Metal cross arms and insulator pins shall be bonded
together and earthed at every fifth pole
• when wood cross arms are used insulator pins are bonded
together and earthed.
4. Special Structures
•Special structures carrying transformers, switches, fuses etc
should be earthed.
3. Wood Poles
EE504.32 6
5.Special Locations
•Supports on either side of a road, railway, river crossing
should be earthed
EE504.32 7
• Pipe Earthing is adopted in special locations
• Coil Earthing (9m length) is adopted for all other locations
• Galvanized steel wire(6 or 8 SWG) is used for earthing
EE504.32 8
4  4  G.I plate 1/2  width or
6 dia G.I pipe of 10 long and ½ 
thick.
2 dia. 10 long G.I pipe or
22 G.I plate of 3/8 thick.
½  dia. G.I pipe of 6 long
Size of earth pipe or plate
1
2
5
Max. earth
Resistance
66Kv and above
33 Kv
Distribution
Transformer
Substation
Capacity
Maximum Earth Resistance values and the size
of the pipe or plates used for Earthing
TABLE.1
EE504.32 9
SUMMARY
We have discussed about
• Procedure of Earthing different line supports for
LT, 11kv,33kv lines.
• Maximum Earth resistance values with the size of pipe or
plate used for earthing.
EE504.32 10
1. Earthing of metal structures, cross arms, insulator pins is
done for LT lines on
(a) All the poles
(b) Every fifth pole
(c) Alternate poles
(d) None
QUIZ
EE504.32 11
2. Maximum Earth resistance value of 33Kv line is
(a) 15 
(b) 10 
(c) 20 
(d) 2 
QUIZ
EE504.32 12
FREQUENTLY ASKED QUESTIONS
1. State Maximum Earth resistance values for earthing of
33 Kv and 66Kv
2. Explain the procedure of earthing different line
supports.

More Related Content

PPT
Line structures transmission and distribution 2
PPT
high voltage engineering power point presentation
PPT
conductors and line spacing in transmission lines
PPTX
A mini project on the transmission tower
PPT
High voltage distribution systems ppt presentaion
PPT
Cross arms and economical spacing in Tramissions
PPT
Cross arms and economical spacing in Tramissions
PPTX
Earthing
Line structures transmission and distribution 2
high voltage engineering power point presentation
conductors and line spacing in transmission lines
A mini project on the transmission tower
High voltage distribution systems ppt presentaion
Cross arms and economical spacing in Tramissions
Cross arms and economical spacing in Tramissions
Earthing

Similar to Procedure for earthing for different sites (20)

PPT
Perhitungan sturktur kolom baja 6162 (4).ppt
PPTX
ZAKIR M.Tech Project presentation
PPTX
Electrical Estimation and Costing Module 3 service connection.pptx
PPTX
DOC-20240828-WA0001..pptxsrbudbih6rfsrvvctg
PPTX
presentationofpowerelectronics-160321202827 (1).pptx
PPT
UNDER GROUND CABLES IN ELECTRICAL POWER SYSTEMS
PPTX
Harish aggarwal
PPT
analysisand designof rccslabsfor varioususes.ppt
PDF
ملزمة
PPT
Presentation on construction of cable stay bridge - a modern technique for su...
PPTX
Mechanical Design of Overhead Lines
PPTX
Transmission lines of Electrical powe
PPTX
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
PPTX
SERVICE CONNECTION, INSPECTION AND TESTING OF INSTALLATION
DOCX
Power house report
DOCX
Power house report
PPT
FinFET technology gives information about how to reduced channel length in na...
PDF
Mike's presentation
PDF
Calculation note suez canal cable stayed bridge
PPTX
Turga PSP_Lower Dam.pptx
Perhitungan sturktur kolom baja 6162 (4).ppt
ZAKIR M.Tech Project presentation
Electrical Estimation and Costing Module 3 service connection.pptx
DOC-20240828-WA0001..pptxsrbudbih6rfsrvvctg
presentationofpowerelectronics-160321202827 (1).pptx
UNDER GROUND CABLES IN ELECTRICAL POWER SYSTEMS
Harish aggarwal
analysisand designof rccslabsfor varioususes.ppt
ملزمة
Presentation on construction of cable stay bridge - a modern technique for su...
Mechanical Design of Overhead Lines
Transmission lines of Electrical powe
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
SERVICE CONNECTION, INSPECTION AND TESTING OF INSTALLATION
Power house report
Power house report
FinFET technology gives information about how to reduced channel length in na...
Mike's presentation
Calculation note suez canal cable stayed bridge
Turga PSP_Lower Dam.pptx
Ad

More from Vara Prasad (20)

PPT
pole guys and stays in erecting of transformers
PPT
line structures and transmissions in Power systems
PPT
Line structurer for line transmission and distribution
PPT
power system II transmission and distribution
PPT
underground cable in distribution systems
PPT
High voltage transmission lecturer fifty eight
PPT
Power systems-II (Transmission & Distribution)
PPT
HIGH VOLTAGE TRANSMISSION AND DISTRIBUTION
PPT
Digital electronics power point Presentaion
PPT
Digital Electronics power point presentation 2
PPT
Digital electronics power point presentation
PPT
SWITCHING THEORY AND LOGIC DESIGN POWER POINT 1.ppt
PPT
switching theory and logical design for ece
PPTX
interduction to electrical power systems
PPT
high voltge engineering useful for diploma
PPT
power point presentation on high voltage
PDF
PPTChapter12.pdf
PPT
EE504.9.ppt
PPT
EE504.5.ppt
PPT
EE504.2.ppt
pole guys and stays in erecting of transformers
line structures and transmissions in Power systems
Line structurer for line transmission and distribution
power system II transmission and distribution
underground cable in distribution systems
High voltage transmission lecturer fifty eight
Power systems-II (Transmission & Distribution)
HIGH VOLTAGE TRANSMISSION AND DISTRIBUTION
Digital electronics power point Presentaion
Digital Electronics power point presentation 2
Digital electronics power point presentation
SWITCHING THEORY AND LOGIC DESIGN POWER POINT 1.ppt
switching theory and logical design for ece
interduction to electrical power systems
high voltge engineering useful for diploma
power point presentation on high voltage
PPTChapter12.pdf
EE504.9.ppt
EE504.5.ppt
EE504.2.ppt
Ad

Recently uploaded (20)

PDF
Digital Logic Computer Design lecture notes
PPTX
bas. eng. economics group 4 presentation 1.pptx
DOCX
573137875-Attendance-Management-System-original
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
CH1 Production IntroductoryConcepts.pptx
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PPT
Project quality management in manufacturing
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
Lecture Notes Electrical Wiring System Components
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPT
introduction to datamining and warehousing
PDF
composite construction of structures.pdf
PDF
PPT on Performance Review to get promotions
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PDF
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
Digital Logic Computer Design lecture notes
bas. eng. economics group 4 presentation 1.pptx
573137875-Attendance-Management-System-original
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
CH1 Production IntroductoryConcepts.pptx
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
CYBER-CRIMES AND SECURITY A guide to understanding
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Project quality management in manufacturing
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
Lecture Notes Electrical Wiring System Components
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
introduction to datamining and warehousing
composite construction of structures.pdf
PPT on Performance Review to get promotions
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Model Code of Practice - Construction Work - 21102022 .pdf
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf

Procedure for earthing for different sites

  • 1. EE504.32 1 DEPARTMENT OF TECHNICAL EDUCATION ANDHRAPRADESH Name :P.Ram Narayana Designation :HEES Branch :EEE Institute :K.D.R.G.P.T,Wanaparthy. Semester :V semester Subject :P.S-II(T&D) Sub-code :EE-504 Topic :Line StructuresforTransmission&Distribution Duration :50mts Sub-topic :Procedure of Earthing different line supports and earth resistance values. Teaching-aids :PPT,diagrams
  • 2. EE504.32 2 OBJECTIVES On completion of this period, you would be able to know • Procedure of Earthing different line supports for LT, 11Kv, 33Kv lines • Maximum earth resistance values with the size of pipe or plate used for Earthing.
  • 3. EE504.32 3 RECAP We have discussed in the last class about • Conductor spacing and ground clearance
  • 4. EE504.32 4 PROCEDURE OF EARTHING DIFFERENT LINE SUPPORTS FOR LT, 11KV AND 33 KV LINES FOR SAFETY 1. Metal supports • Every fifth pole shall be earthed. • All supports provided with mass or block concrete foundation shall be earthed. 2. RCC poles • metal cross arms and insulator pins shall be bonded together and earthed • At every pole for HT lines • At every fifth pole for LT lines.
  • 5. EE504.32 5 • Metal cross arms and insulator pins shall be bonded together and earthed at every fifth pole • when wood cross arms are used insulator pins are bonded together and earthed. 4. Special Structures •Special structures carrying transformers, switches, fuses etc should be earthed. 3. Wood Poles
  • 6. EE504.32 6 5.Special Locations •Supports on either side of a road, railway, river crossing should be earthed
  • 7. EE504.32 7 • Pipe Earthing is adopted in special locations • Coil Earthing (9m length) is adopted for all other locations • Galvanized steel wire(6 or 8 SWG) is used for earthing
  • 8. EE504.32 8 4  4  G.I plate 1/2  width or 6 dia G.I pipe of 10 long and ½  thick. 2 dia. 10 long G.I pipe or 22 G.I plate of 3/8 thick. ½  dia. G.I pipe of 6 long Size of earth pipe or plate 1 2 5 Max. earth Resistance 66Kv and above 33 Kv Distribution Transformer Substation Capacity Maximum Earth Resistance values and the size of the pipe or plates used for Earthing TABLE.1
  • 9. EE504.32 9 SUMMARY We have discussed about • Procedure of Earthing different line supports for LT, 11kv,33kv lines. • Maximum Earth resistance values with the size of pipe or plate used for earthing.
  • 10. EE504.32 10 1. Earthing of metal structures, cross arms, insulator pins is done for LT lines on (a) All the poles (b) Every fifth pole (c) Alternate poles (d) None QUIZ
  • 11. EE504.32 11 2. Maximum Earth resistance value of 33Kv line is (a) 15  (b) 10  (c) 20  (d) 2  QUIZ
  • 12. EE504.32 12 FREQUENTLY ASKED QUESTIONS 1. State Maximum Earth resistance values for earthing of 33 Kv and 66Kv 2. Explain the procedure of earthing different line supports.