Progress 
 Most contract provides the employer/ his 
administrator with little control over 
contractor’s work progress, as it is the 
contractor’s obligation to finish on time-cl 
21.1 
 However, it is common for the contract to 
include a requirement for the contractor to 
submit the work programs to the employer-cl 
3.5
 In any circumstances, the work program shall 
not constitute as the contract document- cl. 
3.6 
Max W Abrahamson in Engineering Law and 
ICE Contracts(1991): 
‘ The programme, for example, is not a 
contractual in the same sense as the 
specification, since neither the contractor nor 
the employer is bound by it. The programme 
is what it is- a document indicating the 
intention of the contractor at the time he 
furnishes it as to how he intends to 
progamme the works’.
Delay 
 If there is no provision in the contract 
relating to extension of contract’s 
period, then if the contract is not 
completed on time, the employer is 
entitled for liquidated damages.
Chua Ngah Chin v Ng Kie En 
The plf employed the def as the 
contractors to build a terrace house in 
Kuching, Sarawak.The contract has no 
provision for extension of contract 
period except for cl.6 of the contract 
which stated:- if the building was not 
completed within 15 months of the date 
of the contract ‘raining days and public 
holidays expressly excluded’, the owner 
could revoke the contract.
The contractor later claimed for extension of 
four months but still failed to complete the 
work after the extension period. The plf gave 
notice of termination and applied for removal 
of def’s caveat of the land. 
Held: The owner (plf) is entitled to revoke the 
contract and removal of the caveat. The term 
raining days was imprecise, but even if the 
contractor had been allowed four months, as 
he had claimed, he had still failed to 
complete.
 In the absence of express provision on extension 
of period of completion, the architect has no 
power to extend the period. 
Peak Construction (Liverpool) Ltd v McKinney 
Foundations Ltd 
Per Salmon LJ: ‘If the employer wishes to recover 
liquidated damages for failure by the contractors, 
to complete on time in spite of the fact that some 
of the delay is due to the employer’s own fault, or 
breach of contract, then the extension of time 
clause should provide, expressly or by necessary 
inference, for an extension on account of such a 
fault or breach on the part of the employer.’
Extension of time (EoT) 
 In the standard form of building 
contract, there is a provision on rights of 
the contractor to apply to extension of 
the contract period-cl.23 
 Rights and procedure: cl 23.1 
 Right of employer via architect – cl 23.4 
– Request for further document- cl 23.3 
–Other Considerations-cl 23.5
 Even though, it is the contractual right 
of the contractor to claim for EoT, the 
contractor also has the obligation to 
prevent any delay-cl.23.6
Events for EoT 
 The architect in exercising his discretion 
to grant Eot has to take into 
consideration the relevant event for 
EoT: cl.23.8 (a)-(x) 
(These circumstances are known as 
grounds for EoT)

More Related Content

DOCX
Law of Duress in Malaysia and United Kingdom
PPT
Jual janji
DOCX
Discharge of Contract By Breach
PPTX
Topic 10_Maintenance of Wife and Children under Civil Law.pptx
PPT
Building contract introduction
PPT
Land law ii (charge general)
PDF
Land Law II notes - For Revision Purposes Only
DOCX
Nota kontrak – Pelepasan melalui doktrin kekecewaan
Law of Duress in Malaysia and United Kingdom
Jual janji
Discharge of Contract By Breach
Topic 10_Maintenance of Wife and Children under Civil Law.pptx
Building contract introduction
Land law ii (charge general)
Land Law II notes - For Revision Purposes Only
Nota kontrak – Pelepasan melalui doktrin kekecewaan

What's hot (20)

PPTX
PPTX
Case Normala samsudin v Keluarga Communication
PPTX
Ll1 slides extent of ownership and enjoyment of land part 2
PPTX
Non fatal offences - criminal force
PPTX
LAND LAW 1 slides dealings part 1
PPT
Formation
PPT
Lien and lien holder's caveat
DOCX
Parol Evidence Rule Contract Law Malaysia
PDF
LAND LAW CASES
PPT
Peranan & Etika Peguam Syarie
PPT
law of contract
PDF
LAW605 Notes (Family Law 1: Islamic) - EXCEPT INTRODUCTION & POLYGAMOUS MARRIAGE
PPTX
PPT
Article 7 prohibition of retrospective criminal law
DOCX
CONTOH MOOTING OLEH PELAJAR TAHUN AKHIR DI UUM
PPTX
PP vs YAP TAI [1947] 1 MLJ 50
PPT
registrars caveat
DOCX
PDF
Equity - Exam Notes (1)
PDF
DIVORCE - FAMILY LAW IN MALAYSIA
Case Normala samsudin v Keluarga Communication
Ll1 slides extent of ownership and enjoyment of land part 2
Non fatal offences - criminal force
LAND LAW 1 slides dealings part 1
Formation
Lien and lien holder's caveat
Parol Evidence Rule Contract Law Malaysia
LAND LAW CASES
Peranan & Etika Peguam Syarie
law of contract
LAW605 Notes (Family Law 1: Islamic) - EXCEPT INTRODUCTION & POLYGAMOUS MARRIAGE
Article 7 prohibition of retrospective criminal law
CONTOH MOOTING OLEH PELAJAR TAHUN AKHIR DI UUM
PP vs YAP TAI [1947] 1 MLJ 50
registrars caveat
Equity - Exam Notes (1)
DIVORCE - FAMILY LAW IN MALAYSIA
Ad

Viewers also liked (14)

PPSX
Week1a pptslides general info jan 14
PPT
Rescission for Breach
PPTX
Social Work 2014 15 APA 6th ed. Formatting Rules
PPTX
APA Basics: Citations
PPTX
Apa citing, paraphrasing and quoting presentation
PPTX
Performance of Contract ,Business Law case
PPT
Week4g pptslides in text citation- quoting 4
PPT
APA Format Examples
PPTX
Review of Related Literature
PPT
Review of related literature
PPTX
Related Literature and Related Studies
PPTX
Literature Review (Review of Related Literature - Research Methodology)
DOCX
Chapter 2-Realated literature and Studies
PDF
Review of Related Literature-Thesis Guide
Week1a pptslides general info jan 14
Rescission for Breach
Social Work 2014 15 APA 6th ed. Formatting Rules
APA Basics: Citations
Apa citing, paraphrasing and quoting presentation
Performance of Contract ,Business Law case
Week4g pptslides in text citation- quoting 4
APA Format Examples
Review of Related Literature
Review of related literature
Related Literature and Related Studies
Literature Review (Review of Related Literature - Research Methodology)
Chapter 2-Realated literature and Studies
Review of Related Literature-Thesis Guide
Ad

Similar to Progress and delay_ (20)

PPTX
Professional Practice II - Presentation - Construction Delays & EOT
PDF
Sectional completion and partial possession by employer PP2 Coursework 1
PPTX
Professional practice 2
PPT
Substitute and vicarious_performance
PPTX
Lecture 8-determination-of-own-employment-by
PDF
Techno Engineering & Associates
PPT
Defects liability
PDF
PP2 Seminar Presentation
DOCX
Cl compilation
PPTX
Seminar p8x
PPTX
Pp2 chapter 1 cheeyong & yih shyang
PDF
PP2 - Seminar Presentation
PPTX
A Case Study based on FIDIC and PAM Form 2006
PDF
Seminar - Partial Possession by Employer
PPTX
PP Seminar Tutorial 7
PDF
CE-CONTRACTS-REPORT.pdf
PDF
Time Bars and their enforceability in English law EPC contracts
PDF
Construction Law Assignment BQS Taylor's University
PDF
PP2 COMPILCATION
PDF
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
Professional Practice II - Presentation - Construction Delays & EOT
Sectional completion and partial possession by employer PP2 Coursework 1
Professional practice 2
Substitute and vicarious_performance
Lecture 8-determination-of-own-employment-by
Techno Engineering & Associates
Defects liability
PP2 Seminar Presentation
Cl compilation
Seminar p8x
Pp2 chapter 1 cheeyong & yih shyang
PP2 - Seminar Presentation
A Case Study based on FIDIC and PAM Form 2006
Seminar - Partial Possession by Employer
PP Seminar Tutorial 7
CE-CONTRACTS-REPORT.pdf
Time Bars and their enforceability in English law EPC contracts
Construction Law Assignment BQS Taylor's University
PP2 COMPILCATION
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد

More from Hafizul Mukhlis (20)

DOCX
Fe practice 4 collaborative learning among msian students (1)
DOCX
Fe practice 3 social networking (1)
DOCX
Fe practice 2 coping strat (1)
DOC
Rp sample full text (lily)
DOCX
Arrrsa mid sem sample test anxiety
PPT
Subject verb agreement
PPT
Week 10 abstracts 2
PPT
Week 10 conclusion grammar notes
PPT
Week 10 the conclusion
PPT
Week 9 writing discussion
PPT
Week 8 presenting data in charts, graphs, and tables 2
PPTX
Week8 writing the results
PPSX
Week6 7a- developing a questionnaire
PPT
Week 6 7c - language in procedures & method
PPT
Week5b writing research questions
PPT
Week5a writing statement of the problem & general purpose 2
PPT
Week4f pptslides in text citation - summarising
PPT
Week4e pptslides in text citation-synthesizing 2
PPSX
Week4d pptslides writing with coherence
PDF
Week4c pdffile reporting verbs
Fe practice 4 collaborative learning among msian students (1)
Fe practice 3 social networking (1)
Fe practice 2 coping strat (1)
Rp sample full text (lily)
Arrrsa mid sem sample test anxiety
Subject verb agreement
Week 10 abstracts 2
Week 10 conclusion grammar notes
Week 10 the conclusion
Week 9 writing discussion
Week 8 presenting data in charts, graphs, and tables 2
Week8 writing the results
Week6 7a- developing a questionnaire
Week 6 7c - language in procedures & method
Week5b writing research questions
Week5a writing statement of the problem & general purpose 2
Week4f pptslides in text citation - summarising
Week4e pptslides in text citation-synthesizing 2
Week4d pptslides writing with coherence
Week4c pdffile reporting verbs

Recently uploaded (20)

PPTX
RULE_4_Out_of_Court_or_Informal_Restructuring_Agreement_or_Rehabilitation.pptx
PPT
Understanding the Impact of the Cyber Act
DOCX
FOE Reviewer 2022.docxhgvgvhghhghyjhghggg
PPTX
FFFFFFFFFFFFFFFFFFFFFFTA_012425_PPT.pptx
PDF
New York State Bar Association Journal, September 2014
PDF
Vinayaka Mission Law School Courses and Infrastructure.pdf
PPTX
Lecture Notes on Family Law - Knowledge Area 5
PPTX
POSH Awareness and policy ppt with all design covering .
PPTX
Ethiopian Civil procedure short note.pptx
PPTX
Ethiopian Tort Law Short Note by Mikiyas.pptx
PDF
OpenAi v. Open AI Summary Judgment Order
PPTX
PART-3-FILIPINO-ADMINISTRATIVE-CULTURE.pptx
PDF
Analysis Childrens act Kenya for the year 2022
PDF
Kayla Coates Wins no-insurance case Against the Illinois Workers’ Benefit Fund
PPT
Over view on IPR and its components :ppt
PDF
Notes to accompany the TMT and FRAND Overview Slides
PDF
250811-FINAL-Bihar_Voter_Deletion_Analysis_Presentation.pdf
PDF
SUMMARY CASES-42-47.pdf tax -1 257++/ hsknsnd
PDF
The AI & LegalTech Surge Reshaping the Indian Legal Landscape
PDF
The Advocate, Vol. 34 No. 1 Fall 2024
RULE_4_Out_of_Court_or_Informal_Restructuring_Agreement_or_Rehabilitation.pptx
Understanding the Impact of the Cyber Act
FOE Reviewer 2022.docxhgvgvhghhghyjhghggg
FFFFFFFFFFFFFFFFFFFFFFTA_012425_PPT.pptx
New York State Bar Association Journal, September 2014
Vinayaka Mission Law School Courses and Infrastructure.pdf
Lecture Notes on Family Law - Knowledge Area 5
POSH Awareness and policy ppt with all design covering .
Ethiopian Civil procedure short note.pptx
Ethiopian Tort Law Short Note by Mikiyas.pptx
OpenAi v. Open AI Summary Judgment Order
PART-3-FILIPINO-ADMINISTRATIVE-CULTURE.pptx
Analysis Childrens act Kenya for the year 2022
Kayla Coates Wins no-insurance case Against the Illinois Workers’ Benefit Fund
Over view on IPR and its components :ppt
Notes to accompany the TMT and FRAND Overview Slides
250811-FINAL-Bihar_Voter_Deletion_Analysis_Presentation.pdf
SUMMARY CASES-42-47.pdf tax -1 257++/ hsknsnd
The AI & LegalTech Surge Reshaping the Indian Legal Landscape
The Advocate, Vol. 34 No. 1 Fall 2024

Progress and delay_

  • 1. Progress, Delay and Completion Lecture week 5/6
  • 2. Progress  Most contract provides the employer/ his administrator with little control over contractor’s work progress, as it is the contractor’s obligation to finish on time-cl 21.1  However, it is common for the contract to include a requirement for the contractor to submit the work programs to the employer-cl 3.5
  • 3.  In any circumstances, the work program shall not constitute as the contract document- cl. 3.6 Max W Abrahamson in Engineering Law and ICE Contracts(1991): ‘ The programme, for example, is not a contractual in the same sense as the specification, since neither the contractor nor the employer is bound by it. The programme is what it is- a document indicating the intention of the contractor at the time he furnishes it as to how he intends to progamme the works’.
  • 4. Delay  If there is no provision in the contract relating to extension of contract’s period, then if the contract is not completed on time, the employer is entitled for liquidated damages.
  • 5. Chua Ngah Chin v Ng Kie En The plf employed the def as the contractors to build a terrace house in Kuching, Sarawak.The contract has no provision for extension of contract period except for cl.6 of the contract which stated:- if the building was not completed within 15 months of the date of the contract ‘raining days and public holidays expressly excluded’, the owner could revoke the contract.
  • 6. The contractor later claimed for extension of four months but still failed to complete the work after the extension period. The plf gave notice of termination and applied for removal of def’s caveat of the land. Held: The owner (plf) is entitled to revoke the contract and removal of the caveat. The term raining days was imprecise, but even if the contractor had been allowed four months, as he had claimed, he had still failed to complete.
  • 7.  In the absence of express provision on extension of period of completion, the architect has no power to extend the period. Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd Per Salmon LJ: ‘If the employer wishes to recover liquidated damages for failure by the contractors, to complete on time in spite of the fact that some of the delay is due to the employer’s own fault, or breach of contract, then the extension of time clause should provide, expressly or by necessary inference, for an extension on account of such a fault or breach on the part of the employer.’
  • 8. Extension of time (EoT)  In the standard form of building contract, there is a provision on rights of the contractor to apply to extension of the contract period-cl.23  Rights and procedure: cl 23.1  Right of employer via architect – cl 23.4 – Request for further document- cl 23.3 –Other Considerations-cl 23.5
  • 9.  Even though, it is the contractual right of the contractor to claim for EoT, the contractor also has the obligation to prevent any delay-cl.23.6
  • 10. Events for EoT  The architect in exercising his discretion to grant Eot has to take into consideration the relevant event for EoT: cl.23.8 (a)-(x) (These circumstances are known as grounds for EoT)