project team
Developer/Owner:
Sasol/Royal Haskoning Dordtse
Engineering
Architect:
Walker Smith Architects
Structural Engineer:
BKS (Pty) Ltd
Quantity Surveyor:
Royal Haskoning
Project Manager:
BKS
Main Contractor:
Haskoning International BV
Steelwork Contractor:
Imbabala/Van Staden Engineering
MEERKAT II –
FT3 BUILDING
Exacting quality assurance and
safety requirements together
with specialist requirements for
corrosion protection are a part
of the challenge of constructing
this great example of an
industrial project.
PROJECTS
32 Steel Construction Vol. 34 No. 4 July 2010
Sasol continues to develop chemical plants to beneficiate and modify by-prod-
ucts from their plants into commercial specialist products.
Steel structures to support a myriad of equipment and piping are the order of
the day. But only those involved in such projects recognise the effort and plan-
ning that goes into this type of project such as pausing the steel erection to
allow for the plant installation.
Exacting quality assurance and safety requirements together with specialist
requirements for corrosion protection are a part of the challenge of construct-
ing this great example of an industrial project.
Steel was the main component and was used due to the ease and speed of erec-
tion and practicality of building around the process. The primary 24m x 18m x
27m high structure went up in under three months using 555 tons of steel.
The main challenge in this interesting project was to replicate an existing
building and process plant in Europe here in Sasolburg where harsh local
climatic conditions had to be taken into account. The BKS-Royal Haskoning
Partnership had to design to South African standards based on the original
European design standard – bringing together European and South African
The structure had to be built according to SA standards interpreting the Eurocode.
The structure went up in three months using 555 tons of steel.
PROJECTS
Steel Construction Vol. 34 No. 4 July 2010 33
thinking to recreate this unique building and process. The Joint Venture
recreated the building to replicate the process under significantly different
local conditions, seamlessly.
Throughout the phased erection, staged compliance checks and certification had
to take place at different points due to vessels being brought in and the instal-
lation of process equipment.
A significant number of steel section sizes had to be created out of plate in
South Africa. This implied that built up sections were manufactured to match
large European rolled sections which do not exist locally. A typical built-up
section was 437 x 412 x 505kg/m with a flange thickness of 50mm.
The cladding is a special feature in that it is a sandwich panel, made up of steel
sheeting inside and out with thermal insulation inside. The massive panels span
six metres horizontally between columns, with no intermediate support. Multi-
level flooring consisted of Q-Deck for the composite or Rectagrid for grated
flooring.
The value of this project was in creating a process which forms the catalyst for
creating a Sasol-patented process of making liquid fuel from gas.
The process vessels on the structure had to be hydro-tested in situ. This meant that
the structural members had to be designed for temporary loading far exceeding the
final design load for accommodating the requirements of a gas plant.
The cladding is a sandwich panel – steel sheeting
the bread and thermal insulation the ham.
Some of the difficulties experienced by the steel-
work fabricators and erectors were a very tight
programme. In addition to this, the structure had
to be erected involving the interface with the
installation of mechanical equipment. Steel erec-
tion took place around some of the larger process
equipment due to the sheer size of it.

More Related Content

PPT
Catalogue for steel structures
PPTX
Custom metal fabrication steel bins, silos and tanks
PPTX
Custom Metal Fabricated Industrial Ducts
PPTX
Custom Fabricated Carts & Totes
PPSX
Plasticon Composites - Non-corosive products for the Power market
PPTX
Product and Market research of steel pipe and tube industry
PPTX
Product and Market Research of Steel Pipe and Tube Industry
PPTX
Lubrication & Metalworking Fluid Performance in the Machining of Ferrous Meta...
Catalogue for steel structures
Custom metal fabrication steel bins, silos and tanks
Custom Metal Fabricated Industrial Ducts
Custom Fabricated Carts & Totes
Plasticon Composites - Non-corosive products for the Power market
Product and Market research of steel pipe and tube industry
Product and Market Research of Steel Pipe and Tube Industry
Lubrication & Metalworking Fluid Performance in the Machining of Ferrous Meta...

What's hot (20)

PDF
GALM Constellium - UACJ - 081016
PDF
Advance section properties_for_students
PPSX
2009 Khaya Presentation
PDF
Refratechnik Burton | Refractory Systems from the Global Market Leader
PDF
The essential contribution of recycling in a sustainable aluminium value chai...
PPTX
Prefabricated structures noida
PDF
Evolution Shotcrete brochure
PDF
REFRA-Rig II - The Complete Installation System
PDF
Akiet casings for anti-corrosion applications - Imperial (Fred Nilson's confl...
PDF
Surtreat Construction Services -SOQ January 2015
DOCX
Pre engg buildings
PDF
SCS -SOQ January 2015 II
DOCX
96382022 pre-engineered-buildings
PDF
The-Shard
PDF
2015 Foundations for larger and deeper Offshore Wind
PPTX
Introduction of Prefabricated structures
PDF
Morocco Mall Post Tensioned Concrete Case Study
PPTX
Steel frame work
PPTX
Prefabricated construction systems in India- Precast Status and needed Impetus
PPT
Hemp Lime Concrete (HLC): A carbon-negative construction material
GALM Constellium - UACJ - 081016
Advance section properties_for_students
2009 Khaya Presentation
Refratechnik Burton | Refractory Systems from the Global Market Leader
The essential contribution of recycling in a sustainable aluminium value chai...
Prefabricated structures noida
Evolution Shotcrete brochure
REFRA-Rig II - The Complete Installation System
Akiet casings for anti-corrosion applications - Imperial (Fred Nilson's confl...
Surtreat Construction Services -SOQ January 2015
Pre engg buildings
SCS -SOQ January 2015 II
96382022 pre-engineered-buildings
The-Shard
2015 Foundations for larger and deeper Offshore Wind
Introduction of Prefabricated structures
Morocco Mall Post Tensioned Concrete Case Study
Steel frame work
Prefabricated construction systems in India- Precast Status and needed Impetus
Hemp Lime Concrete (HLC): A carbon-negative construction material
Ad

Viewers also liked (20)

PDF
PPT
FocalPoint_BusinessCoaching_Overview_BPumphrey 2015-0921
PDF
Cuestionario
PPTX
токтра даурен таксопарк
PPTX
токтар доставка
PPTX
Metodologia bruno munari- trabajo escrito de tecnologia
PPTX
Unit 4 lesson 1
PPTX
Virus Informaticos
PPTX
Groen2012 analytics
PPTX
Green Label - We Are Blood After-Party Recap_FINAL_Compressed
DOCX
Aventuras del-pensamiento
PDF
Diseño ident autor
PDF
Comex report-daily 19 march
PDF
Test
PPTX
Lesson three
PPTX
Gasteizko irteera 2B KIRIKO
PPTX
Fine Art
PDF
Презентация Минэка - Про проект перечня госуслуг (1 июня 2010)
PDF
Politicas alimentarias
POT
FocalPoint_BusinessCoaching_Overview_BPumphrey 2015-0921
Cuestionario
токтра даурен таксопарк
токтар доставка
Metodologia bruno munari- trabajo escrito de tecnologia
Unit 4 lesson 1
Virus Informaticos
Groen2012 analytics
Green Label - We Are Blood After-Party Recap_FINAL_Compressed
Aventuras del-pensamiento
Diseño ident autor
Comex report-daily 19 march
Test
Lesson three
Gasteizko irteera 2B KIRIKO
Fine Art
Презентация Минэка - Про проект перечня госуслуг (1 июня 2010)
Politicas alimentarias
Ad

Projects MeerkatII Copy

  • 1. project team Developer/Owner: Sasol/Royal Haskoning Dordtse Engineering Architect: Walker Smith Architects Structural Engineer: BKS (Pty) Ltd Quantity Surveyor: Royal Haskoning Project Manager: BKS Main Contractor: Haskoning International BV Steelwork Contractor: Imbabala/Van Staden Engineering MEERKAT II – FT3 BUILDING Exacting quality assurance and safety requirements together with specialist requirements for corrosion protection are a part of the challenge of constructing this great example of an industrial project. PROJECTS 32 Steel Construction Vol. 34 No. 4 July 2010 Sasol continues to develop chemical plants to beneficiate and modify by-prod- ucts from their plants into commercial specialist products. Steel structures to support a myriad of equipment and piping are the order of the day. But only those involved in such projects recognise the effort and plan- ning that goes into this type of project such as pausing the steel erection to allow for the plant installation. Exacting quality assurance and safety requirements together with specialist requirements for corrosion protection are a part of the challenge of construct- ing this great example of an industrial project. Steel was the main component and was used due to the ease and speed of erec- tion and practicality of building around the process. The primary 24m x 18m x 27m high structure went up in under three months using 555 tons of steel. The main challenge in this interesting project was to replicate an existing building and process plant in Europe here in Sasolburg where harsh local climatic conditions had to be taken into account. The BKS-Royal Haskoning Partnership had to design to South African standards based on the original European design standard – bringing together European and South African The structure had to be built according to SA standards interpreting the Eurocode. The structure went up in three months using 555 tons of steel.
  • 2. PROJECTS Steel Construction Vol. 34 No. 4 July 2010 33 thinking to recreate this unique building and process. The Joint Venture recreated the building to replicate the process under significantly different local conditions, seamlessly. Throughout the phased erection, staged compliance checks and certification had to take place at different points due to vessels being brought in and the instal- lation of process equipment. A significant number of steel section sizes had to be created out of plate in South Africa. This implied that built up sections were manufactured to match large European rolled sections which do not exist locally. A typical built-up section was 437 x 412 x 505kg/m with a flange thickness of 50mm. The cladding is a special feature in that it is a sandwich panel, made up of steel sheeting inside and out with thermal insulation inside. The massive panels span six metres horizontally between columns, with no intermediate support. Multi- level flooring consisted of Q-Deck for the composite or Rectagrid for grated flooring. The value of this project was in creating a process which forms the catalyst for creating a Sasol-patented process of making liquid fuel from gas. The process vessels on the structure had to be hydro-tested in situ. This meant that the structural members had to be designed for temporary loading far exceeding the final design load for accommodating the requirements of a gas plant. The cladding is a sandwich panel – steel sheeting the bread and thermal insulation the ham. Some of the difficulties experienced by the steel- work fabricators and erectors were a very tight programme. In addition to this, the structure had to be erected involving the interface with the installation of mechanical equipment. Steel erec- tion took place around some of the larger process equipment due to the sheer size of it.