ID Task
Mode
Task Name Duration Start Finish %
Complete
1 OFFSHORE CRITICAL PATH (SDEPCI) 150 days Thu 08/02/24Sat 06/07/24 0%
2 1. Notice to Proceed (NTP) 1 day Thu 08/02/24Thu 08/02/24 0%
3 Day 1: Drawing Approval 1 day Thu 08/02/24Thu 08/02/24 0%
4 2. Production drawing conversion 21 days Tue 20/02/24Mon 11/03/24 0%
5 Component Purchase List 5 days Tue 20/02/24Sat 24/02/24 0%
6 Raw Material Purchase List 14 days Tue 20/02/24Mon 04/03/24 0%
7 Detailed Manufacturing Drawing 7 days Tue 05/03/24Mon 11/03/24 0%
8 3. Material Procurement 63 days Fri 08/03/24 Thu 09/05/24 0%
9 Tap changer, bushing, copper wire, etc
63 days Fri 08/03/24 Thu 09/05/24 0%
10 4. Manufacturing 42 days Thu 11/04/24Wed 22/05/24 0%
11 Clamp 14 days Sat 13/04/24 Fri 26/04/24 0%
12 Silicon Cutting & Core Assembly 7 days Sat 27/04/24 Fri 03/05/24 0%
13 Winding 7 days Sat 27/04/24 Fri 03/05/24 0%
14 Active Part Assembly 7 days Sat 04/05/24 Fri 10/05/24 0%
15 Active Part Drying 5 days Sat 11/05/24 Wed 15/05/24 0%
16 Main Tank 35 days Thu 11/04/24Wed 15/05/24 0%
17 Final Assembly 7 days Thu 16/05/24Wed 22/05/24 0%
18 5. FAT 5 days Mon 27/05/24Fri 31/05/24 0%
19 FAT 5 days Mon 27/05/24Fri 31/05/24 0%
20 6. Disassembly and Packing 25 days Fri 17/05/24 Mon 10/06/24 0%
21 Packaging materials purchase 15 days Fri 17/05/24 Fri 31/05/24 0%
22 Disassembly 5 days Sat 01/06/24 Wed 05/06/24 0%
23 Packing 3 days Thu 06/06/24Sat 08/06/24 0%
24 Final Inspection before Shipment 2 days Sun 09/06/24Mon 10/06/24 0%
25 7. Transportation 26 days Tue 11/06/24Sat 06/07/24 0%
26 Transportation (Factory to Port) 3 days Tue 11/06/24Thu 13/06/24 0%
27 Transportation (China to PH Port)23 days Fri 14/06/24 Sat 06/07/24 0%
28 Onshore Scope (HPSC) 148 days Thu 09/05/24Thu 03/10/24 0%
28 04 11 18 25 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29
Feb '24 Mar '24 Apr '24 May '24 Jun '24 Jul '24 Aug '24 Sep '24 Oct '24
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Project1
Date: Tue 05/03/24

More Related Content

PDF
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
PDF
Project master schedule daughter station cng mini plant
PDF
- Project.pdf
PPTX
Masters family Ltd - case study
PPT
D07 Project Charter
PPT
Solving the Sourcing Puzzle- Dead Stop to Launch in 90 Days - Austin Inventor...
PDF
Integration of modules on site _ final
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
Project master schedule daughter station cng mini plant
- Project.pdf
Masters family Ltd - case study
D07 Project Charter
Solving the Sourcing Puzzle- Dead Stop to Launch in 90 Days - Austin Inventor...
Integration of modules on site _ final

Similar to Proposed Implementation Schedule for Chint.pdf (20)

PDF
Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...
PPTX
Final presentation
PDF
bb.pdf
PDF
4 steps to vsm
PPT
Process Mapping For Modernization
PPT
Process Mapping For Modernization (Updated 10/20/2008)
DOCX
System ImplementationGantt Chart0Going Live (Software Installation.docx
PDF
Mining the Customer Journey, accelerating New Product Introduction
PDF
Planning & Scheduling in Oil and Gas by PM Prodigy.pdf
PDF
Epc for module mm1 mm2 baseline schedule level 3
PPTX
presentation on work breakdown structure and critical path
PPTX
Quality and Cost Management: Methods and Results
PDF
Proposed Process Flow for D&D
PPTX
Quick Turn PCBs - Why an Experienced Supply Chain Matters
PPT
13 Design_for_Manufacturing.ppt
PDF
5 Steps to implementing Lean
PDF
Design For Rapid Product Realization (DFRPR)
DOCX
Resume_戚志揚20160926
PPTX
4 Steps to Drive Process Innovation
Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...
Final presentation
bb.pdf
4 steps to vsm
Process Mapping For Modernization
Process Mapping For Modernization (Updated 10/20/2008)
System ImplementationGantt Chart0Going Live (Software Installation.docx
Mining the Customer Journey, accelerating New Product Introduction
Planning & Scheduling in Oil and Gas by PM Prodigy.pdf
Epc for module mm1 mm2 baseline schedule level 3
presentation on work breakdown structure and critical path
Quality and Cost Management: Methods and Results
Proposed Process Flow for D&D
Quick Turn PCBs - Why an Experienced Supply Chain Matters
13 Design_for_Manufacturing.ppt
5 Steps to implementing Lean
Design For Rapid Product Realization (DFRPR)
Resume_戚志揚20160926
4 Steps to Drive Process Innovation
Ad

Recently uploaded (20)

PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
Sustainable Sites - Green Building Construction
PPTX
Safety Seminar civil to be ensured for safe working.
PPT
Mechanical Engineering MATERIALS Selection
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
Artificial Intelligence
PDF
composite construction of structures.pdf
PPTX
Current and future trends in Computer Vision.pptx
PDF
Well-logging-methods_new................
PDF
PPT on Performance Review to get promotions
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PDF
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PDF
III.4.1.2_The_Space_Environment.p pdffdf
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
Sustainable Sites - Green Building Construction
Safety Seminar civil to be ensured for safe working.
Mechanical Engineering MATERIALS Selection
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
Internet of Things (IOT) - A guide to understanding
R24 SURVEYING LAB MANUAL for civil enggi
Automation-in-Manufacturing-Chapter-Introduction.pdf
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Artificial Intelligence
composite construction of structures.pdf
Current and future trends in Computer Vision.pptx
Well-logging-methods_new................
PPT on Performance Review to get promotions
Operating System & Kernel Study Guide-1 - converted.pdf
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
UNIT-1 - COAL BASED THERMAL POWER PLANTS
III.4.1.2_The_Space_Environment.p pdffdf
Ad

Proposed Implementation Schedule for Chint.pdf

  • 1. ID Task Mode Task Name Duration Start Finish % Complete 1 OFFSHORE CRITICAL PATH (SDEPCI) 150 days Thu 08/02/24Sat 06/07/24 0% 2 1. Notice to Proceed (NTP) 1 day Thu 08/02/24Thu 08/02/24 0% 3 Day 1: Drawing Approval 1 day Thu 08/02/24Thu 08/02/24 0% 4 2. Production drawing conversion 21 days Tue 20/02/24Mon 11/03/24 0% 5 Component Purchase List 5 days Tue 20/02/24Sat 24/02/24 0% 6 Raw Material Purchase List 14 days Tue 20/02/24Mon 04/03/24 0% 7 Detailed Manufacturing Drawing 7 days Tue 05/03/24Mon 11/03/24 0% 8 3. Material Procurement 63 days Fri 08/03/24 Thu 09/05/24 0% 9 Tap changer, bushing, copper wire, etc 63 days Fri 08/03/24 Thu 09/05/24 0% 10 4. Manufacturing 42 days Thu 11/04/24Wed 22/05/24 0% 11 Clamp 14 days Sat 13/04/24 Fri 26/04/24 0% 12 Silicon Cutting & Core Assembly 7 days Sat 27/04/24 Fri 03/05/24 0% 13 Winding 7 days Sat 27/04/24 Fri 03/05/24 0% 14 Active Part Assembly 7 days Sat 04/05/24 Fri 10/05/24 0% 15 Active Part Drying 5 days Sat 11/05/24 Wed 15/05/24 0% 16 Main Tank 35 days Thu 11/04/24Wed 15/05/24 0% 17 Final Assembly 7 days Thu 16/05/24Wed 22/05/24 0% 18 5. FAT 5 days Mon 27/05/24Fri 31/05/24 0% 19 FAT 5 days Mon 27/05/24Fri 31/05/24 0% 20 6. Disassembly and Packing 25 days Fri 17/05/24 Mon 10/06/24 0% 21 Packaging materials purchase 15 days Fri 17/05/24 Fri 31/05/24 0% 22 Disassembly 5 days Sat 01/06/24 Wed 05/06/24 0% 23 Packing 3 days Thu 06/06/24Sat 08/06/24 0% 24 Final Inspection before Shipment 2 days Sun 09/06/24Mon 10/06/24 0% 25 7. Transportation 26 days Tue 11/06/24Sat 06/07/24 0% 26 Transportation (Factory to Port) 3 days Tue 11/06/24Thu 13/06/24 0% 27 Transportation (China to PH Port)23 days Fri 14/06/24 Sat 06/07/24 0% 28 Onshore Scope (HPSC) 148 days Thu 09/05/24Thu 03/10/24 0% 28 04 11 18 25 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 Feb '24 Mar '24 Apr '24 May '24 Jun '24 Jul '24 Aug '24 Sep '24 Oct '24 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: Project1 Date: Tue 05/03/24