Project management tutorial


Purpose:	     To provide the basic skills and knowledge needed to effectively manage a
              group project.


Importance: Project scheduling and understanding/handling risk is crucial to success in
            science and engineering.


Goals:        After this activity, you will be able to:

                  •   Break a complex project into manageable sub-projects
                  •   Assign responsibility/ownership of project components
                  •   Set reasonable milestone's for the completion of major tasks
                  •   Perform a risk analysis and integrate mitigation into your planning
                  •   Develop and complete a project plan



Files:

              Project Management
              (Link provided on the section page)
SECTION 1: INTRODUCTION TO PROJECT MANAGEMENT

Project management is the art of matching a project's goals, tasks, and resources to
accomplish a goal as needed. We say "as needed" because one has limited time, money,
and resources (human and machinery) with which to accomplish a goal. One can think of
a project as a process. Figure 1 shows this process as a simplified block diagram.




Figure 1: Simple Project Management System

The process involves inputs and outputs. Successful projects "do the right things, with the
right tools, and in the right way".
SECTION 2: STAGES OF A PROJECT AND HOW TO COMPLETE
THEM

Stage 1: Defining the goals of the project:

Garbage in equals garbage out. If you do not start a project with the correct goal(s), it is
not likely you will accomplish the goal(s). This must be a team activity to ensure that
everyone is given the opportunity to contribute and "buy-in" to what is going to happen.
At the end of this stage, every team member should have an understanding of what must
be accomplished.

This part of the project should end with a document that lists the goals with a short
statement providing some detail. The statement should include a definition of success.
This is a statement that provides a description of the vital few requirements that define
the goal as accomplished. Vital few implies the minimum required to do a good job.
Defining success is necessary to make sure there is no ambiguity as to whether the goal
has been accomplished or not. It also prevents teams from performing unnecessary
iteration and improvement on a goal which has been sufficiently accomplished.

Stage 2: Define project tasks/activities:

Each goal or sub-set of goals should be matched to the tasks required to accomplish them.
This is best done by listing the goals on the left side of a sheet of paper, then writing the
tasks to their right. The group should agree that the specify task will accomplish the goals
as per required in the definitions for success the team laid out in the previous stage.

Stage 3: Determine and verify resource requirements:

Resources are those things which are needed to accomplish the project goals. Resources
may include, but are not limited to:

   •   People
   •   Time
   •   Money
   •   Space
   •   Computers
   •   Software
   •   Others.....
The most important component of determining resource requirements is to be realistic.
One of the most common mistakes project managers make is to underestimate the amount
and type of resources required. This leads to projects that run over budget and fall behind
schedule. DO NOT attempt to do any of the following:

   • Squeeze a project into a shorter time frame to please your boss
   • Cut corners to minimize resource requirements
   • 	 Plan on a best-case basis, i.e. "If everything goes correctly, we will finish on
       time."

Determine what you need to get the job done correctly, on time, and on budget. It is not a
bad idea to build in a safety margin here. This is often referred to as "padding". For
instance, one might multiply the estimated time to complete a task/project by say 20% to
allow for additional time to deal with unexpected occurrences. The amount of padding
usually depends on the certainty one has as to how effectively the resources can be used.
One should keep padding to a minimum.

Once the requirements have been set, it is important to verify that the team will have
access to them. If not, then it is not likely the project will be accomplished as required. In
some instances it may be necessary to acquire resources as the project progresses. This is
risky business and should be avoided if possible. This is risky business. Speaking of
risk...

Stage 4: Identify risks and develop mitigation (backup) plans:

Projects always involve a finite amount of uncertainty (risk) that may lead to problems
and surprises during the project. Dealing with surprises requires more time, energy, and
money than originally planned. Risk management can help reduce the likelihood and
affects of risks. Risk management is important as it helps the team accomplish the project
with as little trouble as possible.

As a professional scientist, engineer, or project manager, you will be required to help get
the job done. Excuses (whether real or imaginary) generally don't buy any sympathy. For
instance, in the event of a surprise problem which causes project delays, it is all to easy to
deflect responsibility with victim phrases such as, "I did my part, but the other guy did
not." or "We had an unexpected problem which caused us to fall behind." Managers,
professors, CEOs typically do not look favorably on people who invoke victim phrases.
As a result, people who fall back on these types of phrases, even if they are true, typically
do not go far in this world. You must learn how to deal with surprises and adversity, not
be pushed around by them.
By becoming a member of a team, each member dedicates themselves to the success of
the TEAM. If you are waiting on a team member to accomplish a task and they are
behind, it is your responsibility to help them in any way you can. If you cannot help
them, you must make sure they get the help to accomplish their task. The victim phrase
does not absolve you of any responsibility, rather it makes you look like you are not a
team player.

Risk management can be a complex process, for our purposes, we will use a simple
management for dealing with the risk. Identify and list the practical risks for your tasks in
a column to the right of the tasks. For each risk, develop a back up plan that when
implemented will keep you on schedule. You may want to pay special attention to risks
that are so great, that they could "kill" the whole project. A member of the group should
be responsible for monitoring this risk throughout the project.

Stage 5: Develop a schedule

A gant chart is a schedule which plots the tasks, people responsible for these tasks, and a
timeline. Gant charts are useful as they allow the team to look at the architecture
(structure) of the project and easily identify responsibilities. The gant chart can serve as a
document that people use in their planning as a visualization tool to see how tasks depend
on each other. The basic format of a gant chart consists of a listing of tasks on the left
hand side, followed by the start date, number of days to complete, and a finish date. Each
task should be assigned one or more owners. To the right of the text listing is a graphical
representation of the task duration in the context of the project time line. A sample gant
chart is shown in Figure 2.




Figure 2: Sample Gant Chart
After the chart is made, look for conflicts of resources. For instance, make sure that team
members are not assigned too many tasks during a given time period. For instance, in the
schedule above, Lisa appears to be busier than her team mates on July 02nd and 03rd.
Also make sure that different tasks which require the same machines or rooms are not
scheduled for use at the same time. Make the changes and obtain agreement from the
group that this is the schedule that is to be followed. It might be wise to review the risks
during this time and adjust parts of the schedule if it would help.

Stage 6: Execute the schedule

Just do it! Every team member should know what they have to do and should have the
right resources to get the job done.. They should know what the risks are and have back
up plans in case of trouble. During this stage, the project manager is responsible for
coordinating, though group members should communicate among themselves as required.
If a group member feels he is going to go overtime/budget, it is their responsibility to
bring it up to the group as soon as possible. This way, resources can temporarily be
shifted to help keep the team member on schedule.

Each group member should document their activities. This is important as human
memory is shaky at best and it is likely that each team member will be required to recall
details of their activity. There is nothing more frustrating to a manager than to hear an
employee say, "I can't remember what I did." If one can't remember, how can the team
trust that what they did was correct? Documentation is the responsibility of the team
members and will often be a saving grace for them.

It is likely that surprises and conflicts may occur during the course of the project. It is
important to remember that it is the team's responsibility to make the project happen. If
there are problems, the team should help figure them out. If there are conflicts, the team
should act together to resolve them. This can be facilitated by regular meetings (daily,
weekly, monthly, whatever is practical) of the team. At the meetings the team should
review the schedule and the status (complete or not complete) of the project goals. Once
the goals are accomplished, the project is complete.

Stage 7: Finish the project and assessing performance

After the goals have been achieved, it is good practice to evaluate the performance of the
project team. In the last group meeting the team should discuss ways in which the
experience could have been improved. This is where a good deal of learning and
experience is gained. It will help prevent similar problems in future projects.
SECTION 3: PROJECT MANAGEMENT IN OUR ACTIVITIES.

Project management is in large part about being responsible. Today's high school and
college programs rarely force young people to exert their discipline. Most people say it is
impossible for young adults to manage themselves. I do not agree. Consider World War
II. People between the ages of 17 and 22 formed the bulk of the force that fought in the
war. They were responsible for flying fighter planes, bombers, driving tanks, and steering
ships. These are huge responsibilities. If they can do this so can you.

You will be responsible for developing (with our help), implementing, and executing
your own project schedule. There will be no "mercy" for falling behind, except in the
most extreme of circumstances. Basically, it is your turn to step up to the plate and get
the job done.



SECTION 4: ACTIVITY - START YOUR PROJECT

This is an incredibly open ended task. You are now charged with developing your project
plan. Follow the steps above and proceed as best you can. Ask the staff for help if you
have questions.

At the beginning of this document, you can download a template for a project
development sheet and a gant chart. All that is required of the user is to fill in the yellow
cells. The gant chart will automatically plot out the task/project time line for you. This is
a required part of your project management activities.

More Related Content

PDF
Managing your projects effectively in a shared resource environment
PDF
How To Make Your Day Last Longer: Time Management in Marketing Projects
PPTX
Time Management Power Point Presentation
PPT
Project control tools by Samuel obino mokaya
PPT
Top Ten Obstacles To Project Success
PDF
Master Project Management with the Critical Path Method
PPTX
Project management 101
PDF
Chapter5 project-management
Managing your projects effectively in a shared resource environment
How To Make Your Day Last Longer: Time Management in Marketing Projects
Time Management Power Point Presentation
Project control tools by Samuel obino mokaya
Top Ten Obstacles To Project Success
Master Project Management with the Critical Path Method
Project management 101
Chapter5 project-management

What's hot (20)

PPTX
Top Ten Reasons For Project Failure - PMP Webinar
DOCX
Project time
PPT
Why Projects Fail + Four Steps to Succeed
PDF
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
PPTX
Project management for everyone
PPT
Project management
PDF
A guide to creating a quality project schedule it-toolkits
PPTX
Not all projects are the same: One size does not fit all for managing projects
PDF
M08_Hazard ID ebook
PDF
Project management best practices
PDF
Back to Basics: Resource planning
PDF
Project Management Diploma
PPTX
10 me667 chap4 project scheduling
PDF
Project Management Overview by Darryl Vleeming
PPTX
The 8 Worst Managed Projects of All Time
PDF
PMBOK Planning Process Group
PPTX
Troubled projects recovery
PPT
Getting things done
DOCX
Answer sheet project management
PDF
Introduction to Project Management
Top Ten Reasons For Project Failure - PMP Webinar
Project time
Why Projects Fail + Four Steps to Succeed
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Project management for everyone
Project management
A guide to creating a quality project schedule it-toolkits
Not all projects are the same: One size does not fit all for managing projects
M08_Hazard ID ebook
Project management best practices
Back to Basics: Resource planning
Project Management Diploma
10 me667 chap4 project scheduling
Project Management Overview by Darryl Vleeming
The 8 Worst Managed Projects of All Time
PMBOK Planning Process Group
Troubled projects recovery
Getting things done
Answer sheet project management
Introduction to Project Management
Ad

Similar to project Management (20)

PDF
Effective Project Management
DOCX
Pmbok
PDF
Project Management1
DOCX
Module Three Project Scope, Planning, and Time Management.docx
DOCX
Running head PLANNING CONSIDERATIONS FOR THE HR PROJECT1PLANN.docx
DOCX
Running head PLANNING CONSIDERATIONS FOR THE HR PROJECT1PLANN.docx
PPTX
Project Managment overview and definition
DOC
briefing2
PPS
Project Management How To
DOC
Project Management
DOCX
Running head ASSIGNMENT 2 PROJECT MOTORCYCLES1ASSI.docx
PPTX
Project management and Success Criteria
PPT
PDF
Project Management Practitioner: Project Initiation
PDF
Project Management Topic.pdf
PDF
How to Manage innovation projects? Paper REPM 2018-Bilbao
PPT
Project Planning and control in Software Engineering
PPTX
Strategies for successful engineering management
Effective Project Management
Pmbok
Project Management1
Module Three Project Scope, Planning, and Time Management.docx
Running head PLANNING CONSIDERATIONS FOR THE HR PROJECT1PLANN.docx
Running head PLANNING CONSIDERATIONS FOR THE HR PROJECT1PLANN.docx
Project Managment overview and definition
briefing2
Project Management How To
Project Management
Running head ASSIGNMENT 2 PROJECT MOTORCYCLES1ASSI.docx
Project management and Success Criteria
Project Management Practitioner: Project Initiation
Project Management Topic.pdf
How to Manage innovation projects? Paper REPM 2018-Bilbao
Project Planning and control in Software Engineering
Strategies for successful engineering management
Ad

Recently uploaded (20)

PDF
Tortilla Mexican Grill 发射点犯得上发射点发生发射点犯得上发生
PDF
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
PDF
Susan Semmelmann: Enriching the Lives of others through her Talents and Bless...
PPT
Lecture 3344;;,,(,(((((((((((((((((((((((
PDF
Module 2 - Modern Supervison Challenges - Student Resource.pdf
DOCX
Handbook of Entrepreneurship- Chapter 5: Identifying business opportunity.docx
PPTX
operations management : demand supply ch
PPTX
Project Management_ SMART Projects Class.pptx
PDF
ANALYZING THE OPPORTUNITIES OF DIGITAL MARKETING IN BANGLADESH TO PROVIDE AN ...
DOCX
80 DE ÔN VÀO 10 NĂM 2023vhkkkjjhhhhjjjj
PPTX
Principles of Marketing, Industrial, Consumers,
PPTX
Sales & Distribution Management , LOGISTICS, Distribution, Sales Managers
PPT
Lecture notes on Business Research Methods
DOCX
Hand book of Entrepreneurship 4 Chapters.docx
PPTX
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
PDF
NewBase 12 August 2025 Energy News issue - 1812 by Khaled Al Awadi_compresse...
PDF
Technical Architecture - Chainsys dataZap
PPTX
Slide gioi thieu VietinBank Quy 2 - 2025
PDF
THE COMPLETE GUIDE TO BUILDING PASSIVE INCOME ONLINE
PPTX
Astra-Investor- business Presentation (1).pptx
Tortilla Mexican Grill 发射点犯得上发射点发生发射点犯得上发生
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
Susan Semmelmann: Enriching the Lives of others through her Talents and Bless...
Lecture 3344;;,,(,(((((((((((((((((((((((
Module 2 - Modern Supervison Challenges - Student Resource.pdf
Handbook of Entrepreneurship- Chapter 5: Identifying business opportunity.docx
operations management : demand supply ch
Project Management_ SMART Projects Class.pptx
ANALYZING THE OPPORTUNITIES OF DIGITAL MARKETING IN BANGLADESH TO PROVIDE AN ...
80 DE ÔN VÀO 10 NĂM 2023vhkkkjjhhhhjjjj
Principles of Marketing, Industrial, Consumers,
Sales & Distribution Management , LOGISTICS, Distribution, Sales Managers
Lecture notes on Business Research Methods
Hand book of Entrepreneurship 4 Chapters.docx
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
NewBase 12 August 2025 Energy News issue - 1812 by Khaled Al Awadi_compresse...
Technical Architecture - Chainsys dataZap
Slide gioi thieu VietinBank Quy 2 - 2025
THE COMPLETE GUIDE TO BUILDING PASSIVE INCOME ONLINE
Astra-Investor- business Presentation (1).pptx

project Management

  • 1. Project management tutorial Purpose: To provide the basic skills and knowledge needed to effectively manage a group project. Importance: Project scheduling and understanding/handling risk is crucial to success in science and engineering. Goals: After this activity, you will be able to: • Break a complex project into manageable sub-projects • Assign responsibility/ownership of project components • Set reasonable milestone's for the completion of major tasks • Perform a risk analysis and integrate mitigation into your planning • Develop and complete a project plan Files: Project Management (Link provided on the section page)
  • 2. SECTION 1: INTRODUCTION TO PROJECT MANAGEMENT Project management is the art of matching a project's goals, tasks, and resources to accomplish a goal as needed. We say "as needed" because one has limited time, money, and resources (human and machinery) with which to accomplish a goal. One can think of a project as a process. Figure 1 shows this process as a simplified block diagram. Figure 1: Simple Project Management System The process involves inputs and outputs. Successful projects "do the right things, with the right tools, and in the right way".
  • 3. SECTION 2: STAGES OF A PROJECT AND HOW TO COMPLETE THEM Stage 1: Defining the goals of the project: Garbage in equals garbage out. If you do not start a project with the correct goal(s), it is not likely you will accomplish the goal(s). This must be a team activity to ensure that everyone is given the opportunity to contribute and "buy-in" to what is going to happen. At the end of this stage, every team member should have an understanding of what must be accomplished. This part of the project should end with a document that lists the goals with a short statement providing some detail. The statement should include a definition of success. This is a statement that provides a description of the vital few requirements that define the goal as accomplished. Vital few implies the minimum required to do a good job. Defining success is necessary to make sure there is no ambiguity as to whether the goal has been accomplished or not. It also prevents teams from performing unnecessary iteration and improvement on a goal which has been sufficiently accomplished. Stage 2: Define project tasks/activities: Each goal or sub-set of goals should be matched to the tasks required to accomplish them. This is best done by listing the goals on the left side of a sheet of paper, then writing the tasks to their right. The group should agree that the specify task will accomplish the goals as per required in the definitions for success the team laid out in the previous stage. Stage 3: Determine and verify resource requirements: Resources are those things which are needed to accomplish the project goals. Resources may include, but are not limited to: • People • Time • Money • Space • Computers • Software • Others.....
  • 4. The most important component of determining resource requirements is to be realistic. One of the most common mistakes project managers make is to underestimate the amount and type of resources required. This leads to projects that run over budget and fall behind schedule. DO NOT attempt to do any of the following: • Squeeze a project into a shorter time frame to please your boss • Cut corners to minimize resource requirements • Plan on a best-case basis, i.e. "If everything goes correctly, we will finish on time." Determine what you need to get the job done correctly, on time, and on budget. It is not a bad idea to build in a safety margin here. This is often referred to as "padding". For instance, one might multiply the estimated time to complete a task/project by say 20% to allow for additional time to deal with unexpected occurrences. The amount of padding usually depends on the certainty one has as to how effectively the resources can be used. One should keep padding to a minimum. Once the requirements have been set, it is important to verify that the team will have access to them. If not, then it is not likely the project will be accomplished as required. In some instances it may be necessary to acquire resources as the project progresses. This is risky business and should be avoided if possible. This is risky business. Speaking of risk... Stage 4: Identify risks and develop mitigation (backup) plans: Projects always involve a finite amount of uncertainty (risk) that may lead to problems and surprises during the project. Dealing with surprises requires more time, energy, and money than originally planned. Risk management can help reduce the likelihood and affects of risks. Risk management is important as it helps the team accomplish the project with as little trouble as possible. As a professional scientist, engineer, or project manager, you will be required to help get the job done. Excuses (whether real or imaginary) generally don't buy any sympathy. For instance, in the event of a surprise problem which causes project delays, it is all to easy to deflect responsibility with victim phrases such as, "I did my part, but the other guy did not." or "We had an unexpected problem which caused us to fall behind." Managers, professors, CEOs typically do not look favorably on people who invoke victim phrases. As a result, people who fall back on these types of phrases, even if they are true, typically do not go far in this world. You must learn how to deal with surprises and adversity, not be pushed around by them.
  • 5. By becoming a member of a team, each member dedicates themselves to the success of the TEAM. If you are waiting on a team member to accomplish a task and they are behind, it is your responsibility to help them in any way you can. If you cannot help them, you must make sure they get the help to accomplish their task. The victim phrase does not absolve you of any responsibility, rather it makes you look like you are not a team player. Risk management can be a complex process, for our purposes, we will use a simple management for dealing with the risk. Identify and list the practical risks for your tasks in a column to the right of the tasks. For each risk, develop a back up plan that when implemented will keep you on schedule. You may want to pay special attention to risks that are so great, that they could "kill" the whole project. A member of the group should be responsible for monitoring this risk throughout the project. Stage 5: Develop a schedule A gant chart is a schedule which plots the tasks, people responsible for these tasks, and a timeline. Gant charts are useful as they allow the team to look at the architecture (structure) of the project and easily identify responsibilities. The gant chart can serve as a document that people use in their planning as a visualization tool to see how tasks depend on each other. The basic format of a gant chart consists of a listing of tasks on the left hand side, followed by the start date, number of days to complete, and a finish date. Each task should be assigned one or more owners. To the right of the text listing is a graphical representation of the task duration in the context of the project time line. A sample gant chart is shown in Figure 2. Figure 2: Sample Gant Chart
  • 6. After the chart is made, look for conflicts of resources. For instance, make sure that team members are not assigned too many tasks during a given time period. For instance, in the schedule above, Lisa appears to be busier than her team mates on July 02nd and 03rd. Also make sure that different tasks which require the same machines or rooms are not scheduled for use at the same time. Make the changes and obtain agreement from the group that this is the schedule that is to be followed. It might be wise to review the risks during this time and adjust parts of the schedule if it would help. Stage 6: Execute the schedule Just do it! Every team member should know what they have to do and should have the right resources to get the job done.. They should know what the risks are and have back up plans in case of trouble. During this stage, the project manager is responsible for coordinating, though group members should communicate among themselves as required. If a group member feels he is going to go overtime/budget, it is their responsibility to bring it up to the group as soon as possible. This way, resources can temporarily be shifted to help keep the team member on schedule. Each group member should document their activities. This is important as human memory is shaky at best and it is likely that each team member will be required to recall details of their activity. There is nothing more frustrating to a manager than to hear an employee say, "I can't remember what I did." If one can't remember, how can the team trust that what they did was correct? Documentation is the responsibility of the team members and will often be a saving grace for them. It is likely that surprises and conflicts may occur during the course of the project. It is important to remember that it is the team's responsibility to make the project happen. If there are problems, the team should help figure them out. If there are conflicts, the team should act together to resolve them. This can be facilitated by regular meetings (daily, weekly, monthly, whatever is practical) of the team. At the meetings the team should review the schedule and the status (complete or not complete) of the project goals. Once the goals are accomplished, the project is complete. Stage 7: Finish the project and assessing performance After the goals have been achieved, it is good practice to evaluate the performance of the project team. In the last group meeting the team should discuss ways in which the experience could have been improved. This is where a good deal of learning and experience is gained. It will help prevent similar problems in future projects.
  • 7. SECTION 3: PROJECT MANAGEMENT IN OUR ACTIVITIES. Project management is in large part about being responsible. Today's high school and college programs rarely force young people to exert their discipline. Most people say it is impossible for young adults to manage themselves. I do not agree. Consider World War II. People between the ages of 17 and 22 formed the bulk of the force that fought in the war. They were responsible for flying fighter planes, bombers, driving tanks, and steering ships. These are huge responsibilities. If they can do this so can you. You will be responsible for developing (with our help), implementing, and executing your own project schedule. There will be no "mercy" for falling behind, except in the most extreme of circumstances. Basically, it is your turn to step up to the plate and get the job done. SECTION 4: ACTIVITY - START YOUR PROJECT This is an incredibly open ended task. You are now charged with developing your project plan. Follow the steps above and proceed as best you can. Ask the staff for help if you have questions. At the beginning of this document, you can download a template for a project development sheet and a gant chart. All that is required of the user is to fill in the yellow cells. The gant chart will automatically plot out the task/project time line for you. This is a required part of your project management activities.