SlideShare a Scribd company logo
Project Management for Construction
Fundamental Concepts for Owners, Engineers, Architects and Builders
Chapter 7
Financing of Constructed Facilities
Financing of Constructed
Facilities
7.1 The Financing Problem
7.1 The Financing Problem
Investment in a constructed facility represents a cost in the
short term that returns benefits only over the long term use of
the facility. Thus, costs occur earlier than the benefits, and
owners of facilities must obtain the capital resources to finance
the costs of construction. A project cannot proceed without
adequate financing, and the cost of providing adequate
financing can be quite large. For these reasons, attention to
project finance is an important aspect of project management.
Finance is also a concern to the other organizations involved in
a project such as the general contractor and material suppliers.
Unless an owner immediately and completely covers the costs
incurred by each participant, these organizations face financing
problems of their own.
7.1 The Financing Problem
At a more general level, project finance is only one aspect of
the general problem of corporate finance. If numerous projects
are considered and financed together, then the net cash flow
requirements constitutes the corporate financing problem for
capital investment. Whether project finance is performed at the
project or at the corporate level does not alter the basic
financing problem.
7.1 The Financing Problem
In essence, the project finance problem is to obtain funds to
bridge the time between making expenditures and obtaining
revenues. Based on the conceptual plan, the cost estimate and
the construction plan, the cash flow of costs and receipts for a
project can be estimated. Normally, this cash flow will involve
expenditures in early periods. Covering this negative cash
balance in the most beneficial or cost effective fashion is the
project finance problem.
7.1 The Financing Problem
During planning and design, expenditures of the owner are
modest, whereas substantial costs are incurred during
construction. Only after the facility is complete do revenues
begin. In contrast, a contractor would receive periodic payments
from the owner as construction proceeds. However, a
contractor also may have a negative cash balance due to
delays in payment and retainage of profits or cost
reimbursements on the part of the owner.
7.1 The Financing Problem
Plans considered by owners for facility financing typically have
both long and short term aspects. In the long term, sources of
revenue include sales, grants, and tax revenues. Borrowed
funds must be eventually paid back from these other sources. In
the short term, a wider variety of financing options exist,
including borrowing, grants, corporate investment funds,
payment delays and others. Many of these financing options
involve the participation of third parties such as banks or bond
underwriters.
7.1 The Financing Problem
For private facilities such as office buildings, it is customary to
have completely different financing arrangements during the
construction period and during the period of facility use. During
the latter period, mortgage or loan funds can be secured by the
value of the facility itself. Thus, different arrangements of
financing options and participants are possible at different
stages of a project, so the practice of financial planning is often
complicated.
7.1 The Financing Problem
On the other hand, the options for borrowing by contractors to
bridge their expenditures and receipts during construction are
relatively limited. For small or medium size projects, overdrafts
from bank accounts are the most common form of construction
financing. Usually, a maximum limit is imposed on an overdraft
account by the bank on the basis of expected expenditures and
receipts for the duration of construction. Contractors who are
engaged in large projects often own substantial assets and can
make use of other forms of financing which have lower interest
charges than overdrafting.
7.1 The Financing Problem
In recent years, there has been growing interest in design-build-
operate projects in which owners prescribe functional
requirements and a contractor handles financing. Contractors
are repaid over a period of time from project revenues or
government payments. Eventually, ownership of the facilities is
transferred to a government entity. An example of this type of
project is the Confederation Bridge to Prince Edward Island in
Canada.
7.1 The Financing Problem
In this chapter, we will first consider facility financing from the
owner's perspective, with due consideration for its interaction
with other organizations involved in a project. Later, we discuss
the problems of construction financing which are crucial to the
profitability and solvency of construction contractors.
Financing of Constructed
Facilities
7.2 Institutional Arrangements for Facility Financing
7.2 Institutional Arrangements
for Facility Financing
Financing arrangements differ sharply by type of owner and by
the type of facility construction. As one example, many
municipal projects are financed in the United States with tax
exempt bonds for which interest payments to a lender are
exempt from income taxes. As a result, tax exempt municipal
bonds are available at lower interest charges. Different
institutional arrangements have evolved for specific types of
facilities and organizations.
7.2 Institutional Arrangements
for Facility Financing
A private corporation which plans to undertake large capital
projects may use its retained earnings, seek equity partners in
the project, issue bonds, offer new stocks in the financial
markets, or seek borrowed funds in another fashion. Potential
sources of funds would include pension funds, insurance
companies, investment trusts, commercial banks and others.
Developers who invest in real estate properties for rental
purposes have similar sources, plus quasi-governmental
corporations such as urban development authorities.
Syndicators for investment such as real estate investment trusts
(REITs) as well as domestic and foreign pension funds
represent relatively new entries to the financial market for
building mortgage money.
7.2 Institutional Arrangements
for Facility Financing
Public projects may be funded by tax receipts, general revenue
bonds, or special bonds with income dedicated to the specified
facilities. General revenue bonds would be repaid from general
taxes or other revenue sources, while special bonds would be
redeemed either by special taxes or user fees collected for the
project. Grants from higher levels of government are also an
important source of funds for state, county, city or other local
agencies.
7.2 Institutional Arrangements
for Facility Financing
Despite the different sources of borrowed funds, there is a
rough equivalence in the actual cost of borrowing money for
particular types of projects. Because lenders can participate in
many different financial markets, they tend to switch towards
loans that return the highest yield for a particular level of risk.
As a result, borrowed funds that can be obtained from different
sources tend to have very similar costs, including interest
charges and issuing costs.
7.2 Institutional Arrangements
for Facility Financing
As a general principle, however, the costs of funds for
construction will vary inversely with the risk of a loan. Lenders
usually require security for a loan represented by a tangible
asset. If for some reason the borrower cannot repay a loan,
then the borrower can take possession of the loan security. To
the extent that an asset used as security is of uncertain value,
then the lender will demand a greater return and higher interest
payments. Loans made for projects under construction
represent considerable risk to a financial institution.
7.2 Institutional Arrangements
for Facility Financing
If a lender acquires an unfinished facility, then it faces the
difficult task of re-assembling the project team. Moreover, a
default on a facility may result if a problem occurs such as
foundation problems or anticipated unprofitability of the future
facility. As a result of these uncertainties, construction lending
for unfinished facilities commands a premium interest charge of
several percent compared to mortgage lending for completed
facilities.
7.2 Institutional Arrangements
for Facility Financing
Financing plans will typically include a reserve amount to cover
unforeseen expenses, cost increases or cash flow problems.
This reserve can be represented by a special reserve or a
contingency amount in the project budget. In the simplest case,
this reserve might represent a borrowing agreement with a
financial institution to establish a line of credit in case of need.
For publicly traded bonds, specific reserve funds administered
by a third party may be established. The cost of these reserve
funds is the difference between the interest paid to bondholders
and the interest received on the reserve funds plus any
administrative costs.
7.2 Institutional Arrangements
for Facility Financing
Finally, arranging financing may involve a lengthy period of
negotiation and review. Particularly for publicly traded bond
financing, specific legal requirements in the issue must be met.
A typical seven month schedule to issue revenue bonds would
include the various steps outlined in Table 7-1. [1] In many
cases, the speed in which funds may be obtained will determine
a project's financing mechanism.
7.2 Institutional Arrangements
for Facility Financing
Activities Time of Activities
Analysis of financial alternatives
Preparation of legal documents
Preparation of disclosure documents
Forecasts of costs and revenues
Bond Ratings
Bond Marketing
Bond Closing and Receipt of Funds
Weeks 0-4
Weeks 1-17
Weeks 2-20
Weeks 4-20
Weeks 20-23
Weeks 21-24
Weeks 23-26
TABLE 7-1 Illustrative Process and Timing
for Issuing Revenue Bonds
7.2 Institutional Arrangements
for Facility Financing
Example 7-1: Example of financing options
Example 7-1: Example of
financing options
Suppose that you represent a private corporation attempting to
arrange financing for a new headquarters building. These are
several options that might be considered:
• Use corporate equity and retained earnings: The building
could be financed by directly committing corporate
resources. In this case, no other institutional parties would be
involved in the finance. However, these corporate funds
might be too limited to support the full cost of construction.
Example 7-1: Example of
financing options
• Construction loan and long term mortgage: In this plan, a
loan is obtained from a bank or other financial institution to
finance the cost of construction. Once the building is
complete, a variety of institutions may be approached to
supply mortgage or long term funding for the building. This
financing plan would involve both short and long term
borrowing, and the two periods might involve different
lenders. The long term funding would have greater security
since the building would then be complete. As a result, more
organizations might be interested in providing funds
(including pension funds) and the interest charge might be
lower. Also, this basic financing plan might be supplemented
by other sources such as corporate retained earnings or
assistance from a local development agency.
Example 7-1: Example of
financing options
• Lease the building from a third party: In this option, the
corporation would contract to lease space in a headquarters
building from a developer. This developer would be
responsible for obtaining funding and arranging construction.
This plan has the advantage of minimizing the amount of
funds borrowed by the corporation. Under terms of the lease
contract, the corporation still might have considerable
influence over the design of the headquarters building even
though the developer was responsible for design and
construction.
Example 7-1: Example of
financing options
• Initiate a Joint Venture with Local Government: In many
areas, local governments will help local companies with
major new ventures such as a new headquarters. This help
might include assistance in assembling property, low interest
loans or proerty tax reductions. In the extreme, local
governments may force sale of land through their power
of eminent domain to assemble necessary plots.
Financing of Constructed
Facilities
7.3 Evaluation of Alternative Financing Plans
7.3 Evaluation of Alternative
Financing Plans
Since there are numerous different sources and arrangements
for obtaining the funds necessary for facility construction,
owners and other project participants require some mechanism
for evaluating the different potential sources. The relative costs
of different financing plans are certainly important in this regard.
In addition, the flexibility of the plan and availability of reserves
may be critical. As a project manager, it is important to assure
adequate financing to complete a project. Alternative financing
plans can be evaluated using the same techniques that are
employed for the evaluation of investment alternatives.
7.3 Evaluation of Alternative
Financing Plans
As described in Chapter 6, the availability of different financing
plans can affect the selection of alternative projects. A general
approach for obtaining the combined effects of operating and
financing cash flows of a project is to determine the adjusted
net present value (APV) which is the sum of the net present
value of the operating cash flow (NPV) and the net present
value of the financial cash flow (FPV), discounted at their
respective minimum attractive rates of return (MARR), i.e.,
7.3 Evaluation of Alternative
Financing Plans
where r is the MARR reflecting the risk of the operating cash
flow and rf is the MARR representing the cost of borrowing for
the financial cash flow. Thus,
where At and are respectively the operating and financial cash
flows in period t.
7.3 Evaluation of Alternative
Financing Plans
For the sake of simplicity, we shall emphasize in this chapter
the evaluation of financing plans, with occasional references to
the combined effects of operating and financing cash flows. In
all discussions, we shall present various financing schemes with
examples limiting to cases of before-tax cash flows discounted
at a before-tax MARR of r = rf for both operating and financial
cash flows. Once the basic concepts of various financing
schemes are clearly understood, their application to more
complicated situations involving depreciation, tax liability and
risk factors can be considered in combination with the principles
for dealing with such topics enunciated in Chapter 6.
7.3 Evaluation of Alternative
Financing Plans
In this section, we shall concentrate on the computational
techniques associated with the most common types of financing
arrangements. More detailed descriptions of various financing
schemes and the comparisons of their advantages and
disadvantages will be discussed in later sections.
7.3 Evaluation of Alternative
Financing Plans
Typically, the interest rate for borrowing is stated in terms
of annual percentage rate (A.P.R.), but the interest is accrued
according to the rate for the interest period specified in the
borrowing agreement. Let ip be the nominal annual percentage
rate, and i be the interest rate for each of the p interest periods
per year. By definition
7.3 Evaluation of Alternative
Financing Plans
If interest is accrued semi-annually, i.e., p = 2, the interest rate
per period is ip/2; similarly if the interest is accrued monthly, i.e.,
p = 12, the interest rate per period is ip/12. On the other hand,
the effective annual interest rate ie is given by:
7.3 Evaluation of Alternative
Financing Plans
Note that the effective annual interest rate, ie, takes into account
compounding within the year. As a result, ie is greater than ip for
the typical case of more than one compounding period per year.
7.3 Evaluation of Alternative
Financing Plans
For a coupon bond, the face value of the bond denotes the
amount borrowed (called principal) which must be repaid in full
at a maturity or due date, while each coupon designates the
interest to be paid periodically for the total number of coupons
covering all periods until maturity. Let Q be the amount
borrowed, and Ip be the interest payment per period which is
often six months for coupon bonds. If the coupon bond is
prescribed to reach maturity in n years from the date of issue,
the total number of interest periods will be pn = 2n. The semi-
annual interest payment is given by:
7.3 Evaluation of Alternative
Financing Plans
In purchasing a coupon bond, a discount from or a premium
above the face value may be paid.
7.3 Evaluation of Alternative
Financing Plans
An alternative loan arrangement is to make a series of uniform
payments including both interest and part of the principal for a
pre-defined number of repayment periods. In the case of
uniform payments at an interest rate i for n repayment periods,
the uniform repayment amount U is given by:
7.3 Evaluation of Alternative
Financing Plans
where (U|P,i,n) is a capital recovery factor which reads: "to find
U, given P=1, for an interest rate i over n periods." Compound
interest factors are as tabulated in Appendix A. The number of
repayment periods n will clearly influence the amounts of
payments in this uniform payment case. Uniform payment
bonds or mortgages are based on this form of repayment.
7.3 Evaluation of Alternative
Financing Plans
Usually, there is an origination fee associated with borrowing for
legal and other professional services which is payable upon the
receipt of the loan. This fee may appear in the form of issuance
charges for revenue bonds or percentage point charges for
mortgages. The borrower must allow for such fees in addition to
the construction cost in determining the required original
amount of borrowing. Suppose that a sum of Po must be
reserved at t=0 for the construction cost, and K is the origination
fee. Then the original loan needed to cover both is:
7.3 Evaluation of Alternative
Financing Plans
If the origination fee is expressed as k percent of the original
loan, i.e., K = kQ0, then:
7.3 Evaluation of Alternative
Financing Plans
Since interest and sometimes parts of the principal must be
repaid periodically in most financing arrangements, an amount
Q considerably larger than Q0 is usually borrowed in the
beginning to provide adequate reserve funds to cover interest
payments, construction cost increases and other unanticipated
shortfalls. The net amount received from borrowing is deposited
in a separate interest bearing account from which funds will be
withdrawn periodically for necessary payments. Let the
borrowing rate per period be denoted by i and the interest for
the running balance accrued to the project reserve account be
denoted by h.
7.3 Evaluation of Alternative
Financing Plans
Let At be the net operating cash flow for - period t (negative for
construction cost in period t) and be the net financial cash flow
in period t (negative for payment of interest or principal or a
combination of both). Then, the running balance Nt of the
project reserve account can be determined by noting that at t=0,
7.3 Evaluation of Alternative
Financing Plans
and at t = 1,2,...,n:
7.3 Evaluation of Alternative
Financing Plans
where the value of At or t may be zero for some period(s).
Equations (7.9) and (7.10) are approximate in that interest
might be earned on intermediate balances based on the pattern
of payments during a period instead of at the end of a period.
7.3 Evaluation of Alternative
Financing Plans
Because the borrowing rate i will generally exceed the
investment rate h for the running balance in the project account
and since the origination fee increases with the amount
borrowed, the financial planner should minimize the amount of
money borrowed under this finance strategy. Thus, there is an
optimal value for Q such that all estimated shortfalls are
covered, interest payments and expenses are minimized, and
adequate reserve funds are available to cover unanticipated
factors such as construction cost increases. This optimal value
of Q can either be identified analytically or by trial and error.
7.3 Evaluation of Alternative
Financing Plans
Finally, variations in ownership arrangements may also be used
to provide at least partial financing. Leasing a facility removes
the need for direct financing of the facility. Sale-leaseback
involves sale of a facility to a third party with a separate
agreement involving use of the facility for a pre-specified period
of time. In one sense, leasing arrangements can be viewed as a
particular form of financing. In return for obtaining the use of a
facility or piece of equipment, the user (lesser) agrees to pay
the owner (lesser) a lease payment every period for a specified
number of periods.
7.3 Evaluation of Alternative
Financing Plans
Usually, the lease payment is at a fixed level due every month,
semi-annually, or annually. Thus, the cash flow associated with
the equipment or facility use is a series of uniform payments.
This cash flow would be identical to a cash flow resulting from
financing the facility or purchase with sufficient borrowed funds
to cover initial construction (or purchase) and with a repayment
schedule of uniform amounts. Of course, at the end of the lease
period, the ownership of the facility or equipment would reside
with the lesser. However, the lease terms may include a
provision for transferring ownership to the lesser after a fixed
period.
7.3 Evaluation of Alternative
Financing Plans
Example 7-2: A coupon bond cash flow and cost
Example 7-2: A coupon bond
cash flow and cost
A private corporation wishes to borrow $10.5 million for the
construction of a new building by issuing a twenty-year coupon
bond at an annual percentage interest rate of 10% to be paid
semi-annually, i.e. 5% per interest period of six months. The
principal will be repaid at the end of 20 years. The amount
borrowed will cover the construction cost of $10.331 million and
an origination fee of $169,000 for issuing the coupon bond.
Example 7-2: A coupon bond
cash flow and cost
The interest payment per period is (5%) (10.5) = $0.525 million
over a life time of (2) (20) = 40 interest periods. Thus, the cash
flow of financing by the coupon bond consists of a $10.5 million
receipt at period 0, -$0.525 million each for periods 1 through
40, and an additional -$10.5 million for period 40. Assuming a
MARR of 5% per period, the net present value of the financial
cash flow is given by:
[FPV]5%) = 10.5 - (0.525)(P|U, 5%, 40) - (10.5)(P|F, 5%,
40) = 0
Example 7-2: A coupon bond
cash flow and cost
This result is expected since the corporation will be indifferent
between borrowing and diverting capital from other uses when
the MARR is identical to the borrowing rate. Note that the
effective annual rate of the bond may be computed according to
Eq.(7.4) as follows:
ie = (1 + 0.05)2 - 1 = 0.1025 = 10.25%
Example 7-2: A coupon bond
cash flow and cost
If the interest payments were made only at the end of each year
over twenty years, the annual payment should be:
0.525(1 + 0.05) + 0.525 = 1.076
where the first term indicates the deferred payment at the mid-
year which would accrue interest at 5% until the end of the year,
then:
[FPV]10.25% = 10.5 - (1.076)(P|U, 10.25%, 20) -
(10.5)(P|F, 10.25%, 20) = 0
Example 7-2: A coupon bond
cash flow and cost
In other words, if the interest is paid at 10.25% annually over
twenty years of the loan, the result is equivalent to the case of
semi-annual interest payments at 5% over the same lifetime.
7.3 Evaluation of Alternative
Financing Plans
Example 7-3: An example of leasing versus ownership
analysis
Example 7-3: An example of leasing
versus ownership analysis
Suppose that a developer offered a building to a corporation for
an annual lease payment of $10 million over a thirty year
lifetime. For the sake of simplicity, let us assume that the
developer also offers to donate the building to the corporation at
the end of thirty years or, alternatively, the building would then
have no commercial value. Also, suppose that the initial cost of
the building was $65.66 million. For the corporation, the lease is
equivalent to receiving a loan with uniform payments over thirty
years at an interest rate of 15% since the present value of the
lease payments is equal to the initial cost at this interest rate:
Example 7-3: An example of leasing
versus ownership analysis
Example 7-3: An example of leasing
versus ownership analysis
If the minimum attractive rate of return of the corporation is
greater than 15%, then this lease arrangement is advantageous
as a financing scheme since the net present value of the
leasing cash flow would be less than the cash flow associated
with construction from retained earnings. For example, with
MARR equal to 20%:
[FPV]20% = $65.66 million - ($10 million)(P|U, 20%, 30) =
$15.871 million
Example 7-3: An example of leasing
versus ownership analysis
On the other hand, with MARR equal to 10%:
[FPV]10% = $65.66 million - ($10 million)(P|U, 20%, 30) =
$28.609 million
and the lease arrangement is not advantageous.
Example 7-3: An example of leasing
versus ownership analysis
Example 7-4: Example evaluation of alternative financing
plans.
Example 7-4: Example evaluation of
alternative financing plans
Suppose that a small corporation wishes to build a
headquarters building. The construction will require two years
and cost a total of $12 million, assuming that $5 million is spent
at the end of the first year and $7 million at the end of the
second year. To finance this construction, several options are
possible, including:
• Investment from retained corporate earnings;
Example 7-4: Example evaluation of
alternative financing plans
• Borrowing from a local bank at an interest rate of 11.2% with
uniform annual payments over twenty years to pay for the
construction costs. The shortfalls for repayments on loans
will come from corporate earnings. An origination fee of
0.75% of the original loan is required to cover engineer's
reports, legal issues, etc; or
• A twenty year coupon bond at an annual interest rate of
10.25% with interest payments annually, repayment of the
principal in year 20, and a $169,000 origination fee to pay for
the construction cost only.
Example 7-4: Example evaluation of
alternative financing plans
The current corporate MARR is 15%, and short term cash funds
can be deposited in an account having a 10% annual interest
rate.
Example 7-4: Example evaluation of
alternative financing plans
The first step in evaluation is to calculate the required amounts
and cash flows associated with these three alternative financing
plans. First, investment using retained earnings will require a
commitment of $5 million in year 1 and $7 million in year 2.
Example 7-4: Example evaluation of
alternative financing plans
Second, borrowing from the local bank must yield sufficient
funds to cover both years of construction plus the issuing fee.
With the unused fund accumulating interest at a rate of 10%,
the amount of dollars needed at the beginning of the first year
for future construction cost payments is:
P0 = ($5 million)/(1.1) + ($7 million)/(1.1)2 = $10.331 million
Example 7-4: Example evaluation of
alternative financing plans
Discounting at ten percent in this calculation reflects the interest
earned in the intermediate periods. With a 10% annual interest
rate, the accrued interests for the first two years from the project
account of $10.331 at t=0 will be:
Year 1: I1 = (10%)(10.331 million) = $1.033 million
Year 2: I2 = (10%)(10.331 million + $1.033 million - $5.0
million) = 0.636 million
Example 7-4: Example evaluation of
alternative financing plans
Since the issuance charge is 0.75% of the loan, the amount
borrowed from the bank at t=0 to cover both the construction
cost and the issuance charge is
Q0 = ($10.331 million)/(1 - 0.0075) = $ 10.409 million
Example 7-4: Example evaluation of
alternative financing plans
The issuance charge is 10.409 - 10.331 = $ 0.078 million or
$78,000. If this loan is to be repaid by annual uniform payments
from corporate earnings, the amount of each payment over the
twenty year life time of the loan can be calculated by Eq. (7.6)
as follows:
U = ($10.409 million)[(0.112)(1.112)20]/[(1.112)20 - 1] = $1.324
million
Example 7-4: Example evaluation of
alternative financing plans
Finally, the twenty-year coupon bond would have to be issued
in the amount of $10.5 million which will reflect a higher
origination fee of $169,000. Thus, the amount for financing is:
Q0 = $10.331 million + $0.169 million = $10.5 million
Example 7-4: Example evaluation of
alternative financing plans
With an annual interest charge of 10.25% over a twenty year life
time, the annual payment would be $1.076 million except in
year 20 when the sum of principal and interest would be 10.5 +
1.076 = $11.576 million. The computation for this case of
borrowing has been given in Example 7-2.
Example 7-4: Example evaluation of
alternative financing plans
Table 7-2 summarizes the cash flows associated with the three
alternative financing plans. Note that annual incomes generated
from the use of this building have not been included in the
computation. The adjusted net present value of the combined
operating and financial cash flows for each of the three plans
discounted at the corporate MARR of 15% is also shown in the
table. In this case, the coupon bond is the least expensive
financing plan. Since the borrowing rates for both the bank loan
and the coupon bond are lower than the corporate MARR,
these results are expected.
Year Source
Retained
Earnings Bank Loan Coupon Bond
0
0
1
1
1
2
2
2
3-19
20
[APV]15%
Principal
Issuing Cost
Earned Interest
Contractor
Payment
Loan Repayment
Earned Interest
Contractor
Payment
Loan Repayment
Loan Repayment
Loan Repayment
-
-
-
- 5.000
-
-
- 7.000
-
-
-
- 9.641
$10.409
- 0.078
1.033
- 5.000
- 1.324
0.636
- 7.000
- 1.324
- 1.324
- 1.324
- 6.217
$10.500
- 0.169
1.033
- 5.000
- 1.076
0.636
- 7.000
- 1.076
-1.076
- 11.576
- 5.308
Example 7-4: Example evaluation of
alternative financing plans
TABLE 7-2 Cash Flow Illustration of Three Alternative Financing Plans (in $
millions)
Financing of Constructed
Facilities
7.4 Secured Loans with Bonds, Notes and Mortgages
7.4 Secured Loans with
Bonds, Notes and Mortgages
Secured lending involves a contract between a borrower and
lender, where the lender can be an individual, a financial
institution or a trust organization. Notes and mortgages
represent formal contracts between financial institutions and
owners. Usually, repayment amounts and timing are specified in
the loan agreement. Public facilities are often financed by bond
issues for either specific projects or for groups of projects.
7.4 Secured Loans with
Bonds, Notes and Mortgages
For publicly issued bonds, a trust company is usually
designated to represent the diverse bond holders in case of any
problems in the repayment. The borrowed funds are usually
secured by granting the lender some rights to the facility or
other assets in case of defaults on required payments. In
contrast, corporate bonds such as debentures can represent
loans secured only by the good faith and credit worthiness of
the borrower.
7.4 Secured Loans with
Bonds, Notes and Mortgages
Under the terms of many bond agreements, the borrower
reserves the right to repurchase the bonds at any time before
the maturity date by repaying the principal and all interest up to
the time of purchase. The required repayment Rc at the end of
period c is the net future value of the borrowed amount Q - less
the payment made at intermediate periods compounded at
the borrowing rate i to period c as follows:
7.4 Secured Loans with
Bonds, Notes and Mortgages
The required repayment Rc at the end of the period c can also
be obtained by noting the net present value of the repayments
in the remaining (n-c) periods discounted at the borrowing rate i
to t = c as follows:
7.4 Secured Loans with
Bonds, Notes and Mortgages
For coupon bonds, the required repayment Rc after the
redemption of the coupon at the end of period c is simply the
original borrowed amount Q. For uniform payment bonds, the
required repayment Rc after the last payment at the end of
period c is:
7.4 Secured Loans with
Bonds, Notes and Mortgages
Many types of bonds can be traded in a secondary market by
the bond holder. As interest rates fluctuate over time, bonds will
gain or lose in value. The actual value of a bond is reflected in
the market discount or premium paid relative to the original
principal amount (the face value). Another indicator of this value
is the yield to maturity or internal rate of return of the bond. This
yield is calculated by finding the interest rate that sets the
(discounted) future cash flow of the bond equal to the current
market price:
7.4 Secured Loans with
Bonds, Notes and Mortgages
where Vc is the current market value after c periods have lapsed
since the - issuance of the bond, is the bond cash flow in
period t, and r is the market yield. Since all the bond cash flows
are positive after the initial issuance, only one value of the yield
to maturity will result from Eq.
7.4 Secured Loans with
Bonds, Notes and Mortgages
Several other factors come into play in evaluation of bond
values from the lenders point of view, however. First, the lender
must adjust for the possibility that the borrower may default on
required interest and principal payments. In the case of publicly
traded bonds, special rating companies divide bonds into
different categories of risk for just this purpose. Obviously,
bonds that are more likely to default will have a lower value.
Secondly, lenders will typically make adjustments to account for
changes in the tax code affecting their after-tax return from a
bond. Finally, expectations of future inflation or deflation as well
as exchange rates will influence market values.
7.4 Secured Loans with
Bonds, Notes and Mortgages
Another common feature in borrowing agreements is to have a
variable interest rate. In this case, interest payments would vary
with the overall market interest rate in some pre-specified
fashion. From the borrower's perspective, this is less desirable
since cash flows are less predictable. However, variable rate
loans are typically available at lower interest rates because the
lenders are protected in some measure from large increases in
the market interest rate and the consequent decrease in value
of their expected repayments. Variable rate loans can have
floors and ceilings on the applicable interest rate or on rate
changes in each year
7.4 Secured Loans with
Bonds, Notes and Mortgages
Example 7-5: Example of a corporate promissory note
Example 7-5: Example of a
corporate promissory note
A corporation wishes to consider the option of financing the
headquarters building in Example 7-4 by issuing a five year
promissory note which requires an origination fee for the note is
$25,000. Then a total borrowed amount needed at the
beginning of the first year to pay for the construction costs and
origination fee is 10.331 + 0.025 = $10.356 million. Interest
payments are made annually at an annual rate of 10.8% with
repayment of the principal at the end of the fifth year. Thus, the
annual interest payment is (10.8%)(10.356) = $1.118 million.
With the data in Example 7-4 for construction costs and accrued
interests for the first two year, the combined operating and and
financial cash flows in million dollars can be obtained:
Example 7-5: Example of a
corporate promissory note
Year 0, AA0 = 10.356 - 0.025 = 10.331
Year 1, AA1 = 1.033 - 5.0 - 1.118 = -5.085
Year 2, AA2 = 0.636 - 7.0 - 1.118 = -7.482
Year 3, AA3 = -1.118
Year 4, AA4 = -1.118
Year 5, AA5 = -1.118 - 10.356 = -11.474
Example 7-5: Example of a
corporate promissory note
At the current corporate MARR of 15%,
which is inferior to the 20-year coupon bond analyzed in Table
7-3.
Example 7-5: Example of a
corporate promissory note
For this problem as well as for the financing arrangements in
Example 7-4, the project account is maintained to pay the
construction costs only, while the interest and principal
payments are repaid from corporate earnings. - Consequently,
the terms in Eq. (7.10) will disappear when the account
balance in each period is computed for this problem:
At t=0, N0 = 10.356 - 0.025 = $10.331 million
At t=1, N1 = (1 + 0.1) (10.331) - 5.0 = $6.364 million
At t=2, N2 = (1 + 0.1) (6.364) - 7.0 = $0
7.4 Secured Loans with
Bonds, Notes and Mortgages
Example 7-6: Bond financing mechanisms.
Example 7-6: Bond financing
mechanisms.
Suppose that the net operating expenditures and receipts of a
facility investment over a five year time horizon are as shown in
column 2 of Table 7-3 in which each period is six months. This
is a hypothetical example with a deliberately short life time
period to reduce the required number of calculations. Consider
two alternative bond financing mechanisms for this project. Both
involve borrowing $2.5 million at an issuing cost of five percent
of the loan with semi-annual repayments at a nominal annual
interest rate of ten percent i.e., 5% per period.
Example 7-6: Bond financing
mechanisms.
Any excess funds can earn an interest of four percent each
semi-annual period. The coupon bond involves only interest
payments in intermediate periods, plus the repayment of the
principal at the end, whereas the uniform payment bond
requires ten uniform payments to cover both interests and the
principal. Both bonds are subject to optional redemption by the
borrower before maturity.
Example 7-6: Bond financing
mechanisms.
The operating cash flow in column 2 of Table 7-3 represents the
construction expenditures in the early periods and rental
receipts in later periods over the lifetime of the facility. By trial
and error with Eqs. (7.9) and (7.10), it can be found that
Q = $2.5 million (K = $0.125 or 5% of Q) is necessary to insure
a nonnegative balance in the project account for the uniform
payment bond, as shown in Column 6 of Table 7-3. For the
purpose of comparison, the same amount is borrowed for the
coupon bond option even though a smaller loan will be sufficient
for the construction expenditures in this case.
Example 7-6: Bond financing
mechanisms.
The financial cash flow of the coupon bond can easily be
derived from Q = $2.5 million and K = $0.125 million. Using Eq.
(7.5), Ip= (5%)(2.5) = $0.125 million, and the repayment in
Period 10 is Q + Ip = $2.625 million as shown in Column 3 of
Table 7-3. The account balance for the coupon bond in Column
4 is obtained from Eqs. (7.9) and (7.10). On the other hand, the
uniform annual payment U = $0.324 million for the financial
cash flow of the uniform payment bond (Column 5) can be
obtained from Eq. (7.6), and the bond account for this type of
balance is computed by Eqs. (7.9) and (7.10).
Example 7-6: Bond financing
mechanisms.
Because of the optional redemption provision for both types of
bonds, it is advantageous to gradually redeem both options at
the end of period 3 to avoid interest payments resulting from i =
5% and h = 4% unless the account balance beyond period 3 is
needed to fund other corporate investments. corporate earnings
are available for repurchasing the bonds at end of period 3, the
required repayment for coupon bond after redeeming the last
coupon at the end of period 3 is simply $2.625 million. In the
case of the uniform payment bond, the required payment after
the last uniform payment at the end of period 3 is obtained from
Equation (7-13) as:
R3 = (0.324)(P|U, 5%, 7) = (0.324)(5.7864) = $1.875
million.
Example 7-6: Bond financing
mechanisms.
Period
Operating
Cash Flow
Coupon
Cash Flow
Account
Balance
Uniform
Cash Flow
Account
Balance
0
1
2
3
4
5
6
7
8
9
10
-
- $800
-700
-60
400
600
800
1,000
1,000
1,000
1,000
$2,375
- 125
- 125
- 125
- 125
- 125
- 125
- 125
- 125
- 125
- 2,625
$2,375
1,545
782
628
928
1,440
2,173
3,135
4,135
5,176
3,758
$2,375
- 324
- 324
- 324
- 324
- 324
- 324
- 324
- 324
- 324
- 324
$2,375
1,346
376
8
84
364
854
1,565
2,304
3,072
3,871
TABLE 7-3 Example of Two Borrowing Cash Flows (in $ thousands)
7.4 Secured Loans with
Bonds, Notes and Mortgages
Example 7-7: Provision of Reserve Funds
Example 7-7: Provision of
Reserve Funds
Typical borrowing agreements may include various required
reserve funds. [2] Consider an eighteen month project costing
five million dollars. To finance this facility, coupon bonds will be
issued to generate revenues which must be sufficient to pay
interest charges during the eighteen months of construction, to
cover all construction costs, to pay issuance expenses, and to
maintain a debt service reserve fund. The reserve fund is
introduced to assure bondholders of payments in case of
unanticipated construction problems. It is estimated that a total
amount of $7.4 million of bond proceeds is required, including a
two percent discount to underwriters and an issuance expense
of $100,000.
Example 7-7: Provision of
Reserve Funds
Three interest bearing accounts are established with the bond
proceeds to separate various categories of funds:
• A construction fund to provide payments to contractors, with
an initial balance of $4,721,600. Including interest earnings,
this fund will be sufficient to cover the $5,000,000 in
construction expenses.
• A capitalized interest fund to provide interest payments
during the construction period. /li>
• A debt service reserve fund to be used for retiring
outstanding debts after the completion of construction.
The total sources of funds (including interest from account
balances) and uses of funds are summarized in Table 7-4
Example 7-7: Provision of
Reserve Funds
Sources of Funds
Bond Proceeds
Interest Earnings on Construction Fund
Interest Earnings of Capitalized Interest Fund
Interest Earnings on Debt Service Reserve Fund
Total Sources of Funds
$7,400,000
278,400
77,600
287,640
$8,043,640
Uses of Funds
Construction Costs
Interest Payments
Debt Service Reserve Fund
Bond Discount (2.0%)
Issuance Expense
Total Uses of Funds
$5,000,000
904,100
1,891,540
148,000
100,000
$8,043,640
TABLE 7-4 Illustrative Sources and Uses of Funds from Revenue Bonds During
Construction
7.4 Secured Loans with
Bonds, Notes and Mortgages
Example 7-8: Variable rate revenue bonds prospectus
Example 7-8: Variable rate
revenue bonds prospectus
The information in Table 7-5 is abstracted from the Prospectus
for a new issue of revenue bonds for the Atwood City. This
prospectus language is typical for municipal bonds. Notice the
provision for variable rate after the initial interest periods. The
borrower reserves the right to repurchase the bond before the
date for conversion to variable rate takes effect in order to
protect itself from declining market interest rates in the future so
that the borrower can obtain other financing arrangements at
lower rates.
Example 7-8: Variable rate
revenue bonds prospectus
Financing of Constructed
Facilities
7.5 Overdraft Accounts
7.5 Overdraft Accounts
Overdrafts can be arranged with a banking institution to allow
accounts to have either a positive or a negative balance. With a
positive balance, interest is paid on the account balance,
whereas a negative balance incurs interest charges. Usually, an
overdraft account will have a maximum overdraft limit imposed.
Also, the interest rate h available on positive balances is less
than the interest rate i charged for borrowing.
7.5 Overdraft Accounts
Clearly, the effects of overdraft financing depends upon the
pattern of cash flows over time. Suppose that the net cash flow
for period t in the account is denoted by At which is the
difference between the receipt Pt and the payment Et in period t.
Hence, At can either be positive or negative. The amount of
overdraft at the end of period t is the cumulative net cash flow
Nt which may also be positive or negative. If Nt is positive, a
surplus is indicated and the subsequent interest would be paid
to the borrower. Most often, Nt is negative during the early time
periods of a project and becomes positive in the later periods
when the borrower has received payments exceeding
expenses.
7.5 Overdraft Accounts
If the borrower uses overdraft financing and pays the interest
per period on the accumulated overdraft at a borrowing rate i in
each period, then the interest per period for the accumulated
overdraft Nt-1 from the previous period (t-1) is It = iNt-1 where
It would be negative for a negative account balance Nt-1. For a
positive account balance, the interest received is It = hNt-
1 where It would be positive for a positive account balance.
7.5 Overdraft Accounts
The account balance Nt at each period t is the sum of receipts
Pt, payments Et, interest It and the account balance from the
previous period Nt-1. Thus,
7.5 Overdraft Accounts
where It = iNt-1 for a negative Nt-1 and It = hNt-1 for a positive Nt-1.
The net cash flow At = Pt - Et is positive for a net receipt and
negative for a net payment. This equation is approximate in that
the interest might be earned on intermediate balances based on
the pattern of payments during the period instead of at the end
of a period. The account balance in each period is of interest
because there will always be a maximum limit on the amount of
overdraft available.
7.5 Overdraft Accounts
For the purpose of separating project finances with other
receipts and payments in an organization, it is convenient to
establish a credit account into which receipts related to the
project must be deposited when they are received, and all
payments related to the project will be withdrawn from this
account when they are needed.
7.5 Overdraft Accounts
Since receipts typically lag behind payments for a project, this
credit account will have a negative balance until such time when
the receipts plus accrued interests are equal to or exceed
payments in the period. When that happens, any surplus will not
be deposited in the credit account, and the account is then
closed with a zero balance. In that case, for negative Nt-1, Eq.
(7.15) can be expressed as:
and as soon as Nt reaches a positive value or zero, the account
is closed.
7.5 Overdraft Accounts
Example 7-9: Overdraft Financing with Grants to a Local
Agency
Example 7-9: Overdraft Financing
with Grants to a Local Agency
A public project which costs $61,525,000 is funded eighty
percent by a federal grant and twenty percent from a state
grant. The anticipated duration of the project is six years with
receipts from grant funds allocated at the end of each year to a
local agency to cover partial payments to contractors for that
year while the remaining payments to contractors will be
allocated at the end of the sixth year. The end-of-year payments
are given in Table 7-6 in which t=0 refers to the beginning of the
project, and each period is one year.
Example 7-9: Overdraft Financing
with Grants to a Local Agency
If this project is financed with an overdraft at an annual interest
rate i = 10%, then the account balance are computed by Eq.
(7.15) and the results are shown in Table 7-6.
Example 7-9: Overdraft Financing
with Grants to a Local Agency
In this project, the total grant funds to the local agency covered
the cost of construction in the sense that the sum of receipts
equaled the sum of construction payments of $61,525,000.
However, the timing of receipts lagged payments, and the
agency incurred a substantial financing cost, equal in this plan
to the overdraft amount of $1,780,000 at the end of year 6
which must be paid to close the credit account. Clearly, this
financing problem would be a significant concern to the local
agency.
Example 7-9: Overdraft Financing
with Grants to a Local Agency
Period t Receipts Pt Payments Et Interest It Account Nt
0
1
2
3
4
5
6
Total
0
$5.826
8.401
12.013
15.149
13.984
6.152
$61.525
0
$6.473
9.334
13.348
16.832
15.538
0
$61.525
0
0
- $0.065
- 0.165
- 0.315
- 0.514
- 0.721
-$1.780
0
-$0.647
- 1.645
- 3.145
- 5.143
- 7.211
- 1.780
TABLE 7-6 Illustrative Payments, Receipts and Overdrafts for a Six
Year Project
7.5 Overdraft Accounts
Example 7-10: Use of overdraft financing for a facility
Example 7-10: Use of overdraft
financing for a facility
A corporation is contemplating an investment in a facility with
the following before-tax operating net cash flow (in thousands of
dollars) at year ends:
Year 0 1 2 3 4 5 6 7
Cash
Flow
-500 110 112 114 116 118 120 238
Example 7-10: Use of overdraft
financing for a facility
The MARR of the corporation before tax is 10%. The
corporation will finance the facility be using $200,000 from
retained earnings and by borrowing the remaining $300,000
through an overdraft credit account which charges 14% interest
for borrowing. Is this proposed project including financing costs
worthwhile?
Example 7-10: Use of overdraft
financing for a facility
The results of the analysis of this project is shown in Table 7-7
as follows:
N0 = -500 + 200 = -300
N1 = (1.14)(-300) + 110 = -232
N2 = (1.14)(-232) + 112 = -152.48
N3 = (1.14)(-152.48) + 114 = -59.827
N4 = (1.14)(-59.827) +116 = +47.797
Example 7-10: Use of overdraft
financing for a facility
Since N4 is positive, it is revised to exclude the net receipt of
116 for this period. Then, the revised value for the last balance
is
N4' = N4 - 116 = - 68.203
Example 7-10: Use of overdraft
financing for a facility
The financial cash flow resulting from using overdrafts and
making repayments from project receipts will be:
A 0= - N0 = 300
A 0 = - A1 = -110
A 0 = - A2 = -112
A 0 = - A3 = -114
A 0 = N4 - A4 = - 68.203
Example 7-10: Use of overdraft
financing for a facility
The adjusted net present value of the combined cash flow
discounted at 15% is $27,679 as shown in Table 7-7. Hence,
the project including the financing charges is worthwhile.
Example 7-10: Use of overdraft
financing for a facility
End of Year
t
Operating Cash
Flow
At
Overdraft
Balance
Nt
Financing Cash
Flow
Combined
Cash Flow
AAt
0
1
2
3
4
5
6
7
[PV]15%
- $500
110
112
114
116
118
120
122
$21.971
- $300
- 232
- 152.480
-59.827
0
0
0
0
&300
- 110
- 112
- 114
- 68.203
0
0
0
$5.708
- $200
0
0
0
47.797
118
120
122
$27.679
TABLE 7-7 Evaluation of Facility Financing Using Overdraft (in $ thousands)
Financing of Constructed
Facilities
7.6 Refinancing of Debts
7.6 Refinancing of Debts
Refinancing of debts has two major advantages for an owner.
First, they allow re-financing at intermediate stages to save
interest charges. If a borrowing agreement is made during a
period of relatively high interest charges, then a repurchase
agreement allows the borrower to re-finance at a lower interest
rate. Whenever the borrowing interest rate declines such that
the savings in interest payments will cover any transaction
expenses (for purchasing outstanding notes or bonds and
arranging new financing), then it is advantageous to do so.
7.6 Refinancing of Debts
Another reason to repurchase bonds is to permit changes in the
operation of a facility or new investments. Under the terms of
many bond agreements, there may be restrictions on the use of
revenues from a particular facility while any bonds are
outstanding. These restrictions are inserted to insure
bondholders that debts will be repaid. By repurchasing bonds,
these restrictions are removed. For example, several bridge
authorities had bonds that restricted any diversion of toll
revenues to other transportation services such as transit.
7.6 Refinancing of Debts
By repurchasing these bonds, the authority could undertake
new operations. This type of repurchase may occur voluntarily
even without a repurchase agreement in the original bond. The
borrower may give bondholders a premium to retire bonds
early.
7.6 Refinancing of Debts
Example 7-11: Refinancing a loan.
Example 7-11: Refinancing a
loan.
Suppose that the bank loan shown in Example 7-4 had a
provision permitting the borrower to repay the loan without
penalty at any time. Further, suppose that interest rates for new
loans dropped to nine percent at the end of year six of the loan.
Issuing costs for a new loan would be $50,000. Would it be
advantageous to re-finance the loan at that time?
Example 7-11: Refinancing a
loan.
To repay the original loan at the end of year six would require a
payment of the remaining principal plus the interest due at the
end of year six. This amount R6 is equal to the present value of
remaining fourteen payments discounted at the loan interest
rate 11.2% to the end of year 6 as given in Equation (7-13) as
follows:
Example 7-11: Refinancing a
loan.
The new loan would be in the amount of $ 9.152 million plus the
issuing cost of $0.05 million for a total of $ 9.202 million. Based
on the new loan interest rate of 9%, the new uniform annual
payment on this loan from years 7 to 20 would be:
Example 7-11: Refinancing a
loan.
The net present value of the financial cash flow for the new loan
would be obtained by discounting at the corporate MARR of
15% to the end of year six as follows:
Example 7-11: Refinancing a
loan.
Since the annual payment on the new loan is less than the
existing loan ($1.182 versus $1.324 million), the new loan is
preferable.
Financing of Constructed
Facilities
7.7 Project versus Corporate Finance
7.7 Project versus Corporate
Finance
We have focused so far on problems and concerns at the
project level. While this is the appropriate viewpoint for project
managers, it is always worth bearing in mind that projects must
fit into broader organizational decisions and structures. This is
particularly true for the problem of project finance, since it is
often the case that financing is planned on a corporate or
agency level, rather than a project level. Accordingly, project
managers should be aware of the concerns at this level of
decision making.
7.7 Project versus Corporate
Finance
A construction project is only a portion of the general capital
budgeting problem faced by an owner. Unless the project is
very large in scope relative to the owner, a particular
construction project is only a small portion of the capital
budgeting problem. Numerous construction projects may be
lumped together as a single category in the allocation of
investment funds. Construction projects would compete for
attention with equipment purchases or other investments in a
private corporation.
7.7 Project versus Corporate
Finance
Financing is usually performed at the corporate level using a
mixture of long term corporate debt and retained earnings. A
typical set of corporate debt instruments would include the
different bonds and notes discussed in this chapter. Variations
would typically include different maturity dates, different levels
of security interests, different currency denominations, and, of
course, different interest rates.
7.7 Project versus Corporate
Finance
Grouping projects together for financing influences the type of
financing that might be obtained. As noted earlier, small and
large projects usually involve different institutional
arrangements and financing arrangements. For small projects,
the fixed costs of undertaking particular kinds of financing may
be prohibitively expensive. For example, municipal bonds
require fixed costs associated with printing and preparation that
do not vary significantly with the size of the issue. By combining
numerous small construction projects, different financing
arrangements become more practical.
7.7 Project versus Corporate
Finance
While individual projects may not be considered at the
corporate finance level, the problems and analysis procedures
described earlier are directly relevant to financial planning for
groups of projects and other investments. Thus, the net present
values of different financing arrangements can be computed
and compared. Since the net present values of different sub-
sets of either investments or financing alternatives are additive,
each project or finance alternative can be disaggregated for
closer attention or aggregated to provide information at a higher
decision making level.
7.7 Project versus Corporate
Finance
Example 7-12: Basic types of repayment schedules for
loans.
Example 7-12: Basic types of
repayment schedules for loans.
Coupon bonds are used to obtain loans which involve no
payment of principal until the maturity date. By combining loans
of different maturities, however, it is possible to achieve almost
any pattern of principal repayments. However, the interest rates
charged on loans of different maturities will reflect market forces
such as forecasts of how interest rates will vary over time. As
an example, Table 7-8 illustrates the cash flows of debt service
for a series of coupon bonds used to fund a municipal
construction project; for simplicity not all years of payments are
shown in the table.
Example 7-12: Basic types of
repayment schedules for loans.
In this financing plan, a series of coupon bonds were sold with
maturity dates ranging from June 1988 to June 2012. Coupon
interest payments on all outstanding bonds were to be paid
every six months, on December 1 and June 1 of each year. The
interest rate or "coupon rate" was larger on bonds with longer
maturities, reflecting an assumption that inflation would increase
during this period. The total principal obtained for construction
was $26,250,000 from sale of these bonds.
Example 7-12: Basic types of
repayment schedules for loans.
This amount represented the gross sale amount before
subtracting issuing costs or any sales discounts; the amount
available to support construction would be lower. The maturity
dates for bonds were selected to require relative high
repayment amounts until December 1995, with a declining
repayment amount subsequently. By shifting the maturity dates
and amounts of bonds, this pattern of repayments could be
altered. The initial interest payment (of $819,760 on December
1, 1987), reflected a payment for only a portion of a six month
period since the bonds were issued in late June of 1987.
Example 7-12: Basic types of
repayment schedules for loans.
Date Maturing Principal
Corresponding
Interest Rate Interest Due Annual Debt Service
Dec. 1, 1987
June 1, 1988
Dec. 1, 1988
June 1, 1989
Dec. 1, 1989
June 1, 1990
Dec. 1, 1990
June 1, 1991
Dec. 1, 1991
June 1, 1992
Dec. 1, 1992
June 1, 1993
Dec. 1, 1993
.
.
.
June 1, 2011
Dec. 1, 2011
June 1, 2012
Dec. 1, 2012
$1,350,000
1,450,000
1,550,000
1,600,000
1,700,000
1,800,000
.
.
.
880,000
96,000
5.00%
5.25
5.50
5.80
6.00
6.20
.
.
.
8.00
8.00
$819,760
894,429
860,540
860,540
822,480
822,480
779,850
779,850
733,450
733,450
682,450
682,450
626,650
.
.
.
68,000
36,000
36,000
$819,760
3,104,969
3,133,020
3,152,330
3,113,300
3,115,900
3,109,100
.
.
.
984,000
996,000
TABLE 7-8 Illustration of a Twenty-five Year Maturity Schedule for Bonds
Financing of Constructed
Facilities
7.8 Shifting Financial Burdens
7.8 Shifting Financial
Burdens
The different participants in the construction process have quite
distinct perspectives on financing. In the realm of project
finance, the revenues to one participant represent an
expenditure to some other participant. Payment delays from
one participant result in a financial burden and a cash flow
problem to other participants. It is common occurrence in
construction to reduce financing costs by delaying payments in
just this fashion. Shifting payment times does not eliminate
financing costs, however, since the financial burden still exists.
7.8 Shifting Financial
Burdens
Traditionally, many organizations have used payment delays
both to shift financing expenses to others or to overcome
momentary shortfalls in financial resources. From the owner's
perspective, this policy may have short term benefits, but it
certainly has long term costs. Since contractors do not have
large capital assets, they typically do not have large amounts of
credit available to cover payment delays. Contractors are also
perceived as credit risks in many cases, so loans often require
a premium interest charge. Contractors faced with large
financing problems are likely to add premiums to bids or not bid
at all on particular work. For example, A. Maevis noted: [3]
7.8 Shifting Financial
Burdens
...there were days in New York City when city agencies had
trouble attracting bidders; yet contractors were beating on the
door to get work from Consolidated Edison, the local utility.
Why? First, the city was a notoriously slow payer, COs (change
orders) years behind, decision process chaotic, and payments
made 60 days after close of estimate. Con Edison paid on the
20th of the month for work done to the first of the month.
Change orders negotiated and paid within 30 days-60 days. If a
decision was needed, it came in 10 days. The number of bids
you receive on your projects are one measure of your
administrative efficiency. Further, competition is bound to give
you the lowest possible construction price.
7.8 Shifting Financial
Burdens
Even after bids are received and contracts signed, delays in
payments may form the basis for a successful claim against an
agency on the part of the contractor.
7.8 Shifting Financial
Burdens
The owner of a constructed facility usually has a better credit
rating and can secure loans at a lower borrowing rate, but there
are some notable exceptions to this rule, particularly for
construction projects in developing countries. Under certain
circumstances, it is advisable for the owner to advance periodic
payments to the contractor in return for some concession in the
contract price. This is particularly true for large-scale
construction projects with long durations for which financing
costs and capital requirements are high. If the owner is willing to
advance these amounts to the contractor, the gain in lower
financing costs can be shared by both parties through prior
agreement.
7.8 Shifting Financial
Burdens
Unfortunately, the choice of financing during the construction
period is often left to the contractor who cannot take advantage
of all available options alone. The owner is often shielded from
participation through the traditional method of price quotation for
construction contracts. This practice merely exacerbates the
problem by excluding the owner from participating in decisions
which may reduce the cost of the project.
7.8 Shifting Financial
Burdens
Under conditions of economic uncertainty, a premium to hedge
the risk must be added to the estimation of construction cost by
both the owner and the contractor. The larger and longer the
project is, the greater is the risk. For an unsophisticated owner
who tries to avoid all risks and to place the financing burdens of
construction on the contractor, the contract prices for
construction facilities are likely to be increased to reflect the risk
premium charged by the contractors. In dealing with small
projects with short durations, this practice may be acceptable
particularly when the owner lacks any expertise to evaluate the
project financing alternatives or the financial stability to adopt
innovative financing schemes.
7.8 Shifting Financial
Burdens
However, for large scale projects of long duration, the owner
cannot escape the responsibility of participation if it wants to
avoid catastrophes of run-away costs and expensive litigation.
The construction of nuclear power plants in the private sector
and the construction of transportation facilities in the public
sector offer ample examples of such problems. If the
responsibilities of risk sharing among various parties in a
construction project can be clearly defined in the planning
stage, all parties can be benefited to take advantage of cost
saving and early use of the constructed facility.
7.8 Shifting Financial
Burdens
Example 7-13: Effects of payment delays
Example 7-13: Effects of
payment delays
Table 7-9 shows an example of the effects of payment timing on
the general contractor and subcontractors. The total contract
price for this project is $5,100,000 with scheduled payments
from the owner shown in Column 2. The general contractor's
expenses in each period over the lifetime of the project are
given in Column 3 while the subcontractor's expenses are
shown in Column 4. If the general contractor must pay the
subcontractor's expenses as well as its own at the end of each
period, the net cash flow of the general contractor is obtained in
Column 5, and its cumulative cash flow in Column 6.
Example 7-13: Effects of
payment delays
Period
Owner
Payments
General
Contractor'
s
Expenses
Subcontrac
tor's
Expenses
General
Contractor'
s
Net Cash
Flow
Cumulative
Cash Flow
1
2
3
4
5
6
Total
---
$950,000
950,000
950,000
950,000
1,300,000
$5,100,000
$100,000
100,000
100,000
100,000
100,000
-
$500,000
$900,000
900,000
900,000
900,000
900,000
-
$4,500,000
- $1,000,000
- 50,000
- 50,000
- 50,000
- 50,000
1,300,000
$100,000
- $1,000,000
- 1,050,000
- 1,100,000
- 1,150,000
- 1,200,000
100,000
TABLE 7-9 An Example of the Effects of Payment Timing
Example 7-13: Effects of
payment delays
In this example, the owner withholds a five percent retainage on
cost as well as a payment of $100,000 until the completion of
the project. This $100,000 is equal to the expected gross profit
of the contractor without considering financing costs or cash
flow discounting. Processing time and contractual agreements
with the owner result in a delay of one period in receiving
payments. The actual construction expenses from the viewpoint
of the general contractor consist of $100,000 in each
construction period plus payments due to subcontractors of
$900,000 in each period.
Example 7-13: Effects of
payment delays
While the net cash flow without regard to discounting or
financing is equal to a $100,000 profit for the general contractor,
financial costs are likely to be substantial. With immediate
payment to subcontractors, over $1,000,000 must be financed
by the contractor throughout the duration of the project. If the
general contractor uses borrowing to finance its expenses, a
maximum borrowing amount of $1,200,000 in period five is
required even without considering intermediate interest
charges. Financing this amount is likely to be quite expensive
and may easily exceed the expected project profit.
Example 7-13: Effects of
payment delays
By delaying payments to subcontractors, the general contractor
can substantially reduce its financing requirement. For example,
Table 7-10 shows the resulting cash flows from delaying
payments to subcontractors for one period and for two periods,
respectively. With a one period delay, a maximum amount of
$300,000 (plus intermediate interest charges) would have to be
financed by the general contractor. That is, from the data in
Table 7-10, the net cash flow in period 1 is -$100,000, and the
net cash flow for each of the periods 2 through 5 is given by:
$950,000 - $100,000 - $900,000 = -$ 50,000
Example 7-13: Effects of
payment delays
Finally, the net cash flow for period 6 is:
$1,300,000 - $900,000 = $400,000
Example 7-13: Effects of
payment delays
Thus, the cumulative net cash flow from periods 1 through 5 as
shown in Column 2 of Table 7-10 results in maximum shortfall
of $300,000 in period 5 in Column 3. For the case of a two
period payment delay to the subcontractors, the general
contractor even runs a positive balance during construction as
shown in Column 5. The positive balance results from the
receipt of owner payments prior to reimbursing the
subcontractor's expenses. This positive balance can be placed
in an interest bearing account to earn additional revenues for
the general contractor.
Example 7-13: Effects of
payment delays
Needless to say, however, these payment delays mean extra
costs and financing problems to the subcontractors. With a two
period delay in payments from the general contractor, the
subcontractors have an unpaid balance of $1,800,000, which
would represent a considerable financial cost.
Example 7-13: Effects of
payment delays
Period
One Period Payment Delay Two Period Payment Delay
Net Cash
Flow
Cumulative
Cash Flow
Net Cash
Flow
Cumulative
Cash Flow
1
2
3
4
5
6
7
- $100,000
- 50,000
- 50,000
- 50,000
- 50,000
400,000
- $100,000
- 150,000
- 200,000
- 250,000
- 300,000
100,000
- $100,000
850,000
- 50,000
- 50,000
- 50,000
400,000
- 900,000
- $100,000
750,000
700,000
650,000
600,000
1,000,000
100,000
TABLE 7-10 An Example of the Cash Flow Effects of Delayed Payments
Financing of Constructed
Facilities
7.9 Construction Financing for Contractors
7.9 Construction Financing
for Contractors
For a general contractor or subcontractor, the cash flow profile
of expenses and incomes for a construction project typically
follows the work in progress for which the contractor will be paid
periodically. The markup by the contractor above the estimated
expenses is included in the total contract price and the terms of
most contracts generally call for monthly reimbursements of
work completed less retainage. At time period 0, which denotes
the beginning of the construction contract, a considerable sum
may have been spent in preparation.
7.9 Construction Financing
for Contractors
The contractor's expenses which occur more or less
continuously for the project duration are depicted by a
piecewise continuous curve while the receipts (such as
progress payments from the owner) are represented by a step
function as shown in Fig. 7-1. The owner's payments for the
work completed are assumed to lag one period behind
expenses except that a withholding proportion or remainder is
paid at the end of construction. This method of analysis is
applicable to realistic situations where a time period is
represented by one month and the number of time periods is
extended to cover delayed receipts as a result of retainage.
7.9 Construction Financing
for Contractors
Figure 7-1 Contractor's Expenses and
Owner's Payments
7.9 Construction Financing
for Contractors
While the cash flow profiles of expenses and receipts are
expected to vary for different projects, the characteristics of the
curves depicted in Fig. 7-1 are sufficiently general for most
cases. Let Et represent the contractor's expenses in period t,
and Pt represent owner's payments in period t, for t=0,1,2,...,n
for n=5 in this case. The net operating cash flow at the end of
period t for t 0 is given by:
7.9 Construction Financing
for Contractors
where At is positive for a surplus and negative for a shortfall.
The cumulative operating cash flow at the end of period t just
before receiving payment Pt (for t 1) is:
7.9 Construction Financing
for Contractors
where Nt-1 is the cumulative net cash flows from period 0 to
period (t-1). Furthermore, the cumulative net operating cash
flow after receiving payment Pt at the end of period t (for t 1) is:
7.9 Construction Financing
for Contractors
The gross operating profit G for a n-period project is defined as
net operating cash flow at t=n and is given by:
The use of Nn as a measure of the gross operating profit has
the disadvantage that it is not adjusted for the time value of
money.
7.9 Construction Financing
for Contractors
Since the net cash flow At (for t=0,1,...,n) for a construction
project represents the amount of cash required or accrued after
the owner's payment is plowed back to the project at the end of
period t, the internal rate of return (IRR) of this cash flow is
often cited in the traditional literature in construction as a profit
measure. To compute IRR, let the net present value (NPV) of
At discounted at a discount rate i per period be zero, i.e.,
7.9 Construction Financing
for Contractors
The resulting i (if it is unique) from the solution of Eq. (7.21) is
the IRR of the net cash flow At. Aside from the complications
that may be involved in the solution of Eq. (7.21), the resulting i
= IRR has a meaning to the contractor only if the firm finances
the entire project from its own equity. This is seldom if ever the
case since most construction firms are highly leveraged, i.e.
they have relatively small equity in fixed assets such as
construction equipment, and depend almost entirely on
borrowing in financing individual construction projects.
7.9 Construction Financing
for Contractors
The use of the IRR of the net cash flows as a measure of profit
for the contractor is thus misleading. It does not represent even
the IRR of the bank when the contractor finances the project
through overdraft since the gross operating profit would not be
given to the bank.
7.9 Construction Financing
for Contractors
Since overdraft is the most common form of financing for small
or medium size projects, we shall consider the financing costs
and effects on profit of - the use of overdrafts. Let be the
cumulative cash flow before the owner's payment in period
t including interest and be the cumulative net cash flow in
period t including interest. At t = 0 when there is no accrued
interest, = F0 and = N0. For t in period t can be
obtained by considering the contractor's expensesI Et to be
dispersed uniformly during the period.
7.9 Construction Financing
for Contractors
The inclusion of enterest on contractor's expenses Et during
period t (for G 1) is based on the rationale that the S-shaped
curve depicting the contractor's expenses in Figure 7-1 is fairly
typical of actual situations, where the owner's payments are
typically made at the end of well defined periods.
7.9 Construction Financing
for Contractors
Hence, interest on expenses during period t is approximated by
one half of the amount as if the expenses were paid at the
beginning of the period. In fact, Et is the accumulation of all
expenses in period t and is treated - as an expense at the end
of the period. Thus, the interest per period (for t 1) is the
combination of interest charge for Nt-1 in period t and that for
one half of Et in the same period t. If is negative and i is the
borrowing rate for the shortfall,
7.9 Construction Financing
for Contractors
If is positive and h is the investment rate for the surplus,
7.9 Construction Financing
for Contractors
Hence, if the cumulative net cash flow is negative, the interest
on the overdraft for each period t is paid by the contractor at the
end of each period. If Nt is positive, a surplus is indicated and
the subsequent interest would be paid to the contractor. Most
often, Nt is negative during the early time periods of a project
and becomes positive in the later periods when the contractor
has received payments exceeding expenses.
7.9 Construction Financing
for Contractors
Including the interest accrued in period t, the cumulative cash
flow at the end of period t just before receiving payment Pt (for
t ≥1) is:
7.9 Construction Financing
for Contractors
The gross operating profit at the end of a n-period project
including interest charges is:
where is the cumulative net cash flow for t = n.
7.9 Construction Financing
for Contractors
Example 7-14: Contractor's gross profit from a project
Example 7-14: Contractor's
gross profit from a project
The contractor's expenses and owner's payments for a multi-
year construction project are given in Columns 2 and 3,
respectively, of Table 7-11. Each time period is represented by
one year, and the annual interest rate i is for borrowing 11%.
The computation has been carried out in Table 7-11, and the
contractor's gross profit G is found to be N5 = $8.025 million in
the last column of the table.
Example 7-14: Contractor's
gross profit from a project
TABLE 7-11 Example of Contractor's Expenses and Owner's
Payments ($ Million)
Period
t
Contractor's
Expenses
Et
Owner's
Payments
Pt
Net Cash
Flow
At
Cumulative
Cash
Before
Payments
Ft
Cumulative
Net Cash
Nt
0
1
2
3
4
5
Total
$3.782
7.458
10.425
14.736
11.420
5.679
$53.500
$0
6.473
9.334
13.348
16.832
15.538
$61.525
-$3.782
-0.985
-1.091
-1.388
+5.412
+9.859
+$8.025
-$3.782
-11.240
-15.192
-20.594
-18.666
-7.513
-$3.782
-4.767
-5.858
-7.246
-1.834
+8.025
7.9 Construction Financing
for Contractors
Example 7-15: Effects of Construction Financing
Example 7-15: Effects of
Construction Financing
The computation of the cumulative cash flows including interest
charges at i = 11% for Example 7-14 is shown in Table 7-12
with gross profit = = $1.384 million. The results of
computation are also shown in Figure 7-2.
Example 7-15: Effects of
Construction Financing
Period
(year)
t
Constructio
n Expenses
Et
Owner's
Payments
Pt
Annual
Interest
Cumulative
Before
Payments
Cumulative
Net Cash
Flow
0
1
2
3
4
5
$3.782
7.458
10.425
14.736
11.420
5.679
0
$6.473
9.334
13.348
16.832
15.538
0
-$0.826
-1.188
-1.676
-1.831
-1.121
-$3.782
-12.066
-17.206
-24.284
-24.187
-14.154
-$3.782
-5.593
-7.872
-10.936
-7.354
+1.384
TABLE 7-12 Example Cumulative Cash Flows Including Interests for a
Contractor ($ Million)
Example 7-15: Effects of
Construction Financing
Example 7-15: Effects of
Construction Financing
Figure 7-2 Effects of Overdraft Financing
Financing of Constructed
Facilities
7.10 Effects of Other Factors on a Contractor's Profits
7.10 Effects of Other Factors
on a Contractor's Profits
In times of economic uncertainty, the fluctuations in inflation
rates and market interest rates affect profits significantly. The
total contract price is usually a composite of expenses and
payments in then-current dollars at different payment periods. In
this case, estimated expenses are also expressed in then-
current dollars.
7.10 Effects of Other Factors
on a Contractor's Profits
During periods of high inflation, the contractor's profits are
particularly vulnerable to delays caused by uncontrollable
events for which the owner will not be responsible. Hence, the
owner's payments will not be changed while the contractor's
expenses will increase with inflation.
7.10 Effects of Other Factors
on a Contractor's Profits
Example 7-16: Effects of Inflation
Example 7-16: Effects of
Inflation
Suppose that both expenses and receipts for the construction
project in the Example 7-14 are now expressed in then-current
dollars (with annual inflation rate of 4%) in Table 7-13. The
market interest rate reflecting this inflation is now 15%. In
considering these expenses and receipts in then-current dollars
and using an interest rate of 15% including inflation, we can
recompute the cumulative net cash flow (with interest). Thus,
the gross profit less financing costs becomes = = $0.4
million. There will be a loss rather than a profit after deducting
financing costs and adjusting for the effects of inflation with this
project.
Example 7-16: Effects of
Inflation
TABLE 7-13 Example of Overdraft Financing Based on Inflated
Dollars ($ Million)
Period
(year)
t
Constructi
on
Expenses
Et
Owner's
Payments
Pt
Annual
Interest
Cumulative
Before
Payments
Cumulative
Net Cash
Flow
0
1
2
3
4
5
$3.782
7.756
11.276
16.576
13.360
6.909
0
$6.732
10.096
15.015
16.691
18.904
0
-$1.149
-1.739
-2.574
-2.953
-1.964
-$3.782
-12.687
-18.970
-28.024
-29.322
-18.504
-$3.782
-5.955
-8.874
-13.009
-9.631
+0.400
7.10 Effects of Other Factors
on a Contractor's Profits
Example 7-17: Effects of Work Stoppage at Periods of
Inflation
Example 7-17: Effects of Work
Stoppage at Periods of Inflation
Suppose further that besides the inflation rate of 4%, the project
in Example 7-16 is suspended at the end of year 2 due to a
labor strike and resumed after one year. Also, assume that
while the contractor will incur higher interest expenses due to
the work stoppage, the owner will not increase the payments to
the contractor. The cumulative net cash flows for the cases of
operation and financing expenses are recomputed and
tabulated in Table 7-14.
Example 7-17: Effects of Work
Stoppage at Periods of Inflation
The construction expenses and receipts in then-current dollars
resulting from the work stopping and the corresponding net
cash flow of the project including financing (with annual interest
accumulated in the overdraft to the end of the project) is shown
in Fig. 7-3. It is noteworthy that, with or without the work
stoppage, the gross operating profit declines in value at the end
of the project as a result of inflation, but with the work stoppage
it has eroded - further to a loss of $3.524 million as indicated
by = -3.524 in Table 7-14.
Example 7-17: Effects of Work
Stoppage at Periods of Inflation
Period
(year)
t
Constructi
on
Expenses
Et
Owner's
Payments
Pt
Annual
Interest
Cumulative
Before
Payments
Cumulative
Net Cash
Flow
0
1
2
3
4
5
6
$3.782
7.756
11.276
0
17.239
13.894
7.185
0
$6.732
10.096
0
15.015
16.691
18.904
0
-$1.149
-1.739
-1.331
-2.824
-3.330
-2.457
-$3.782
-12.687
-18.970
-10.205
-30.268
-32.477
22.428
-$3.782
-5.955
-8.874
-10.205
-15.253
-12.786
-3.524
TABLE 7-14 Example of the Effects of Work Stoppage and Inflation on a
Contractor ($ Million)
Example 7-17: Effects of Work
Stoppage at Periods of Inflation
Figure 7-3 Effects of Inflation and Work Stoppage
Example 7-17: Effects of Work
Stoppage at Periods of Inflation
Figure 7-3 Effects of Inflation and Work Stoppage
7.10 Effects of Other Factors
on a Contractor's Profits
Example 7-18: Exchange Rate Fluctuation
Example 7-18: Exchange
Rate Fluctuation
Contracting firms engaged in international practice also face
financial issues associated with exchange rate fluctuations.
Firms are typically paid in local currencies, and the local
currency may loose value relative to the contractor's home
currency. Moreover, a construction contractor may have to
purchase component parts in the home currency. Various
strategies can be used to reduce this exchange rate risk,
including:
Example 7-18: Exchange
Rate Fluctuation
• Pooling expenses and incomes from multiple projects to
reduce the amount of currency exchanged.
• Purchasing futures contracts to exchange currency at a
future date at a guaranteed rate. If the exchange rate does
not change or changes in a favorable direction, the
contractor may decide not to exercise or use the futures
contract.
• Borrowing funds in local currencies and immediately
exchanging the expected profit, with the borrowing paid by
eventual payments from the owner.
Financing of Constructed
Facilities
7.11 References
7.11 References
1. Au, T., and C. Hendrickson, "Profit Measures for
Construction Projects," ASCE Journal of Construction
Engineering and Management, Vol. 112, No. CO-2, 1986,
pp. 273-286.
2. Brealey, R. and S. Myers, Principles of Corporate
Finance, McGraw-Hill, Sixth Edition, 2002.
3. Collier, C.A. and D.A. Halperin, Construction Funding:
Where the Money Comes From, Second Edition, John Wiley
and Sons, New York, 1984.
7.11 References
4. Dipasquale, D. and C. Hendrickson, "Options for Financing a
Regional Transit Authority," Transportation Research
Record, No. 858, 1982, pp. 29-35.
5. Kapila, Prashant and Chris Hendrickson, "Exchange Rate
Risk Management in International Construction
Ventures," ASCE J. of Construction Eng. and Mgmt, 17(4),
October 2001.
6. Goss, C.A., "Financing: The Contractor's
Perspective," Construction Contracting, Vol. 62, No. 10, pp.
15-17, 1980.
Financing of Constructed
Facilities
7.13 Footnotes
7.13 Footnotes
1. This table is adapted from A.J. Henkel, "The Mechanics of a
Revenue Bond Financing: An Overview," Infrastructure
Financing, Kidder, Peabody & Co., New York, 1984.
2. The calculations for this bond issue are adapted from a
hypothetical example in F. H. Fuller, "Analyzing Cash Flows for
Revenue Bond Financing," Infrastructure Financing, Kidder,
Peabody & Co., Inc., New York, 1984, pp. 37-47.
3. Maevis, Alfred C.,"Construction Cost Control by the
Owner," ASCE Journal of the Construction Division, Vol. 106,
No. 4, December, 1980, pg. 444.

More Related Content

ODP
Project financing and sources of funding
PPTX
Project finance
PPT
Project Financing
PPTX
Banking finance
PPT
Ppt of term loan
PPTX
Project financing methods
PDF
financing projects
PPT
Real estate financing
Project financing and sources of funding
Project finance
Project Financing
Banking finance
Ppt of term loan
Project financing methods
financing projects
Real estate financing

What's hot (20)

PDF
Real Estate Financing
PDF
Project Financing in Public Projects
PPTX
Project Finance - Session 05
PDF
HSE - Introduction to Project Finance
PDF
Project finance good one
PPT
Project financing
PPT
Financing of the Project
PPSX
Steps to Issuing a Municipal Bond:
PPT
Project financing
PPTX
Sources of project financing
PPTX
Project finance presentation ppp conference- south africa 2015
PPTX
An Overview Of Project Financing
PPTX
Types of sponsors and investors in project finance
PPTX
Solar Project Finance: Turning Sunlight Into Green
PDF
Power plant project finance overview
PDF
Collateral loan info pdf
PDF
Bp Amoco (case study)
PPTX
An introduction to project finance
PPT
Project Finance Modeling
PPTX
Long Term Debt Instrument
Real Estate Financing
Project Financing in Public Projects
Project Finance - Session 05
HSE - Introduction to Project Finance
Project finance good one
Project financing
Financing of the Project
Steps to Issuing a Municipal Bond:
Project financing
Sources of project financing
Project finance presentation ppp conference- south africa 2015
An Overview Of Project Financing
Types of sponsors and investors in project finance
Solar Project Finance: Turning Sunlight Into Green
Power plant project finance overview
Collateral loan info pdf
Bp Amoco (case study)
An introduction to project finance
Project Finance Modeling
Long Term Debt Instrument
Ad

Similar to Project management chapter 7 (20)

PDF
Financing Alternatives For Government Contractors
PPT
Project Financing
PPTX
UNIT- 4.pptx
PDF
Effective Financing Responses Chapter 3
PDF
projectfinancing.pdfPROJECT FINANCING WITH ECONOMICAL
PPT
All about the knowledge ofProject Finance.ppt
PPTX
Project management chapter 6
PPTX
Project management chapter 6
DOCX
Financial for development final project
DOCX
understand challenges for infrastructure
PPTX
Project Finance types and explanations.pptx
PPT
Project financing
PPTX
Project funding
PDF
INDEV308 Class 5 - Financing Considerations for Social Enterprise
DOC
Capital investment programming and its financial implications
DOC
21042504 union-bank-credit-appraisal-project-report
PPT
Infrastructure finance nibm
PPT
Funding Your Social Enterprise: Approaches & Resources for Nonprofits
PDF
Infrastructure Planning & Housing Delivery - Who Pays?
PPTX
L10_Risk Management.pptxssssssssssssssssssssssssssssss
Financing Alternatives For Government Contractors
Project Financing
UNIT- 4.pptx
Effective Financing Responses Chapter 3
projectfinancing.pdfPROJECT FINANCING WITH ECONOMICAL
All about the knowledge ofProject Finance.ppt
Project management chapter 6
Project management chapter 6
Financial for development final project
understand challenges for infrastructure
Project Finance types and explanations.pptx
Project financing
Project funding
INDEV308 Class 5 - Financing Considerations for Social Enterprise
Capital investment programming and its financial implications
21042504 union-bank-credit-appraisal-project-report
Infrastructure finance nibm
Funding Your Social Enterprise: Approaches & Resources for Nonprofits
Infrastructure Planning & Housing Delivery - Who Pays?
L10_Risk Management.pptxssssssssssssssssssssssssssssss
Ad

More from VancityInstitute (20)

PPTX
Appendix and Introduction
PPTX
Session 13
PPTX
Session 12
PPTX
Session 11
PPTX
Session 10
PPTX
Session 9
PPTX
Session 8
PPTX
Session 7
PPTX
Session 6
PPTX
Session 5
PPTX
Session 4
PPTX
Session 3
PPTX
Session 2
PPTX
Session 1
PPTX
Construction safety session 1 (new)
PPTX
Project management chapter 14
PPTX
Project management chapter 13
PPTX
Project management chapter 12
PPTX
Project management chapter 12
PPTX
Project management chapter 11
Appendix and Introduction
Session 13
Session 12
Session 11
Session 10
Session 9
Session 8
Session 7
Session 6
Session 5
Session 4
Session 3
Session 2
Session 1
Construction safety session 1 (new)
Project management chapter 14
Project management chapter 13
Project management chapter 12
Project management chapter 12
Project management chapter 11

Recently uploaded (20)

PDF
Weekly quiz Compilation Jan -July 25.pdf
PPTX
History, Philosophy and sociology of education (1).pptx
PDF
1_English_Language_Set_2.pdf probationary
DOC
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
PPTX
Digestion and Absorption of Carbohydrates, Proteina and Fats
PDF
Classroom Observation Tools for Teachers
PDF
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PPTX
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PPTX
UV-Visible spectroscopy..pptx UV-Visible Spectroscopy – Electronic Transition...
PDF
Computing-Curriculum for Schools in Ghana
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
PDF
What if we spent less time fighting change, and more time building what’s rig...
PDF
SOIL: Factor, Horizon, Process, Classification, Degradation, Conservation
PDF
Practical Manual AGRO-233 Principles and Practices of Natural Farming
PPTX
202450812 BayCHI UCSC-SV 20250812 v17.pptx
PPTX
A powerpoint presentation on the Revised K-10 Science Shaping Paper
PDF
Paper A Mock Exam 9_ Attempt review.pdf.
Weekly quiz Compilation Jan -July 25.pdf
History, Philosophy and sociology of education (1).pptx
1_English_Language_Set_2.pdf probationary
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
Digestion and Absorption of Carbohydrates, Proteina and Fats
Classroom Observation Tools for Teachers
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
Supply Chain Operations Speaking Notes -ICLT Program
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
Chinmaya Tiranga quiz Grand Finale.pdf
UV-Visible spectroscopy..pptx UV-Visible Spectroscopy – Electronic Transition...
Computing-Curriculum for Schools in Ghana
Final Presentation General Medicine 03-08-2024.pptx
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
What if we spent less time fighting change, and more time building what’s rig...
SOIL: Factor, Horizon, Process, Classification, Degradation, Conservation
Practical Manual AGRO-233 Principles and Practices of Natural Farming
202450812 BayCHI UCSC-SV 20250812 v17.pptx
A powerpoint presentation on the Revised K-10 Science Shaping Paper
Paper A Mock Exam 9_ Attempt review.pdf.

Project management chapter 7

  • 1. Project Management for Construction Fundamental Concepts for Owners, Engineers, Architects and Builders
  • 2. Chapter 7 Financing of Constructed Facilities
  • 4. 7.1 The Financing Problem Investment in a constructed facility represents a cost in the short term that returns benefits only over the long term use of the facility. Thus, costs occur earlier than the benefits, and owners of facilities must obtain the capital resources to finance the costs of construction. A project cannot proceed without adequate financing, and the cost of providing adequate financing can be quite large. For these reasons, attention to project finance is an important aspect of project management. Finance is also a concern to the other organizations involved in a project such as the general contractor and material suppliers. Unless an owner immediately and completely covers the costs incurred by each participant, these organizations face financing problems of their own.
  • 5. 7.1 The Financing Problem At a more general level, project finance is only one aspect of the general problem of corporate finance. If numerous projects are considered and financed together, then the net cash flow requirements constitutes the corporate financing problem for capital investment. Whether project finance is performed at the project or at the corporate level does not alter the basic financing problem.
  • 6. 7.1 The Financing Problem In essence, the project finance problem is to obtain funds to bridge the time between making expenditures and obtaining revenues. Based on the conceptual plan, the cost estimate and the construction plan, the cash flow of costs and receipts for a project can be estimated. Normally, this cash flow will involve expenditures in early periods. Covering this negative cash balance in the most beneficial or cost effective fashion is the project finance problem.
  • 7. 7.1 The Financing Problem During planning and design, expenditures of the owner are modest, whereas substantial costs are incurred during construction. Only after the facility is complete do revenues begin. In contrast, a contractor would receive periodic payments from the owner as construction proceeds. However, a contractor also may have a negative cash balance due to delays in payment and retainage of profits or cost reimbursements on the part of the owner.
  • 8. 7.1 The Financing Problem Plans considered by owners for facility financing typically have both long and short term aspects. In the long term, sources of revenue include sales, grants, and tax revenues. Borrowed funds must be eventually paid back from these other sources. In the short term, a wider variety of financing options exist, including borrowing, grants, corporate investment funds, payment delays and others. Many of these financing options involve the participation of third parties such as banks or bond underwriters.
  • 9. 7.1 The Financing Problem For private facilities such as office buildings, it is customary to have completely different financing arrangements during the construction period and during the period of facility use. During the latter period, mortgage or loan funds can be secured by the value of the facility itself. Thus, different arrangements of financing options and participants are possible at different stages of a project, so the practice of financial planning is often complicated.
  • 10. 7.1 The Financing Problem On the other hand, the options for borrowing by contractors to bridge their expenditures and receipts during construction are relatively limited. For small or medium size projects, overdrafts from bank accounts are the most common form of construction financing. Usually, a maximum limit is imposed on an overdraft account by the bank on the basis of expected expenditures and receipts for the duration of construction. Contractors who are engaged in large projects often own substantial assets and can make use of other forms of financing which have lower interest charges than overdrafting.
  • 11. 7.1 The Financing Problem In recent years, there has been growing interest in design-build- operate projects in which owners prescribe functional requirements and a contractor handles financing. Contractors are repaid over a period of time from project revenues or government payments. Eventually, ownership of the facilities is transferred to a government entity. An example of this type of project is the Confederation Bridge to Prince Edward Island in Canada.
  • 12. 7.1 The Financing Problem In this chapter, we will first consider facility financing from the owner's perspective, with due consideration for its interaction with other organizations involved in a project. Later, we discuss the problems of construction financing which are crucial to the profitability and solvency of construction contractors.
  • 13. Financing of Constructed Facilities 7.2 Institutional Arrangements for Facility Financing
  • 14. 7.2 Institutional Arrangements for Facility Financing Financing arrangements differ sharply by type of owner and by the type of facility construction. As one example, many municipal projects are financed in the United States with tax exempt bonds for which interest payments to a lender are exempt from income taxes. As a result, tax exempt municipal bonds are available at lower interest charges. Different institutional arrangements have evolved for specific types of facilities and organizations.
  • 15. 7.2 Institutional Arrangements for Facility Financing A private corporation which plans to undertake large capital projects may use its retained earnings, seek equity partners in the project, issue bonds, offer new stocks in the financial markets, or seek borrowed funds in another fashion. Potential sources of funds would include pension funds, insurance companies, investment trusts, commercial banks and others. Developers who invest in real estate properties for rental purposes have similar sources, plus quasi-governmental corporations such as urban development authorities. Syndicators for investment such as real estate investment trusts (REITs) as well as domestic and foreign pension funds represent relatively new entries to the financial market for building mortgage money.
  • 16. 7.2 Institutional Arrangements for Facility Financing Public projects may be funded by tax receipts, general revenue bonds, or special bonds with income dedicated to the specified facilities. General revenue bonds would be repaid from general taxes or other revenue sources, while special bonds would be redeemed either by special taxes or user fees collected for the project. Grants from higher levels of government are also an important source of funds for state, county, city or other local agencies.
  • 17. 7.2 Institutional Arrangements for Facility Financing Despite the different sources of borrowed funds, there is a rough equivalence in the actual cost of borrowing money for particular types of projects. Because lenders can participate in many different financial markets, they tend to switch towards loans that return the highest yield for a particular level of risk. As a result, borrowed funds that can be obtained from different sources tend to have very similar costs, including interest charges and issuing costs.
  • 18. 7.2 Institutional Arrangements for Facility Financing As a general principle, however, the costs of funds for construction will vary inversely with the risk of a loan. Lenders usually require security for a loan represented by a tangible asset. If for some reason the borrower cannot repay a loan, then the borrower can take possession of the loan security. To the extent that an asset used as security is of uncertain value, then the lender will demand a greater return and higher interest payments. Loans made for projects under construction represent considerable risk to a financial institution.
  • 19. 7.2 Institutional Arrangements for Facility Financing If a lender acquires an unfinished facility, then it faces the difficult task of re-assembling the project team. Moreover, a default on a facility may result if a problem occurs such as foundation problems or anticipated unprofitability of the future facility. As a result of these uncertainties, construction lending for unfinished facilities commands a premium interest charge of several percent compared to mortgage lending for completed facilities.
  • 20. 7.2 Institutional Arrangements for Facility Financing Financing plans will typically include a reserve amount to cover unforeseen expenses, cost increases or cash flow problems. This reserve can be represented by a special reserve or a contingency amount in the project budget. In the simplest case, this reserve might represent a borrowing agreement with a financial institution to establish a line of credit in case of need. For publicly traded bonds, specific reserve funds administered by a third party may be established. The cost of these reserve funds is the difference between the interest paid to bondholders and the interest received on the reserve funds plus any administrative costs.
  • 21. 7.2 Institutional Arrangements for Facility Financing Finally, arranging financing may involve a lengthy period of negotiation and review. Particularly for publicly traded bond financing, specific legal requirements in the issue must be met. A typical seven month schedule to issue revenue bonds would include the various steps outlined in Table 7-1. [1] In many cases, the speed in which funds may be obtained will determine a project's financing mechanism.
  • 22. 7.2 Institutional Arrangements for Facility Financing Activities Time of Activities Analysis of financial alternatives Preparation of legal documents Preparation of disclosure documents Forecasts of costs and revenues Bond Ratings Bond Marketing Bond Closing and Receipt of Funds Weeks 0-4 Weeks 1-17 Weeks 2-20 Weeks 4-20 Weeks 20-23 Weeks 21-24 Weeks 23-26 TABLE 7-1 Illustrative Process and Timing for Issuing Revenue Bonds
  • 23. 7.2 Institutional Arrangements for Facility Financing Example 7-1: Example of financing options
  • 24. Example 7-1: Example of financing options Suppose that you represent a private corporation attempting to arrange financing for a new headquarters building. These are several options that might be considered: • Use corporate equity and retained earnings: The building could be financed by directly committing corporate resources. In this case, no other institutional parties would be involved in the finance. However, these corporate funds might be too limited to support the full cost of construction.
  • 25. Example 7-1: Example of financing options • Construction loan and long term mortgage: In this plan, a loan is obtained from a bank or other financial institution to finance the cost of construction. Once the building is complete, a variety of institutions may be approached to supply mortgage or long term funding for the building. This financing plan would involve both short and long term borrowing, and the two periods might involve different lenders. The long term funding would have greater security since the building would then be complete. As a result, more organizations might be interested in providing funds (including pension funds) and the interest charge might be lower. Also, this basic financing plan might be supplemented by other sources such as corporate retained earnings or assistance from a local development agency.
  • 26. Example 7-1: Example of financing options • Lease the building from a third party: In this option, the corporation would contract to lease space in a headquarters building from a developer. This developer would be responsible for obtaining funding and arranging construction. This plan has the advantage of minimizing the amount of funds borrowed by the corporation. Under terms of the lease contract, the corporation still might have considerable influence over the design of the headquarters building even though the developer was responsible for design and construction.
  • 27. Example 7-1: Example of financing options • Initiate a Joint Venture with Local Government: In many areas, local governments will help local companies with major new ventures such as a new headquarters. This help might include assistance in assembling property, low interest loans or proerty tax reductions. In the extreme, local governments may force sale of land through their power of eminent domain to assemble necessary plots.
  • 28. Financing of Constructed Facilities 7.3 Evaluation of Alternative Financing Plans
  • 29. 7.3 Evaluation of Alternative Financing Plans Since there are numerous different sources and arrangements for obtaining the funds necessary for facility construction, owners and other project participants require some mechanism for evaluating the different potential sources. The relative costs of different financing plans are certainly important in this regard. In addition, the flexibility of the plan and availability of reserves may be critical. As a project manager, it is important to assure adequate financing to complete a project. Alternative financing plans can be evaluated using the same techniques that are employed for the evaluation of investment alternatives.
  • 30. 7.3 Evaluation of Alternative Financing Plans As described in Chapter 6, the availability of different financing plans can affect the selection of alternative projects. A general approach for obtaining the combined effects of operating and financing cash flows of a project is to determine the adjusted net present value (APV) which is the sum of the net present value of the operating cash flow (NPV) and the net present value of the financial cash flow (FPV), discounted at their respective minimum attractive rates of return (MARR), i.e.,
  • 31. 7.3 Evaluation of Alternative Financing Plans where r is the MARR reflecting the risk of the operating cash flow and rf is the MARR representing the cost of borrowing for the financial cash flow. Thus, where At and are respectively the operating and financial cash flows in period t.
  • 32. 7.3 Evaluation of Alternative Financing Plans For the sake of simplicity, we shall emphasize in this chapter the evaluation of financing plans, with occasional references to the combined effects of operating and financing cash flows. In all discussions, we shall present various financing schemes with examples limiting to cases of before-tax cash flows discounted at a before-tax MARR of r = rf for both operating and financial cash flows. Once the basic concepts of various financing schemes are clearly understood, their application to more complicated situations involving depreciation, tax liability and risk factors can be considered in combination with the principles for dealing with such topics enunciated in Chapter 6.
  • 33. 7.3 Evaluation of Alternative Financing Plans In this section, we shall concentrate on the computational techniques associated with the most common types of financing arrangements. More detailed descriptions of various financing schemes and the comparisons of their advantages and disadvantages will be discussed in later sections.
  • 34. 7.3 Evaluation of Alternative Financing Plans Typically, the interest rate for borrowing is stated in terms of annual percentage rate (A.P.R.), but the interest is accrued according to the rate for the interest period specified in the borrowing agreement. Let ip be the nominal annual percentage rate, and i be the interest rate for each of the p interest periods per year. By definition
  • 35. 7.3 Evaluation of Alternative Financing Plans If interest is accrued semi-annually, i.e., p = 2, the interest rate per period is ip/2; similarly if the interest is accrued monthly, i.e., p = 12, the interest rate per period is ip/12. On the other hand, the effective annual interest rate ie is given by:
  • 36. 7.3 Evaluation of Alternative Financing Plans Note that the effective annual interest rate, ie, takes into account compounding within the year. As a result, ie is greater than ip for the typical case of more than one compounding period per year.
  • 37. 7.3 Evaluation of Alternative Financing Plans For a coupon bond, the face value of the bond denotes the amount borrowed (called principal) which must be repaid in full at a maturity or due date, while each coupon designates the interest to be paid periodically for the total number of coupons covering all periods until maturity. Let Q be the amount borrowed, and Ip be the interest payment per period which is often six months for coupon bonds. If the coupon bond is prescribed to reach maturity in n years from the date of issue, the total number of interest periods will be pn = 2n. The semi- annual interest payment is given by:
  • 38. 7.3 Evaluation of Alternative Financing Plans In purchasing a coupon bond, a discount from or a premium above the face value may be paid.
  • 39. 7.3 Evaluation of Alternative Financing Plans An alternative loan arrangement is to make a series of uniform payments including both interest and part of the principal for a pre-defined number of repayment periods. In the case of uniform payments at an interest rate i for n repayment periods, the uniform repayment amount U is given by:
  • 40. 7.3 Evaluation of Alternative Financing Plans where (U|P,i,n) is a capital recovery factor which reads: "to find U, given P=1, for an interest rate i over n periods." Compound interest factors are as tabulated in Appendix A. The number of repayment periods n will clearly influence the amounts of payments in this uniform payment case. Uniform payment bonds or mortgages are based on this form of repayment.
  • 41. 7.3 Evaluation of Alternative Financing Plans Usually, there is an origination fee associated with borrowing for legal and other professional services which is payable upon the receipt of the loan. This fee may appear in the form of issuance charges for revenue bonds or percentage point charges for mortgages. The borrower must allow for such fees in addition to the construction cost in determining the required original amount of borrowing. Suppose that a sum of Po must be reserved at t=0 for the construction cost, and K is the origination fee. Then the original loan needed to cover both is:
  • 42. 7.3 Evaluation of Alternative Financing Plans If the origination fee is expressed as k percent of the original loan, i.e., K = kQ0, then:
  • 43. 7.3 Evaluation of Alternative Financing Plans Since interest and sometimes parts of the principal must be repaid periodically in most financing arrangements, an amount Q considerably larger than Q0 is usually borrowed in the beginning to provide adequate reserve funds to cover interest payments, construction cost increases and other unanticipated shortfalls. The net amount received from borrowing is deposited in a separate interest bearing account from which funds will be withdrawn periodically for necessary payments. Let the borrowing rate per period be denoted by i and the interest for the running balance accrued to the project reserve account be denoted by h.
  • 44. 7.3 Evaluation of Alternative Financing Plans Let At be the net operating cash flow for - period t (negative for construction cost in period t) and be the net financial cash flow in period t (negative for payment of interest or principal or a combination of both). Then, the running balance Nt of the project reserve account can be determined by noting that at t=0,
  • 45. 7.3 Evaluation of Alternative Financing Plans and at t = 1,2,...,n:
  • 46. 7.3 Evaluation of Alternative Financing Plans where the value of At or t may be zero for some period(s). Equations (7.9) and (7.10) are approximate in that interest might be earned on intermediate balances based on the pattern of payments during a period instead of at the end of a period.
  • 47. 7.3 Evaluation of Alternative Financing Plans Because the borrowing rate i will generally exceed the investment rate h for the running balance in the project account and since the origination fee increases with the amount borrowed, the financial planner should minimize the amount of money borrowed under this finance strategy. Thus, there is an optimal value for Q such that all estimated shortfalls are covered, interest payments and expenses are minimized, and adequate reserve funds are available to cover unanticipated factors such as construction cost increases. This optimal value of Q can either be identified analytically or by trial and error.
  • 48. 7.3 Evaluation of Alternative Financing Plans Finally, variations in ownership arrangements may also be used to provide at least partial financing. Leasing a facility removes the need for direct financing of the facility. Sale-leaseback involves sale of a facility to a third party with a separate agreement involving use of the facility for a pre-specified period of time. In one sense, leasing arrangements can be viewed as a particular form of financing. In return for obtaining the use of a facility or piece of equipment, the user (lesser) agrees to pay the owner (lesser) a lease payment every period for a specified number of periods.
  • 49. 7.3 Evaluation of Alternative Financing Plans Usually, the lease payment is at a fixed level due every month, semi-annually, or annually. Thus, the cash flow associated with the equipment or facility use is a series of uniform payments. This cash flow would be identical to a cash flow resulting from financing the facility or purchase with sufficient borrowed funds to cover initial construction (or purchase) and with a repayment schedule of uniform amounts. Of course, at the end of the lease period, the ownership of the facility or equipment would reside with the lesser. However, the lease terms may include a provision for transferring ownership to the lesser after a fixed period.
  • 50. 7.3 Evaluation of Alternative Financing Plans Example 7-2: A coupon bond cash flow and cost
  • 51. Example 7-2: A coupon bond cash flow and cost A private corporation wishes to borrow $10.5 million for the construction of a new building by issuing a twenty-year coupon bond at an annual percentage interest rate of 10% to be paid semi-annually, i.e. 5% per interest period of six months. The principal will be repaid at the end of 20 years. The amount borrowed will cover the construction cost of $10.331 million and an origination fee of $169,000 for issuing the coupon bond.
  • 52. Example 7-2: A coupon bond cash flow and cost The interest payment per period is (5%) (10.5) = $0.525 million over a life time of (2) (20) = 40 interest periods. Thus, the cash flow of financing by the coupon bond consists of a $10.5 million receipt at period 0, -$0.525 million each for periods 1 through 40, and an additional -$10.5 million for period 40. Assuming a MARR of 5% per period, the net present value of the financial cash flow is given by: [FPV]5%) = 10.5 - (0.525)(P|U, 5%, 40) - (10.5)(P|F, 5%, 40) = 0
  • 53. Example 7-2: A coupon bond cash flow and cost This result is expected since the corporation will be indifferent between borrowing and diverting capital from other uses when the MARR is identical to the borrowing rate. Note that the effective annual rate of the bond may be computed according to Eq.(7.4) as follows: ie = (1 + 0.05)2 - 1 = 0.1025 = 10.25%
  • 54. Example 7-2: A coupon bond cash flow and cost If the interest payments were made only at the end of each year over twenty years, the annual payment should be: 0.525(1 + 0.05) + 0.525 = 1.076 where the first term indicates the deferred payment at the mid- year which would accrue interest at 5% until the end of the year, then: [FPV]10.25% = 10.5 - (1.076)(P|U, 10.25%, 20) - (10.5)(P|F, 10.25%, 20) = 0
  • 55. Example 7-2: A coupon bond cash flow and cost In other words, if the interest is paid at 10.25% annually over twenty years of the loan, the result is equivalent to the case of semi-annual interest payments at 5% over the same lifetime.
  • 56. 7.3 Evaluation of Alternative Financing Plans Example 7-3: An example of leasing versus ownership analysis
  • 57. Example 7-3: An example of leasing versus ownership analysis Suppose that a developer offered a building to a corporation for an annual lease payment of $10 million over a thirty year lifetime. For the sake of simplicity, let us assume that the developer also offers to donate the building to the corporation at the end of thirty years or, alternatively, the building would then have no commercial value. Also, suppose that the initial cost of the building was $65.66 million. For the corporation, the lease is equivalent to receiving a loan with uniform payments over thirty years at an interest rate of 15% since the present value of the lease payments is equal to the initial cost at this interest rate:
  • 58. Example 7-3: An example of leasing versus ownership analysis
  • 59. Example 7-3: An example of leasing versus ownership analysis If the minimum attractive rate of return of the corporation is greater than 15%, then this lease arrangement is advantageous as a financing scheme since the net present value of the leasing cash flow would be less than the cash flow associated with construction from retained earnings. For example, with MARR equal to 20%: [FPV]20% = $65.66 million - ($10 million)(P|U, 20%, 30) = $15.871 million
  • 60. Example 7-3: An example of leasing versus ownership analysis On the other hand, with MARR equal to 10%: [FPV]10% = $65.66 million - ($10 million)(P|U, 20%, 30) = $28.609 million and the lease arrangement is not advantageous.
  • 61. Example 7-3: An example of leasing versus ownership analysis Example 7-4: Example evaluation of alternative financing plans.
  • 62. Example 7-4: Example evaluation of alternative financing plans Suppose that a small corporation wishes to build a headquarters building. The construction will require two years and cost a total of $12 million, assuming that $5 million is spent at the end of the first year and $7 million at the end of the second year. To finance this construction, several options are possible, including: • Investment from retained corporate earnings;
  • 63. Example 7-4: Example evaluation of alternative financing plans • Borrowing from a local bank at an interest rate of 11.2% with uniform annual payments over twenty years to pay for the construction costs. The shortfalls for repayments on loans will come from corporate earnings. An origination fee of 0.75% of the original loan is required to cover engineer's reports, legal issues, etc; or • A twenty year coupon bond at an annual interest rate of 10.25% with interest payments annually, repayment of the principal in year 20, and a $169,000 origination fee to pay for the construction cost only.
  • 64. Example 7-4: Example evaluation of alternative financing plans The current corporate MARR is 15%, and short term cash funds can be deposited in an account having a 10% annual interest rate.
  • 65. Example 7-4: Example evaluation of alternative financing plans The first step in evaluation is to calculate the required amounts and cash flows associated with these three alternative financing plans. First, investment using retained earnings will require a commitment of $5 million in year 1 and $7 million in year 2.
  • 66. Example 7-4: Example evaluation of alternative financing plans Second, borrowing from the local bank must yield sufficient funds to cover both years of construction plus the issuing fee. With the unused fund accumulating interest at a rate of 10%, the amount of dollars needed at the beginning of the first year for future construction cost payments is: P0 = ($5 million)/(1.1) + ($7 million)/(1.1)2 = $10.331 million
  • 67. Example 7-4: Example evaluation of alternative financing plans Discounting at ten percent in this calculation reflects the interest earned in the intermediate periods. With a 10% annual interest rate, the accrued interests for the first two years from the project account of $10.331 at t=0 will be: Year 1: I1 = (10%)(10.331 million) = $1.033 million Year 2: I2 = (10%)(10.331 million + $1.033 million - $5.0 million) = 0.636 million
  • 68. Example 7-4: Example evaluation of alternative financing plans Since the issuance charge is 0.75% of the loan, the amount borrowed from the bank at t=0 to cover both the construction cost and the issuance charge is Q0 = ($10.331 million)/(1 - 0.0075) = $ 10.409 million
  • 69. Example 7-4: Example evaluation of alternative financing plans The issuance charge is 10.409 - 10.331 = $ 0.078 million or $78,000. If this loan is to be repaid by annual uniform payments from corporate earnings, the amount of each payment over the twenty year life time of the loan can be calculated by Eq. (7.6) as follows: U = ($10.409 million)[(0.112)(1.112)20]/[(1.112)20 - 1] = $1.324 million
  • 70. Example 7-4: Example evaluation of alternative financing plans Finally, the twenty-year coupon bond would have to be issued in the amount of $10.5 million which will reflect a higher origination fee of $169,000. Thus, the amount for financing is: Q0 = $10.331 million + $0.169 million = $10.5 million
  • 71. Example 7-4: Example evaluation of alternative financing plans With an annual interest charge of 10.25% over a twenty year life time, the annual payment would be $1.076 million except in year 20 when the sum of principal and interest would be 10.5 + 1.076 = $11.576 million. The computation for this case of borrowing has been given in Example 7-2.
  • 72. Example 7-4: Example evaluation of alternative financing plans Table 7-2 summarizes the cash flows associated with the three alternative financing plans. Note that annual incomes generated from the use of this building have not been included in the computation. The adjusted net present value of the combined operating and financial cash flows for each of the three plans discounted at the corporate MARR of 15% is also shown in the table. In this case, the coupon bond is the least expensive financing plan. Since the borrowing rates for both the bank loan and the coupon bond are lower than the corporate MARR, these results are expected.
  • 73. Year Source Retained Earnings Bank Loan Coupon Bond 0 0 1 1 1 2 2 2 3-19 20 [APV]15% Principal Issuing Cost Earned Interest Contractor Payment Loan Repayment Earned Interest Contractor Payment Loan Repayment Loan Repayment Loan Repayment - - - - 5.000 - - - 7.000 - - - - 9.641 $10.409 - 0.078 1.033 - 5.000 - 1.324 0.636 - 7.000 - 1.324 - 1.324 - 1.324 - 6.217 $10.500 - 0.169 1.033 - 5.000 - 1.076 0.636 - 7.000 - 1.076 -1.076 - 11.576 - 5.308 Example 7-4: Example evaluation of alternative financing plans TABLE 7-2 Cash Flow Illustration of Three Alternative Financing Plans (in $ millions)
  • 74. Financing of Constructed Facilities 7.4 Secured Loans with Bonds, Notes and Mortgages
  • 75. 7.4 Secured Loans with Bonds, Notes and Mortgages Secured lending involves a contract between a borrower and lender, where the lender can be an individual, a financial institution or a trust organization. Notes and mortgages represent formal contracts between financial institutions and owners. Usually, repayment amounts and timing are specified in the loan agreement. Public facilities are often financed by bond issues for either specific projects or for groups of projects.
  • 76. 7.4 Secured Loans with Bonds, Notes and Mortgages For publicly issued bonds, a trust company is usually designated to represent the diverse bond holders in case of any problems in the repayment. The borrowed funds are usually secured by granting the lender some rights to the facility or other assets in case of defaults on required payments. In contrast, corporate bonds such as debentures can represent loans secured only by the good faith and credit worthiness of the borrower.
  • 77. 7.4 Secured Loans with Bonds, Notes and Mortgages Under the terms of many bond agreements, the borrower reserves the right to repurchase the bonds at any time before the maturity date by repaying the principal and all interest up to the time of purchase. The required repayment Rc at the end of period c is the net future value of the borrowed amount Q - less the payment made at intermediate periods compounded at the borrowing rate i to period c as follows:
  • 78. 7.4 Secured Loans with Bonds, Notes and Mortgages The required repayment Rc at the end of the period c can also be obtained by noting the net present value of the repayments in the remaining (n-c) periods discounted at the borrowing rate i to t = c as follows:
  • 79. 7.4 Secured Loans with Bonds, Notes and Mortgages For coupon bonds, the required repayment Rc after the redemption of the coupon at the end of period c is simply the original borrowed amount Q. For uniform payment bonds, the required repayment Rc after the last payment at the end of period c is:
  • 80. 7.4 Secured Loans with Bonds, Notes and Mortgages Many types of bonds can be traded in a secondary market by the bond holder. As interest rates fluctuate over time, bonds will gain or lose in value. The actual value of a bond is reflected in the market discount or premium paid relative to the original principal amount (the face value). Another indicator of this value is the yield to maturity or internal rate of return of the bond. This yield is calculated by finding the interest rate that sets the (discounted) future cash flow of the bond equal to the current market price:
  • 81. 7.4 Secured Loans with Bonds, Notes and Mortgages where Vc is the current market value after c periods have lapsed since the - issuance of the bond, is the bond cash flow in period t, and r is the market yield. Since all the bond cash flows are positive after the initial issuance, only one value of the yield to maturity will result from Eq.
  • 82. 7.4 Secured Loans with Bonds, Notes and Mortgages Several other factors come into play in evaluation of bond values from the lenders point of view, however. First, the lender must adjust for the possibility that the borrower may default on required interest and principal payments. In the case of publicly traded bonds, special rating companies divide bonds into different categories of risk for just this purpose. Obviously, bonds that are more likely to default will have a lower value. Secondly, lenders will typically make adjustments to account for changes in the tax code affecting their after-tax return from a bond. Finally, expectations of future inflation or deflation as well as exchange rates will influence market values.
  • 83. 7.4 Secured Loans with Bonds, Notes and Mortgages Another common feature in borrowing agreements is to have a variable interest rate. In this case, interest payments would vary with the overall market interest rate in some pre-specified fashion. From the borrower's perspective, this is less desirable since cash flows are less predictable. However, variable rate loans are typically available at lower interest rates because the lenders are protected in some measure from large increases in the market interest rate and the consequent decrease in value of their expected repayments. Variable rate loans can have floors and ceilings on the applicable interest rate or on rate changes in each year
  • 84. 7.4 Secured Loans with Bonds, Notes and Mortgages Example 7-5: Example of a corporate promissory note
  • 85. Example 7-5: Example of a corporate promissory note A corporation wishes to consider the option of financing the headquarters building in Example 7-4 by issuing a five year promissory note which requires an origination fee for the note is $25,000. Then a total borrowed amount needed at the beginning of the first year to pay for the construction costs and origination fee is 10.331 + 0.025 = $10.356 million. Interest payments are made annually at an annual rate of 10.8% with repayment of the principal at the end of the fifth year. Thus, the annual interest payment is (10.8%)(10.356) = $1.118 million. With the data in Example 7-4 for construction costs and accrued interests for the first two year, the combined operating and and financial cash flows in million dollars can be obtained:
  • 86. Example 7-5: Example of a corporate promissory note Year 0, AA0 = 10.356 - 0.025 = 10.331 Year 1, AA1 = 1.033 - 5.0 - 1.118 = -5.085 Year 2, AA2 = 0.636 - 7.0 - 1.118 = -7.482 Year 3, AA3 = -1.118 Year 4, AA4 = -1.118 Year 5, AA5 = -1.118 - 10.356 = -11.474
  • 87. Example 7-5: Example of a corporate promissory note At the current corporate MARR of 15%, which is inferior to the 20-year coupon bond analyzed in Table 7-3.
  • 88. Example 7-5: Example of a corporate promissory note For this problem as well as for the financing arrangements in Example 7-4, the project account is maintained to pay the construction costs only, while the interest and principal payments are repaid from corporate earnings. - Consequently, the terms in Eq. (7.10) will disappear when the account balance in each period is computed for this problem: At t=0, N0 = 10.356 - 0.025 = $10.331 million At t=1, N1 = (1 + 0.1) (10.331) - 5.0 = $6.364 million At t=2, N2 = (1 + 0.1) (6.364) - 7.0 = $0
  • 89. 7.4 Secured Loans with Bonds, Notes and Mortgages Example 7-6: Bond financing mechanisms.
  • 90. Example 7-6: Bond financing mechanisms. Suppose that the net operating expenditures and receipts of a facility investment over a five year time horizon are as shown in column 2 of Table 7-3 in which each period is six months. This is a hypothetical example with a deliberately short life time period to reduce the required number of calculations. Consider two alternative bond financing mechanisms for this project. Both involve borrowing $2.5 million at an issuing cost of five percent of the loan with semi-annual repayments at a nominal annual interest rate of ten percent i.e., 5% per period.
  • 91. Example 7-6: Bond financing mechanisms. Any excess funds can earn an interest of four percent each semi-annual period. The coupon bond involves only interest payments in intermediate periods, plus the repayment of the principal at the end, whereas the uniform payment bond requires ten uniform payments to cover both interests and the principal. Both bonds are subject to optional redemption by the borrower before maturity.
  • 92. Example 7-6: Bond financing mechanisms. The operating cash flow in column 2 of Table 7-3 represents the construction expenditures in the early periods and rental receipts in later periods over the lifetime of the facility. By trial and error with Eqs. (7.9) and (7.10), it can be found that Q = $2.5 million (K = $0.125 or 5% of Q) is necessary to insure a nonnegative balance in the project account for the uniform payment bond, as shown in Column 6 of Table 7-3. For the purpose of comparison, the same amount is borrowed for the coupon bond option even though a smaller loan will be sufficient for the construction expenditures in this case.
  • 93. Example 7-6: Bond financing mechanisms. The financial cash flow of the coupon bond can easily be derived from Q = $2.5 million and K = $0.125 million. Using Eq. (7.5), Ip= (5%)(2.5) = $0.125 million, and the repayment in Period 10 is Q + Ip = $2.625 million as shown in Column 3 of Table 7-3. The account balance for the coupon bond in Column 4 is obtained from Eqs. (7.9) and (7.10). On the other hand, the uniform annual payment U = $0.324 million for the financial cash flow of the uniform payment bond (Column 5) can be obtained from Eq. (7.6), and the bond account for this type of balance is computed by Eqs. (7.9) and (7.10).
  • 94. Example 7-6: Bond financing mechanisms. Because of the optional redemption provision for both types of bonds, it is advantageous to gradually redeem both options at the end of period 3 to avoid interest payments resulting from i = 5% and h = 4% unless the account balance beyond period 3 is needed to fund other corporate investments. corporate earnings are available for repurchasing the bonds at end of period 3, the required repayment for coupon bond after redeeming the last coupon at the end of period 3 is simply $2.625 million. In the case of the uniform payment bond, the required payment after the last uniform payment at the end of period 3 is obtained from Equation (7-13) as: R3 = (0.324)(P|U, 5%, 7) = (0.324)(5.7864) = $1.875 million.
  • 95. Example 7-6: Bond financing mechanisms. Period Operating Cash Flow Coupon Cash Flow Account Balance Uniform Cash Flow Account Balance 0 1 2 3 4 5 6 7 8 9 10 - - $800 -700 -60 400 600 800 1,000 1,000 1,000 1,000 $2,375 - 125 - 125 - 125 - 125 - 125 - 125 - 125 - 125 - 125 - 2,625 $2,375 1,545 782 628 928 1,440 2,173 3,135 4,135 5,176 3,758 $2,375 - 324 - 324 - 324 - 324 - 324 - 324 - 324 - 324 - 324 - 324 $2,375 1,346 376 8 84 364 854 1,565 2,304 3,072 3,871 TABLE 7-3 Example of Two Borrowing Cash Flows (in $ thousands)
  • 96. 7.4 Secured Loans with Bonds, Notes and Mortgages Example 7-7: Provision of Reserve Funds
  • 97. Example 7-7: Provision of Reserve Funds Typical borrowing agreements may include various required reserve funds. [2] Consider an eighteen month project costing five million dollars. To finance this facility, coupon bonds will be issued to generate revenues which must be sufficient to pay interest charges during the eighteen months of construction, to cover all construction costs, to pay issuance expenses, and to maintain a debt service reserve fund. The reserve fund is introduced to assure bondholders of payments in case of unanticipated construction problems. It is estimated that a total amount of $7.4 million of bond proceeds is required, including a two percent discount to underwriters and an issuance expense of $100,000.
  • 98. Example 7-7: Provision of Reserve Funds Three interest bearing accounts are established with the bond proceeds to separate various categories of funds: • A construction fund to provide payments to contractors, with an initial balance of $4,721,600. Including interest earnings, this fund will be sufficient to cover the $5,000,000 in construction expenses. • A capitalized interest fund to provide interest payments during the construction period. /li> • A debt service reserve fund to be used for retiring outstanding debts after the completion of construction. The total sources of funds (including interest from account balances) and uses of funds are summarized in Table 7-4
  • 99. Example 7-7: Provision of Reserve Funds Sources of Funds Bond Proceeds Interest Earnings on Construction Fund Interest Earnings of Capitalized Interest Fund Interest Earnings on Debt Service Reserve Fund Total Sources of Funds $7,400,000 278,400 77,600 287,640 $8,043,640 Uses of Funds Construction Costs Interest Payments Debt Service Reserve Fund Bond Discount (2.0%) Issuance Expense Total Uses of Funds $5,000,000 904,100 1,891,540 148,000 100,000 $8,043,640 TABLE 7-4 Illustrative Sources and Uses of Funds from Revenue Bonds During Construction
  • 100. 7.4 Secured Loans with Bonds, Notes and Mortgages Example 7-8: Variable rate revenue bonds prospectus
  • 101. Example 7-8: Variable rate revenue bonds prospectus The information in Table 7-5 is abstracted from the Prospectus for a new issue of revenue bonds for the Atwood City. This prospectus language is typical for municipal bonds. Notice the provision for variable rate after the initial interest periods. The borrower reserves the right to repurchase the bond before the date for conversion to variable rate takes effect in order to protect itself from declining market interest rates in the future so that the borrower can obtain other financing arrangements at lower rates.
  • 102. Example 7-8: Variable rate revenue bonds prospectus
  • 104. 7.5 Overdraft Accounts Overdrafts can be arranged with a banking institution to allow accounts to have either a positive or a negative balance. With a positive balance, interest is paid on the account balance, whereas a negative balance incurs interest charges. Usually, an overdraft account will have a maximum overdraft limit imposed. Also, the interest rate h available on positive balances is less than the interest rate i charged for borrowing.
  • 105. 7.5 Overdraft Accounts Clearly, the effects of overdraft financing depends upon the pattern of cash flows over time. Suppose that the net cash flow for period t in the account is denoted by At which is the difference between the receipt Pt and the payment Et in period t. Hence, At can either be positive or negative. The amount of overdraft at the end of period t is the cumulative net cash flow Nt which may also be positive or negative. If Nt is positive, a surplus is indicated and the subsequent interest would be paid to the borrower. Most often, Nt is negative during the early time periods of a project and becomes positive in the later periods when the borrower has received payments exceeding expenses.
  • 106. 7.5 Overdraft Accounts If the borrower uses overdraft financing and pays the interest per period on the accumulated overdraft at a borrowing rate i in each period, then the interest per period for the accumulated overdraft Nt-1 from the previous period (t-1) is It = iNt-1 where It would be negative for a negative account balance Nt-1. For a positive account balance, the interest received is It = hNt- 1 where It would be positive for a positive account balance.
  • 107. 7.5 Overdraft Accounts The account balance Nt at each period t is the sum of receipts Pt, payments Et, interest It and the account balance from the previous period Nt-1. Thus,
  • 108. 7.5 Overdraft Accounts where It = iNt-1 for a negative Nt-1 and It = hNt-1 for a positive Nt-1. The net cash flow At = Pt - Et is positive for a net receipt and negative for a net payment. This equation is approximate in that the interest might be earned on intermediate balances based on the pattern of payments during the period instead of at the end of a period. The account balance in each period is of interest because there will always be a maximum limit on the amount of overdraft available.
  • 109. 7.5 Overdraft Accounts For the purpose of separating project finances with other receipts and payments in an organization, it is convenient to establish a credit account into which receipts related to the project must be deposited when they are received, and all payments related to the project will be withdrawn from this account when they are needed.
  • 110. 7.5 Overdraft Accounts Since receipts typically lag behind payments for a project, this credit account will have a negative balance until such time when the receipts plus accrued interests are equal to or exceed payments in the period. When that happens, any surplus will not be deposited in the credit account, and the account is then closed with a zero balance. In that case, for negative Nt-1, Eq. (7.15) can be expressed as: and as soon as Nt reaches a positive value or zero, the account is closed.
  • 111. 7.5 Overdraft Accounts Example 7-9: Overdraft Financing with Grants to a Local Agency
  • 112. Example 7-9: Overdraft Financing with Grants to a Local Agency A public project which costs $61,525,000 is funded eighty percent by a federal grant and twenty percent from a state grant. The anticipated duration of the project is six years with receipts from grant funds allocated at the end of each year to a local agency to cover partial payments to contractors for that year while the remaining payments to contractors will be allocated at the end of the sixth year. The end-of-year payments are given in Table 7-6 in which t=0 refers to the beginning of the project, and each period is one year.
  • 113. Example 7-9: Overdraft Financing with Grants to a Local Agency If this project is financed with an overdraft at an annual interest rate i = 10%, then the account balance are computed by Eq. (7.15) and the results are shown in Table 7-6.
  • 114. Example 7-9: Overdraft Financing with Grants to a Local Agency In this project, the total grant funds to the local agency covered the cost of construction in the sense that the sum of receipts equaled the sum of construction payments of $61,525,000. However, the timing of receipts lagged payments, and the agency incurred a substantial financing cost, equal in this plan to the overdraft amount of $1,780,000 at the end of year 6 which must be paid to close the credit account. Clearly, this financing problem would be a significant concern to the local agency.
  • 115. Example 7-9: Overdraft Financing with Grants to a Local Agency Period t Receipts Pt Payments Et Interest It Account Nt 0 1 2 3 4 5 6 Total 0 $5.826 8.401 12.013 15.149 13.984 6.152 $61.525 0 $6.473 9.334 13.348 16.832 15.538 0 $61.525 0 0 - $0.065 - 0.165 - 0.315 - 0.514 - 0.721 -$1.780 0 -$0.647 - 1.645 - 3.145 - 5.143 - 7.211 - 1.780 TABLE 7-6 Illustrative Payments, Receipts and Overdrafts for a Six Year Project
  • 116. 7.5 Overdraft Accounts Example 7-10: Use of overdraft financing for a facility
  • 117. Example 7-10: Use of overdraft financing for a facility A corporation is contemplating an investment in a facility with the following before-tax operating net cash flow (in thousands of dollars) at year ends: Year 0 1 2 3 4 5 6 7 Cash Flow -500 110 112 114 116 118 120 238
  • 118. Example 7-10: Use of overdraft financing for a facility The MARR of the corporation before tax is 10%. The corporation will finance the facility be using $200,000 from retained earnings and by borrowing the remaining $300,000 through an overdraft credit account which charges 14% interest for borrowing. Is this proposed project including financing costs worthwhile?
  • 119. Example 7-10: Use of overdraft financing for a facility The results of the analysis of this project is shown in Table 7-7 as follows: N0 = -500 + 200 = -300 N1 = (1.14)(-300) + 110 = -232 N2 = (1.14)(-232) + 112 = -152.48 N3 = (1.14)(-152.48) + 114 = -59.827 N4 = (1.14)(-59.827) +116 = +47.797
  • 120. Example 7-10: Use of overdraft financing for a facility Since N4 is positive, it is revised to exclude the net receipt of 116 for this period. Then, the revised value for the last balance is N4' = N4 - 116 = - 68.203
  • 121. Example 7-10: Use of overdraft financing for a facility The financial cash flow resulting from using overdrafts and making repayments from project receipts will be: A 0= - N0 = 300 A 0 = - A1 = -110 A 0 = - A2 = -112 A 0 = - A3 = -114 A 0 = N4 - A4 = - 68.203
  • 122. Example 7-10: Use of overdraft financing for a facility The adjusted net present value of the combined cash flow discounted at 15% is $27,679 as shown in Table 7-7. Hence, the project including the financing charges is worthwhile.
  • 123. Example 7-10: Use of overdraft financing for a facility End of Year t Operating Cash Flow At Overdraft Balance Nt Financing Cash Flow Combined Cash Flow AAt 0 1 2 3 4 5 6 7 [PV]15% - $500 110 112 114 116 118 120 122 $21.971 - $300 - 232 - 152.480 -59.827 0 0 0 0 &300 - 110 - 112 - 114 - 68.203 0 0 0 $5.708 - $200 0 0 0 47.797 118 120 122 $27.679 TABLE 7-7 Evaluation of Facility Financing Using Overdraft (in $ thousands)
  • 125. 7.6 Refinancing of Debts Refinancing of debts has two major advantages for an owner. First, they allow re-financing at intermediate stages to save interest charges. If a borrowing agreement is made during a period of relatively high interest charges, then a repurchase agreement allows the borrower to re-finance at a lower interest rate. Whenever the borrowing interest rate declines such that the savings in interest payments will cover any transaction expenses (for purchasing outstanding notes or bonds and arranging new financing), then it is advantageous to do so.
  • 126. 7.6 Refinancing of Debts Another reason to repurchase bonds is to permit changes in the operation of a facility or new investments. Under the terms of many bond agreements, there may be restrictions on the use of revenues from a particular facility while any bonds are outstanding. These restrictions are inserted to insure bondholders that debts will be repaid. By repurchasing bonds, these restrictions are removed. For example, several bridge authorities had bonds that restricted any diversion of toll revenues to other transportation services such as transit.
  • 127. 7.6 Refinancing of Debts By repurchasing these bonds, the authority could undertake new operations. This type of repurchase may occur voluntarily even without a repurchase agreement in the original bond. The borrower may give bondholders a premium to retire bonds early.
  • 128. 7.6 Refinancing of Debts Example 7-11: Refinancing a loan.
  • 129. Example 7-11: Refinancing a loan. Suppose that the bank loan shown in Example 7-4 had a provision permitting the borrower to repay the loan without penalty at any time. Further, suppose that interest rates for new loans dropped to nine percent at the end of year six of the loan. Issuing costs for a new loan would be $50,000. Would it be advantageous to re-finance the loan at that time?
  • 130. Example 7-11: Refinancing a loan. To repay the original loan at the end of year six would require a payment of the remaining principal plus the interest due at the end of year six. This amount R6 is equal to the present value of remaining fourteen payments discounted at the loan interest rate 11.2% to the end of year 6 as given in Equation (7-13) as follows:
  • 131. Example 7-11: Refinancing a loan. The new loan would be in the amount of $ 9.152 million plus the issuing cost of $0.05 million for a total of $ 9.202 million. Based on the new loan interest rate of 9%, the new uniform annual payment on this loan from years 7 to 20 would be:
  • 132. Example 7-11: Refinancing a loan. The net present value of the financial cash flow for the new loan would be obtained by discounting at the corporate MARR of 15% to the end of year six as follows:
  • 133. Example 7-11: Refinancing a loan. Since the annual payment on the new loan is less than the existing loan ($1.182 versus $1.324 million), the new loan is preferable.
  • 134. Financing of Constructed Facilities 7.7 Project versus Corporate Finance
  • 135. 7.7 Project versus Corporate Finance We have focused so far on problems and concerns at the project level. While this is the appropriate viewpoint for project managers, it is always worth bearing in mind that projects must fit into broader organizational decisions and structures. This is particularly true for the problem of project finance, since it is often the case that financing is planned on a corporate or agency level, rather than a project level. Accordingly, project managers should be aware of the concerns at this level of decision making.
  • 136. 7.7 Project versus Corporate Finance A construction project is only a portion of the general capital budgeting problem faced by an owner. Unless the project is very large in scope relative to the owner, a particular construction project is only a small portion of the capital budgeting problem. Numerous construction projects may be lumped together as a single category in the allocation of investment funds. Construction projects would compete for attention with equipment purchases or other investments in a private corporation.
  • 137. 7.7 Project versus Corporate Finance Financing is usually performed at the corporate level using a mixture of long term corporate debt and retained earnings. A typical set of corporate debt instruments would include the different bonds and notes discussed in this chapter. Variations would typically include different maturity dates, different levels of security interests, different currency denominations, and, of course, different interest rates.
  • 138. 7.7 Project versus Corporate Finance Grouping projects together for financing influences the type of financing that might be obtained. As noted earlier, small and large projects usually involve different institutional arrangements and financing arrangements. For small projects, the fixed costs of undertaking particular kinds of financing may be prohibitively expensive. For example, municipal bonds require fixed costs associated with printing and preparation that do not vary significantly with the size of the issue. By combining numerous small construction projects, different financing arrangements become more practical.
  • 139. 7.7 Project versus Corporate Finance While individual projects may not be considered at the corporate finance level, the problems and analysis procedures described earlier are directly relevant to financial planning for groups of projects and other investments. Thus, the net present values of different financing arrangements can be computed and compared. Since the net present values of different sub- sets of either investments or financing alternatives are additive, each project or finance alternative can be disaggregated for closer attention or aggregated to provide information at a higher decision making level.
  • 140. 7.7 Project versus Corporate Finance Example 7-12: Basic types of repayment schedules for loans.
  • 141. Example 7-12: Basic types of repayment schedules for loans. Coupon bonds are used to obtain loans which involve no payment of principal until the maturity date. By combining loans of different maturities, however, it is possible to achieve almost any pattern of principal repayments. However, the interest rates charged on loans of different maturities will reflect market forces such as forecasts of how interest rates will vary over time. As an example, Table 7-8 illustrates the cash flows of debt service for a series of coupon bonds used to fund a municipal construction project; for simplicity not all years of payments are shown in the table.
  • 142. Example 7-12: Basic types of repayment schedules for loans. In this financing plan, a series of coupon bonds were sold with maturity dates ranging from June 1988 to June 2012. Coupon interest payments on all outstanding bonds were to be paid every six months, on December 1 and June 1 of each year. The interest rate or "coupon rate" was larger on bonds with longer maturities, reflecting an assumption that inflation would increase during this period. The total principal obtained for construction was $26,250,000 from sale of these bonds.
  • 143. Example 7-12: Basic types of repayment schedules for loans. This amount represented the gross sale amount before subtracting issuing costs or any sales discounts; the amount available to support construction would be lower. The maturity dates for bonds were selected to require relative high repayment amounts until December 1995, with a declining repayment amount subsequently. By shifting the maturity dates and amounts of bonds, this pattern of repayments could be altered. The initial interest payment (of $819,760 on December 1, 1987), reflected a payment for only a portion of a six month period since the bonds were issued in late June of 1987.
  • 144. Example 7-12: Basic types of repayment schedules for loans. Date Maturing Principal Corresponding Interest Rate Interest Due Annual Debt Service Dec. 1, 1987 June 1, 1988 Dec. 1, 1988 June 1, 1989 Dec. 1, 1989 June 1, 1990 Dec. 1, 1990 June 1, 1991 Dec. 1, 1991 June 1, 1992 Dec. 1, 1992 June 1, 1993 Dec. 1, 1993 . . . June 1, 2011 Dec. 1, 2011 June 1, 2012 Dec. 1, 2012 $1,350,000 1,450,000 1,550,000 1,600,000 1,700,000 1,800,000 . . . 880,000 96,000 5.00% 5.25 5.50 5.80 6.00 6.20 . . . 8.00 8.00 $819,760 894,429 860,540 860,540 822,480 822,480 779,850 779,850 733,450 733,450 682,450 682,450 626,650 . . . 68,000 36,000 36,000 $819,760 3,104,969 3,133,020 3,152,330 3,113,300 3,115,900 3,109,100 . . . 984,000 996,000 TABLE 7-8 Illustration of a Twenty-five Year Maturity Schedule for Bonds
  • 145. Financing of Constructed Facilities 7.8 Shifting Financial Burdens
  • 146. 7.8 Shifting Financial Burdens The different participants in the construction process have quite distinct perspectives on financing. In the realm of project finance, the revenues to one participant represent an expenditure to some other participant. Payment delays from one participant result in a financial burden and a cash flow problem to other participants. It is common occurrence in construction to reduce financing costs by delaying payments in just this fashion. Shifting payment times does not eliminate financing costs, however, since the financial burden still exists.
  • 147. 7.8 Shifting Financial Burdens Traditionally, many organizations have used payment delays both to shift financing expenses to others or to overcome momentary shortfalls in financial resources. From the owner's perspective, this policy may have short term benefits, but it certainly has long term costs. Since contractors do not have large capital assets, they typically do not have large amounts of credit available to cover payment delays. Contractors are also perceived as credit risks in many cases, so loans often require a premium interest charge. Contractors faced with large financing problems are likely to add premiums to bids or not bid at all on particular work. For example, A. Maevis noted: [3]
  • 148. 7.8 Shifting Financial Burdens ...there were days in New York City when city agencies had trouble attracting bidders; yet contractors were beating on the door to get work from Consolidated Edison, the local utility. Why? First, the city was a notoriously slow payer, COs (change orders) years behind, decision process chaotic, and payments made 60 days after close of estimate. Con Edison paid on the 20th of the month for work done to the first of the month. Change orders negotiated and paid within 30 days-60 days. If a decision was needed, it came in 10 days. The number of bids you receive on your projects are one measure of your administrative efficiency. Further, competition is bound to give you the lowest possible construction price.
  • 149. 7.8 Shifting Financial Burdens Even after bids are received and contracts signed, delays in payments may form the basis for a successful claim against an agency on the part of the contractor.
  • 150. 7.8 Shifting Financial Burdens The owner of a constructed facility usually has a better credit rating and can secure loans at a lower borrowing rate, but there are some notable exceptions to this rule, particularly for construction projects in developing countries. Under certain circumstances, it is advisable for the owner to advance periodic payments to the contractor in return for some concession in the contract price. This is particularly true for large-scale construction projects with long durations for which financing costs and capital requirements are high. If the owner is willing to advance these amounts to the contractor, the gain in lower financing costs can be shared by both parties through prior agreement.
  • 151. 7.8 Shifting Financial Burdens Unfortunately, the choice of financing during the construction period is often left to the contractor who cannot take advantage of all available options alone. The owner is often shielded from participation through the traditional method of price quotation for construction contracts. This practice merely exacerbates the problem by excluding the owner from participating in decisions which may reduce the cost of the project.
  • 152. 7.8 Shifting Financial Burdens Under conditions of economic uncertainty, a premium to hedge the risk must be added to the estimation of construction cost by both the owner and the contractor. The larger and longer the project is, the greater is the risk. For an unsophisticated owner who tries to avoid all risks and to place the financing burdens of construction on the contractor, the contract prices for construction facilities are likely to be increased to reflect the risk premium charged by the contractors. In dealing with small projects with short durations, this practice may be acceptable particularly when the owner lacks any expertise to evaluate the project financing alternatives or the financial stability to adopt innovative financing schemes.
  • 153. 7.8 Shifting Financial Burdens However, for large scale projects of long duration, the owner cannot escape the responsibility of participation if it wants to avoid catastrophes of run-away costs and expensive litigation. The construction of nuclear power plants in the private sector and the construction of transportation facilities in the public sector offer ample examples of such problems. If the responsibilities of risk sharing among various parties in a construction project can be clearly defined in the planning stage, all parties can be benefited to take advantage of cost saving and early use of the constructed facility.
  • 154. 7.8 Shifting Financial Burdens Example 7-13: Effects of payment delays
  • 155. Example 7-13: Effects of payment delays Table 7-9 shows an example of the effects of payment timing on the general contractor and subcontractors. The total contract price for this project is $5,100,000 with scheduled payments from the owner shown in Column 2. The general contractor's expenses in each period over the lifetime of the project are given in Column 3 while the subcontractor's expenses are shown in Column 4. If the general contractor must pay the subcontractor's expenses as well as its own at the end of each period, the net cash flow of the general contractor is obtained in Column 5, and its cumulative cash flow in Column 6.
  • 156. Example 7-13: Effects of payment delays Period Owner Payments General Contractor' s Expenses Subcontrac tor's Expenses General Contractor' s Net Cash Flow Cumulative Cash Flow 1 2 3 4 5 6 Total --- $950,000 950,000 950,000 950,000 1,300,000 $5,100,000 $100,000 100,000 100,000 100,000 100,000 - $500,000 $900,000 900,000 900,000 900,000 900,000 - $4,500,000 - $1,000,000 - 50,000 - 50,000 - 50,000 - 50,000 1,300,000 $100,000 - $1,000,000 - 1,050,000 - 1,100,000 - 1,150,000 - 1,200,000 100,000 TABLE 7-9 An Example of the Effects of Payment Timing
  • 157. Example 7-13: Effects of payment delays In this example, the owner withholds a five percent retainage on cost as well as a payment of $100,000 until the completion of the project. This $100,000 is equal to the expected gross profit of the contractor without considering financing costs or cash flow discounting. Processing time and contractual agreements with the owner result in a delay of one period in receiving payments. The actual construction expenses from the viewpoint of the general contractor consist of $100,000 in each construction period plus payments due to subcontractors of $900,000 in each period.
  • 158. Example 7-13: Effects of payment delays While the net cash flow without regard to discounting or financing is equal to a $100,000 profit for the general contractor, financial costs are likely to be substantial. With immediate payment to subcontractors, over $1,000,000 must be financed by the contractor throughout the duration of the project. If the general contractor uses borrowing to finance its expenses, a maximum borrowing amount of $1,200,000 in period five is required even without considering intermediate interest charges. Financing this amount is likely to be quite expensive and may easily exceed the expected project profit.
  • 159. Example 7-13: Effects of payment delays By delaying payments to subcontractors, the general contractor can substantially reduce its financing requirement. For example, Table 7-10 shows the resulting cash flows from delaying payments to subcontractors for one period and for two periods, respectively. With a one period delay, a maximum amount of $300,000 (plus intermediate interest charges) would have to be financed by the general contractor. That is, from the data in Table 7-10, the net cash flow in period 1 is -$100,000, and the net cash flow for each of the periods 2 through 5 is given by: $950,000 - $100,000 - $900,000 = -$ 50,000
  • 160. Example 7-13: Effects of payment delays Finally, the net cash flow for period 6 is: $1,300,000 - $900,000 = $400,000
  • 161. Example 7-13: Effects of payment delays Thus, the cumulative net cash flow from periods 1 through 5 as shown in Column 2 of Table 7-10 results in maximum shortfall of $300,000 in period 5 in Column 3. For the case of a two period payment delay to the subcontractors, the general contractor even runs a positive balance during construction as shown in Column 5. The positive balance results from the receipt of owner payments prior to reimbursing the subcontractor's expenses. This positive balance can be placed in an interest bearing account to earn additional revenues for the general contractor.
  • 162. Example 7-13: Effects of payment delays Needless to say, however, these payment delays mean extra costs and financing problems to the subcontractors. With a two period delay in payments from the general contractor, the subcontractors have an unpaid balance of $1,800,000, which would represent a considerable financial cost.
  • 163. Example 7-13: Effects of payment delays Period One Period Payment Delay Two Period Payment Delay Net Cash Flow Cumulative Cash Flow Net Cash Flow Cumulative Cash Flow 1 2 3 4 5 6 7 - $100,000 - 50,000 - 50,000 - 50,000 - 50,000 400,000 - $100,000 - 150,000 - 200,000 - 250,000 - 300,000 100,000 - $100,000 850,000 - 50,000 - 50,000 - 50,000 400,000 - 900,000 - $100,000 750,000 700,000 650,000 600,000 1,000,000 100,000 TABLE 7-10 An Example of the Cash Flow Effects of Delayed Payments
  • 164. Financing of Constructed Facilities 7.9 Construction Financing for Contractors
  • 165. 7.9 Construction Financing for Contractors For a general contractor or subcontractor, the cash flow profile of expenses and incomes for a construction project typically follows the work in progress for which the contractor will be paid periodically. The markup by the contractor above the estimated expenses is included in the total contract price and the terms of most contracts generally call for monthly reimbursements of work completed less retainage. At time period 0, which denotes the beginning of the construction contract, a considerable sum may have been spent in preparation.
  • 166. 7.9 Construction Financing for Contractors The contractor's expenses which occur more or less continuously for the project duration are depicted by a piecewise continuous curve while the receipts (such as progress payments from the owner) are represented by a step function as shown in Fig. 7-1. The owner's payments for the work completed are assumed to lag one period behind expenses except that a withholding proportion or remainder is paid at the end of construction. This method of analysis is applicable to realistic situations where a time period is represented by one month and the number of time periods is extended to cover delayed receipts as a result of retainage.
  • 167. 7.9 Construction Financing for Contractors Figure 7-1 Contractor's Expenses and Owner's Payments
  • 168. 7.9 Construction Financing for Contractors While the cash flow profiles of expenses and receipts are expected to vary for different projects, the characteristics of the curves depicted in Fig. 7-1 are sufficiently general for most cases. Let Et represent the contractor's expenses in period t, and Pt represent owner's payments in period t, for t=0,1,2,...,n for n=5 in this case. The net operating cash flow at the end of period t for t 0 is given by:
  • 169. 7.9 Construction Financing for Contractors where At is positive for a surplus and negative for a shortfall. The cumulative operating cash flow at the end of period t just before receiving payment Pt (for t 1) is:
  • 170. 7.9 Construction Financing for Contractors where Nt-1 is the cumulative net cash flows from period 0 to period (t-1). Furthermore, the cumulative net operating cash flow after receiving payment Pt at the end of period t (for t 1) is:
  • 171. 7.9 Construction Financing for Contractors The gross operating profit G for a n-period project is defined as net operating cash flow at t=n and is given by: The use of Nn as a measure of the gross operating profit has the disadvantage that it is not adjusted for the time value of money.
  • 172. 7.9 Construction Financing for Contractors Since the net cash flow At (for t=0,1,...,n) for a construction project represents the amount of cash required or accrued after the owner's payment is plowed back to the project at the end of period t, the internal rate of return (IRR) of this cash flow is often cited in the traditional literature in construction as a profit measure. To compute IRR, let the net present value (NPV) of At discounted at a discount rate i per period be zero, i.e.,
  • 173. 7.9 Construction Financing for Contractors The resulting i (if it is unique) from the solution of Eq. (7.21) is the IRR of the net cash flow At. Aside from the complications that may be involved in the solution of Eq. (7.21), the resulting i = IRR has a meaning to the contractor only if the firm finances the entire project from its own equity. This is seldom if ever the case since most construction firms are highly leveraged, i.e. they have relatively small equity in fixed assets such as construction equipment, and depend almost entirely on borrowing in financing individual construction projects.
  • 174. 7.9 Construction Financing for Contractors The use of the IRR of the net cash flows as a measure of profit for the contractor is thus misleading. It does not represent even the IRR of the bank when the contractor finances the project through overdraft since the gross operating profit would not be given to the bank.
  • 175. 7.9 Construction Financing for Contractors Since overdraft is the most common form of financing for small or medium size projects, we shall consider the financing costs and effects on profit of - the use of overdrafts. Let be the cumulative cash flow before the owner's payment in period t including interest and be the cumulative net cash flow in period t including interest. At t = 0 when there is no accrued interest, = F0 and = N0. For t in period t can be obtained by considering the contractor's expensesI Et to be dispersed uniformly during the period.
  • 176. 7.9 Construction Financing for Contractors The inclusion of enterest on contractor's expenses Et during period t (for G 1) is based on the rationale that the S-shaped curve depicting the contractor's expenses in Figure 7-1 is fairly typical of actual situations, where the owner's payments are typically made at the end of well defined periods.
  • 177. 7.9 Construction Financing for Contractors Hence, interest on expenses during period t is approximated by one half of the amount as if the expenses were paid at the beginning of the period. In fact, Et is the accumulation of all expenses in period t and is treated - as an expense at the end of the period. Thus, the interest per period (for t 1) is the combination of interest charge for Nt-1 in period t and that for one half of Et in the same period t. If is negative and i is the borrowing rate for the shortfall,
  • 178. 7.9 Construction Financing for Contractors If is positive and h is the investment rate for the surplus,
  • 179. 7.9 Construction Financing for Contractors Hence, if the cumulative net cash flow is negative, the interest on the overdraft for each period t is paid by the contractor at the end of each period. If Nt is positive, a surplus is indicated and the subsequent interest would be paid to the contractor. Most often, Nt is negative during the early time periods of a project and becomes positive in the later periods when the contractor has received payments exceeding expenses.
  • 180. 7.9 Construction Financing for Contractors Including the interest accrued in period t, the cumulative cash flow at the end of period t just before receiving payment Pt (for t ≥1) is:
  • 181. 7.9 Construction Financing for Contractors The gross operating profit at the end of a n-period project including interest charges is: where is the cumulative net cash flow for t = n.
  • 182. 7.9 Construction Financing for Contractors Example 7-14: Contractor's gross profit from a project
  • 183. Example 7-14: Contractor's gross profit from a project The contractor's expenses and owner's payments for a multi- year construction project are given in Columns 2 and 3, respectively, of Table 7-11. Each time period is represented by one year, and the annual interest rate i is for borrowing 11%. The computation has been carried out in Table 7-11, and the contractor's gross profit G is found to be N5 = $8.025 million in the last column of the table.
  • 184. Example 7-14: Contractor's gross profit from a project TABLE 7-11 Example of Contractor's Expenses and Owner's Payments ($ Million) Period t Contractor's Expenses Et Owner's Payments Pt Net Cash Flow At Cumulative Cash Before Payments Ft Cumulative Net Cash Nt 0 1 2 3 4 5 Total $3.782 7.458 10.425 14.736 11.420 5.679 $53.500 $0 6.473 9.334 13.348 16.832 15.538 $61.525 -$3.782 -0.985 -1.091 -1.388 +5.412 +9.859 +$8.025 -$3.782 -11.240 -15.192 -20.594 -18.666 -7.513 -$3.782 -4.767 -5.858 -7.246 -1.834 +8.025
  • 185. 7.9 Construction Financing for Contractors Example 7-15: Effects of Construction Financing
  • 186. Example 7-15: Effects of Construction Financing The computation of the cumulative cash flows including interest charges at i = 11% for Example 7-14 is shown in Table 7-12 with gross profit = = $1.384 million. The results of computation are also shown in Figure 7-2.
  • 187. Example 7-15: Effects of Construction Financing Period (year) t Constructio n Expenses Et Owner's Payments Pt Annual Interest Cumulative Before Payments Cumulative Net Cash Flow 0 1 2 3 4 5 $3.782 7.458 10.425 14.736 11.420 5.679 0 $6.473 9.334 13.348 16.832 15.538 0 -$0.826 -1.188 -1.676 -1.831 -1.121 -$3.782 -12.066 -17.206 -24.284 -24.187 -14.154 -$3.782 -5.593 -7.872 -10.936 -7.354 +1.384 TABLE 7-12 Example Cumulative Cash Flows Including Interests for a Contractor ($ Million)
  • 188. Example 7-15: Effects of Construction Financing
  • 189. Example 7-15: Effects of Construction Financing Figure 7-2 Effects of Overdraft Financing
  • 190. Financing of Constructed Facilities 7.10 Effects of Other Factors on a Contractor's Profits
  • 191. 7.10 Effects of Other Factors on a Contractor's Profits In times of economic uncertainty, the fluctuations in inflation rates and market interest rates affect profits significantly. The total contract price is usually a composite of expenses and payments in then-current dollars at different payment periods. In this case, estimated expenses are also expressed in then- current dollars.
  • 192. 7.10 Effects of Other Factors on a Contractor's Profits During periods of high inflation, the contractor's profits are particularly vulnerable to delays caused by uncontrollable events for which the owner will not be responsible. Hence, the owner's payments will not be changed while the contractor's expenses will increase with inflation.
  • 193. 7.10 Effects of Other Factors on a Contractor's Profits Example 7-16: Effects of Inflation
  • 194. Example 7-16: Effects of Inflation Suppose that both expenses and receipts for the construction project in the Example 7-14 are now expressed in then-current dollars (with annual inflation rate of 4%) in Table 7-13. The market interest rate reflecting this inflation is now 15%. In considering these expenses and receipts in then-current dollars and using an interest rate of 15% including inflation, we can recompute the cumulative net cash flow (with interest). Thus, the gross profit less financing costs becomes = = $0.4 million. There will be a loss rather than a profit after deducting financing costs and adjusting for the effects of inflation with this project.
  • 195. Example 7-16: Effects of Inflation TABLE 7-13 Example of Overdraft Financing Based on Inflated Dollars ($ Million) Period (year) t Constructi on Expenses Et Owner's Payments Pt Annual Interest Cumulative Before Payments Cumulative Net Cash Flow 0 1 2 3 4 5 $3.782 7.756 11.276 16.576 13.360 6.909 0 $6.732 10.096 15.015 16.691 18.904 0 -$1.149 -1.739 -2.574 -2.953 -1.964 -$3.782 -12.687 -18.970 -28.024 -29.322 -18.504 -$3.782 -5.955 -8.874 -13.009 -9.631 +0.400
  • 196. 7.10 Effects of Other Factors on a Contractor's Profits Example 7-17: Effects of Work Stoppage at Periods of Inflation
  • 197. Example 7-17: Effects of Work Stoppage at Periods of Inflation Suppose further that besides the inflation rate of 4%, the project in Example 7-16 is suspended at the end of year 2 due to a labor strike and resumed after one year. Also, assume that while the contractor will incur higher interest expenses due to the work stoppage, the owner will not increase the payments to the contractor. The cumulative net cash flows for the cases of operation and financing expenses are recomputed and tabulated in Table 7-14.
  • 198. Example 7-17: Effects of Work Stoppage at Periods of Inflation The construction expenses and receipts in then-current dollars resulting from the work stopping and the corresponding net cash flow of the project including financing (with annual interest accumulated in the overdraft to the end of the project) is shown in Fig. 7-3. It is noteworthy that, with or without the work stoppage, the gross operating profit declines in value at the end of the project as a result of inflation, but with the work stoppage it has eroded - further to a loss of $3.524 million as indicated by = -3.524 in Table 7-14.
  • 199. Example 7-17: Effects of Work Stoppage at Periods of Inflation Period (year) t Constructi on Expenses Et Owner's Payments Pt Annual Interest Cumulative Before Payments Cumulative Net Cash Flow 0 1 2 3 4 5 6 $3.782 7.756 11.276 0 17.239 13.894 7.185 0 $6.732 10.096 0 15.015 16.691 18.904 0 -$1.149 -1.739 -1.331 -2.824 -3.330 -2.457 -$3.782 -12.687 -18.970 -10.205 -30.268 -32.477 22.428 -$3.782 -5.955 -8.874 -10.205 -15.253 -12.786 -3.524 TABLE 7-14 Example of the Effects of Work Stoppage and Inflation on a Contractor ($ Million)
  • 200. Example 7-17: Effects of Work Stoppage at Periods of Inflation Figure 7-3 Effects of Inflation and Work Stoppage
  • 201. Example 7-17: Effects of Work Stoppage at Periods of Inflation Figure 7-3 Effects of Inflation and Work Stoppage
  • 202. 7.10 Effects of Other Factors on a Contractor's Profits Example 7-18: Exchange Rate Fluctuation
  • 203. Example 7-18: Exchange Rate Fluctuation Contracting firms engaged in international practice also face financial issues associated with exchange rate fluctuations. Firms are typically paid in local currencies, and the local currency may loose value relative to the contractor's home currency. Moreover, a construction contractor may have to purchase component parts in the home currency. Various strategies can be used to reduce this exchange rate risk, including:
  • 204. Example 7-18: Exchange Rate Fluctuation • Pooling expenses and incomes from multiple projects to reduce the amount of currency exchanged. • Purchasing futures contracts to exchange currency at a future date at a guaranteed rate. If the exchange rate does not change or changes in a favorable direction, the contractor may decide not to exercise or use the futures contract. • Borrowing funds in local currencies and immediately exchanging the expected profit, with the borrowing paid by eventual payments from the owner.
  • 206. 7.11 References 1. Au, T., and C. Hendrickson, "Profit Measures for Construction Projects," ASCE Journal of Construction Engineering and Management, Vol. 112, No. CO-2, 1986, pp. 273-286. 2. Brealey, R. and S. Myers, Principles of Corporate Finance, McGraw-Hill, Sixth Edition, 2002. 3. Collier, C.A. and D.A. Halperin, Construction Funding: Where the Money Comes From, Second Edition, John Wiley and Sons, New York, 1984.
  • 207. 7.11 References 4. Dipasquale, D. and C. Hendrickson, "Options for Financing a Regional Transit Authority," Transportation Research Record, No. 858, 1982, pp. 29-35. 5. Kapila, Prashant and Chris Hendrickson, "Exchange Rate Risk Management in International Construction Ventures," ASCE J. of Construction Eng. and Mgmt, 17(4), October 2001. 6. Goss, C.A., "Financing: The Contractor's Perspective," Construction Contracting, Vol. 62, No. 10, pp. 15-17, 1980.
  • 209. 7.13 Footnotes 1. This table is adapted from A.J. Henkel, "The Mechanics of a Revenue Bond Financing: An Overview," Infrastructure Financing, Kidder, Peabody & Co., New York, 1984. 2. The calculations for this bond issue are adapted from a hypothetical example in F. H. Fuller, "Analyzing Cash Flows for Revenue Bond Financing," Infrastructure Financing, Kidder, Peabody & Co., Inc., New York, 1984, pp. 37-47. 3. Maevis, Alfred C.,"Construction Cost Control by the Owner," ASCE Journal of the Construction Division, Vol. 106, No. 4, December, 1980, pg. 444.