Agile Program Management Process 
(Hypothetical) R&R Initiative 
Vishal Sheth, CSM, CSP, CSPO, PMP 
Copyright Vishal Sheth 2012
Why Are We Here? 
 Project R&R is ready for launch 
 Scope: 
 Reinvent Ratings & Reviews 
 Expected Timeline: 
 Up to a year 
 Estimated Resources: 
 3 Product Teams (PO, Dev, QA, UX, Pubs) 
 1 Marketing / 1 Product Mktg Resource 
 1 Client Services Resource 
 0.5 Sales / 0.5 Support Resource 
 Benefit: 
 Revolutionize the world of Ratings & 
Reviews while generating MIRR >= 20% 
Copyright Vishal Sheth 2012
What Does The Opportunity Look Like? 
 Value Proposition (Tangible & Intangible) 
 Target Market 
 Market Size (Revenues/Savings) 
 Success Metrics 
 Competitive Landscape 
 Our Differentiator 
 Market Timing 
 Deployment Strategy 
 Critical Success Factors 
*Supplemental handout has R&R Opportunity Assessment 
Copyright Vishal Sheth 2012
What are our Assumptions? 
 R&R Initiative is the highest value opportunity at this time 
 We want to be nimble to market opportunities/changes 
 Teams are available for the planned duration and are co-located 
except for some Sales/Mktg folks 
 Each Feature is independently releasable/configurable 
 Users will be available as needed for Usability Tests 
 Program Manager will play a multi-faceted role: 
 Overall oversight & cross-functional coordination 
 ScrumMaster for the 3 Delivery teams 
 Release Manager (managing business readiness) 
 Vendor Manager (if needed) 
 No 3rd Party Vendor/Tool needed 
 Sprints are 2 weeks long 
Copyright Vishal Sheth 2012
What Is Our Game Plan? 
1. Smart Scoping: Zoom in on 20% of the features that derive 80% of benefit 
2. Integrated Quality: Not just Robustness but Usefulness and Usability too 
3. Cross Functional Discovery: Involve all functions up-front 
4. Feedback Loops: Understand feedback to drive positive change – Agility 
5. Escalation Protocol: Surface concerns early and often 
6. Proactive Risk Management: Identify and address highest risk at all times 
7. Success Metrics: Keep an eye on objective and subjective measurements 
8. Phase Gate Approach: Regular checkpoints and course correction 
9. Meticulous Planning, Coordination and Communication: Planning and 
visibility Cross Team, Inter Team, Stakeholders, Sponsor 
Copyright Vishal Sheth 2012
Smart Scoping 
 Simplicity will be our overarching theme 
 The art of maximizing the amount of work not done 
 Smart Scoping - Secure highest value (to customers & 
business) as early as possible 
 80% of value is typically derived from 20% of the features 
 MS Word, Excel etc 
 Smart Prioritization 
 Mitigate highest risk (by Probability and Impact) as early as 
possible 
 Architectural Feasibility/Technical challenges 
 Legal issues 
 Align cross-team integration points 
 Ensure early validation of technology touch points 
Copyright Vishal Sheth 2012
Integrated Quality – Fitness For Use 
 We ensure robustness in smart yet cost effective 
ways 
Manual 
System 
Affected Sub-System 
Integration 
UI Functional 
Unit 
As Needed; 
As Little As 
Possible 
Every 
Sprint 
Daily 
Every 
Build 
Copyright Vishal Sheth 2012
Integrated Quality – Useful & Usable 
 Usability validation 
is built into process 
 Usability Testing 
 Visual Design 
 Interaction Design 
 UI Implementation 
 Usability Testing & 
Localization for 
International Clients 
from Phase 1 
Copyright Vishal Sheth 2012
Cross-Functional Discovery 
PO 
UX 
TL/ARCH 
PGM 
STAKE 
HOLDERS 
User Needs 
Assessment 
Create/Maint 
ain Epics 
Use Cases / 
Workflows 
Update 
Roadmap Write Stories 
Persona 
Study 
Clickable 
Prototypes 
Preliminary 
IA 
High Fidelity 
Prototypes 
Buy v/s Build 
Decisions 
3rd Party 
Evaluation 
Proof of 
Concept 
Create Release Roadmap / Release Plan 
Plan High Level Dependencies 
Facilitation 
GATE II 
Review Roadmap 
/ Prototypes 
User/Client 
Svcs F/back 
GATE 1 
Review Use 
Case Details 
t 
Copyright Vishal Sheth 2012
Feedback Loops 
 We will use every opportunity to Inspect-and-Adapt 
 Product Feedback Loops 
 Global Usability Testing – Wireframes/Prototypes 
 Sprint Demos / UATs 
 Usability Testing – Functional 
 Stage Gates 
 Post Release - Alpha, Beta, GA releases 
 Process/Status Feedback Loops (PGM to facilitate) 
 Daily Scrum (Delivery Team) 
 Scrum-of-Scrum (Delivery Leads for Dev, QA, PO) – As needed 
 Weekly Discovery Team Meetings (incl. Pubs, UX, Client Svcs) 
 Weekly Grooming Meetings (Delivery Team) 
 Sprint Retrospective (Delivery Team) - keep an eye on recurring topics 
 Bi-Weekly Program Meeting (Sponsor/Stakeholder/Lead) 
 Market Launch Team Meeting - Sales, Mktg, Product Mktg, Client Svcs, PO 
 Post-Launch Review Meetings 
 (Optional) Agile Brown Bag Lunches 
Copyright Vishal Sheth 2012
Established Escalation Protocol 
 We are an empowered and responsible Team 
 If issue can be resolved by Individual, it should be 
 If issue can be resolved by Team, it should be 
 If issue is across Teams, it should be addressed at Scrum-of- 
Scrum level 
 If issue is Organizational, it should be raised at SoS or to PGM 
 Escalation Opportunities 
 Report to PGM – Always & Anytime 
 Team – Email, Daily Scrum, Retrospective 
 Program – Email, Daily SoS 
 Sponsor – Tier 1: Immediate; Tier 2: Bi-weekly Sponsor Mtg 
 Public log of Open Blockers 
Date Details Severity Impact Owner Status / ETA 
Copyright Vishal Sheth 2012
Proactive Risk Management 
 We will succeed and fail together 
 An unmitigated risk can wipe out best laid plans 
 No one person can identify all Issues/Risks 
 Environment of collective ownership, openness, awareness 
 All Risks Matter and should be reported to PGM 
 Address Highest Risk Item(s) by Probability & Impact 
 Not all Risks require action but all require a mitigation plan 
 P/I Assessment conducted by Discovery Team 
 Public log of Potential Risk 
Date Details Probability Impact Owner Mitigation Plan 
Copyright Vishal Sheth 2012
Success Metrics 
 We will take calculated, measured, Risks 
 We will monitor tangible and intangible benefits at each phase 
 Primary focus on Leading Indicators as we iterate in Production 
 We plan to re-plan and course correct 
 Tracking to be built in as features are developed 
 Appropriate Metrics will be reviewed at Phase Gates 
 Only Features that meet or exceed targets will be 
promoted from Beta to GA (this comes with a huge side 
benefit) 
Feature Category 
Stated 
Goal 
Operational 
Definition 
Specification 
Units 
Data 
Needed 
Leading / 
Lagging 
Indicator? 
Expected 
Measurable 
LL UL Target Benefit Actual 
Copyright Vishal Sheth 2012
Phase Gate Approach 
 While we believe in our ideas, we will optimize spend by 
testing each hypothesis as quickly as possible 
 We will review objectively across various dimensions and 
course correct as appropriate 
PAB 
Review 
MMF 
Review 
Architectural 
Feasibility 
Usability 
Review 
Sprint 
Demos 
Alpha 
Feedback 
Beta 
Feedback 
Post-GA Leading 
Indicators Review 
Post-GA Lagging 
Indicators Review 
Opportunity 
Assessment Phase Discovery Phase 
Implementation 
Phase 
Limited 
Availability Phase 
General 
Availability Phase 
Market Opportunity Window/Competitive Factors Analysis 
Copyright Vishal Sheth 2012
Planning 
 Release/Feature Level Plans to include: 
 Milestones 
 Release/Feature Description 
 Release/Feature Goals/Metrics 
 Customer Benefits (to be used by and for Marketing) 
 Inter-Team Dependencies (Inbound and Outbound) 
 UX/Design Needs (provided by UX Leads, PO) 
 Technical Needs (provided by Tech. Leads & IT/Ops) 
 Regression Needs (provided by QA Lead) 
 Other Needs (Alpha/Beta Testers, Consulting etc) 
Copyright Vishal Sheth 2012
Milestones 
t 
Feature1 
DISCOVERY: 
User Needs, 
Persona, 
Use Cases 
PHASE 
GATE 1 
PHASE 
GATE 2 
PHASE 
GATE 3 
PHASE 
GATE 4 
PHASE 
GATE 5 
PHASE 
GATE 6 
DISCOVERY: IA, 
Usability Testing, 
MMF/Stories, PoC 
SPRINTS ALPHA BETA GA 
HARDENING: 
Bug Fixing, 
Usability Testing 
VALIDATION: 
Metrics Collection, 
Fdbck/Improvements 
GA Launch Prep 
HARDENING: 
Bug Fixing, 
Metrics Collection 
MONITORING/IMPROVEMENTS: 
Metrics Collection, 
Fdbck/Improvements 
Copyright Vishal Sheth 2012
Coordination & Communication 
 Dashboard 
 Regular Product/Process/Status Meetings 
 Management 
 Cross-Functional 
 Cross-Team 
 Inter & Intra Team 
 Mailing lists for each of the above groups 
 Phase Gate Review Meetings 
 Docs – Tech Pubs, Samples, Marketing/Sales Pitch 
 Training – Videos, Sessions (Client Svcs, Support) 
 Escalation Protocol (for anything outside the norm) 
Copyright Vishal Sheth 2012
Dashboard 
 Pulls everything together into a consistent snapshot 
 Overall timeline with critical Milestones from Release Plan 
 For each Release/Feature currently in-flight: 
 Current state of Minimum Marketable Feature (MMF) 
 Blockers/Risks/Delays 
 Dependency Tracking 
 Current Spend (# of FTE) v/s Budgeted Spend - Burn Rate 
 Success Metrics 
 For each Team currently assigned: 
 MMF/Component being worked on 
 Blockers/Risks/Delays 
 Dependency Tracking 
 Sprint Burndown/Velocity/Total MMF Size 
 For each Feature already released: 
 Maintenance Spend (Man Hours) 
 Customer Satisfaction (SUS Score) 
 Metrics - Expected v/s Realized Benefit in Production 
Copyright Vishal Sheth 2012
Summary – Agile PGM Model 
Successful Programs depend on pulling together multiple Factors 
1. Smart Scoping: Zoom in on 20% of features that derive 80% of 
benefit 
2. Integrated Quality: Robustness, Usefulness and Usability too 
3. Cross Functional Discovery: Involve all functions up-front 
4. Feedback Loops: Understand feedback to drive positive change – 
Agility 
5. Escalation Protocol: Surface concerns early and often 
6. Proactive Risk Management: Identify and address highest risk at 
all times 
7. Success Metrics: Keep an eye on objective and subjective 
measurements 
8. Phase Gate Approach: Regular checkpoints and course correction 
9. Meticulous Planning, Coordination and Communication: 
Planning and visibility Cross Team, Inter Team, Stakeholders, 
Sponsor(s). 
Copyright Vishal Sheth 2012
Questions? 
Vishal Sheth, CSM, CSP, CSPO, PMP 
Pragmatic Agile PMO 
vsheth@yahoo.com 
Copyright Vishal Sheth 2012

More Related Content

PPT
Agile adoption julen c. mohanty
PDF
Agile Planning Powerpoint Presentation Slides
PDF
Dr Dev Kambhampati | Stage Gate Innovation Management
PPTX
Project Management in Agile Organizations - Stage Gate and Agile
PPTX
Stage gate process in IT product development
PDF
Asset Finance Systems: Project Initiation "101"
PPTX
Agile, PMI and PMBOK
PDF
Tool Kit: Requirements management plan (babok on a page)
Agile adoption julen c. mohanty
Agile Planning Powerpoint Presentation Slides
Dr Dev Kambhampati | Stage Gate Innovation Management
Project Management in Agile Organizations - Stage Gate and Agile
Stage gate process in IT product development
Asset Finance Systems: Project Initiation "101"
Agile, PMI and PMBOK
Tool Kit: Requirements management plan (babok on a page)

What's hot (18)

DOCX
Presentation by lavika upadhyay
PPT
Introduction to six sigma (www.gotoaims.com)
PPT
An Overview of RUP methodology
PPTX
Requirement management presentation to a software team
PDF
PDMA Process StageGate
PDF
Five immutable principles of project success
PDF
From Productivity to Profitability by Saket Bansal - Lean India Summit 2014
PPT
Presentation - Rational Unified Process
PDF
Project Management Cookbook Part 1 (ARA) Feb16
PPSX
Project Portfolio Selection Model - Voice narrated
PPTX
RUP In A Nutshell Slide Share
PDF
Management techniques of the world by khawar nehal 4 august 2020-1
PDF
Project Management Cookbook Part 3 (ARA) Feb16
PDF
A Review of RUP (Rational Unified Process)
PDF
The art of agile project initiation
PPT
ITIL Practical Guide - Service Transition
Presentation by lavika upadhyay
Introduction to six sigma (www.gotoaims.com)
An Overview of RUP methodology
Requirement management presentation to a software team
PDMA Process StageGate
Five immutable principles of project success
From Productivity to Profitability by Saket Bansal - Lean India Summit 2014
Presentation - Rational Unified Process
Project Management Cookbook Part 1 (ARA) Feb16
Project Portfolio Selection Model - Voice narrated
RUP In A Nutshell Slide Share
Management techniques of the world by khawar nehal 4 august 2020-1
Project Management Cookbook Part 3 (ARA) Feb16
A Review of RUP (Rational Unified Process)
The art of agile project initiation
ITIL Practical Guide - Service Transition
Ad

Viewers also liked (7)

PDF
Leading Agile Product Discovery
PPTX
Agile Requirements Discovery
PDF
Discovery toolbox working products 2016 web
PDF
Discovery Model— An Approach for Agile at Scale
PDF
Agile Start Me Up - Using the Minimum Viable Discovery (MVD)
PPTX
Agile requirements discovery
PDF
Agile velocity - Requirements Discovery Presentation
Leading Agile Product Discovery
Agile Requirements Discovery
Discovery toolbox working products 2016 web
Discovery Model— An Approach for Agile at Scale
Agile Start Me Up - Using the Minimum Viable Discovery (MVD)
Agile requirements discovery
Agile velocity - Requirements Discovery Presentation
Ad

Similar to Step-by-Step Complete Agile Program Management Model (20)

PPT
Risk Driven Testing
DOCX
Test manager resume
PDF
Resume of Shwetabh Kumar, Project Manager at Deloitte
DOC
Resume_Pallavi_Updated
PPT
Collaborative Roadmapping
PDF
Asset Finance Systems: Project Initiation "101"
PPT
Outsourcing With Agile
PPT
Sample Product Management Lifecycle Presentation
PPT
ALM Assessment Program
PDF
Hemant_Kolhe_Resume.doc
PDF
Neerad SirkanungoBusiness Analyst
PPTX
Empirical Product Development
PPT
Practical Product Management for new Product Managers
PPTX
Benefits of Agile Software Development for Senior Management
PDF
Webinar app testing and distribution
PDF
Agile software-development-overview-1231560734008086-2
PPTX
Read Curriculum vitae of Shwetabh Kumar as Project Manager at Deloitte
DOCX
G Holmes CV - BA-STA
PPTX
Unified process,agile process,process assesment ppt
DOCX
Jaya S Verma_Resume
Risk Driven Testing
Test manager resume
Resume of Shwetabh Kumar, Project Manager at Deloitte
Resume_Pallavi_Updated
Collaborative Roadmapping
Asset Finance Systems: Project Initiation "101"
Outsourcing With Agile
Sample Product Management Lifecycle Presentation
ALM Assessment Program
Hemant_Kolhe_Resume.doc
Neerad SirkanungoBusiness Analyst
Empirical Product Development
Practical Product Management for new Product Managers
Benefits of Agile Software Development for Senior Management
Webinar app testing and distribution
Agile software-development-overview-1231560734008086-2
Read Curriculum vitae of Shwetabh Kumar as Project Manager at Deloitte
G Holmes CV - BA-STA
Unified process,agile process,process assesment ppt
Jaya S Verma_Resume

Recently uploaded (20)

PDF
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
PDF
Electronic commerce courselecture one. Pdf
PPTX
MYSQL Presentation for SQL database connectivity
PPTX
Big Data Technologies - Introduction.pptx
PPTX
A Presentation on Artificial Intelligence
PDF
Diabetes mellitus diagnosis method based random forest with bat algorithm
PPTX
Tartificialntelligence_presentation.pptx
PPTX
Machine Learning_overview_presentation.pptx
PDF
gpt5_lecture_notes_comprehensive_20250812015547.pdf
PDF
Getting Started with Data Integration: FME Form 101
PDF
Building Integrated photovoltaic BIPV_UPV.pdf
PPT
Teaching material agriculture food technology
PPTX
SOPHOS-XG Firewall Administrator PPT.pptx
PDF
MIND Revenue Release Quarter 2 2025 Press Release
PPTX
Group 1 Presentation -Planning and Decision Making .pptx
PPT
“AI and Expert System Decision Support & Business Intelligence Systems”
PPTX
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
PPTX
1. Introduction to Computer Programming.pptx
PDF
Agricultural_Statistics_at_a_Glance_2022_0.pdf
PDF
cuic standard and advanced reporting.pdf
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
Electronic commerce courselecture one. Pdf
MYSQL Presentation for SQL database connectivity
Big Data Technologies - Introduction.pptx
A Presentation on Artificial Intelligence
Diabetes mellitus diagnosis method based random forest with bat algorithm
Tartificialntelligence_presentation.pptx
Machine Learning_overview_presentation.pptx
gpt5_lecture_notes_comprehensive_20250812015547.pdf
Getting Started with Data Integration: FME Form 101
Building Integrated photovoltaic BIPV_UPV.pdf
Teaching material agriculture food technology
SOPHOS-XG Firewall Administrator PPT.pptx
MIND Revenue Release Quarter 2 2025 Press Release
Group 1 Presentation -Planning and Decision Making .pptx
“AI and Expert System Decision Support & Business Intelligence Systems”
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
1. Introduction to Computer Programming.pptx
Agricultural_Statistics_at_a_Glance_2022_0.pdf
cuic standard and advanced reporting.pdf

Step-by-Step Complete Agile Program Management Model

  • 1. Agile Program Management Process (Hypothetical) R&R Initiative Vishal Sheth, CSM, CSP, CSPO, PMP Copyright Vishal Sheth 2012
  • 2. Why Are We Here?  Project R&R is ready for launch  Scope:  Reinvent Ratings & Reviews  Expected Timeline:  Up to a year  Estimated Resources:  3 Product Teams (PO, Dev, QA, UX, Pubs)  1 Marketing / 1 Product Mktg Resource  1 Client Services Resource  0.5 Sales / 0.5 Support Resource  Benefit:  Revolutionize the world of Ratings & Reviews while generating MIRR >= 20% Copyright Vishal Sheth 2012
  • 3. What Does The Opportunity Look Like?  Value Proposition (Tangible & Intangible)  Target Market  Market Size (Revenues/Savings)  Success Metrics  Competitive Landscape  Our Differentiator  Market Timing  Deployment Strategy  Critical Success Factors *Supplemental handout has R&R Opportunity Assessment Copyright Vishal Sheth 2012
  • 4. What are our Assumptions?  R&R Initiative is the highest value opportunity at this time  We want to be nimble to market opportunities/changes  Teams are available for the planned duration and are co-located except for some Sales/Mktg folks  Each Feature is independently releasable/configurable  Users will be available as needed for Usability Tests  Program Manager will play a multi-faceted role:  Overall oversight & cross-functional coordination  ScrumMaster for the 3 Delivery teams  Release Manager (managing business readiness)  Vendor Manager (if needed)  No 3rd Party Vendor/Tool needed  Sprints are 2 weeks long Copyright Vishal Sheth 2012
  • 5. What Is Our Game Plan? 1. Smart Scoping: Zoom in on 20% of the features that derive 80% of benefit 2. Integrated Quality: Not just Robustness but Usefulness and Usability too 3. Cross Functional Discovery: Involve all functions up-front 4. Feedback Loops: Understand feedback to drive positive change – Agility 5. Escalation Protocol: Surface concerns early and often 6. Proactive Risk Management: Identify and address highest risk at all times 7. Success Metrics: Keep an eye on objective and subjective measurements 8. Phase Gate Approach: Regular checkpoints and course correction 9. Meticulous Planning, Coordination and Communication: Planning and visibility Cross Team, Inter Team, Stakeholders, Sponsor Copyright Vishal Sheth 2012
  • 6. Smart Scoping  Simplicity will be our overarching theme  The art of maximizing the amount of work not done  Smart Scoping - Secure highest value (to customers & business) as early as possible  80% of value is typically derived from 20% of the features  MS Word, Excel etc  Smart Prioritization  Mitigate highest risk (by Probability and Impact) as early as possible  Architectural Feasibility/Technical challenges  Legal issues  Align cross-team integration points  Ensure early validation of technology touch points Copyright Vishal Sheth 2012
  • 7. Integrated Quality – Fitness For Use  We ensure robustness in smart yet cost effective ways Manual System Affected Sub-System Integration UI Functional Unit As Needed; As Little As Possible Every Sprint Daily Every Build Copyright Vishal Sheth 2012
  • 8. Integrated Quality – Useful & Usable  Usability validation is built into process  Usability Testing  Visual Design  Interaction Design  UI Implementation  Usability Testing & Localization for International Clients from Phase 1 Copyright Vishal Sheth 2012
  • 9. Cross-Functional Discovery PO UX TL/ARCH PGM STAKE HOLDERS User Needs Assessment Create/Maint ain Epics Use Cases / Workflows Update Roadmap Write Stories Persona Study Clickable Prototypes Preliminary IA High Fidelity Prototypes Buy v/s Build Decisions 3rd Party Evaluation Proof of Concept Create Release Roadmap / Release Plan Plan High Level Dependencies Facilitation GATE II Review Roadmap / Prototypes User/Client Svcs F/back GATE 1 Review Use Case Details t Copyright Vishal Sheth 2012
  • 10. Feedback Loops  We will use every opportunity to Inspect-and-Adapt  Product Feedback Loops  Global Usability Testing – Wireframes/Prototypes  Sprint Demos / UATs  Usability Testing – Functional  Stage Gates  Post Release - Alpha, Beta, GA releases  Process/Status Feedback Loops (PGM to facilitate)  Daily Scrum (Delivery Team)  Scrum-of-Scrum (Delivery Leads for Dev, QA, PO) – As needed  Weekly Discovery Team Meetings (incl. Pubs, UX, Client Svcs)  Weekly Grooming Meetings (Delivery Team)  Sprint Retrospective (Delivery Team) - keep an eye on recurring topics  Bi-Weekly Program Meeting (Sponsor/Stakeholder/Lead)  Market Launch Team Meeting - Sales, Mktg, Product Mktg, Client Svcs, PO  Post-Launch Review Meetings  (Optional) Agile Brown Bag Lunches Copyright Vishal Sheth 2012
  • 11. Established Escalation Protocol  We are an empowered and responsible Team  If issue can be resolved by Individual, it should be  If issue can be resolved by Team, it should be  If issue is across Teams, it should be addressed at Scrum-of- Scrum level  If issue is Organizational, it should be raised at SoS or to PGM  Escalation Opportunities  Report to PGM – Always & Anytime  Team – Email, Daily Scrum, Retrospective  Program – Email, Daily SoS  Sponsor – Tier 1: Immediate; Tier 2: Bi-weekly Sponsor Mtg  Public log of Open Blockers Date Details Severity Impact Owner Status / ETA Copyright Vishal Sheth 2012
  • 12. Proactive Risk Management  We will succeed and fail together  An unmitigated risk can wipe out best laid plans  No one person can identify all Issues/Risks  Environment of collective ownership, openness, awareness  All Risks Matter and should be reported to PGM  Address Highest Risk Item(s) by Probability & Impact  Not all Risks require action but all require a mitigation plan  P/I Assessment conducted by Discovery Team  Public log of Potential Risk Date Details Probability Impact Owner Mitigation Plan Copyright Vishal Sheth 2012
  • 13. Success Metrics  We will take calculated, measured, Risks  We will monitor tangible and intangible benefits at each phase  Primary focus on Leading Indicators as we iterate in Production  We plan to re-plan and course correct  Tracking to be built in as features are developed  Appropriate Metrics will be reviewed at Phase Gates  Only Features that meet or exceed targets will be promoted from Beta to GA (this comes with a huge side benefit) Feature Category Stated Goal Operational Definition Specification Units Data Needed Leading / Lagging Indicator? Expected Measurable LL UL Target Benefit Actual Copyright Vishal Sheth 2012
  • 14. Phase Gate Approach  While we believe in our ideas, we will optimize spend by testing each hypothesis as quickly as possible  We will review objectively across various dimensions and course correct as appropriate PAB Review MMF Review Architectural Feasibility Usability Review Sprint Demos Alpha Feedback Beta Feedback Post-GA Leading Indicators Review Post-GA Lagging Indicators Review Opportunity Assessment Phase Discovery Phase Implementation Phase Limited Availability Phase General Availability Phase Market Opportunity Window/Competitive Factors Analysis Copyright Vishal Sheth 2012
  • 15. Planning  Release/Feature Level Plans to include:  Milestones  Release/Feature Description  Release/Feature Goals/Metrics  Customer Benefits (to be used by and for Marketing)  Inter-Team Dependencies (Inbound and Outbound)  UX/Design Needs (provided by UX Leads, PO)  Technical Needs (provided by Tech. Leads & IT/Ops)  Regression Needs (provided by QA Lead)  Other Needs (Alpha/Beta Testers, Consulting etc) Copyright Vishal Sheth 2012
  • 16. Milestones t Feature1 DISCOVERY: User Needs, Persona, Use Cases PHASE GATE 1 PHASE GATE 2 PHASE GATE 3 PHASE GATE 4 PHASE GATE 5 PHASE GATE 6 DISCOVERY: IA, Usability Testing, MMF/Stories, PoC SPRINTS ALPHA BETA GA HARDENING: Bug Fixing, Usability Testing VALIDATION: Metrics Collection, Fdbck/Improvements GA Launch Prep HARDENING: Bug Fixing, Metrics Collection MONITORING/IMPROVEMENTS: Metrics Collection, Fdbck/Improvements Copyright Vishal Sheth 2012
  • 17. Coordination & Communication  Dashboard  Regular Product/Process/Status Meetings  Management  Cross-Functional  Cross-Team  Inter & Intra Team  Mailing lists for each of the above groups  Phase Gate Review Meetings  Docs – Tech Pubs, Samples, Marketing/Sales Pitch  Training – Videos, Sessions (Client Svcs, Support)  Escalation Protocol (for anything outside the norm) Copyright Vishal Sheth 2012
  • 18. Dashboard  Pulls everything together into a consistent snapshot  Overall timeline with critical Milestones from Release Plan  For each Release/Feature currently in-flight:  Current state of Minimum Marketable Feature (MMF)  Blockers/Risks/Delays  Dependency Tracking  Current Spend (# of FTE) v/s Budgeted Spend - Burn Rate  Success Metrics  For each Team currently assigned:  MMF/Component being worked on  Blockers/Risks/Delays  Dependency Tracking  Sprint Burndown/Velocity/Total MMF Size  For each Feature already released:  Maintenance Spend (Man Hours)  Customer Satisfaction (SUS Score)  Metrics - Expected v/s Realized Benefit in Production Copyright Vishal Sheth 2012
  • 19. Summary – Agile PGM Model Successful Programs depend on pulling together multiple Factors 1. Smart Scoping: Zoom in on 20% of features that derive 80% of benefit 2. Integrated Quality: Robustness, Usefulness and Usability too 3. Cross Functional Discovery: Involve all functions up-front 4. Feedback Loops: Understand feedback to drive positive change – Agility 5. Escalation Protocol: Surface concerns early and often 6. Proactive Risk Management: Identify and address highest risk at all times 7. Success Metrics: Keep an eye on objective and subjective measurements 8. Phase Gate Approach: Regular checkpoints and course correction 9. Meticulous Planning, Coordination and Communication: Planning and visibility Cross Team, Inter Team, Stakeholders, Sponsor(s). Copyright Vishal Sheth 2012
  • 20. Questions? Vishal Sheth, CSM, CSP, CSPO, PMP Pragmatic Agile PMO vsheth@yahoo.com Copyright Vishal Sheth 2012