SlideShare a Scribd company logo
Project Execution
Martin Sillaots
2019
# 12
Project Phases and Processes
Initiation
Planning
Execution Control
Closing
www.projektor.ee/pm/#execution
Project Execution and Control
Information
distribution
Project
execution
Procurement
management
Reporting
Team
development
Schedule
control
Scope
verification
Cost
control
Quality
control
Risk
monitoring
Change
management
Planning
Closing
www.projektor.ee/pm/#execution
Execution and Control in Short
• Information distribution
• Work execution
• Work reporting
• Comparing actual and baseline plans
• Making changes in the plans
www.projektor.ee/pm/#execution
Information Distribution
Making information available in timely manner
www.projektor.ee/pm/#execution
Communication in the Project Execution
Information
distribution
Project
execution
Procurement
management
Reporting
Team
development
Schedule
control
Scope
verification
Cost
control
Quality
control
Risk
monitoring
Change
management
Planning
Closing
www.projektor.ee/pm/#execution
Inputs:
- Project Plan
- Communication
management plan
- Work Results
Methods:
- Communication Skills
- Distribution Methods
- IS
Outputs
- Change requests
Information Distribution
www.projektor.ee/pm/#execution
Communication Methods
• Meetings
• Time sheets
• Document distribution system
• Databases
• PMIS
• Virtual meeting and workspaces
www.projektor.ee/pm/#execution
Information Gathering and Retrieval
System
• Data that needs to be collected
• Data collection frequency
• Data reliability
• Data input
• Change management
• Comparisons with the initial plans
www.projektor.ee/pm/#execution
e.g. Collected data
• What is the task actual starting date
• If the actual start is different from the baseline beginning then
why?
• What is the actual finis of the task?
• If different from the plan then why?
• If task is not finished then what is the estimation for
remaining duration?
• If estimation is different from the plan then why?
www.projektor.ee/pm/#execution
Date Number
of Hours
WP Activity description
20.09.16 4 Management Projet meeting
Total: 4
e.g. Time Sheet
www.projektor.ee/pm/#execution
Work Execution
Performing actins to accomplish the project
deliverables
www.projektor.ee/pm/#execution
Execution in the Project Execution 
Information
distribution
Project
execution
Procurement
management
Reporting
Team
development
Schedule
control
Scope
verification
Cost
control
Quality
control
Risk
monitoring
Change
management
Planning
Closing
www.projektor.ee/pm/#execution
Inputs:
- Project plan
- Approved preventive
actions
- Approved change
requests
Methods:
- PM methods
- PMIS
Outputs
- Deliverables
- Change requests
- Corrective actions
- Preventive actions
- Defect repairs
- Performance
information
Work Execution
www.projektor.ee/pm/#execution
Procurement Contract
Administration
Ensuring that seller’s performance meets
contractual requirements
www.projektor.ee/pm/#execution
Procurement in the Project Execution
Information
distribution
Project
execution
Procurement
management
Reporting
Team
development
Schedule
control
Scope
verification
Cost
control
Quality
control
Risk
monitoring
Change
management
Planning
Closing
www.projektor.ee/pm/#execution
Inputs:
- Contract
- Selected sellers
- Performance reports
- Approved change
requests
Methods:
- Contract change
control system
- Performance review
- Inspections
- Performance
reporting
- Payment system
- Claims admin
- IS
Outputs
- Documentation
- Change Requests
- Corrective actions
- Plan updates
Procurement Contract
Administration
www.projektor.ee/pm/#execution
Stakeholders Management
Satisfying stakeholders communication needs
and resolving issues
www.projektor.ee/pm/#execution
Inputs:
- Communication plan
- Organizational
assets
Methods:
- Communication
techniques
- Issue log
Outputs
- Resolved issues
- Change requests
- Corrective actions
- Plan updates
Stakeholders Management
www.projektor.ee/pm/#execution
Performance Reporting
Collecting baseline and performance data and
distributing to stakeholders
www.projektor.ee/pm/#execution
Reporting in the Project Execution
Information
distribution
Project
execution
Procurement
management
Reporting
Team
development
Schedule
control
Scope
verification
Cost
control
Quality
control
Risk
monitoring
Change
management
Planning
Closing
www.projektor.ee/pm/#execution
Inputs:
- Project plan
- Performance
information
- Performance
measurements
- Deliverables
- Approved change
requests
Methods:
- Information
presentation tools
- Information
gathering and
compilation
- Review meetings
- Reporting systems
Outputs
- Performance reports
- Forecasts
- Change requests
Performance Reporting
www.projektor.ee/pm/#execution
Performance Information
• Initial plan
• Current status
• Estimations
www.projektor.ee/pm/#execution
Reporting methods
• Data gathering
• Difference analysis
• Earned Value Analysis (EVA)
• Trend analysis
www.projektor.ee/pm/#execution
Data Gathering with the Time Table
www.projektor.ee/pm/#execution
Difference Analysis With the Gantt
www.projektor.ee/pm/#execution
Milestone Analysis
Baseline
Actual
Baseline
Actual
www.projektor.ee/pm/#execution
Earned Value Analysis EVA
• Method for measuring project progress
• Project scope, duration and cost integration
• Enables to estimate project final cost and duration in
the middle of the project
www.projektor.ee/pm/#execution
Concept of Earned Value
• Planned value (PV) = planned work × budget price
• Earned value (EV) = work completed ratio × budget
price (actual performance % × budgeted total cost)
• Actual cost (AC) = actual work × actual cost
www.projektor.ee/pm/#execution
Planned Value - Earned Value - Actual Value
BMBOK Guide 2009 www.projektor.ee/pm/#execution
Earned Value Implementation
• Cost variance (CV) = earned value (EV) – actual cost (AC)
• Schedule variance (SV) = earned value (EV) – planned value
(PV)
• Cost estimation (cost performance index CPI) = earned
value(EV) / actual cost (AC)
• Duration estimation (schedule performance index SPI) =
earned value (EV) / planned value (PV)
www.projektor.ee/pm/#execution
Planned task duration 4 d
Planned resource cost 30 $/h
Planned task total cost 960 $/h
Completed duration 2 d
Planned percent complete 50%
Remaining duration estimation 3 d
Actual percent complete 40%
Actual resource cost 25 $/h
How big is:
Planned value 480 $
Earned value 384 $
Actual value 400 $
Estimated total cost 1000 $
www.projektor.ee/pm/#execution
Planned task duration 4 d
Planned resource cost 30 $/h
Planned task total cost 960 $/h = 4d x 30 x 8h
Completed duration 2 d
Planned percent complete 50% = 2d / 4d
Remaining duration estimation 3 d
Actual percent complete 40% = 2d / 5d
Actual resource cost 25 $/h
How big is:
Planned value 480 $ = 2d x 30 x 8h
Earned value 384 $ = 960 x 40%
Actual value 400 $ = 2d x 25 x 8h
Estimated total cost 1000 $ = 5d x 8d x 25$/h
www.projektor.ee/pm/#execution
Trend Analysis
Cumulative Cost
Estimation
Budget
www.projektor.ee/pm/#execution
www.projektor.ee/pm/#execution
End Execution
martinsillaots@gmail.com

More Related Content

PPTX
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
PPT
Animal guessing
PPT
Construction Claims
PDF
Project Execution Powerpoint Presentation Slides
PDF
Project Management Plan
PDF
Project Resource Management
PDF
Best Tea shop Franchise - TEA TIME
PDF
Sap activate overview
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
Animal guessing
Construction Claims
Project Execution Powerpoint Presentation Slides
Project Management Plan
Project Resource Management
Best Tea shop Franchise - TEA TIME
Sap activate overview

What's hot (20)

PPTX
Project cost control
PPTX
5 phases of project management
PPTX
Evolution of project management
PPT
09. Project Cost Management
PPTX
Project management process and Project Management Knowledge areas
PPTX
Project management and project life cycle
PPTX
Project Management Tools
PPTX
Project management
PPTX
tcc primavera
PPT
project management concepts
PPTX
Project Management Foundations Course 101 - Project Management Concepts
PPT
Project planning and Scheduling
PPT
Project Management Tools and Techniques
PPS
An Introduction To Project Management
PDF
Introduction to Project Management
PPTX
Project Management
DOC
Roles and-responsibilities-project manager
PPTX
03 Construction Project Planning and Scheduling
PDF
Project Management Concepts (from PMBOK 5th Ed)
PDF
Fundamentals of project management
Project cost control
5 phases of project management
Evolution of project management
09. Project Cost Management
Project management process and Project Management Knowledge areas
Project management and project life cycle
Project Management Tools
Project management
tcc primavera
project management concepts
Project Management Foundations Course 101 - Project Management Concepts
Project planning and Scheduling
Project Management Tools and Techniques
An Introduction To Project Management
Introduction to Project Management
Project Management
Roles and-responsibilities-project manager
03 Construction Project Planning and Scheduling
Project Management Concepts (from PMBOK 5th Ed)
Fundamentals of project management
Ad

Similar to Project Execution (20)

PPTX
Project Cost Management
PPTX
Project Control
PPTX
Project Communication Management
PDF
C03.08-09-ExecutionMonitoringControl.key.pdf
PDF
C03.07-BudgetingAndAccounting.key.pdf
PPTX
Project Integration Management
PPTX
Epm dimensys introductie gvk
PPTX
Project Scope Management
PPSX
PMP Exam Preparation Course: 06 Project Cost Management
PDF
Main Features
PDF
Unifier webinar-final-printed
PDF
CAD and BIM Outsourcing Services
PDF
Sap solutions presentation
PDF
Bridging the cost schedule divide - integrating primavera and cost systems ppt
PDF
Engineering and_SAP_Solutions_for_ECO_Presentation.pdf
PPTX
6- PMP Training - Cost Management
PPTX
Cost management
PPTX
Aviation grants GSA/EEX.0030/2015 - Project Management Training
PPTX
Epm demonstration projerct online and project server 2013
PDF
Rising from projects to programs and improve accountability - Oracle Primaver...
Project Cost Management
Project Control
Project Communication Management
C03.08-09-ExecutionMonitoringControl.key.pdf
C03.07-BudgetingAndAccounting.key.pdf
Project Integration Management
Epm dimensys introductie gvk
Project Scope Management
PMP Exam Preparation Course: 06 Project Cost Management
Main Features
Unifier webinar-final-printed
CAD and BIM Outsourcing Services
Sap solutions presentation
Bridging the cost schedule divide - integrating primavera and cost systems ppt
Engineering and_SAP_Solutions_for_ECO_Presentation.pdf
6- PMP Training - Cost Management
Cost management
Aviation grants GSA/EEX.0030/2015 - Project Management Training
Epm demonstration projerct online and project server 2013
Rising from projects to programs and improve accountability - Oracle Primaver...
Ad

More from Martin Sillaots (20)

PPTX
eAdventureEN
PPTX
Documents
PPTX
Game Monetisation and Marketing
PPTX
Prototyping
PPTX
User Interface
PPTX
Level Design
PPTX
PPTX
Characters
PPTX
Game World
PPTX
Game Balancing
PPTX
Core Mechanics
PPTX
Gameplay
PPTX
Game Concept
PPTX
Game Idea
PPTX
Game Design Process
PPTX
Game Elements
PPTX
Introduction to Game Design
PPTX
Project Closing
PPTX
Project Plan Presentation Example
PPTX
Project Risk Management
eAdventureEN
Documents
Game Monetisation and Marketing
Prototyping
User Interface
Level Design
Characters
Game World
Game Balancing
Core Mechanics
Gameplay
Game Concept
Game Idea
Game Design Process
Game Elements
Introduction to Game Design
Project Closing
Project Plan Presentation Example
Project Risk Management

Recently uploaded (20)

PDF
Complications of Minimal Access Surgery at WLH
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
SOIL: Factor, Horizon, Process, Classification, Degradation, Conservation
PDF
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
PPTX
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
PPTX
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
PDF
What if we spent less time fighting change, and more time building what’s rig...
PDF
medical_surgical_nursing_10th_edition_ignatavicius_TEST_BANK_pdf.pdf
PDF
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
PPTX
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
DOC
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
PPTX
Lesson notes of climatology university.
PPTX
Unit 4 Skeletal System.ppt.pptxopresentatiom
PDF
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
PDF
advance database management system book.pdf
PPTX
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
PPTX
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
PDF
Trump Administration's workforce development strategy
PPTX
Digestion and Absorption of Carbohydrates, Proteina and Fats
PDF
Empowerment Technology for Senior High School Guide
Complications of Minimal Access Surgery at WLH
Final Presentation General Medicine 03-08-2024.pptx
SOIL: Factor, Horizon, Process, Classification, Degradation, Conservation
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
What if we spent less time fighting change, and more time building what’s rig...
medical_surgical_nursing_10th_edition_ignatavicius_TEST_BANK_pdf.pdf
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
Lesson notes of climatology university.
Unit 4 Skeletal System.ppt.pptxopresentatiom
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
advance database management system book.pdf
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
Trump Administration's workforce development strategy
Digestion and Absorption of Carbohydrates, Proteina and Fats
Empowerment Technology for Senior High School Guide

Project Execution

  • 2. Project Phases and Processes Initiation Planning Execution Control Closing www.projektor.ee/pm/#execution
  • 3. Project Execution and Control Information distribution Project execution Procurement management Reporting Team development Schedule control Scope verification Cost control Quality control Risk monitoring Change management Planning Closing www.projektor.ee/pm/#execution
  • 4. Execution and Control in Short • Information distribution • Work execution • Work reporting • Comparing actual and baseline plans • Making changes in the plans www.projektor.ee/pm/#execution
  • 5. Information Distribution Making information available in timely manner www.projektor.ee/pm/#execution
  • 6. Communication in the Project Execution Information distribution Project execution Procurement management Reporting Team development Schedule control Scope verification Cost control Quality control Risk monitoring Change management Planning Closing www.projektor.ee/pm/#execution
  • 7. Inputs: - Project Plan - Communication management plan - Work Results Methods: - Communication Skills - Distribution Methods - IS Outputs - Change requests Information Distribution www.projektor.ee/pm/#execution
  • 8. Communication Methods • Meetings • Time sheets • Document distribution system • Databases • PMIS • Virtual meeting and workspaces www.projektor.ee/pm/#execution
  • 9. Information Gathering and Retrieval System • Data that needs to be collected • Data collection frequency • Data reliability • Data input • Change management • Comparisons with the initial plans www.projektor.ee/pm/#execution
  • 10. e.g. Collected data • What is the task actual starting date • If the actual start is different from the baseline beginning then why? • What is the actual finis of the task? • If different from the plan then why? • If task is not finished then what is the estimation for remaining duration? • If estimation is different from the plan then why? www.projektor.ee/pm/#execution
  • 11. Date Number of Hours WP Activity description 20.09.16 4 Management Projet meeting Total: 4 e.g. Time Sheet www.projektor.ee/pm/#execution
  • 12. Work Execution Performing actins to accomplish the project deliverables www.projektor.ee/pm/#execution
  • 13. Execution in the Project Execution  Information distribution Project execution Procurement management Reporting Team development Schedule control Scope verification Cost control Quality control Risk monitoring Change management Planning Closing www.projektor.ee/pm/#execution
  • 14. Inputs: - Project plan - Approved preventive actions - Approved change requests Methods: - PM methods - PMIS Outputs - Deliverables - Change requests - Corrective actions - Preventive actions - Defect repairs - Performance information Work Execution www.projektor.ee/pm/#execution
  • 15. Procurement Contract Administration Ensuring that seller’s performance meets contractual requirements www.projektor.ee/pm/#execution
  • 16. Procurement in the Project Execution Information distribution Project execution Procurement management Reporting Team development Schedule control Scope verification Cost control Quality control Risk monitoring Change management Planning Closing www.projektor.ee/pm/#execution
  • 17. Inputs: - Contract - Selected sellers - Performance reports - Approved change requests Methods: - Contract change control system - Performance review - Inspections - Performance reporting - Payment system - Claims admin - IS Outputs - Documentation - Change Requests - Corrective actions - Plan updates Procurement Contract Administration www.projektor.ee/pm/#execution
  • 18. Stakeholders Management Satisfying stakeholders communication needs and resolving issues www.projektor.ee/pm/#execution
  • 19. Inputs: - Communication plan - Organizational assets Methods: - Communication techniques - Issue log Outputs - Resolved issues - Change requests - Corrective actions - Plan updates Stakeholders Management www.projektor.ee/pm/#execution
  • 20. Performance Reporting Collecting baseline and performance data and distributing to stakeholders www.projektor.ee/pm/#execution
  • 21. Reporting in the Project Execution Information distribution Project execution Procurement management Reporting Team development Schedule control Scope verification Cost control Quality control Risk monitoring Change management Planning Closing www.projektor.ee/pm/#execution
  • 22. Inputs: - Project plan - Performance information - Performance measurements - Deliverables - Approved change requests Methods: - Information presentation tools - Information gathering and compilation - Review meetings - Reporting systems Outputs - Performance reports - Forecasts - Change requests Performance Reporting www.projektor.ee/pm/#execution
  • 23. Performance Information • Initial plan • Current status • Estimations www.projektor.ee/pm/#execution
  • 24. Reporting methods • Data gathering • Difference analysis • Earned Value Analysis (EVA) • Trend analysis www.projektor.ee/pm/#execution
  • 25. Data Gathering with the Time Table www.projektor.ee/pm/#execution
  • 26. Difference Analysis With the Gantt www.projektor.ee/pm/#execution
  • 28. Earned Value Analysis EVA • Method for measuring project progress • Project scope, duration and cost integration • Enables to estimate project final cost and duration in the middle of the project www.projektor.ee/pm/#execution
  • 29. Concept of Earned Value • Planned value (PV) = planned work × budget price • Earned value (EV) = work completed ratio × budget price (actual performance % × budgeted total cost) • Actual cost (AC) = actual work × actual cost www.projektor.ee/pm/#execution
  • 30. Planned Value - Earned Value - Actual Value BMBOK Guide 2009 www.projektor.ee/pm/#execution
  • 31. Earned Value Implementation • Cost variance (CV) = earned value (EV) – actual cost (AC) • Schedule variance (SV) = earned value (EV) – planned value (PV) • Cost estimation (cost performance index CPI) = earned value(EV) / actual cost (AC) • Duration estimation (schedule performance index SPI) = earned value (EV) / planned value (PV) www.projektor.ee/pm/#execution
  • 32. Planned task duration 4 d Planned resource cost 30 $/h Planned task total cost 960 $/h Completed duration 2 d Planned percent complete 50% Remaining duration estimation 3 d Actual percent complete 40% Actual resource cost 25 $/h How big is: Planned value 480 $ Earned value 384 $ Actual value 400 $ Estimated total cost 1000 $ www.projektor.ee/pm/#execution
  • 33. Planned task duration 4 d Planned resource cost 30 $/h Planned task total cost 960 $/h = 4d x 30 x 8h Completed duration 2 d Planned percent complete 50% = 2d / 4d Remaining duration estimation 3 d Actual percent complete 40% = 2d / 5d Actual resource cost 25 $/h How big is: Planned value 480 $ = 2d x 30 x 8h Earned value 384 $ = 960 x 40% Actual value 400 $ = 2d x 25 x 8h Estimated total cost 1000 $ = 5d x 8d x 25$/h www.projektor.ee/pm/#execution

Editor's Notes

  • #4: Manage stakeholders – in parallel with Procurement management.
  • #8: SOW - Statement of Work
  • #15: Depends on the domain and plan
  • #18: SOW - Statement of Work
  • #22: SOW - Statement of Work
  • #24: SOW - Statement of Work
  • #26: Provide information on scope, schedule, cost and quality, risk control.
  • #28: SOW - Statement of Work
  • #39: Total: 5D x 8H x 25$/h = 1000 Eelmine valem ???: 400 / 384 x 960