Girls in Tech Design-a-Thon Project
Brea Silva
MET AD 642 Project Management
Virginia A. Greiman
October 13, 2014
Abstract
This paper is an analysis of the project management of the planned Girls in Tech Design-a-thon.
It touches on the scope, work breakdown structure, macro and micro estimates, schedule,
network diagram, critical path, risk planning and monitoring, controlling and execution of the
project. Recommendations to the project management of the event are sprinkled throughout,
along with final recommendations ending the paper.
Girls in Tech Design-a-Thon 2
Girls in Tech Design-a-Thon
Introduction
Girls in Tech is a non-profit organization dedicated to the engagement, education and
empowerment of women in technology. In order to promote this goal, the local Girls in Tech Las
Vegas chapter has decided to take on producing a design-a-thon. A design-a-thon is an event
similar to a hackathon but without requiring software programing. The goal is to design any sort
of product or solution that helps a problem in the community. By not needing programing
knowledge or requiring the use of a specific software solution they hope to encourage more
women to participate in this other hackathons, which are great events for learning and
networking in the technology and product development fields. Currently, AT&T and Girls in
Tech are in talks to collaborate for this event. AT&T has will have sponsored over 100 events
including at least two in Las Vegas. With their sponsorship, they have requirements including
using a particular venue and a prize pool of at least a certain amount. This project will go from a
small local event to one with global interest. Therefore, the stakes are high if the joint venture
comes to fruition.
Scope
The scope for this project includes the fact that this event will be over the course of three
days, before the CES convention, and will have two networking mixers including all day and
night solution designing, in teams of about 10. There will be speakers, coaches and breakout
sessions for the participants to learn and get help for the projects. At the end of the development
time, each team has a 3-minute presentation and the judges will award a winner along with
specialty winners. The main sponsor is AT&T; they will be funding all things for the event that
Girls in Tech Design-a-Thon 3
need a cash investment. Other sponsors will provide thing like information sessions, prizes, etc.
Girls in Tech Las Vegas is in charge of planning and management of the event.
The scope helps all of the stakeholders see all of the work and requirements of the project
along with an outline of the risks and constraints. The more specific a scope is the more
successful a project will be. This scope for this project is very detailed but still has wiggle room
allowing for scope creep. The scope shows there are many things one needs to think about when
starting a project. The information is laid out in such a way that allows the project manager and
stakeholders to ask important questions that need to be addressed prior to starting the project
including: what about this, what about that, should I leave this out, is it too specific?
Scopes are documents can easily have the same information multiple times. Practicing
writing and revising scope should be very high on a project managers list of skills. If a project
manager develops a scope that has the same information multiple times, then when there are
edits made during the course of the project, there are bound to be misses and
miscommunications. Leading to unhappy stakeholders and project failures.
Projects are inherently hard to manage, as they have not been done before, so some things
must be figured out during the course of the preparing for the event and thus causing the scope
creep. There is almost no way to avoid scope creep. Also, the more a project manager knows
about the field their project is in, the less likely they are to have missing information in the
scope. In the article Project Management for Chemical Engineers, they note, “The project
manager must realize that due to his or her limited expertise and usually even more limited time,
he or she cannot possibly complete engineering projects on their own.” (Peachey, Evitts, & Hill,
2007, p. 15) This is true with in all disciplines a project manager works in, especially the new
Girls in Tech Design-a-Thon 4
project manager. A project manager is wise to get outside collaboration with specialists even if
they are well versed with the project subject in general.
A project manager cannot do their work alone and they must put their ego aside to help
the project succeed. When it comes to writing the scope, they must do research, ask questions
and get specialized help when required. In addition, they also must hone their written and verbal
communication skills in order to make sure all stakeholders understand the specific goal of the
project and facilitate discovery of the things that the initial charter may not have mentioned but
are required.
Cost Estimate - Macro
Hackathons can wildly range in size. However, AT&T Sponsored Hackathons tend have
over 300 people. Last year’s AT&T’s CES Developer Summit Hackathon there were over 400
participants. ("TA Group: A Holding Company," n.d.) Since this event is to be held in
conjunction with the Girls in Tech Design-a-thon, we can estimate the size of the participants
will be about 200. The cost of the entire event is given to AT&T and other sponsors. Cost person
of these types of events can be wildly different depending upon how in long, how in-depth and
how many services are offered. According to Ishaan Gulrajani analysis in his blog titled The
Hackathon Budget usually the more people you expect, the higher the cost per person. (2014)
Analogous estimation method was used for the macro estimate. The formulas for figuring
out the preliminary budget are:
F&B = p * h* $2.70(m)
E = p * h * $0.71(m)
D = p * h * $7.67(m)
Girls in Tech Design-a-Thon 5
Food and Beverage, equipment/supplies and the total Design-a-thon budget all are
figured by multiplying and estimated number of people (p), the number of hours the event is to
be held (h) by the average of four different Hackathons per person, per hour cost of the events.
These were amounts were broken down to the per person, per hour in order to negate differences
in number of people and the length of the event.
The multiplier (m) of 1.5 was determine due initially chosen due to the fact that the
events that were used for the analogy were flexible in what they could choose for their food &
beverage and equipment. These formulas without the multiplier would be accurate had the
location requirement of a major resort not been required by the main sponsor.
Work Breakdown Structure
The Work Breakdown Structure (WBS) is an essential part of understanding the project.
It makes all of the activities of the Design-a-thon listed in easy to understand bites for the project
manager and anyone else using the document to see. In addition, this deliverable also gives
another chance for Girls in Tech to find problems in the scope of the project. The WBS also can
showed that some requirements listed in the scope of the Design-a-thon are much longer than
initially placed in the scope, including the expansion of the marketing for the event and the
amount of work needed to organize the activities to take place during the event.
Schedule, Network Diagram and Critical Path
For the Girls in Tech Design-a-Thon network diagram there are 54 tasks and 3 milestones
for the project and if started right away there is a large amount of slack. When analyzing this
network diagram, you have to consider that all of the resources are volunteer or donated.
Therefore, the slack in necessary in order to mitigate the risk of the resources (volunteers) not
being able do their assigned task on time. The free slack becomes incredibly diminished as in the
Girls in Tech Design-a-Thon 6
last month before the milestone of day one. In addition, the project has not commenced and the
slack is dwindling away, therefore increasing the risk involved with completing a successful
event.
Choosing the time measurement can alter the look and information that a network
diagram shows. The process also really gets you thinking about the time required and the wait
(lag) of each activity. When analyzing the network diagram as it is now, I must consider how it
was laid out. First, the activity times were determined by the amount of hours required to do the
work, however these times do not necessarily reflect the span of time in which the activity will
be completed. For example, an 8-hour task may consist of two 4-hour sessions over the course of
a month. This makes the project look like it can be completed in 81 hours but that is not the case.
Because this project is to be spread out over 3 months.
The Critical Path of the project has 11 primary activities and 12 sub activities that will
take a total of 81 hours. The primary activities include; develop cost estimate, give AT&T cost,
determine if additional funding needed, do networking promotions, direct volunteers and venue
staff of event set up, get final event count, direct volunteers for clean up, get feedback and the
management of each day. The secondary activities are the activities need to manage each day of
the event including things like serve meals and facilitate teams.
This project has a large number of activities that are concurrent as well as two very large
burst and one very large merge. During the management of the project, these activities need to be
carefully managed because two of these are directly on the critical path and the slack on a
number of preceding activities is very tight. If this project were to be completed nonstop with a
deadline of three weeks then it would be a very sensitive to delays in the stream of activities U,
P, Q, R, S and T.
Girls in Tech Design-a-Thon 7
When assessing the risk of this project, the risk of failure becomes higher the closer the
project comes to the milestone of day one, because all of the tasks prior are in preparation of this
and the next two days. However, even though there are only 13 tasks during these milestones,
they can be considered the most important throughout the project because the final success of the
project will be determined on these days.
Risk Planning
Risks can cause the project to fail, but they can be beneficial as well. The design-a-thon’s
risk management plan did not determine any beneficial risks; however, most of the risks to the
design-a-thon can be avoided or mitigated through proper planning, management, and
communication. The entire project is highly depended upon the official start and properly
outlined of the joint venture between AT&T and Girls in Tech. Girls in Tech has not attempted
an event of this type before let alone this scale, so the risk management plan is imperative to help
protect all of the stakeholders.
Micro Cost Estimate
Two of the WBS work packages with the costliest deliverables were used for the micro
cost estimate, plan meals and plan equipment. WBS package estimate pricing based on Palms
Resort catering and A/V pricing list as of October 2014. Pricing is subject to change before final
decisions are made. Some of the equipment needed is included in the catering packages and
discounted rates may be negotiated down due to the non-profit status of the event. Breaking these
packages down you can get a very accurate cost of these two of the most costly portions of the
Design-a-thon
The analogous and the micro estimate are very different; the food and beverage estimate
is off by almost $100,000.00. Upon further research, we would find that the total event cost
Girls in Tech Design-a-Thon 8
would be extremely off as well. Chou & Tseng stated “Even when activities in two projects are
similar, different backgrounds and environments including technology used and materials or
equipment can easily result in estimates that differ considerably.” (2011, p. 641) For an event of
this size with the requirements of the sponsor, we have learned that the projects used in the
analogous estimation were not necessarily appropriate or the multiplier was not accurate. A
better comparison would have been previous hackathons sponsored by major companies. Though
Henry, McCray, Purvis, & Roberts determined that “analogous estimating is less useful in
diverse and complex projects,” (2007, p. 607) so this may not even be the right choice for this
project.
Had Girls in Tech not been offered a major sponsorship with the location requirement,
the macro estimate would have more accurate. Doing a quick food & beverage cost estimate
from Jason’s Deli, one of the original catering considered, proves this to be. This project at its
current course is impossible without the full sponsorship of AT&T. Girls in Tech should
consider the risks of AT&T pulling out before moving forward and signing any guarantees on
the project.
Monitoring, Controlling and Execution
Planning of the design-a-thon is imperative but the execution of the activities will be
what makes or breaks the project. Monitoring and controlling using the network diagram
managed in MS Project will make all of the different variables easier to see the effects changes
made will have on the entire project. Communications management is also important to this
particular project, most of the work being completed on a volunteer basis and much of the
communications and “meetings’” will be conducted virtually.
Girls in Tech Design-a-Thon 9
Monitoring of the project should be considered from at least two points, the closing date
of the project as a whole and the all activities from start through a week before the event start
date. The value of the activities a week before the event start date and earlier have more meaning
to the status of the earned value of the event and variances in what is planned and what produced
will have more of an effect than including the activities that run through the event.
Recommendations
Recommendations are from a general analysis of the project, Girls in Tech perspective
and goals; and what AT&T publically has announced as their hackathon goals and what they
have made know to Girls in Tech as of this date. The joint venture is an excellent way to spread
the risk throughout the project. However, “parties who enter into joint ventures without knowing
and fully understanding the implications of their actions, would certainly encounter later
problems.” (Norwood & Mansfield, 1999, p. 89) I recommend that it be formalized and the
requirements of each team be specifically outlined as soon as possible so that the project can
commence. There is risk of misunderstanding if this is not done prior to starting of the project
that can lead to stakeholder dissatisfaction. This could impede future projects of this kind or even
stop the project before completion. If the project is started and announced then canceled, it could
lead to additional stakeholder unhappiness, via the attendees, who may lose money for their
travel expenses and bad public relations for AT&T or Girls in Tech.
Once the joint venture is solidified, the scope should be edited to include a budget and a
more detailed outline of all other sections of the scope. Currently, a large amount of scope creep
is expected in this project. It can be managed by including the expertise of AT&T in the final
scope document as well as implementing a change process that considers the priority matrix and
will it help the end goal of the project and increase the three main stakeholder’s satisfaction with
Girls in Tech Design-a-Thon 10
the project. The production stakeholders need to realize that, “the larger the scale of an event
project the more likely the scope creep and higher the price tag of the event.” (Jennings, 2012)
Even though cost will be enhanced to improve the project, it is not an unlimited resource.
To get an accurate estimate prior to the commencement of work, AT&T and Girls in
Tech need to average the other hackathon events that AT&T has completed in Las Vegas,
Nevada in order to mitigate the risk of using an analogous estimate that is not as accurate. In
addition, expert consultation of the risk management plan needs to be done in order to ensure
that it is as inclusive as possible. Research shows that events of this type need at least three
months planning and execution time. Currently the time allotted for this event has gone down to
2.5 months and it is during major holiday season. Leading to less time for the project to me
worked on and the volunteers will need to dedicate more structured time to complete activities or
decrease the scope of the design-a-thon.
Girls in Tech Design-a-Thon 11
Appendix 1
References
Amsterdam Hackathon 2013/Budget - MediaWiki. (2014, July 28). Retrieved October 3, 2014,
from https://www.mediawiki.org/wiki/Amsterdam_Hackathon_2013/Budget
Chou, J., & Tseng, H. (2011). Establishing expert system for prediction based on the project-
oriented data warehouse. Expert Systems With Applications, 38(1), 640–651.
doi:10.1016/j.eswa.2010.07.015
Donn, A. (n.d.). Alex Donn (AT&T Developer Program) - Eventbrite. Retrieved October 3,
2014, from http://www.eventbrite.com/o/alex-donn-atampt-developer-program-
1153839733?s=23092423
Feig, E. J. (2014, August). How to run a hackathon. - RecursiveRobot | E. John Feig. Retrieved
from http://www.recursiverobot.com/post/91272128309/how-to-run-a-hackathon
Feig, E. J. (2014, August). The Story - Hackathon - RecursiveRobot | E. John Feig. Retrieved
from http://www.recursiverobot.com/post/90565633684/the-story-hackathon
Food & Beverage Catering-How to calculate quantities to order. Planning Helper. (2011).
Retrieved from http://www.planninghelper.com/spv-245.aspx
Get Hacking!. (2014). HR Magazine, 59(5), 47-49.
Greiman, V., & Warburton, R. (2014, September 2). Introduction to Projects. Retrieved
September 20, 2014.
Gulrajani, I. (2014, June 23). The Hackathon Budget — Hackers and Hacking — Medium.
Retrieved from https://medium.com/hackers-and-hacking/the-hackathon-budget-
d636b5b2ed6c
HACKMIT - Oct 4-5. (2014). Retrieved October 3, 2014, from https://hackmit.org/
Girls in Tech Design-a-Thon 12
Henry, R. M., McCray, G. E., Purvis, R. L., & Roberts, T. L. (2007). Exploiting organizational
knowledge in developing IS project cost and schedule estimates: An empirical study.
Information & Management, 44(6), 598–612. doi:10.1016/j.im.2007.06.002
Hillson, D., Grimaldi, S., & Rafele, C. (2006). Managing Project Risks Using a Cross Risk
Breakdown Matrix. Risk Management. doi:10.1057/palgrave.rm.8250004
How to Run a Hackathon. (2014). Retrieved from www.socrata.com/open-data-field-guide/how-
to-run-a-hackathon/
Jason's Deli Online Ordering. (n.d.). Retrieved October 5, 2014, from
https://online.jasonsdeli.com/jasonsdeli/web/default.aspx?tab=home
Meetings. (2014). Retrieved October 3, 2014, from http://www.palms.com/business-
groups/meetings
Peachey, B., Evitts, R., & Hill, G. (2007). Project Management for Chemical Engineers.
Education for Chemical Engineers, 2(1), 14-19. doi:10.1205/ece06019
Phillips, M. (2011, August 11). A Cost/Benefit Analysis of the Ripple Hackathon. Retrieved
from http://www.themarkphillips.com/2011/08/09/A-Cost-Benefit-Analysis-of-the-Ruby-
Hackathon.html
Shearman, S., & Barnes, R. (2012). Time to hack your brand. (cover story). Marketing
(00253650), 10-13.
TA Group: A Holding Company. (n.d.). Retrieved from
http://tagroupholdings.com/news_items/23
Tao, E. (201, March 31). Hackathon Planning In Less Than 10 Steps | TechCrunch. Retrieved
from http://techcrunch.com/2012/03/31/hackathon-planning/
Girls in Tech Design-a-Thon 13
Warburton, R., & Kanabar, V. (2013). The Art and Science of Project Management (2nd ed.).
Newport, RI: RW-Press.
Zürich Hackathon 2014/Budget - MediaWiki. (2014, July 28). Retrieved October 3, 2014, from
https://www.mediawiki.org/wiki/Z%C3%BCrich_Hackathon_2014/Budget
Girls in Tech Design-a-Thon 14
Appendix 2
Scope Statement
Objective:
To organize a Design-a-Thon to encourage women to participate product and solution design in
January.
Justification:
To further Girls in Tech’s mission of inspiring and leading women in being entrepreneurial and
innovative.
Deliverables and Milestones:
DELIVERABLE OR MILESTONE DATE DUE
COST ESTIMATE September 22, 2014
MARKETING PLAN September 29, 2014
MARKETING PLAN EXECUTION
On Going from September 29, 2014 - January 7,
2015
SPEAKER CONFIRMATIONS October 27, 2014
EVENT EQUIPMENT LIST November 3, 2014
EVENT PLANS AND LOGISTICS November 10, 2014
EVENT MENU November 24, 2014
VOLUNTEER AND SPEAKER BAG December 8, 2014
PARTICIPANT BAG December 15, 2014
FINAL PREPARATION AND COUNT FOR
EVENT
December 22 ,2014
DAY 1 January 2, 2015
DAY 2 January 3, 2015
DAY 3 January 4, 2015
POST EVENT SURVEY January 7, 2015
Specification:
Girls in Tech Design-a-Thon 15
Theme: Designing a Better Tomorrow – Teams of about 10 participants are to identify a problem
in their community that needs a solution and then design a product/solution to solve that problem
Location: Palms Las Vegas Resort and Convention Center
Event Dates: Friday January 2 - Sunday January 4, 2015
Category Requirement Stakeholder
Product Registration Packet GiT
Planning
Keynote Speakers –
At least 2
GiT
Planning
Event Schedule and
Logistics Plan
GiT
Food
Kickoff Event
Food and Beverage
GiT
Food
Saturday & Sunday
Breakfast, Lunch,
Dinner and Snacks
Food and Beverage
GiT
Planning
Breakout Speakers –
At least 6
GiT
Event Management Volunteers GiT
Planning Experts GiT
Planning Judges GiT
Product Post Event Survey GiT
Planning Marketing and PR Christina/Melissa
Product Prizes GiT
Planning
Breakout Session
Entertainment
GiT
Planning Event Equipment GiT & Palms
Planning
TED talk Video
Curation
GiT
Funding Preliminary Funding AT&T & GiT
Funding Additional Funding GiT
Product Event Shirts Amber
Product Participant Swag Bag GiT
Product
Speaker and Volunteer
thank you bags
GiT
Girls in Tech Design-a-Thon 16
Risks:
Alcohol consumption by underage attendees
Equipment and supplies may not arrive on time.
People may become extremely tired or sick over long days
Limits and Exclusions:
The location will have requirements for use of the venue.
Constraints:
Schedule: Event must occur the weekend of January 2, 2015
The Palms Resort and Casino must provide food, beverage and most of the A/V equipment
SCOPE SCHEDULE COST
CONSTRAIN X
ENHANCE X
ACCEPT X
Assumptions:
AT&T to Supply: Location, food and drinks, paper/pens, markers/whiteboards,
posterboard/paint, Wi-Fi, prototyping equipment (5 3D printers for teams to print out their
designs for final presentations, and/or a “trial” version of Sketchup/Solidworks/etc so they can
present the framework of a design), funds needed for speakers equipment and other
entertainment.
Attendant to Supply: Laptop
Girls in Tech to Supply: Event Management and Volunteers
Girls in Tech Design-a-Thon 17
Technical Requirements:
All dietary restrictions must be accommodated and 50% of food and beverage offerings must be
healthy
Review of Deliverables:
Monthly Girls in Tech Meetings, Meetings with AT&T as needed
Girls in Tech Design-a-Thon 18
Appendix 4
Work Breakdown Structure
0. Design-a-thon
1. Do Project Management
2. Do Event Management
2.1 Manage Day 1
1. Perform Registration
2. Serve Dinner
3. Do Welcome
4. Make Teams
2.2 Manage Day 2
2.2.1. Serve Meals
2.2.2. Do Breakouts
2.2.3. Facilitate teams
2.3 Manage Day 3
2.3.1. Serve Meals
2.3.2. Do Breakouts
2.3.3. Facilitate teams
2.3.4. Facilitate Judging
2.3.5. Present winners and closing
2.4 Direct Event Setup
2.4.1. Get Pre Event Count
2.4.2. Direct Volunteers and Venue Staff for Event Setup
Girls in Tech Design-a-Thon 19
2.5 Do Event Closing Activities
2.5.1. Get Final Event Count
2.5.2. Send Event Survey
2.5.3. Direct Volunteers for Cleanup and collection of GiT
belongings
2.5.4. Get Feedback from Event Donors and Volunteers
3. Plan Event
3.1 Develop Cost Estimate
1. Give AT&T Cost
2. Determine if Additional funding is needed
3.2 Plan Menus – Breakfast, lunch, dinner and snacks for Saturday and
Sunday, Kickoff event dinner
3.2.1. Sign Contracts with Palms and AT&T
3.2.2. Develop plan for service alcohol during event kickoff and
closing event
3.3 Plan Equipment List
3.3.1. Separate Palms Equipment List
3.3.2. Find items required not available at the Palms
3.4 Set up Event and Logistics Plan
3.4.1. Get volunteers
3.5 Plan Activities
3.5.1. Select Speakers
a. Give Breakout Speakers Session time
Girls in Tech Design-a-Thon 20
b. Give Opening Speakers Event time
c. Give Closing Speakers Event time
3.5.2. Select Judges
3.5.2.1. Give Judges Event time
3.5.3. Select Breakout activities
3.5.4. Select ongoing event activities
3.5.4.1. TEDtalk curation
3.5.5. Select Experts
4. Do Marketing
4.1 Set up Social Media
4.2 Contact CES to be listed in events
4.3 Do Press Release
4.4 Do Online Promotion
1. Set up Event website
4.5 Do Networking Promotion
5. Arrange Event
5.1 Make Bags
1. Have Shirts Made
2. Get donated items for bags
5.2 Make Registration Packet
5.3 Create Post Event Survey
5.4 Organize Prizes
5.4.1. Get Donated prizes from vendors
Girls in Tech Design-a-Thon 21
5.4.2. Write prize letter for Prizes
5.4.3. Put together prize packets
Girls in Tech Design-a-Thon 22
Appendix 5
Preliminary Network Diagram
Girls in Tech Design-a-Thon 23
Appendix 6
Preliminary Network Diagram List
Activity Description Predecessor Duration (Hours)
A Manage Day 1 E 5
A1 Do Registration A 2
A2 Serve Dinner A 1
A3 Do Welcome A 1
A4 Make Teams A 1
B Manage Day 2 A1, A2, A3, A4 16
B1 Serve Meals B 4
B2 Do Breakouts B 3.5
B3 Facilitate teams B 8.5
C Manage Day 3 B1, B2, B3 14
C1 Serve Meals C 4
C2 Do Breakouts C 1
C3 Facilitate teams C 7
C4 Facilitate Judging C 1
C5 Present winners and
closing
C 1
D Get Pre Event Count S 1
E Direct Volunteers and
Venue Staff for Event
Setup
2
F Get Final Event
Count
C1, C2, C3, C4, C5 1
G Send Event Survey H 1
H Direct Volunteers for
Cleanup and
collection of GiT
belongings
F 1
I Get Feedback from
Event Donors and
Volunteers
H 2
J Develop Cost
Estimate
NONE 2
K Give AT&T Cost J 1
L Determine if
Additional funding is
needed
K 1
M Plan Menus –
Breakfast, lunch,
dinner and snacks for
Saturday and Sunday,
Kickoff event dinner
N 2
N Sign Contracts with
Palms and AT&T
K 1
Girls in Tech Design-a-Thon 24
O Develop plan for
service alcohol during
event kickoff and
closing event
N 1
P Plan Equipment List N, U, AA, BB 2
Q Give list to the Palms P 1
R Find items required
no available at the
Palms
Q 4
S Set up Event and
Logistics Plan
R, Y, DD 8
T Get volunteers S 8
U Select Speakers NONE 16
V Give Breakout
Speakers Session time
S .5
W Give Opening
Speakers Event time
S .5
X Give Closing Speakers
Event time
S .5
Y Select Judges NONE 8
Z Give Judges Event
time
S .5
AA Select Breakout
activities
L 2
BB Select ongoing event
activities
L 1
CC TEDtalk curation L 8
DD Select Experts NONE 16
EE Make Bags HH, FF 13
FF Have Shirts Made L 4
HH Get donated items for
bags
L 8
II Make Registration
Packet
K 3
JJ Create Post Event
Survey
NONE 2
KK Get Donated prizes
from vendors
L 8
LL Write prize letter for
Prizes
KK 1
MM Put together prize
packets
LL 1
NN Set up Social Media L 8
OO Contact CES to be
listed in events
L 8
PP Do Press Release L 4
QQ Do Online Promotion L 8
RR Set up Event website L 2
SS Do Networking
Promotion
L 36
Girls in Tech Design-a-Thon 25
Girls in Tech Design-a-Thon 26
Appendix 7
Macro Estimate
Method Used: Analogous
Pre-I/O Google Glass Hackathon – 24 Hour Event
Number of
Participants
Food & Bev Costs Equipment Costs Total Event Cost
91 $1037.90 $3507.65 $9500.00
F&B per Person: 11.41 Equipment per Person: $38.55 Event per Person: $104.40
F&B PP/PH: 0.13 Equipment PP/PH: $1.61 Event PP/PH: $4.35
HackMIT – 24 Hour Event
Number of
Participants
Food & Bev Costs Equipment Costs Total Event Cost
1050 $40,000.00 $27,000.00 $250,000.00
F&B per Person: $38.10
F&B PP/PH: $1.59
Equipment per Person: $25.71
Equipment PP/PH: $1.07
Event per Person: $238.10
Event PP/PH: $9.92
Zürich Hackathon 2014 – 46 Hour Event
Number of
Participants
Food & Bev Costs Equipment Costs Total Event Cost
208 $33,195.66 $830.80 $46,441.63
F&B per Person: $159.59
F&B PP/PH: $3.47
Equipment per Person: $3.99
Equipment PP/PH: $0.09
Event per Person: $223.28
Event PP/PH: $4.85
Amsterdam Hackathon 2013 -30 Hour Event
Number of
Participants
Food & Bev Costs Equipment Costs Total Event Cost
149 € 20,055.00 € 242,48 €41,324.13
F&B per Person: €134.60 / $168.45
Equipment per Person: €1.62 / $2.03
Event per Person: €277.34 / $347.09
F&B PP/PH: $5.62
Equipment PP/PH: 0.07
Event PP/PH: $11.57
Girls in Tech Design-a-Thon MS 27
Average Food and Beverage Cost per Person per Hour: $2.70
Average Equipment per Person per Hour: $0.71
Average Event per Person per Hour: $7.67
GiT Design-a-thon Hours Estimate – 24
GiT Design-a-thon Participant Estimate – 200
Multiplier – 1.5
Equipment Multiplier -
F&B = p * h* $2.70(m) $19,440.00 Food and Beverage
E = p * h * $0.71(m) $5,112.00 Equipment
D = p * h * $7.67(m) $55,224.00 Design-a-thon
Girls in Tech Design-a-Thon MS 28
Appendix 8
Micro Estimate
Work Package Estimate Project Title
GiT Design-a-Thon
Work Package Title WBS Code
Separate Palms Equipment List 3.3.1
Deliverable Description of Work:
Equipment List
Select Equiptment needed from the
Palms
Activity/Cost
Item
Resource
Duration
(days)
Labor
(hrs)
Rate Units
Unit
Cost
Total
Menu Planning
& Consultation
Volunteer 2.00 2.00 $0.00 $0.00
TV Equiptment 3.00 1.00 $425.00 $1,275.00
Wireless
Microphone
Equiptment 3.00 1.00 $185.00 $555.00
Printer Equiptment 2.00 1.00 $175.00 $350.00
Laser Pointer Equiptment 1.00 1.00 $55.00 $55.00
Slide Advacer Equiptment 3.00 1.00 $55.00 $165.00
Easel for
Signage
Equiptment 3.00 3.00 $20.00 $180.00
Powerstrips Equiptment 2.00 45.00 $30.00 $2,700.00
Draping Equiptment 4.00 $190.00 $760.00
Labor 2.00 1.00 $83.00 $166.00
Fee 21.00% $1,268.40
Total Cost $7,474.40
Girls in Tech Design-a-Thon MS 29
Work Package Estimate
Project Title
GiT Design-a-Thon
Work Package Title WBS Code
Plan Menus 3.2
Deliverable Description of Work:
Event Menus & Pricing Select menus for all meal
Activity/Cost
Item
Resource
Duration
(days)
Labor
(hrs)
Rate Units
Unit
Cost
Total
Menu Planning
& Consultation
Volunteer 2.00 2.00 $0.00 $0.00
Opening
Reception
F&B 1.00 200.00 $70.00 $14,000.00
Breakfast F&B 2.00 200.00 $26.00 $10,400.00
Lunch F&B 2.00 200.00 $36.00 $14,400.00
Dinner F&B 1.00 200.00 $65.00 $13,000.00
Snack F&B 2.00 200.00 $15.00 $6,000.00
Snack F&B 2.00 200.00 $20.00 $8,000.00
Closing
Reception Food
Displays
F&B 1.00 3.00 $2,400.00 $7,200.00
Closing
Reception
Beverage
F&B 1.00 2.00 250.00 $10.00 $5,000.00
Closing
Reception
Bartender
F&B 1.00 4.00 $175.00 $700.00
Coffee F&B 2.00 22.00 $66.00 $2,904.00
Energy Drinks F&B 2.00 200.00 $7.00 $2,800.00
Water F&B 2.00 400.00 $5.00 $4,000.00
Whole Fruit F&B 2.00 16.00 $42.00 $1,344.00
Chips F&B 2.00 200.00 $3.50 $1,400.00
Tax 8.10% $7,382.99
Service fee 21.00% $19,141.08
Total Cost $117,672.07
Girls in Tech Design-a-Thon MS 30
Appendix 9
Risk Management Plan
Risk Response
Pull back of budget from AT&T Obtain clearly defined budget in joint venture
agreement.
Dropping of sponsorship by AT&T Have joint venture agreement include a
penalty for dropping sponsorship after public
announcement and only us AT&T as
guarantees for contracts
Small participant count Frequently communicate with venue the
participant count to ensure space is not over
allocated or event space can be combined
with space of AT&T concurrent hack-a-thon
Lack of volunteers Enlist Girls in Tech family and friends, and
AT&T staff to assist with event facilitation
Travel delays of judges or presenters Create a plan of secondary people that can be
obtained at last minute and activities that can
be run by volunteers
Inability of venue to provide healthy food
options
Communicate with venue to ensure options
can be obtained, if not ask for allowances to
bring in outside food.
Girls in Tech volunteers unable to complete
planning and preparation tasks by deadlines
Have regular team meetings and
communications to the status of activities
Pull out of prize sponsors Do not announce specifics of prizes without
written confirmation of prize sponsor
Not enough food provided Work with venue to prepare for last minute
additions and estimate food needs based on
previous similar events held at the venue
Event equipment not set up on time Consult and communicate with equipment
vendor and venue to ensure equipment is set
up a day prior to event starting.
Weak Wi-Fi Request Wi-Fi extenders and have access to
additional should they be needed
Unsecure Wi-Fi Recommend participants using Wi-Fi take
proper person security methods on their
devices
Delay of “product” for gift bags Have “product” sent one month prior to event.
Lack of response from post event survey Require feedback during event prior to
awards ceremony
Not enough product for gift bags Do not announce participant gift bags, and
use what has been obtained for surprise prizes
Participant or Volunteer becomes ill during
event
Make sure all volunteers and staff have
emergency contact card.
Girls in Tech Design-a-Thon MS 31
Venue not prepared for number of
participants
Frequently communicate with venue the
participant count to ensure space is properly
allocated and put a limit on the number
participants
Schedule too tight to complete tasks needed to
properly manage event
Removal of deliverables to lower time needed
to complete planning.
Lack of communication between Girls in
Tech and AT&T
Schedule bi-weekly calls and regular email
with AT&T and Girls in Tech for status
reviews and rapid request for assistance when
needed
Girls in Tech Design-a-Thon MS 32
Appendix 10
Final Network Task List
Task
Number
Task Name Duration Start Finish Predecessors
23
Develop Cost
Estimate
2 hrs
Wed
10/15/14
Wed
10/15/14
24
Give AT&T Cost 1 hr
Wed
10/15/14
Wed
10/15/14
23
25
Determine if
Additional funding is
needed
1 hr
Wed
10/15/14
Wed
10/15/14
24
27
Sign Contracts with
Palms and AT&T
1 hr
Wed
10/15/14
Wed
10/15/14
24
52
Set up Social Media 32 hrs
Wed
10/15/14
Thu
10/16/14
25
56
Set up Event website 2 hrs
Wed
10/15/14
Wed
10/15/14
25
40
Select Breakout
activities
2 hrs
Wed
10/15/14
Wed
10/15/14
25
38
Select Judges 8 hrs
Thu
10/16/14
Thu
10/16/14
53
Contact CES to be
listed in events
16 hrs
Thu
10/16/14
Fri
10/17/14
25
34
Select Speakers 16 hrs
Fri
10/17/14
Mon
10/20/14
54
Do Press Release 4 hrs
Fri
10/17/14
Fri
10/17/14
25
28
Develop plan for
service alcohol
during event kickoff
and closing event
1 hr
Mon
10/20/14
Mon
10/20/14
27
43
Select Experts 16 hrs
Mon
10/20/14
Tue
10/21/14
55
Do Online Promotion 32 hrs
Mon
10/20/14
Tue
10/21/14
25
57
Do Networking
Promotion
36 hrs?
Tue
10/21/14
Wed
10/22/14
25
26
Plan Menus –
Breakfast, lunch,
dinner and snacks for
Saturday and
Sunday, Kickoff event
dinner
2 hrs
Wed
10/22/14
Wed
10/22/14
27
Girls in Tech Design-a-Thon MS 33
41
Select ongoing event
activities
1 hr
Thu
10/23/14
Thu
10/23/14
25
29
Plan Equipment List 2 hrs
Fri
10/24/14
Fri
10/24/14
27,34,40,41
30
Give list to the Palms 1 hr
Fri
10/24/14
Fri
10/24/14
29
31
Find items required
no available at the
Palms
4 hrs
Fri
10/24/14
Fri
10/24/14
30
32
Set up Event and
Logistics Plan
8 hrs
Fri
10/24/14
Mon
10/27/14
31,38,43
35
Give Breakout
Speakers Session
time
0.5 hrs
Mon
10/27/14
Mon
10/27/14
32
36
Give Opening
Speakers Event time
0.5 hrs
Mon
10/27/14
Mon
10/27/14
32
37
Give Closing
Speakers Event time
0.5 hrs
Mon
10/27/14
Mon
10/27/14
32
39
Give Judges Event
time
0.5 hrs
Mon
10/27/14
Mon
10/27/14
32
33
Get volunteers 8 hrs
Mon
11/3/14
Mon
11/3/14
32
45
Have Shirts Made 4 hrs
Mon
11/17/14
Mon
11/17/14
25
46
Get donated items
for bags
8 hrs
Tue
11/18/14
Tue
11/18/14
25
42
TEDtalk curation 8 hrs
Tue
12/2/14
Tue
12/2/14
25
49
Get Donated prizes
from vendors
8 hrs
Wed
12/10/14
Wed
12/10/14
25
50
Write prize letter for
Prizes
1 hr
Thu
12/11/14
Thu
12/11/14
49
44
Make Bags 13 hrs
Mon
12/15/14
Tue
12/16/14
46,45
47
Make Registration
Packet
3 hrs
Wed
12/17/14
Wed
12/17/14
24
51
Put together prize
packets
1 hr
Thu
12/18/14
Thu
12/18/14
50
48
Create Post Event
Survey
2 hrs
Fri
12/19/14
Fri
12/19/14
17
Get Pre Event Count 8 hrs
Fri
12/26/14
Fri
12/26/14
32
Girls in Tech Design-a-Thon MS 34
1
Day 1 0.8 days
Fri
1/2/15
Fri 1/2/15
36,39,35,28,37,26,48,47,51,44,
57,55,53,52,54,42,56,33,17
2
Direct Volunteers
and Venue Staff for
Event Setup
2 hrs
Fri
1/2/15
Fri 1/2/15 1FS-8 hrs
3
Perform Registration 4 hrs
Fri
1/2/15
Fri 1/2/15 2
4
Serve Dinner 1 hr
Fri
1/2/15
Fri 1/2/15 3
5
Present Welcome 1 hr
Fri
1/2/15
Fri 1/2/15 4
6
Make Teams 1 hr
Fri
1/2/15
Fri 1/2/15 5
7
Day 2 0.8 days
Sat
1/3/15
Sat 1/3/15 6
8
Serve Meals 4 hrs
Sat
1/3/15
Sat 1/3/15 7FS-8 hrs
9
Do Breakouts 3.5 hrs
Sat
1/3/15
Sat 1/3/15 7FS-8 hrs
10
Facilitate teams 8 hrs
Sat
1/3/15
Sat 1/3/15 7FS-8 hrs
11
Day 3 0.8 days
Sun
1/4/15
Sun
1/4/15
8,9,10
12
Serve Meals 4 hrs
Sun
1/4/15
Sun
1/4/15
11FS-8 hrs
13
Do Breakouts 1 hr
Sun
1/4/15
Sun
1/4/15
11FS-8 hrs
14
Facilitate teams 7 hrs
Sun
1/4/15
Sun
1/4/15
11FS-8 hrs
15
Facilitate Judging 1 hr
Sun
1/4/15
Sun
1/4/15
14,12,13
16
Present winners and
closing
1 hr
Sun
1/4/15
Sun
1/4/15
15
18
Get Final Event
Count
1 hr
Sun
1/4/15
Sun
1/4/15
16
21
Direct Volunteers for
Cleanup and
collection of GiT
belongings
1 hr
Sun
1/4/15
Sun
1/4/15
18
19
Send Event Survey 1 hr
Mon
1/5/15
Mon
1/5/15
21
22
Get Feedback from
Event Donors and
Volunteers
2 hrs
Mon
1/5/15
Mon
1/5/15
21
20
Event Review
Meeting
2 hrs
Sun
1/18/15
Sun
1/18/15
19,22
Girls in Tech Design-a-Thon MS 35
Appendix 11
Final Network Diagram
See Attachment

More Related Content

PDF
Volkswagen - Developing Strategies for Competitive Advantage
DOCX
Report on supply chain management of coca cola.
PPT
Reiko penerbangan Haji
DOCX
EMU transcript
DOCX
Resumen de cooperativas
PPTX
Presentación1g
PDF
Cronograma
DOC
fuerza de rozamiento
Volkswagen - Developing Strategies for Competitive Advantage
Report on supply chain management of coca cola.
Reiko penerbangan Haji
EMU transcript
Resumen de cooperativas
Presentación1g
Cronograma
fuerza de rozamiento

Viewers also liked (6)

PPTX
Estadistica
PDF
Market Research 856 Final Project
PDF
SlideShare 101
PDF
COMMONWEALTH BUSINESS FORUM - 24-26 November 2015
PPT
LAS TIC
PPT
Порядок и формы проведения ГИА 9класс 2016 г
Estadistica
Market Research 856 Final Project
SlideShare 101
COMMONWEALTH BUSINESS FORUM - 24-26 November 2015
LAS TIC
Порядок и формы проведения ГИА 9класс 2016 г
Ad

Similar to Project Management Final Project (20)

PDF
Lessons learnt
PDF
Supporting The Initial Stages of The Product Design Process: Towards Knowledg...
PDF
50120130406031
PDF
ICT-Go-Girls! project brochure
PDF
Danielle Sherman - CPR Submission
PDF
Techmeetup Glasgow 24 03-13 (slideshare version)
PDF
asdfas
PDF
DOCX
Planning booklet
PPT
Dtui5 chap03rev
PDF
Girls in ICT 2023 - Toolkit.
PDF
White paper - Adhoc 2.0
PPT
Design process initial ideas - done
PPT
Spm unit 3
PPTX
From school in mass media
PPT
Network analysis-design-and-implementation-part-a2252
PDF
Dt report1-liyang
PDF
Personal dashboards for individual learning and project awareness in social s...
PDF
201001162_report
PPTX
Chapter 1 6 step design process
Lessons learnt
Supporting The Initial Stages of The Product Design Process: Towards Knowledg...
50120130406031
ICT-Go-Girls! project brochure
Danielle Sherman - CPR Submission
Techmeetup Glasgow 24 03-13 (slideshare version)
asdfas
Planning booklet
Dtui5 chap03rev
Girls in ICT 2023 - Toolkit.
White paper - Adhoc 2.0
Design process initial ideas - done
Spm unit 3
From school in mass media
Network analysis-design-and-implementation-part-a2252
Dt report1-liyang
Personal dashboards for individual learning and project awareness in social s...
201001162_report
Chapter 1 6 step design process
Ad

Recently uploaded (20)

PDF
Solaris Resources Presentation - Corporate August 2025.pdf
PPT
Chapter four Project-Preparation material
PPTX
Principles of Marketing, Industrial, Consumers,
PDF
TyAnn Osborn: A Visionary Leader Shaping Corporate Workforce Dynamics
PDF
NEW - FEES STRUCTURES (01-july-2024).pdf
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PDF
Module 3 - Functions of the Supervisor - Part 1 - Student Resource (1).pdf
PDF
Laughter Yoga Basic Learning Workshop Manual
PDF
Hindu Circuler Economy - Model (Concept)
PPTX
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
PDF
Nidhal Samdaie CV - International Business Consultant
PPT
Lecture 3344;;,,(,(((((((((((((((((((((((
PDF
Family Law: The Role of Communication in Mediation (www.kiu.ac.ug)
PDF
NewBase 12 August 2025 Energy News issue - 1812 by Khaled Al Awadi_compresse...
PDF
Comments on Crystal Cloud and Energy Star.pdf
PDF
Keppel_Proposed Divestment of M1 Limited
PPTX
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
PPTX
DMT - Profile Brief About Business .pptx
PDF
SBI Securities Weekly Wrap 08-08-2025_250808_205045.pdf
PDF
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
Solaris Resources Presentation - Corporate August 2025.pdf
Chapter four Project-Preparation material
Principles of Marketing, Industrial, Consumers,
TyAnn Osborn: A Visionary Leader Shaping Corporate Workforce Dynamics
NEW - FEES STRUCTURES (01-july-2024).pdf
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
Module 3 - Functions of the Supervisor - Part 1 - Student Resource (1).pdf
Laughter Yoga Basic Learning Workshop Manual
Hindu Circuler Economy - Model (Concept)
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
Nidhal Samdaie CV - International Business Consultant
Lecture 3344;;,,(,(((((((((((((((((((((((
Family Law: The Role of Communication in Mediation (www.kiu.ac.ug)
NewBase 12 August 2025 Energy News issue - 1812 by Khaled Al Awadi_compresse...
Comments on Crystal Cloud and Energy Star.pdf
Keppel_Proposed Divestment of M1 Limited
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
DMT - Profile Brief About Business .pptx
SBI Securities Weekly Wrap 08-08-2025_250808_205045.pdf
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions

Project Management Final Project

  • 1. Girls in Tech Design-a-Thon 1 Girls in Tech Design-a-Thon Project Brea Silva MET AD 642 Project Management Virginia A. Greiman October 13, 2014 Abstract This paper is an analysis of the project management of the planned Girls in Tech Design-a-thon. It touches on the scope, work breakdown structure, macro and micro estimates, schedule, network diagram, critical path, risk planning and monitoring, controlling and execution of the project. Recommendations to the project management of the event are sprinkled throughout, along with final recommendations ending the paper.
  • 2. Girls in Tech Design-a-Thon 2 Girls in Tech Design-a-Thon Introduction Girls in Tech is a non-profit organization dedicated to the engagement, education and empowerment of women in technology. In order to promote this goal, the local Girls in Tech Las Vegas chapter has decided to take on producing a design-a-thon. A design-a-thon is an event similar to a hackathon but without requiring software programing. The goal is to design any sort of product or solution that helps a problem in the community. By not needing programing knowledge or requiring the use of a specific software solution they hope to encourage more women to participate in this other hackathons, which are great events for learning and networking in the technology and product development fields. Currently, AT&T and Girls in Tech are in talks to collaborate for this event. AT&T has will have sponsored over 100 events including at least two in Las Vegas. With their sponsorship, they have requirements including using a particular venue and a prize pool of at least a certain amount. This project will go from a small local event to one with global interest. Therefore, the stakes are high if the joint venture comes to fruition. Scope The scope for this project includes the fact that this event will be over the course of three days, before the CES convention, and will have two networking mixers including all day and night solution designing, in teams of about 10. There will be speakers, coaches and breakout sessions for the participants to learn and get help for the projects. At the end of the development time, each team has a 3-minute presentation and the judges will award a winner along with specialty winners. The main sponsor is AT&T; they will be funding all things for the event that
  • 3. Girls in Tech Design-a-Thon 3 need a cash investment. Other sponsors will provide thing like information sessions, prizes, etc. Girls in Tech Las Vegas is in charge of planning and management of the event. The scope helps all of the stakeholders see all of the work and requirements of the project along with an outline of the risks and constraints. The more specific a scope is the more successful a project will be. This scope for this project is very detailed but still has wiggle room allowing for scope creep. The scope shows there are many things one needs to think about when starting a project. The information is laid out in such a way that allows the project manager and stakeholders to ask important questions that need to be addressed prior to starting the project including: what about this, what about that, should I leave this out, is it too specific? Scopes are documents can easily have the same information multiple times. Practicing writing and revising scope should be very high on a project managers list of skills. If a project manager develops a scope that has the same information multiple times, then when there are edits made during the course of the project, there are bound to be misses and miscommunications. Leading to unhappy stakeholders and project failures. Projects are inherently hard to manage, as they have not been done before, so some things must be figured out during the course of the preparing for the event and thus causing the scope creep. There is almost no way to avoid scope creep. Also, the more a project manager knows about the field their project is in, the less likely they are to have missing information in the scope. In the article Project Management for Chemical Engineers, they note, “The project manager must realize that due to his or her limited expertise and usually even more limited time, he or she cannot possibly complete engineering projects on their own.” (Peachey, Evitts, & Hill, 2007, p. 15) This is true with in all disciplines a project manager works in, especially the new
  • 4. Girls in Tech Design-a-Thon 4 project manager. A project manager is wise to get outside collaboration with specialists even if they are well versed with the project subject in general. A project manager cannot do their work alone and they must put their ego aside to help the project succeed. When it comes to writing the scope, they must do research, ask questions and get specialized help when required. In addition, they also must hone their written and verbal communication skills in order to make sure all stakeholders understand the specific goal of the project and facilitate discovery of the things that the initial charter may not have mentioned but are required. Cost Estimate - Macro Hackathons can wildly range in size. However, AT&T Sponsored Hackathons tend have over 300 people. Last year’s AT&T’s CES Developer Summit Hackathon there were over 400 participants. ("TA Group: A Holding Company," n.d.) Since this event is to be held in conjunction with the Girls in Tech Design-a-thon, we can estimate the size of the participants will be about 200. The cost of the entire event is given to AT&T and other sponsors. Cost person of these types of events can be wildly different depending upon how in long, how in-depth and how many services are offered. According to Ishaan Gulrajani analysis in his blog titled The Hackathon Budget usually the more people you expect, the higher the cost per person. (2014) Analogous estimation method was used for the macro estimate. The formulas for figuring out the preliminary budget are: F&B = p * h* $2.70(m) E = p * h * $0.71(m) D = p * h * $7.67(m)
  • 5. Girls in Tech Design-a-Thon 5 Food and Beverage, equipment/supplies and the total Design-a-thon budget all are figured by multiplying and estimated number of people (p), the number of hours the event is to be held (h) by the average of four different Hackathons per person, per hour cost of the events. These were amounts were broken down to the per person, per hour in order to negate differences in number of people and the length of the event. The multiplier (m) of 1.5 was determine due initially chosen due to the fact that the events that were used for the analogy were flexible in what they could choose for their food & beverage and equipment. These formulas without the multiplier would be accurate had the location requirement of a major resort not been required by the main sponsor. Work Breakdown Structure The Work Breakdown Structure (WBS) is an essential part of understanding the project. It makes all of the activities of the Design-a-thon listed in easy to understand bites for the project manager and anyone else using the document to see. In addition, this deliverable also gives another chance for Girls in Tech to find problems in the scope of the project. The WBS also can showed that some requirements listed in the scope of the Design-a-thon are much longer than initially placed in the scope, including the expansion of the marketing for the event and the amount of work needed to organize the activities to take place during the event. Schedule, Network Diagram and Critical Path For the Girls in Tech Design-a-Thon network diagram there are 54 tasks and 3 milestones for the project and if started right away there is a large amount of slack. When analyzing this network diagram, you have to consider that all of the resources are volunteer or donated. Therefore, the slack in necessary in order to mitigate the risk of the resources (volunteers) not being able do their assigned task on time. The free slack becomes incredibly diminished as in the
  • 6. Girls in Tech Design-a-Thon 6 last month before the milestone of day one. In addition, the project has not commenced and the slack is dwindling away, therefore increasing the risk involved with completing a successful event. Choosing the time measurement can alter the look and information that a network diagram shows. The process also really gets you thinking about the time required and the wait (lag) of each activity. When analyzing the network diagram as it is now, I must consider how it was laid out. First, the activity times were determined by the amount of hours required to do the work, however these times do not necessarily reflect the span of time in which the activity will be completed. For example, an 8-hour task may consist of two 4-hour sessions over the course of a month. This makes the project look like it can be completed in 81 hours but that is not the case. Because this project is to be spread out over 3 months. The Critical Path of the project has 11 primary activities and 12 sub activities that will take a total of 81 hours. The primary activities include; develop cost estimate, give AT&T cost, determine if additional funding needed, do networking promotions, direct volunteers and venue staff of event set up, get final event count, direct volunteers for clean up, get feedback and the management of each day. The secondary activities are the activities need to manage each day of the event including things like serve meals and facilitate teams. This project has a large number of activities that are concurrent as well as two very large burst and one very large merge. During the management of the project, these activities need to be carefully managed because two of these are directly on the critical path and the slack on a number of preceding activities is very tight. If this project were to be completed nonstop with a deadline of three weeks then it would be a very sensitive to delays in the stream of activities U, P, Q, R, S and T.
  • 7. Girls in Tech Design-a-Thon 7 When assessing the risk of this project, the risk of failure becomes higher the closer the project comes to the milestone of day one, because all of the tasks prior are in preparation of this and the next two days. However, even though there are only 13 tasks during these milestones, they can be considered the most important throughout the project because the final success of the project will be determined on these days. Risk Planning Risks can cause the project to fail, but they can be beneficial as well. The design-a-thon’s risk management plan did not determine any beneficial risks; however, most of the risks to the design-a-thon can be avoided or mitigated through proper planning, management, and communication. The entire project is highly depended upon the official start and properly outlined of the joint venture between AT&T and Girls in Tech. Girls in Tech has not attempted an event of this type before let alone this scale, so the risk management plan is imperative to help protect all of the stakeholders. Micro Cost Estimate Two of the WBS work packages with the costliest deliverables were used for the micro cost estimate, plan meals and plan equipment. WBS package estimate pricing based on Palms Resort catering and A/V pricing list as of October 2014. Pricing is subject to change before final decisions are made. Some of the equipment needed is included in the catering packages and discounted rates may be negotiated down due to the non-profit status of the event. Breaking these packages down you can get a very accurate cost of these two of the most costly portions of the Design-a-thon The analogous and the micro estimate are very different; the food and beverage estimate is off by almost $100,000.00. Upon further research, we would find that the total event cost
  • 8. Girls in Tech Design-a-Thon 8 would be extremely off as well. Chou & Tseng stated “Even when activities in two projects are similar, different backgrounds and environments including technology used and materials or equipment can easily result in estimates that differ considerably.” (2011, p. 641) For an event of this size with the requirements of the sponsor, we have learned that the projects used in the analogous estimation were not necessarily appropriate or the multiplier was not accurate. A better comparison would have been previous hackathons sponsored by major companies. Though Henry, McCray, Purvis, & Roberts determined that “analogous estimating is less useful in diverse and complex projects,” (2007, p. 607) so this may not even be the right choice for this project. Had Girls in Tech not been offered a major sponsorship with the location requirement, the macro estimate would have more accurate. Doing a quick food & beverage cost estimate from Jason’s Deli, one of the original catering considered, proves this to be. This project at its current course is impossible without the full sponsorship of AT&T. Girls in Tech should consider the risks of AT&T pulling out before moving forward and signing any guarantees on the project. Monitoring, Controlling and Execution Planning of the design-a-thon is imperative but the execution of the activities will be what makes or breaks the project. Monitoring and controlling using the network diagram managed in MS Project will make all of the different variables easier to see the effects changes made will have on the entire project. Communications management is also important to this particular project, most of the work being completed on a volunteer basis and much of the communications and “meetings’” will be conducted virtually.
  • 9. Girls in Tech Design-a-Thon 9 Monitoring of the project should be considered from at least two points, the closing date of the project as a whole and the all activities from start through a week before the event start date. The value of the activities a week before the event start date and earlier have more meaning to the status of the earned value of the event and variances in what is planned and what produced will have more of an effect than including the activities that run through the event. Recommendations Recommendations are from a general analysis of the project, Girls in Tech perspective and goals; and what AT&T publically has announced as their hackathon goals and what they have made know to Girls in Tech as of this date. The joint venture is an excellent way to spread the risk throughout the project. However, “parties who enter into joint ventures without knowing and fully understanding the implications of their actions, would certainly encounter later problems.” (Norwood & Mansfield, 1999, p. 89) I recommend that it be formalized and the requirements of each team be specifically outlined as soon as possible so that the project can commence. There is risk of misunderstanding if this is not done prior to starting of the project that can lead to stakeholder dissatisfaction. This could impede future projects of this kind or even stop the project before completion. If the project is started and announced then canceled, it could lead to additional stakeholder unhappiness, via the attendees, who may lose money for their travel expenses and bad public relations for AT&T or Girls in Tech. Once the joint venture is solidified, the scope should be edited to include a budget and a more detailed outline of all other sections of the scope. Currently, a large amount of scope creep is expected in this project. It can be managed by including the expertise of AT&T in the final scope document as well as implementing a change process that considers the priority matrix and will it help the end goal of the project and increase the three main stakeholder’s satisfaction with
  • 10. Girls in Tech Design-a-Thon 10 the project. The production stakeholders need to realize that, “the larger the scale of an event project the more likely the scope creep and higher the price tag of the event.” (Jennings, 2012) Even though cost will be enhanced to improve the project, it is not an unlimited resource. To get an accurate estimate prior to the commencement of work, AT&T and Girls in Tech need to average the other hackathon events that AT&T has completed in Las Vegas, Nevada in order to mitigate the risk of using an analogous estimate that is not as accurate. In addition, expert consultation of the risk management plan needs to be done in order to ensure that it is as inclusive as possible. Research shows that events of this type need at least three months planning and execution time. Currently the time allotted for this event has gone down to 2.5 months and it is during major holiday season. Leading to less time for the project to me worked on and the volunteers will need to dedicate more structured time to complete activities or decrease the scope of the design-a-thon.
  • 11. Girls in Tech Design-a-Thon 11 Appendix 1 References Amsterdam Hackathon 2013/Budget - MediaWiki. (2014, July 28). Retrieved October 3, 2014, from https://www.mediawiki.org/wiki/Amsterdam_Hackathon_2013/Budget Chou, J., & Tseng, H. (2011). Establishing expert system for prediction based on the project- oriented data warehouse. Expert Systems With Applications, 38(1), 640–651. doi:10.1016/j.eswa.2010.07.015 Donn, A. (n.d.). Alex Donn (AT&T Developer Program) - Eventbrite. Retrieved October 3, 2014, from http://www.eventbrite.com/o/alex-donn-atampt-developer-program- 1153839733?s=23092423 Feig, E. J. (2014, August). How to run a hackathon. - RecursiveRobot | E. John Feig. Retrieved from http://www.recursiverobot.com/post/91272128309/how-to-run-a-hackathon Feig, E. J. (2014, August). The Story - Hackathon - RecursiveRobot | E. John Feig. Retrieved from http://www.recursiverobot.com/post/90565633684/the-story-hackathon Food & Beverage Catering-How to calculate quantities to order. Planning Helper. (2011). Retrieved from http://www.planninghelper.com/spv-245.aspx Get Hacking!. (2014). HR Magazine, 59(5), 47-49. Greiman, V., & Warburton, R. (2014, September 2). Introduction to Projects. Retrieved September 20, 2014. Gulrajani, I. (2014, June 23). The Hackathon Budget — Hackers and Hacking — Medium. Retrieved from https://medium.com/hackers-and-hacking/the-hackathon-budget- d636b5b2ed6c HACKMIT - Oct 4-5. (2014). Retrieved October 3, 2014, from https://hackmit.org/
  • 12. Girls in Tech Design-a-Thon 12 Henry, R. M., McCray, G. E., Purvis, R. L., & Roberts, T. L. (2007). Exploiting organizational knowledge in developing IS project cost and schedule estimates: An empirical study. Information & Management, 44(6), 598–612. doi:10.1016/j.im.2007.06.002 Hillson, D., Grimaldi, S., & Rafele, C. (2006). Managing Project Risks Using a Cross Risk Breakdown Matrix. Risk Management. doi:10.1057/palgrave.rm.8250004 How to Run a Hackathon. (2014). Retrieved from www.socrata.com/open-data-field-guide/how- to-run-a-hackathon/ Jason's Deli Online Ordering. (n.d.). Retrieved October 5, 2014, from https://online.jasonsdeli.com/jasonsdeli/web/default.aspx?tab=home Meetings. (2014). Retrieved October 3, 2014, from http://www.palms.com/business- groups/meetings Peachey, B., Evitts, R., & Hill, G. (2007). Project Management for Chemical Engineers. Education for Chemical Engineers, 2(1), 14-19. doi:10.1205/ece06019 Phillips, M. (2011, August 11). A Cost/Benefit Analysis of the Ripple Hackathon. Retrieved from http://www.themarkphillips.com/2011/08/09/A-Cost-Benefit-Analysis-of-the-Ruby- Hackathon.html Shearman, S., & Barnes, R. (2012). Time to hack your brand. (cover story). Marketing (00253650), 10-13. TA Group: A Holding Company. (n.d.). Retrieved from http://tagroupholdings.com/news_items/23 Tao, E. (201, March 31). Hackathon Planning In Less Than 10 Steps | TechCrunch. Retrieved from http://techcrunch.com/2012/03/31/hackathon-planning/
  • 13. Girls in Tech Design-a-Thon 13 Warburton, R., & Kanabar, V. (2013). The Art and Science of Project Management (2nd ed.). Newport, RI: RW-Press. Zürich Hackathon 2014/Budget - MediaWiki. (2014, July 28). Retrieved October 3, 2014, from https://www.mediawiki.org/wiki/Z%C3%BCrich_Hackathon_2014/Budget
  • 14. Girls in Tech Design-a-Thon 14 Appendix 2 Scope Statement Objective: To organize a Design-a-Thon to encourage women to participate product and solution design in January. Justification: To further Girls in Tech’s mission of inspiring and leading women in being entrepreneurial and innovative. Deliverables and Milestones: DELIVERABLE OR MILESTONE DATE DUE COST ESTIMATE September 22, 2014 MARKETING PLAN September 29, 2014 MARKETING PLAN EXECUTION On Going from September 29, 2014 - January 7, 2015 SPEAKER CONFIRMATIONS October 27, 2014 EVENT EQUIPMENT LIST November 3, 2014 EVENT PLANS AND LOGISTICS November 10, 2014 EVENT MENU November 24, 2014 VOLUNTEER AND SPEAKER BAG December 8, 2014 PARTICIPANT BAG December 15, 2014 FINAL PREPARATION AND COUNT FOR EVENT December 22 ,2014 DAY 1 January 2, 2015 DAY 2 January 3, 2015 DAY 3 January 4, 2015 POST EVENT SURVEY January 7, 2015 Specification:
  • 15. Girls in Tech Design-a-Thon 15 Theme: Designing a Better Tomorrow – Teams of about 10 participants are to identify a problem in their community that needs a solution and then design a product/solution to solve that problem Location: Palms Las Vegas Resort and Convention Center Event Dates: Friday January 2 - Sunday January 4, 2015 Category Requirement Stakeholder Product Registration Packet GiT Planning Keynote Speakers – At least 2 GiT Planning Event Schedule and Logistics Plan GiT Food Kickoff Event Food and Beverage GiT Food Saturday & Sunday Breakfast, Lunch, Dinner and Snacks Food and Beverage GiT Planning Breakout Speakers – At least 6 GiT Event Management Volunteers GiT Planning Experts GiT Planning Judges GiT Product Post Event Survey GiT Planning Marketing and PR Christina/Melissa Product Prizes GiT Planning Breakout Session Entertainment GiT Planning Event Equipment GiT & Palms Planning TED talk Video Curation GiT Funding Preliminary Funding AT&T & GiT Funding Additional Funding GiT Product Event Shirts Amber Product Participant Swag Bag GiT Product Speaker and Volunteer thank you bags GiT
  • 16. Girls in Tech Design-a-Thon 16 Risks: Alcohol consumption by underage attendees Equipment and supplies may not arrive on time. People may become extremely tired or sick over long days Limits and Exclusions: The location will have requirements for use of the venue. Constraints: Schedule: Event must occur the weekend of January 2, 2015 The Palms Resort and Casino must provide food, beverage and most of the A/V equipment SCOPE SCHEDULE COST CONSTRAIN X ENHANCE X ACCEPT X Assumptions: AT&T to Supply: Location, food and drinks, paper/pens, markers/whiteboards, posterboard/paint, Wi-Fi, prototyping equipment (5 3D printers for teams to print out their designs for final presentations, and/or a “trial” version of Sketchup/Solidworks/etc so they can present the framework of a design), funds needed for speakers equipment and other entertainment. Attendant to Supply: Laptop Girls in Tech to Supply: Event Management and Volunteers
  • 17. Girls in Tech Design-a-Thon 17 Technical Requirements: All dietary restrictions must be accommodated and 50% of food and beverage offerings must be healthy Review of Deliverables: Monthly Girls in Tech Meetings, Meetings with AT&T as needed
  • 18. Girls in Tech Design-a-Thon 18 Appendix 4 Work Breakdown Structure 0. Design-a-thon 1. Do Project Management 2. Do Event Management 2.1 Manage Day 1 1. Perform Registration 2. Serve Dinner 3. Do Welcome 4. Make Teams 2.2 Manage Day 2 2.2.1. Serve Meals 2.2.2. Do Breakouts 2.2.3. Facilitate teams 2.3 Manage Day 3 2.3.1. Serve Meals 2.3.2. Do Breakouts 2.3.3. Facilitate teams 2.3.4. Facilitate Judging 2.3.5. Present winners and closing 2.4 Direct Event Setup 2.4.1. Get Pre Event Count 2.4.2. Direct Volunteers and Venue Staff for Event Setup
  • 19. Girls in Tech Design-a-Thon 19 2.5 Do Event Closing Activities 2.5.1. Get Final Event Count 2.5.2. Send Event Survey 2.5.3. Direct Volunteers for Cleanup and collection of GiT belongings 2.5.4. Get Feedback from Event Donors and Volunteers 3. Plan Event 3.1 Develop Cost Estimate 1. Give AT&T Cost 2. Determine if Additional funding is needed 3.2 Plan Menus – Breakfast, lunch, dinner and snacks for Saturday and Sunday, Kickoff event dinner 3.2.1. Sign Contracts with Palms and AT&T 3.2.2. Develop plan for service alcohol during event kickoff and closing event 3.3 Plan Equipment List 3.3.1. Separate Palms Equipment List 3.3.2. Find items required not available at the Palms 3.4 Set up Event and Logistics Plan 3.4.1. Get volunteers 3.5 Plan Activities 3.5.1. Select Speakers a. Give Breakout Speakers Session time
  • 20. Girls in Tech Design-a-Thon 20 b. Give Opening Speakers Event time c. Give Closing Speakers Event time 3.5.2. Select Judges 3.5.2.1. Give Judges Event time 3.5.3. Select Breakout activities 3.5.4. Select ongoing event activities 3.5.4.1. TEDtalk curation 3.5.5. Select Experts 4. Do Marketing 4.1 Set up Social Media 4.2 Contact CES to be listed in events 4.3 Do Press Release 4.4 Do Online Promotion 1. Set up Event website 4.5 Do Networking Promotion 5. Arrange Event 5.1 Make Bags 1. Have Shirts Made 2. Get donated items for bags 5.2 Make Registration Packet 5.3 Create Post Event Survey 5.4 Organize Prizes 5.4.1. Get Donated prizes from vendors
  • 21. Girls in Tech Design-a-Thon 21 5.4.2. Write prize letter for Prizes 5.4.3. Put together prize packets
  • 22. Girls in Tech Design-a-Thon 22 Appendix 5 Preliminary Network Diagram
  • 23. Girls in Tech Design-a-Thon 23 Appendix 6 Preliminary Network Diagram List Activity Description Predecessor Duration (Hours) A Manage Day 1 E 5 A1 Do Registration A 2 A2 Serve Dinner A 1 A3 Do Welcome A 1 A4 Make Teams A 1 B Manage Day 2 A1, A2, A3, A4 16 B1 Serve Meals B 4 B2 Do Breakouts B 3.5 B3 Facilitate teams B 8.5 C Manage Day 3 B1, B2, B3 14 C1 Serve Meals C 4 C2 Do Breakouts C 1 C3 Facilitate teams C 7 C4 Facilitate Judging C 1 C5 Present winners and closing C 1 D Get Pre Event Count S 1 E Direct Volunteers and Venue Staff for Event Setup 2 F Get Final Event Count C1, C2, C3, C4, C5 1 G Send Event Survey H 1 H Direct Volunteers for Cleanup and collection of GiT belongings F 1 I Get Feedback from Event Donors and Volunteers H 2 J Develop Cost Estimate NONE 2 K Give AT&T Cost J 1 L Determine if Additional funding is needed K 1 M Plan Menus – Breakfast, lunch, dinner and snacks for Saturday and Sunday, Kickoff event dinner N 2 N Sign Contracts with Palms and AT&T K 1
  • 24. Girls in Tech Design-a-Thon 24 O Develop plan for service alcohol during event kickoff and closing event N 1 P Plan Equipment List N, U, AA, BB 2 Q Give list to the Palms P 1 R Find items required no available at the Palms Q 4 S Set up Event and Logistics Plan R, Y, DD 8 T Get volunteers S 8 U Select Speakers NONE 16 V Give Breakout Speakers Session time S .5 W Give Opening Speakers Event time S .5 X Give Closing Speakers Event time S .5 Y Select Judges NONE 8 Z Give Judges Event time S .5 AA Select Breakout activities L 2 BB Select ongoing event activities L 1 CC TEDtalk curation L 8 DD Select Experts NONE 16 EE Make Bags HH, FF 13 FF Have Shirts Made L 4 HH Get donated items for bags L 8 II Make Registration Packet K 3 JJ Create Post Event Survey NONE 2 KK Get Donated prizes from vendors L 8 LL Write prize letter for Prizes KK 1 MM Put together prize packets LL 1 NN Set up Social Media L 8 OO Contact CES to be listed in events L 8 PP Do Press Release L 4 QQ Do Online Promotion L 8 RR Set up Event website L 2 SS Do Networking Promotion L 36
  • 25. Girls in Tech Design-a-Thon 25
  • 26. Girls in Tech Design-a-Thon 26 Appendix 7 Macro Estimate Method Used: Analogous Pre-I/O Google Glass Hackathon – 24 Hour Event Number of Participants Food & Bev Costs Equipment Costs Total Event Cost 91 $1037.90 $3507.65 $9500.00 F&B per Person: 11.41 Equipment per Person: $38.55 Event per Person: $104.40 F&B PP/PH: 0.13 Equipment PP/PH: $1.61 Event PP/PH: $4.35 HackMIT – 24 Hour Event Number of Participants Food & Bev Costs Equipment Costs Total Event Cost 1050 $40,000.00 $27,000.00 $250,000.00 F&B per Person: $38.10 F&B PP/PH: $1.59 Equipment per Person: $25.71 Equipment PP/PH: $1.07 Event per Person: $238.10 Event PP/PH: $9.92 Zürich Hackathon 2014 – 46 Hour Event Number of Participants Food & Bev Costs Equipment Costs Total Event Cost 208 $33,195.66 $830.80 $46,441.63 F&B per Person: $159.59 F&B PP/PH: $3.47 Equipment per Person: $3.99 Equipment PP/PH: $0.09 Event per Person: $223.28 Event PP/PH: $4.85 Amsterdam Hackathon 2013 -30 Hour Event Number of Participants Food & Bev Costs Equipment Costs Total Event Cost 149 € 20,055.00 € 242,48 €41,324.13 F&B per Person: €134.60 / $168.45 Equipment per Person: €1.62 / $2.03 Event per Person: €277.34 / $347.09 F&B PP/PH: $5.62 Equipment PP/PH: 0.07 Event PP/PH: $11.57
  • 27. Girls in Tech Design-a-Thon MS 27 Average Food and Beverage Cost per Person per Hour: $2.70 Average Equipment per Person per Hour: $0.71 Average Event per Person per Hour: $7.67 GiT Design-a-thon Hours Estimate – 24 GiT Design-a-thon Participant Estimate – 200 Multiplier – 1.5 Equipment Multiplier - F&B = p * h* $2.70(m) $19,440.00 Food and Beverage E = p * h * $0.71(m) $5,112.00 Equipment D = p * h * $7.67(m) $55,224.00 Design-a-thon
  • 28. Girls in Tech Design-a-Thon MS 28 Appendix 8 Micro Estimate Work Package Estimate Project Title GiT Design-a-Thon Work Package Title WBS Code Separate Palms Equipment List 3.3.1 Deliverable Description of Work: Equipment List Select Equiptment needed from the Palms Activity/Cost Item Resource Duration (days) Labor (hrs) Rate Units Unit Cost Total Menu Planning & Consultation Volunteer 2.00 2.00 $0.00 $0.00 TV Equiptment 3.00 1.00 $425.00 $1,275.00 Wireless Microphone Equiptment 3.00 1.00 $185.00 $555.00 Printer Equiptment 2.00 1.00 $175.00 $350.00 Laser Pointer Equiptment 1.00 1.00 $55.00 $55.00 Slide Advacer Equiptment 3.00 1.00 $55.00 $165.00 Easel for Signage Equiptment 3.00 3.00 $20.00 $180.00 Powerstrips Equiptment 2.00 45.00 $30.00 $2,700.00 Draping Equiptment 4.00 $190.00 $760.00 Labor 2.00 1.00 $83.00 $166.00 Fee 21.00% $1,268.40 Total Cost $7,474.40
  • 29. Girls in Tech Design-a-Thon MS 29 Work Package Estimate Project Title GiT Design-a-Thon Work Package Title WBS Code Plan Menus 3.2 Deliverable Description of Work: Event Menus & Pricing Select menus for all meal Activity/Cost Item Resource Duration (days) Labor (hrs) Rate Units Unit Cost Total Menu Planning & Consultation Volunteer 2.00 2.00 $0.00 $0.00 Opening Reception F&B 1.00 200.00 $70.00 $14,000.00 Breakfast F&B 2.00 200.00 $26.00 $10,400.00 Lunch F&B 2.00 200.00 $36.00 $14,400.00 Dinner F&B 1.00 200.00 $65.00 $13,000.00 Snack F&B 2.00 200.00 $15.00 $6,000.00 Snack F&B 2.00 200.00 $20.00 $8,000.00 Closing Reception Food Displays F&B 1.00 3.00 $2,400.00 $7,200.00 Closing Reception Beverage F&B 1.00 2.00 250.00 $10.00 $5,000.00 Closing Reception Bartender F&B 1.00 4.00 $175.00 $700.00 Coffee F&B 2.00 22.00 $66.00 $2,904.00 Energy Drinks F&B 2.00 200.00 $7.00 $2,800.00 Water F&B 2.00 400.00 $5.00 $4,000.00 Whole Fruit F&B 2.00 16.00 $42.00 $1,344.00 Chips F&B 2.00 200.00 $3.50 $1,400.00 Tax 8.10% $7,382.99 Service fee 21.00% $19,141.08 Total Cost $117,672.07
  • 30. Girls in Tech Design-a-Thon MS 30 Appendix 9 Risk Management Plan Risk Response Pull back of budget from AT&T Obtain clearly defined budget in joint venture agreement. Dropping of sponsorship by AT&T Have joint venture agreement include a penalty for dropping sponsorship after public announcement and only us AT&T as guarantees for contracts Small participant count Frequently communicate with venue the participant count to ensure space is not over allocated or event space can be combined with space of AT&T concurrent hack-a-thon Lack of volunteers Enlist Girls in Tech family and friends, and AT&T staff to assist with event facilitation Travel delays of judges or presenters Create a plan of secondary people that can be obtained at last minute and activities that can be run by volunteers Inability of venue to provide healthy food options Communicate with venue to ensure options can be obtained, if not ask for allowances to bring in outside food. Girls in Tech volunteers unable to complete planning and preparation tasks by deadlines Have regular team meetings and communications to the status of activities Pull out of prize sponsors Do not announce specifics of prizes without written confirmation of prize sponsor Not enough food provided Work with venue to prepare for last minute additions and estimate food needs based on previous similar events held at the venue Event equipment not set up on time Consult and communicate with equipment vendor and venue to ensure equipment is set up a day prior to event starting. Weak Wi-Fi Request Wi-Fi extenders and have access to additional should they be needed Unsecure Wi-Fi Recommend participants using Wi-Fi take proper person security methods on their devices Delay of “product” for gift bags Have “product” sent one month prior to event. Lack of response from post event survey Require feedback during event prior to awards ceremony Not enough product for gift bags Do not announce participant gift bags, and use what has been obtained for surprise prizes Participant or Volunteer becomes ill during event Make sure all volunteers and staff have emergency contact card.
  • 31. Girls in Tech Design-a-Thon MS 31 Venue not prepared for number of participants Frequently communicate with venue the participant count to ensure space is properly allocated and put a limit on the number participants Schedule too tight to complete tasks needed to properly manage event Removal of deliverables to lower time needed to complete planning. Lack of communication between Girls in Tech and AT&T Schedule bi-weekly calls and regular email with AT&T and Girls in Tech for status reviews and rapid request for assistance when needed
  • 32. Girls in Tech Design-a-Thon MS 32 Appendix 10 Final Network Task List Task Number Task Name Duration Start Finish Predecessors 23 Develop Cost Estimate 2 hrs Wed 10/15/14 Wed 10/15/14 24 Give AT&T Cost 1 hr Wed 10/15/14 Wed 10/15/14 23 25 Determine if Additional funding is needed 1 hr Wed 10/15/14 Wed 10/15/14 24 27 Sign Contracts with Palms and AT&T 1 hr Wed 10/15/14 Wed 10/15/14 24 52 Set up Social Media 32 hrs Wed 10/15/14 Thu 10/16/14 25 56 Set up Event website 2 hrs Wed 10/15/14 Wed 10/15/14 25 40 Select Breakout activities 2 hrs Wed 10/15/14 Wed 10/15/14 25 38 Select Judges 8 hrs Thu 10/16/14 Thu 10/16/14 53 Contact CES to be listed in events 16 hrs Thu 10/16/14 Fri 10/17/14 25 34 Select Speakers 16 hrs Fri 10/17/14 Mon 10/20/14 54 Do Press Release 4 hrs Fri 10/17/14 Fri 10/17/14 25 28 Develop plan for service alcohol during event kickoff and closing event 1 hr Mon 10/20/14 Mon 10/20/14 27 43 Select Experts 16 hrs Mon 10/20/14 Tue 10/21/14 55 Do Online Promotion 32 hrs Mon 10/20/14 Tue 10/21/14 25 57 Do Networking Promotion 36 hrs? Tue 10/21/14 Wed 10/22/14 25 26 Plan Menus – Breakfast, lunch, dinner and snacks for Saturday and Sunday, Kickoff event dinner 2 hrs Wed 10/22/14 Wed 10/22/14 27
  • 33. Girls in Tech Design-a-Thon MS 33 41 Select ongoing event activities 1 hr Thu 10/23/14 Thu 10/23/14 25 29 Plan Equipment List 2 hrs Fri 10/24/14 Fri 10/24/14 27,34,40,41 30 Give list to the Palms 1 hr Fri 10/24/14 Fri 10/24/14 29 31 Find items required no available at the Palms 4 hrs Fri 10/24/14 Fri 10/24/14 30 32 Set up Event and Logistics Plan 8 hrs Fri 10/24/14 Mon 10/27/14 31,38,43 35 Give Breakout Speakers Session time 0.5 hrs Mon 10/27/14 Mon 10/27/14 32 36 Give Opening Speakers Event time 0.5 hrs Mon 10/27/14 Mon 10/27/14 32 37 Give Closing Speakers Event time 0.5 hrs Mon 10/27/14 Mon 10/27/14 32 39 Give Judges Event time 0.5 hrs Mon 10/27/14 Mon 10/27/14 32 33 Get volunteers 8 hrs Mon 11/3/14 Mon 11/3/14 32 45 Have Shirts Made 4 hrs Mon 11/17/14 Mon 11/17/14 25 46 Get donated items for bags 8 hrs Tue 11/18/14 Tue 11/18/14 25 42 TEDtalk curation 8 hrs Tue 12/2/14 Tue 12/2/14 25 49 Get Donated prizes from vendors 8 hrs Wed 12/10/14 Wed 12/10/14 25 50 Write prize letter for Prizes 1 hr Thu 12/11/14 Thu 12/11/14 49 44 Make Bags 13 hrs Mon 12/15/14 Tue 12/16/14 46,45 47 Make Registration Packet 3 hrs Wed 12/17/14 Wed 12/17/14 24 51 Put together prize packets 1 hr Thu 12/18/14 Thu 12/18/14 50 48 Create Post Event Survey 2 hrs Fri 12/19/14 Fri 12/19/14 17 Get Pre Event Count 8 hrs Fri 12/26/14 Fri 12/26/14 32
  • 34. Girls in Tech Design-a-Thon MS 34 1 Day 1 0.8 days Fri 1/2/15 Fri 1/2/15 36,39,35,28,37,26,48,47,51,44, 57,55,53,52,54,42,56,33,17 2 Direct Volunteers and Venue Staff for Event Setup 2 hrs Fri 1/2/15 Fri 1/2/15 1FS-8 hrs 3 Perform Registration 4 hrs Fri 1/2/15 Fri 1/2/15 2 4 Serve Dinner 1 hr Fri 1/2/15 Fri 1/2/15 3 5 Present Welcome 1 hr Fri 1/2/15 Fri 1/2/15 4 6 Make Teams 1 hr Fri 1/2/15 Fri 1/2/15 5 7 Day 2 0.8 days Sat 1/3/15 Sat 1/3/15 6 8 Serve Meals 4 hrs Sat 1/3/15 Sat 1/3/15 7FS-8 hrs 9 Do Breakouts 3.5 hrs Sat 1/3/15 Sat 1/3/15 7FS-8 hrs 10 Facilitate teams 8 hrs Sat 1/3/15 Sat 1/3/15 7FS-8 hrs 11 Day 3 0.8 days Sun 1/4/15 Sun 1/4/15 8,9,10 12 Serve Meals 4 hrs Sun 1/4/15 Sun 1/4/15 11FS-8 hrs 13 Do Breakouts 1 hr Sun 1/4/15 Sun 1/4/15 11FS-8 hrs 14 Facilitate teams 7 hrs Sun 1/4/15 Sun 1/4/15 11FS-8 hrs 15 Facilitate Judging 1 hr Sun 1/4/15 Sun 1/4/15 14,12,13 16 Present winners and closing 1 hr Sun 1/4/15 Sun 1/4/15 15 18 Get Final Event Count 1 hr Sun 1/4/15 Sun 1/4/15 16 21 Direct Volunteers for Cleanup and collection of GiT belongings 1 hr Sun 1/4/15 Sun 1/4/15 18 19 Send Event Survey 1 hr Mon 1/5/15 Mon 1/5/15 21 22 Get Feedback from Event Donors and Volunteers 2 hrs Mon 1/5/15 Mon 1/5/15 21 20 Event Review Meeting 2 hrs Sun 1/18/15 Sun 1/18/15 19,22
  • 35. Girls in Tech Design-a-Thon MS 35 Appendix 11 Final Network Diagram See Attachment