PV Installations & Errors
                             Prevent Errors upfront
                                Andreas Iliou / Suntech




All Rights Reserved
Photovoltaic Systems
                 Energy Audits
                 Protection

                 Maximum Power Point Tracking (MPPT)
                 Weak light – Shading

                 Microcracks Production,
                 during Transport and Installation

                 Photovoltaic Systems
                 Energy Audits
                 Protection

                 Backfeed Current
                 Leakage Current

All Rights Reserved
01

                      Photovoltaic Systems
                      Energy Audits
                      Protection




All Rights Reserved
Reason for less power output
                  Power Plant with less kWh/kWp compared
                   with nearby installations
                         Planning layout / Optimization
                         Mismatch losses due to wrong inverter / module
                          combination (high losses ) resize cable diameters
                         Strings not correctly installed,single modules not
                          Connected polarity wise – connectors without contact
                         Mismatch losses can be changed regards inverter
                          e.g Multistring inverter agains 1 Tracker
                         Shading not upfront recognised, restring or
                          reinstallation of different invertertype


                      Cleaning of inverters regularly (heat transfer /cooling!)
                      to hot surface temperature at cooling and/or AC side
                      testing procedureI-V curve testing




All Rights Reserved                                                               Source Iliou
Reason for less power output
                  Power Plant with less kWh/kWp compared
                   with nearby installations
                         Planninglayout/Optimizing
                         Distance of inverters to close by
                         Inverter cools down from right to left therefore
                          heating up uneccessarily second and third inverter
                         Losses due to planning and/ or installation
                          mistakes accumulates up to 250 W losses
                         Systems runs without ( Datalogger )
                          no stringcontrol,
                         Inverter covered and overheats , built in a small room
                          no cooling possible,
                          cuts off frequently without problems
                          Iso faults, shortcuts etc.




All Rights Reserved                                                                Source Iliou
Reason for less power output




                         Inverters must be installed according manual


                                                                        Source Mastervolt
All Rights Reserved
Reason for less power output




                       Alternative Solution: Board can be used to split incoming Air



All Rights Reserved                                                                    Source Mastervolt
Reason for less power output
                      Different topologies involved




All Rights Reserved                                   Source google
Reason for less power output
                 Shaded or already to less modules planned




All Rights Reserved                                          Source Iliou
Reason for less power output
                 Shaded or already to less modules planned




All Rights Reserved                                          Source Iliou
Optimising Power output
                 Optimum East- / Westconfiguration: 2:1 = 2 Strings right and 1 String left
                                                    3:1 = 3 Strings right and 1 String left




All Rights Reserved                                                                           Source Iliou
Tests to determine less power output
                 Shaded or already to less modules planned



                     Check of all AC outlets

                     Check of all earth wires

                     Polaritytest of each string

                     Testing of all Stringvoltages

                     Measurements of shortcut current

                     Isotest of all DC strings

                     Performance test and visual inspection
                      of all components




All Rights Reserved                                            Source Iliou
Tests to determine less power output
                 Check poweroutput with the Voltage AC grid




All Rights Reserved                                           Source Iliou
Testing procedure – less power output
                 Shaded or already to less modules planned




                 •    Visual Inspection Check of all AC outlets

                 •    Isolationtest

                 •    Check of all deactivation figures

                 •    Cable size and resistance check

                 •    Values should be underneath <1 Ohm

                 •    Feed in AC checked with AC site




All Rights Reserved                                               Source Iliou
Testing procedure – less power output
                 Shaded or already to less modules planned



                 •    Are modules covered with grease or dust ->
                      please check

                 •    Contacts faulty , check each single string



                 •    Bushes or trees grown up

                 Is it possible to increase or still decrease MPPT
                 from the inverter or are to less modules connected
                       when Shading occures with more than 1 single
                       module
                 Involved.
                 Temperature zone concept been used
                 Are more systems already been built in the
                       neighbourhood


All Rights Reserved                                                   Source Iliou
Testing procedure – less power output
                 No power output during daytime
                 Shaded or already to less modules planned

                 Meter doesn t turn
                 Still to dark outside, check later on again

                     Circuit breaker turned down ?
                     Switch defect ?
                     Lightning protection device faulty? ->current flowing
                     During winter everything worked fine , ½ year later
                      extremely poor output achieved

                      always during high peak and high temp->low output
                     Power failure Main Grid
                     Iso fault with no reason, check contacts involved
                     Single test of each string
                     Data locked at inverter -> please check
                     Failure in AC Supply , please check with earth loop tester


All Rights Reserved                                                                Source Iliou
Less power output due to stray currents




All Rights Reserved                                        Source Iliou
Less power output due to stray currents




All Rights Reserved                                        Source EP
Less power output
                 cause is stray , and ground currents




                  PE+Neutral bound together- lot s of stray currents ,more losses

All Rights Reserved                                                                 Source EP
Less power output
                 cause is stray , and ground currents




                  PE+Neutral seperate - NO currents ,less losses involved

All Rights Reserved                                                         Source EP
Thank you              1

                             Andreas Iliou




All Rights Reserved

More Related Content

PPTX
Solar pv installation systems
PPTX
Webinar 03 electrical installation of pv system
PPT
041813 rs 120 rule and test taking strat
PPTX
Integrated circuit
PPT
#SolarMOOC Random Problems from 2009 NABCEP STUDY GUIDE
PDF
Electronics 01
DOCX
Solar Panel Installations
PPTX
Under Cabinet Lighting - UC2A Series from iLuXx - Installation Guide
Solar pv installation systems
Webinar 03 electrical installation of pv system
041813 rs 120 rule and test taking strat
Integrated circuit
#SolarMOOC Random Problems from 2009 NABCEP STUDY GUIDE
Electronics 01
Solar Panel Installations
Under Cabinet Lighting - UC2A Series from iLuXx - Installation Guide

What's hot (20)

PPTX
Audio Amplifier
PPTX
Automatic light control Using LDR
DOCX
DOCX
Electronic letter box
PDF
Electric Fences with Automated Monitoring System
PPTX
Automatic emergency light using led ppt
PPTX
Mcb, rccb, elcb
PPTX
Building Utilities 2
PDF
Residual current-circuit-breaker www.meba.net
ODT
Mini emergency-light
PDF
30.led .projects
PDF
How to build a Inverters
PPTX
Section 1;11&amp;12
DOC
Report on live wire detector
DOCX
Automatic led emergency light
PPTX
Automatic Emergency Light
PPT
Electronic devices circuits
DOC
BTC108 2 Introduction To Electronics 2
DOCX
Report on inverters
PDF
What is the Difference Between MCB, MCCB, ELCB and RCCB?
Audio Amplifier
Automatic light control Using LDR
Electronic letter box
Electric Fences with Automated Monitoring System
Automatic emergency light using led ppt
Mcb, rccb, elcb
Building Utilities 2
Residual current-circuit-breaker www.meba.net
Mini emergency-light
30.led .projects
How to build a Inverters
Section 1;11&amp;12
Report on live wire detector
Automatic led emergency light
Automatic Emergency Light
Electronic devices circuits
BTC108 2 Introduction To Electronics 2
Report on inverters
What is the Difference Between MCB, MCCB, ELCB and RCCB?
Ad

Viewers also liked (20)

PPTX
Inter row shading 4-19-12
PDF
053013 pv system site assessment (1)
PDF
MY ME PROJECT 2013-2015
PPTX
Progressive Cavity Pump (PCP) Petroleum Production Engineering
PPT
Solargy energy analysis
PPTX
PRESENTATION SEEP
PDF
2014 PV Performance Modeling Workshop: Optimization strategies with Pvsyst fo...
PPTX
Precipitation ppt
PPTX
Solar Power Plant Design and PV Syst
PPT
Precipitation presentation
PDF
Historia de internet
PPTX
Ingles
PPTX
обл конкур эко_безопасность
PDF
SIAA 39th Semi-Annual Business Meeting
PDF
Juniper QFabric
PPSX
Questionnaire analysis amir
PPT
Actividades de los equipos
PPTX
Blood types
PPTX
PPT
Special Needs Ppp Final
Inter row shading 4-19-12
053013 pv system site assessment (1)
MY ME PROJECT 2013-2015
Progressive Cavity Pump (PCP) Petroleum Production Engineering
Solargy energy analysis
PRESENTATION SEEP
2014 PV Performance Modeling Workshop: Optimization strategies with Pvsyst fo...
Precipitation ppt
Solar Power Plant Design and PV Syst
Precipitation presentation
Historia de internet
Ingles
обл конкур эко_безопасность
SIAA 39th Semi-Annual Business Meeting
Juniper QFabric
Questionnaire analysis amir
Actividades de los equipos
Blood types
Special Needs Ppp Final
Ad

Similar to PV Installations & Errors (20)

PDF
Embedded Systems Power Management
PDF
Reducing Electrical Control Panel Size
PPTX
Presentasi kompel
PDF
17648889-Introduction-to-Power-System-Protection-Relays.pdf
PPTX
Protection Systems for Power generators
PDF
10 electrical-systems
PPTX
AES System Presentation
PDF
Maximum Energy Case Studies - EUPVSEC
PDF
PPTX
Lec6 impact of embedded generation (1)
PDF
UST Power Quality Basics
PDF
An-Overview-of-Protection-System-Analysis-3.pdf
PPTX
isoPower®: Isolated DC to DC Converter
PDF
Ieee generator protection
PDF
Probador de alternador
PPSX
ELVD Shock Preventer
PDF
9096 Enphase Introduction
PPT
Generator protection by bhushan kumbhalkar
PDF
Ip power stone data sheet 8 20-09
Embedded Systems Power Management
Reducing Electrical Control Panel Size
Presentasi kompel
17648889-Introduction-to-Power-System-Protection-Relays.pdf
Protection Systems for Power generators
10 electrical-systems
AES System Presentation
Maximum Energy Case Studies - EUPVSEC
Lec6 impact of embedded generation (1)
UST Power Quality Basics
An-Overview-of-Protection-System-Analysis-3.pdf
isoPower®: Isolated DC to DC Converter
Ieee generator protection
Probador de alternador
ELVD Shock Preventer
9096 Enphase Introduction
Generator protection by bhushan kumbhalkar
Ip power stone data sheet 8 20-09

More from solpowerpeople (15)

PPTX
NABCEP Exam Prep Review for PV Installation & Tech Sales 
PPTX
Changes to 2014 NEC Interconnection Rule 705.12
PDF
012413 passive solar design
PPT
Metering Solutions
PPTX
"Grid-Interactive Systems- A Matter of Energy Storage" w/ Dr Jeffery Lee Joh...
PPTX
PV Monitoring Systems w/Arturo Zarate
PPTX
Webinar 02 demonstration of pv system design pvsyst
PPTX
#SolarMOOC: Webinar on Project Management of Solar PV with Jeffery Lee Johnso...
PPTX
Using sohcahtoa
PPTX
What is a triangle
PPTX
#Solar mooc voltage drop calculations
PPTX
Final trig problem solution
PDF
#Solar mooc 2009 nabcep study guide solutions 1-29
PPTX
#Solarmooc Arctan Solution
PPTX
#Solar mooc problem set 1 alternate exercise 1 solution.
NABCEP Exam Prep Review for PV Installation & Tech Sales 
Changes to 2014 NEC Interconnection Rule 705.12
012413 passive solar design
Metering Solutions
"Grid-Interactive Systems- A Matter of Energy Storage" w/ Dr Jeffery Lee Joh...
PV Monitoring Systems w/Arturo Zarate
Webinar 02 demonstration of pv system design pvsyst
#SolarMOOC: Webinar on Project Management of Solar PV with Jeffery Lee Johnso...
Using sohcahtoa
What is a triangle
#Solar mooc voltage drop calculations
Final trig problem solution
#Solar mooc 2009 nabcep study guide solutions 1-29
#Solarmooc Arctan Solution
#Solar mooc problem set 1 alternate exercise 1 solution.

Recently uploaded (20)

PPTX
human mycosis Human fungal infections are called human mycosis..pptx
PDF
O5-L3 Freight Transport Ops (International) V1.pdf
PDF
Pre independence Education in Inndia.pdf
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
TR - Agricultural Crops Production NC III.pdf
PPTX
Introduction_to_Human_Anatomy_and_Physiology_for_B.Pharm.pptx
PDF
Anesthesia in Laparoscopic Surgery in India
PPTX
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
PDF
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
PDF
Computing-Curriculum for Schools in Ghana
PDF
O7-L3 Supply Chain Operations - ICLT Program
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PPTX
master seminar digital applications in india
PPTX
GDM (1) (1).pptx small presentation for students
PPTX
Cell Structure & Organelles in detailed.
PPTX
Pharmacology of Heart Failure /Pharmacotherapy of CHF
PDF
Basic Mud Logging Guide for educational purpose
PPTX
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
PDF
01-Introduction-to-Information-Management.pdf
PDF
Insiders guide to clinical Medicine.pdf
human mycosis Human fungal infections are called human mycosis..pptx
O5-L3 Freight Transport Ops (International) V1.pdf
Pre independence Education in Inndia.pdf
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
TR - Agricultural Crops Production NC III.pdf
Introduction_to_Human_Anatomy_and_Physiology_for_B.Pharm.pptx
Anesthesia in Laparoscopic Surgery in India
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
Computing-Curriculum for Schools in Ghana
O7-L3 Supply Chain Operations - ICLT Program
Supply Chain Operations Speaking Notes -ICLT Program
master seminar digital applications in india
GDM (1) (1).pptx small presentation for students
Cell Structure & Organelles in detailed.
Pharmacology of Heart Failure /Pharmacotherapy of CHF
Basic Mud Logging Guide for educational purpose
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
01-Introduction-to-Information-Management.pdf
Insiders guide to clinical Medicine.pdf

PV Installations & Errors

  • 1. PV Installations & Errors Prevent Errors upfront Andreas Iliou / Suntech All Rights Reserved
  • 2. Photovoltaic Systems Energy Audits Protection Maximum Power Point Tracking (MPPT) Weak light – Shading Microcracks Production, during Transport and Installation Photovoltaic Systems Energy Audits Protection Backfeed Current Leakage Current All Rights Reserved
  • 3. 01 Photovoltaic Systems Energy Audits Protection All Rights Reserved
  • 4. Reason for less power output  Power Plant with less kWh/kWp compared with nearby installations  Planning layout / Optimization  Mismatch losses due to wrong inverter / module combination (high losses ) resize cable diameters  Strings not correctly installed,single modules not Connected polarity wise – connectors without contact  Mismatch losses can be changed regards inverter e.g Multistring inverter agains 1 Tracker  Shading not upfront recognised, restring or reinstallation of different invertertype Cleaning of inverters regularly (heat transfer /cooling!) to hot surface temperature at cooling and/or AC side testing procedureI-V curve testing All Rights Reserved Source Iliou
  • 5. Reason for less power output  Power Plant with less kWh/kWp compared with nearby installations  Planninglayout/Optimizing  Distance of inverters to close by  Inverter cools down from right to left therefore heating up uneccessarily second and third inverter  Losses due to planning and/ or installation mistakes accumulates up to 250 W losses  Systems runs without ( Datalogger ) no stringcontrol,  Inverter covered and overheats , built in a small room no cooling possible, cuts off frequently without problems Iso faults, shortcuts etc. All Rights Reserved Source Iliou
  • 6. Reason for less power output Inverters must be installed according manual Source Mastervolt All Rights Reserved
  • 7. Reason for less power output Alternative Solution: Board can be used to split incoming Air All Rights Reserved Source Mastervolt
  • 8. Reason for less power output Different topologies involved All Rights Reserved Source google
  • 9. Reason for less power output Shaded or already to less modules planned All Rights Reserved Source Iliou
  • 10. Reason for less power output Shaded or already to less modules planned All Rights Reserved Source Iliou
  • 11. Optimising Power output Optimum East- / Westconfiguration: 2:1 = 2 Strings right and 1 String left 3:1 = 3 Strings right and 1 String left All Rights Reserved Source Iliou
  • 12. Tests to determine less power output Shaded or already to less modules planned  Check of all AC outlets  Check of all earth wires  Polaritytest of each string  Testing of all Stringvoltages  Measurements of shortcut current  Isotest of all DC strings  Performance test and visual inspection of all components All Rights Reserved Source Iliou
  • 13. Tests to determine less power output Check poweroutput with the Voltage AC grid All Rights Reserved Source Iliou
  • 14. Testing procedure – less power output Shaded or already to less modules planned • Visual Inspection Check of all AC outlets • Isolationtest • Check of all deactivation figures • Cable size and resistance check • Values should be underneath <1 Ohm • Feed in AC checked with AC site All Rights Reserved Source Iliou
  • 15. Testing procedure – less power output Shaded or already to less modules planned • Are modules covered with grease or dust -> please check • Contacts faulty , check each single string • Bushes or trees grown up Is it possible to increase or still decrease MPPT from the inverter or are to less modules connected when Shading occures with more than 1 single module Involved. Temperature zone concept been used Are more systems already been built in the neighbourhood All Rights Reserved Source Iliou
  • 16. Testing procedure – less power output No power output during daytime Shaded or already to less modules planned Meter doesn t turn Still to dark outside, check later on again  Circuit breaker turned down ?  Switch defect ?  Lightning protection device faulty? ->current flowing  During winter everything worked fine , ½ year later extremely poor output achieved always during high peak and high temp->low output  Power failure Main Grid  Iso fault with no reason, check contacts involved  Single test of each string  Data locked at inverter -> please check  Failure in AC Supply , please check with earth loop tester All Rights Reserved Source Iliou
  • 17. Less power output due to stray currents All Rights Reserved Source Iliou
  • 18. Less power output due to stray currents All Rights Reserved Source EP
  • 19. Less power output cause is stray , and ground currents PE+Neutral bound together- lot s of stray currents ,more losses All Rights Reserved Source EP
  • 20. Less power output cause is stray , and ground currents PE+Neutral seperate - NO currents ,less losses involved All Rights Reserved Source EP
  • 21. Thank you 1 Andreas Iliou All Rights Reserved