S-CurveHydrograph
Prepared by
Prof. S. G. Taji
Dept. of Civil Engineering
S.R.E.S’s Sanjivani College of Engineering,
Kopargaon
Type-III (B): Derivation of req. T-hr UH from Given
D-hr UH (where T is not multiple integral of D)
 In this type, S-curve approach should be used for calculation.
S-curve or S-Hydrograph
 A ‘S’ hydrograph is nothing but a hydrograph generated by a
continuous effective rainfall occurring at an uniform rate for an
indefinite period.
 It is called ‘S’ hydrograph because the shape of the hydrograph
comes out like alphabet ‘S’ though slightly deformed. Figure
shows a typical ‘S’ hydrograph.
 It can be derived by summation of the ordinates of an infinite
series of unit hydrographs of same .unit duration spaced at the
same unit duration apart and hence the name summation
hydrograph.
 It is a curve which rises continuously in the form or shape of the
letter S, till a constant discharge value i.e. equilibrium is reached.
S curve hydrograph
 The discharge of the S-curve at the time of equilibrium,
A = Area of catchment in hectares
I = Constant rate of effective rainfall in cm/hour
If ‘A’ is taken in Sq. Km., then above eq. becomes
 The ordinates of S-curve can be plotted by using eq.
S(t) = U (t) + S (t-D)
Where, S(t)= req. ordinate of S-curve hydrograph at time
duration t.
U(t) = Ordinate of Given UH at time duration t.
t = required duration (hr)
D= Given duration of UH.
Therefore, S(t-D) = s-curve ordinate of preceding interval
 Q. Derive S-curve ordinates from given UH
 Ordinates of S-curve
 S(t) = U (t) + S (t-D)
 For S (0): At t = 0, U (t) = 0, S(t-D) = 0, Thus, S (0) = 0
(D=4hr i.e. given duration of UH)
 For S (4): At t = 4, U (t) = 10 m3/s, S(t-D) = S(4-4) = S (0) = 0,
 Thus, S (4) = 10 + 0 = 10 m3/s
 For S (8): At t = 8, U (t) = 30, S(t-D) = S(8-4)= S (4) = 10,
 Thus, S (4) = 30 + 10 = 40 m3/s
 For S (12): At t = 12, U (t) = 25, S(t-D) = S(12-4)= S (8) = 40,
 Thus, S (4) = 25 + 40 = 65 m3/s
 ……… continue till the end.
 These calculation can also be perform in table as shown below.
S curve hydrograph
 Q. Determine 12 hr UH from given 4 hr UH by using S-curve
method.
 Soln:
 In this case, D=given duration= 4 hr and T=req. duration = 12hr
 Step-1: Draw two columns next to given UH (i.e. col. 3 and col. 4). These
two columns are filled consequently as follows:
 Initially, mark dash in first rows up to preceding interval of D hr of 3rd
col (i.e. in this case D=4hr, thus mark dash up to t=0 only)
 Step-2.1: Now, make addition col.2 and col. 3 and write it in col. 4.
 Step-2.2:Then, write that result at next row in col. 3 (as shown by
arrow).
 Step-2.3: Again make addition col.2 and col. 3 and write it in col. 4.
 Step-2.4: Then again, write that result at next row in col. 3 (as shown by
arrow).
 For ex. At time 8 hr, drag last ordinate from col.4 in col.
3 (i.e. 20 as shown by arrow), now do addition of 80 +
20 = 100 and write in col. 4.
 Continue this operation till the end of col. 3 and col. 4.
 Step-3: In col. 4, we get S-curve ordinates which are
nothing but the running summation of flow.
 Now, lag these s-curve ordinates by T-hr as shown in
col. 5 (in this case, T=12hr)
 Note: Always be lag your S-curve ordinate by that
duration for which you are going to derive UH (for ex. If
you going to plot 8 hr UH from given 24 hr UH, then in
step-3 lag your S-curve ordinates by 8 hr and vice
versa)
 Step-4: Now deduct that lagged column from S-
curve ordinates (i.e. col. 4 – col. 5 = col. 6)
 This is necessary because we have a summed valued
which should be converted into single flow value.
This will give us DRH of T/D cm ER (i.e. in this case,
T/D = 12/4 = 3cm ER)
 Thus, col. 6 is DRH of T/D = 12/4 = 3 cm ER.
 Step-5: This is the last step, in which divide last
column by ratio of T/D. (i.e. in this case, T/D = 12/4
= 3 cm) for getting req. 12 hr Uh.
S curve hydrograph
Thank You……….

More Related Content

PPTX
Unit hydrograph
PPTX
1 introduction to hydrology
PPTX
Synthetic unit hydrograph
PPTX
PRECISION FARMING
PDF
Unit 2 shallow foundations Hand written notes
PPTX
Introduction to Engineering Hydrology
PPTX
Hydrology and Water Resources Engineering
PPTX
precision agriculture.pptx
Unit hydrograph
1 introduction to hydrology
Synthetic unit hydrograph
PRECISION FARMING
Unit 2 shallow foundations Hand written notes
Introduction to Engineering Hydrology
Hydrology and Water Resources Engineering
precision agriculture.pptx

What's hot (20)

PPTX
Slope stability
PPTX
PDF
Chapter 4 seepage theories
PPTX
Design of gravity dams
PPTX
Effective stress
PPTX
Shear strength of soil
PPTX
Shear strength of soil
PDF
Bearing capacity of shallow foundations by abhishek sharma
PPT
Kennedy's and laccy's theory
PPTX
pre consolidation pressure
PPTX
Spillway and its types
PPTX
Unconsolidated Undrained Test
PDF
Lecture 6 soil permeability
PPTX
Reservoir Planning
PPT
Types of earth dams
PDF
Class 5 Permeability Test ( Geotechnical Engineering )
PPT
Siteinvestigation
Slope stability
Chapter 4 seepage theories
Design of gravity dams
Effective stress
Shear strength of soil
Shear strength of soil
Bearing capacity of shallow foundations by abhishek sharma
Kennedy's and laccy's theory
pre consolidation pressure
Spillway and its types
Unconsolidated Undrained Test
Lecture 6 soil permeability
Reservoir Planning
Types of earth dams
Class 5 Permeability Test ( Geotechnical Engineering )
Siteinvestigation
Ad

Similar to S curve hydrograph (20)

PPTX
Class lecture on Hydrology by Rabindra Ranjan saha Lecture 13
PDF
phyricspresentationandpracticequestions.pdf
PPTX
Physics F3 (IGCSE) speed, velocity and acceleration
PPTX
Speed, velocity and acceleration
PPTX
GRAPHICAL REPRESENTATION OF MOTION💖.pptx
DOCX
Chapter 3, Introduction to Graphing” from Elementary Algebra .docx
PDF
CE222-Erratic Motion CE222-Erratic Motion
PPSX
MEC2047 LECTURE 03+Rectilinear+Motion (3).ppsx
PPT
Motion graphs
PDF
MA101-Lecturenotes(2019-20)-Module 13 (1).pdf
PDF
MA101-Lecturenotes(2019-20)-Module 13 (1).pdf
PDF
Diagramatic Representation.pdf
PPT
Angular Motionnnnnnnnnnnnnnnnnnnnnnnnnnnn.ppt
PDF
Pat 2012 paper_pdf_10581
DOCX
Tacheometry 1
PPT
StewartCalc7e_01_01.ppt
PPT
Scales in Engineering
PPTX
Bar Pendulum experiment ppt.pptx
PDF
Laboratory manual surveying_ii
PPTX
presentation_equation_of_motion_1663608809_139366.pptx
Class lecture on Hydrology by Rabindra Ranjan saha Lecture 13
phyricspresentationandpracticequestions.pdf
Physics F3 (IGCSE) speed, velocity and acceleration
Speed, velocity and acceleration
GRAPHICAL REPRESENTATION OF MOTION💖.pptx
Chapter 3, Introduction to Graphing” from Elementary Algebra .docx
CE222-Erratic Motion CE222-Erratic Motion
MEC2047 LECTURE 03+Rectilinear+Motion (3).ppsx
Motion graphs
MA101-Lecturenotes(2019-20)-Module 13 (1).pdf
MA101-Lecturenotes(2019-20)-Module 13 (1).pdf
Diagramatic Representation.pdf
Angular Motionnnnnnnnnnnnnnnnnnnnnnnnnnnn.ppt
Pat 2012 paper_pdf_10581
Tacheometry 1
StewartCalc7e_01_01.ppt
Scales in Engineering
Bar Pendulum experiment ppt.pptx
Laboratory manual surveying_ii
presentation_equation_of_motion_1663608809_139366.pptx
Ad

More from Satish Taji (18)

PDF
Draft Tube and Cavitation | Fluid Mechanics
PDF
Selection of Turbine | Fluid Mechanics
PDF
Governing of the Turbine | Fluid Mechanics
PDF
Unit Quantities of Turbine | Fluid Mechanics
PDF
Specific Speed of Turbine | Fluid Mechanics
PDF
Kaplan Turbine - Design and Numerical
PDF
Francis Turbine
PDF
Pelton Wheel Turbine Part 2
PPTX
Classification of Turbines
PDF
Basics of Turbine
PDF
Elements of Water Conductor System
PDF
Run of River and Pumped Storage Plants
PDF
Component of Hydro Power Plant
PDF
Hydropower Development in India
PDF
Base Load Plants and Peak Load Plant
PDF
Classification of hydro power plant
PDF
Properties of Fluids, Fluid Static, Buoyancy and Dimensional Analysis
PPTX
Introduction and Application of GIS
Draft Tube and Cavitation | Fluid Mechanics
Selection of Turbine | Fluid Mechanics
Governing of the Turbine | Fluid Mechanics
Unit Quantities of Turbine | Fluid Mechanics
Specific Speed of Turbine | Fluid Mechanics
Kaplan Turbine - Design and Numerical
Francis Turbine
Pelton Wheel Turbine Part 2
Classification of Turbines
Basics of Turbine
Elements of Water Conductor System
Run of River and Pumped Storage Plants
Component of Hydro Power Plant
Hydropower Development in India
Base Load Plants and Peak Load Plant
Classification of hydro power plant
Properties of Fluids, Fluid Static, Buoyancy and Dimensional Analysis
Introduction and Application of GIS

Recently uploaded (20)

PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PDF
Digital Logic Computer Design lecture notes
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPTX
CH1 Production IntroductoryConcepts.pptx
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PDF
Well-logging-methods_new................
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPT
Mechanical Engineering MATERIALS Selection
PPTX
Sustainable Sites - Green Building Construction
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PDF
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
PPTX
Lecture Notes Electrical Wiring System Components
DOCX
573137875-Attendance-Management-System-original
PDF
composite construction of structures.pdf
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
Digital Logic Computer Design lecture notes
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
CH1 Production IntroductoryConcepts.pptx
Foundation to blockchain - A guide to Blockchain Tech
Automation-in-Manufacturing-Chapter-Introduction.pdf
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
Well-logging-methods_new................
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
Mechanical Engineering MATERIALS Selection
Sustainable Sites - Green Building Construction
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
Lecture Notes Electrical Wiring System Components
573137875-Attendance-Management-System-original
composite construction of structures.pdf

S curve hydrograph

  • 1. S-CurveHydrograph Prepared by Prof. S. G. Taji Dept. of Civil Engineering S.R.E.S’s Sanjivani College of Engineering, Kopargaon
  • 2. Type-III (B): Derivation of req. T-hr UH from Given D-hr UH (where T is not multiple integral of D)  In this type, S-curve approach should be used for calculation. S-curve or S-Hydrograph  A ‘S’ hydrograph is nothing but a hydrograph generated by a continuous effective rainfall occurring at an uniform rate for an indefinite period.  It is called ‘S’ hydrograph because the shape of the hydrograph comes out like alphabet ‘S’ though slightly deformed. Figure shows a typical ‘S’ hydrograph.  It can be derived by summation of the ordinates of an infinite series of unit hydrographs of same .unit duration spaced at the same unit duration apart and hence the name summation hydrograph.  It is a curve which rises continuously in the form or shape of the letter S, till a constant discharge value i.e. equilibrium is reached.
  • 4.  The discharge of the S-curve at the time of equilibrium, A = Area of catchment in hectares I = Constant rate of effective rainfall in cm/hour If ‘A’ is taken in Sq. Km., then above eq. becomes  The ordinates of S-curve can be plotted by using eq. S(t) = U (t) + S (t-D) Where, S(t)= req. ordinate of S-curve hydrograph at time duration t. U(t) = Ordinate of Given UH at time duration t. t = required duration (hr) D= Given duration of UH. Therefore, S(t-D) = s-curve ordinate of preceding interval
  • 5.  Q. Derive S-curve ordinates from given UH
  • 6.  Ordinates of S-curve  S(t) = U (t) + S (t-D)  For S (0): At t = 0, U (t) = 0, S(t-D) = 0, Thus, S (0) = 0 (D=4hr i.e. given duration of UH)  For S (4): At t = 4, U (t) = 10 m3/s, S(t-D) = S(4-4) = S (0) = 0,  Thus, S (4) = 10 + 0 = 10 m3/s  For S (8): At t = 8, U (t) = 30, S(t-D) = S(8-4)= S (4) = 10,  Thus, S (4) = 30 + 10 = 40 m3/s  For S (12): At t = 12, U (t) = 25, S(t-D) = S(12-4)= S (8) = 40,  Thus, S (4) = 25 + 40 = 65 m3/s  ……… continue till the end.  These calculation can also be perform in table as shown below.
  • 8.  Q. Determine 12 hr UH from given 4 hr UH by using S-curve method.  Soln:  In this case, D=given duration= 4 hr and T=req. duration = 12hr  Step-1: Draw two columns next to given UH (i.e. col. 3 and col. 4). These two columns are filled consequently as follows:  Initially, mark dash in first rows up to preceding interval of D hr of 3rd col (i.e. in this case D=4hr, thus mark dash up to t=0 only)  Step-2.1: Now, make addition col.2 and col. 3 and write it in col. 4.  Step-2.2:Then, write that result at next row in col. 3 (as shown by arrow).  Step-2.3: Again make addition col.2 and col. 3 and write it in col. 4.  Step-2.4: Then again, write that result at next row in col. 3 (as shown by arrow).
  • 9.  For ex. At time 8 hr, drag last ordinate from col.4 in col. 3 (i.e. 20 as shown by arrow), now do addition of 80 + 20 = 100 and write in col. 4.  Continue this operation till the end of col. 3 and col. 4.  Step-3: In col. 4, we get S-curve ordinates which are nothing but the running summation of flow.  Now, lag these s-curve ordinates by T-hr as shown in col. 5 (in this case, T=12hr)  Note: Always be lag your S-curve ordinate by that duration for which you are going to derive UH (for ex. If you going to plot 8 hr UH from given 24 hr UH, then in step-3 lag your S-curve ordinates by 8 hr and vice versa)
  • 10.  Step-4: Now deduct that lagged column from S- curve ordinates (i.e. col. 4 – col. 5 = col. 6)  This is necessary because we have a summed valued which should be converted into single flow value. This will give us DRH of T/D cm ER (i.e. in this case, T/D = 12/4 = 3cm ER)  Thus, col. 6 is DRH of T/D = 12/4 = 3 cm ER.  Step-5: This is the last step, in which divide last column by ratio of T/D. (i.e. in this case, T/D = 12/4 = 3 cm) for getting req. 12 hr Uh.