1 ODELL KRUAH PROJECT MANAGEMENT UNIT VI
NOVEMBER 30,
2018
Part 1
1 DEVELOP AN IN-DEPTH SCHEDULE FOR THE PROJECT
YOU
SELECTED AND USED TO DEVELOP THE STATEMENT OF
WORK AND
WORK BREAKDOWN STRUCTURE IN UNIT III. PLEASE
REFER TO
THE INTEGRATED PROJECT IN CHAPTER 10 ON PAGE 363
(PROJECT
SCHEDULING) OF THE TEXTBOOK FOR MORE
INFORMATION. BE
SURE TO INCLUDE THE FOLLOWING COMPONENTS:
· AN ACTIVITY PRECEDENCE DIAGRAM, · AN ACTIVITY
DURATION
TABLE, AND · A NETWORK DIAGRAM AND GANTT
CHARTS.
· AN ACTIVITY PRECEDENCE DIAGRAM:
(http://safeassign.blackboard.com/)
PROJECT VI.docx
Word Count: 862 Attachment ID: 244309330
100%
ACTIVITY DURATION TABLE:
ACTIVITY EXPECTED DURATION PREDECESSOR
A 5 DAYS ----
B 10 DAYS A
C 8 DAYS A
D 1 DAY A
E 5 DAYS B, C
F 10 DAYS D, E
G 14 DAYS F
H 3 DAYS G
I 12 DAYS F
J 6 DAYS H, I
A NETWORK DIAGRAM AND GANTT CHARTS:
A
B
C
D
E
F
G
H
I
J
Part 2
1 PLEASE COMPLETE CASE STUDY 10.1: PROJECT
SCHEDULING AT
BLANQUE CHECK CONSTRUCTION ON PAGE 360 OF THE
TEXTBOOK,
AND ANSWER THE THREE QUESTIONS AT THE END.
Q1(ANS)
PRECEDENCE DIAGRAM:
1 C=DIFFERENT CONSRUCTION TYPES OF SCHEDULING
METHODS
TYPE FROM 1 TO 9 P= DIFFERENT CONSRUCTION
PROJECTS WHICH
SHOW THE TYPES OF SCHEDULING METHODS TYPE
FROM 1 TO 9
O1=ORGANIZATION ONE O2= ORGANIZATION 2
S E C4 C5 O1 P9 P8 O2 P7 P6 P5 P4 P3 P2 C9 C8 C7 C6 C1 C2
C3 P1
Q2(ANS) ACCORDING TO MY RESEARCH LEVEL AND
LITERATURE
REVIEW THE EXPERT OPINION AND PAST HISTORY
BOTH ARE THE
BEST TO SOLVE PROBLEM FOR CALCULATING THE
CRITICAL
PATH ,WHICH MAY ALSO TELL US THE DURATION OR
PROJECT
DELAY TO HANDLE OR RUN OUR CONSTRUCTION
COMPANY.
Q3(ANS) THESE BOTH HAVE SOME STRENGTHENS AND
WEAKNESSES AND BOTH GIVE THE RESULTS PROBABLY
SAME , BUT
ACCORDING TO LITERATURE AOA IS THE BENEFICIAL
FOR
MODELING IT WILL BE HELPFUL AND IN THE BUSINESS
FIELD IT
WILL BE IMPORTANT AON WILL BE LESS WIDELY USED
, IN CASE OF
LARGE AND COMPLEX PROJECTS IT IS EASIER TO
EMPLOY THE
PATH PROCESS USED IN THE AOA. ACCORDING TO AOA
WE
ACHIEVE THE EVERY MILESTONE AND PARTICULARLY
USED THE
DUMMY PROJECTS OR ACTIVITIES THE CONCEPT OF
DUMMY
PROJECT IS NOT SIMPLE AND EASY IT REQUIRE MORE
TRAINING
AND PRACTICE. AON CONVENTION ,AOA NETWORK
USED BOTH
NODES AND ARROW TO LABEL THE PROJECT.
Part 3
1 DEVELOP A NETWORK ACTIVITY CHART, AND
IDENTIFY THE
CRITICAL PATH FOR A PROJECT BASED ON THE
INFORMATION
PROVIDED IN THE GANTT CHART BELOW. DRAW THE
ACTIVITY
NETWORK AS A GANTT CHART. WHAT IS THE EXPECTED
DURATION
OF THE PROJECT?
ACTIVITY EXPECTED DURATION PREDECESSOR
A 5 DAYS ----
B 10 DAYS A
C 8 DAYS A
D 1 DAY A
E 5 DAYS B, C
F 10 DAYS D, E
G 14 DAYS F
H 3 DAYS G
I 12 DAYS F
J 6 DAYS H, I
AN ACTIVITY PRECEDENCE DIAGRAM:
THE TOTAL PATHS CAN BE CALCULATED THERE THE
FIRST
DIAGRAM CAN BE DEFINED THE OVERALL PATHS
WHICH ARE
GIVEN BELOW
ABEFIJ=5+10+5+10+12+6=48
ABEFGHJ=5+10+5+10+14+3+6=53
ACEFIJ=5+8+5+10+12+6=46
ACEFGHJ=5+10+5+10+14+3+6=51
ADFIJ=5+1+10+12+6=34 ADFGHJ=5+1+10+14+3+6=39
Critical path:
1 THE 2ND PATH CAN BE CONSTRUCTED FOR THE
CRITICAL PATH
WHICH HAVE THE LONGEST PATH DURATION
ABEFGHJ=5+10+5+10+14+3+6=53 ITS KNOWN AS A
CRITICAL PATH
FOR THE GIVEN ACTIVITY.
PRECEDENCE DIAGRAM AND CRITICAL PATH
END H J G F E B A A J H G E F I START D C B J END
START END END
Part 4
1 USING THE INFORMATION PROVIDED IN THE GANTT
CHART
BELOW, CONSTRUCT THE PROJECT ACTIVITY NETWORK
USING THE
ACTIVITY-ON-NODE (AON) METHODOLOGY, AND LABEL
EACH
NODE. IDENTIFY THE CRITICAL PATH AND OTHER
PATHS
THROUGH THE NETWORK.
Activity
Duration
Predecessors
A
3
--
B
5
A
C
7
A
D
3
B, C
E
5
B
F
4
D
G
2
C
H
5
1 E, F, G
ACTIVITY DURATION ES EF LS
LF Slack
1 A 3 0 3 0
0 --
1 B 5 3 8 8
13 5
1 C 7 3 10 3
10 --
1 D 3 10 13 13
13 --
1 E 5 8 13 13
17 5
1 F 4 13 17 13
17
1 G 2 10 12 15
17 5
1 H 5 17 22 17
22 --
SOLUTION:
1 1 PART 1:
6
0
3
3
8
8
13
0 A
5 B
10
13
5 E
3 D
1 0 3 0
8 5 13
3 5 17
17
22
1 13 3 13
0 H
END
13
17
3
10
0 F
1 17 5 22
0 C
1 13 4 17
3 7 10
10
12
5 G
LEGEND
1 15 2 17
ES ID EF
SL DISCRIPTION
1 LS DURATION LF
THE CRITICAL PATH CAN BE CHOOSE WHICH HAVE THE
MINIMUM
SLACK AND THEN FIND THE DURATION OR DELAY OF
CRITICAL
PATH FIRST OF ALL WE FIND THE CRITICAL PATH OF
GIVEN
ACTIVITY THE CRITICAL PATH HAVE MINIMUM SLACK
BUT DELAY
SHOULD BE MAXIMUM ,WHICH ARE GIVEN BELOW
ACDFH=3+7+3+4+5=22DAYS/MIN WITH THE CRITICAL
POINT OF
SLACK THE FLEXIBILITY OF THE PROJECT IS LIMITED
G
Citations (1/1)
Matched Text
1 Another student's paper
Suspected Entry: 62% match
Uploaded - PROJECT VI.docx
ODELL KRUAH PROJECT MANAGEMENT
UNIT VI NOVEMBER 30, 2018
Source - Another student's paper
Unit VI Project Odell Kruah Columbia Southern
University 11/18/2018
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
DEVELOP AN IN-DEPTH SCHEDULE FOR
THE PROJECT YOU SELECTED AND USED
TO DEVELOP THE STATEMENT OF WORK
AND WORK BREAKDOWN STRUCTURE IN
UNIT III
Source - Another student's paper
Develop an in-depth schedule for the project
you selected and used to develop the statement
of work and work breakdown structure in Unit III
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
PLEASE REFER TO THE INTEGRATED
PROJECT IN CHAPTER 10 ON PAGE 363
(PROJECT SCHEDULING) OF THE
TEXTBOOK FOR MORE INFORMATION
Source - Another student's paper
Please refer to the Integrated Project in Chapter
10 on page 363 (Project Scheduling) of the
textbook for more information
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
BE SURE TO INCLUDE THE FOLLOWING
COMPONENTS
Source - Another student's paper
Be sure to include the following components
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
· AN ACTIVITY PRECEDENCE DIAGRAM, ·
AN ACTIVITY DURATION TABLE, AND · A
NETWORK DIAGRAM AND GANTT CHARTS
Source - Another student's paper
· an activity precedence diagram, · an activity
duration table, and · a network diagram and
Gantt charts
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
· AN ACTIVITY PRECEDENCE DIAGRAM
Source - Another student's paper
· An activity precedence diagram
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
ACTIVITY DURATION TABLE
Source - Another student's paper
Activity duration table
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
ACTIVITY EXPECTED DURATION
PREDECESSOR
Source - Another student's paper
Activity Expected Duration Predecessor
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
A 5 DAYS ----
Source - Another student's paper
A 5 days ----
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
B 10 DAYS A
Source - Another student's paper
B 10 days A
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
C 8 DAYS A
Source - Another student's paper
C 8 days A
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
D 1 DAY A
Source - Another student's paper
D 1 day A
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
E 5 DAYS B, C
Source - Another student's paper
E 5 days B, C
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
F 10 DAYS D, E
Source - Another student's paper
F 10 days D, E
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
G 14 DAYS F
Source - Another student's paper
G 14 days F
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
H 3 DAYS G
Source - Another student's paper
H 3 days G
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
I 12 DAYS F
Source - Another student's paper
I 12 days F
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
J 6 DAYS H, I
Source - Another student's paper
j 6 days H, I
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
A NETWORK DIAGRAM AND GANTT
CHARTS
Source - Another student's paper
A network diagram and Gantt charts
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
PLEASE COMPLETE CASE STUDY 10.1
Source - Another student's paper
Please complete Case Study 10.1
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
PROJECT SCHEDULING AT BLANQUE
CHECK CONSTRUCTION ON PAGE 360 OF
THE TEXTBOOK, AND ANSWER THE THREE
QUESTIONS AT THE END
Source - Another student's paper
Project Scheduling at Blanque Check
Construction on page 360 of the textbook and
answer the three questions at the end
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
C=DIFFERENT CONSRUCTION TYPES OF
SCHEDULING METHODS TYPE FROM 1 TO 9
P= DIFFERENT CONSRUCTION PROJECTS
WHICH SHOW THE TYPES OF SCHEDULING
METHODS TYPE FROM 1 TO 9
O1=ORGANIZATION ONE O2=
ORGANIZATION 2
Source - Another student's paper
C=DIFFERENT CONSRUCTION TYPES OF
SCHEDULING METHODS TYPE FROM 1 TO 9
P= DIFFERENT CONSRUCTION PROJECTS
WHICH SHOW THE TYPES OF SCHEDULING
METHODS TYPE FROM 1 TO 9
O1=ORGANIZATION ONE O2=
ORGANIZATION 2
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
S E C4 C5 O1 P9 P8 O2 P7 P6 P5 P4 P3 P2
C9 C8 C7 C6 C1 C2 C3 P1
Source - Another student's paper
S E C4 C5 O1 P9 P8 O2 P7 P6 P5 P4 P3 P2
C9 C8 C7 C6 C1 C2 C3 P1
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
Q2(ANS) ACCORDING TO MY RESEARCH
LEVEL AND LITERATURE REVIEW THE
EXPERT OPINION AND PAST HISTORY
BOTH ARE THE BEST TO SOLVE PROBLEM
FOR CALCULATING THE CRITICAL
PATH ,WHICH MAY ALSO TELL US THE
DURATION OR PROJECT DELAY TO
HANDLE OR RUN OUR CONSTRUCTION
COMPANY
Source - Another student's paper
Q2(ANS) According to my research level and
literature review the expert opinion and past
history both are the best to solve problem for
calculating the critical path ,which may also tell
us the duration or project delay to handle or run
our construction company
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
Q3(ANS) THESE BOTH HAVE SOME
STRENGTHENS AND WEAKNESSES AND
BOTH GIVE THE RESULTS PROBABLY
SAME , BUT ACCORDING TO LITERATURE
AOA IS THE BENEFICIAL FOR MODELING IT
WILL BE HELPFUL AND IN THE BUSINESS
FIELD IT WILL BE IMPORTANT AON WILL
BE LESS WIDELY USED , IN CASE OF
LARGE AND COMPLEX PROJECTS IT IS
EASIER TO EMPLOY THE PATH PROCESS
USED IN THE AOA
Source - Another student's paper
Q3(ANS) These both have some strengthens
and weaknesses and both give the results
probably same , but according to literature AOA
is the beneficial for modeling it will be helpful
and in the business field it will be important
AON will be less widely used , in case of large
and complex projects it is easier to employ the
path process used in the AOA
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
ACCORDING TO AOA WE ACHIEVE THE
EVERY MILESTONE AND PARTICULARLY
USED THE DUMMY PROJECTS OR
ACTIVITIES THE CONCEPT OF DUMMY
PROJECT IS NOT SIMPLE AND EASY IT
REQUIRE MORE TRAINING AND PRACTICE
Source - Another student's paper
according to AOA we achieve the every
milestone and particularly used the dummy
projects or activities the concept of dummy
project is not simple and easy it require more
training and practice
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
AON CONVENTION ,AOA NETWORK USED
BOTH NODES AND ARROW TO LABEL THE
PROJECT
Source - Another student's paper
AON Convention ,AOA network used both
nodes and arrow to label the project
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
DEVELOP A NETWORK ACTIVITY CHART,
AND IDENTIFY THE CRITICAL PATH FOR A
PROJECT BASED ON THE INFORMATION
PROVIDED IN THE GANTT CHART BELOW
Source - Another student's paper
Develop a network activity chart and identify the
critical path for a project based on the
information provided in the Gantt chart below
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
DRAW THE ACTIVITY NETWORK AS A
GANTT CHART
Source - Another student's paper
Draw the activity network as a Gantt chart
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
WHAT IS THE EXPECTED DURATION OF
THE PROJECT
Source - Another student's paper
What is the expected duration of the project
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
ACTIVITY EXPECTED DURATION
PREDECESSOR
Source - Another student's paper
Activity Expected Duration Predecessor
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx Source - Another student's paper
A 5 DAYS ---- A 5 days ----
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
B 10 DAYS A
Source - Another student's paper
B 10 days A
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
C 8 DAYS A
Source - Another student's paper
C 8 days A
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
D 1 DAY A
Source - Another student's paper
D 1 day A
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
E 5 DAYS B, C
Source - Another student's paper
E 5 days B, C
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
F 10 DAYS D, E
Source - Another student's paper
F 10 days D, E
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
G 14 DAYS F
Source - Another student's paper
G 14 days F
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
H 3 DAYS G
Source - Another student's paper
H 3 days G
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
I 12 DAYS F
Source - Another student's paper
I 12 days F
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
J 6 DAYS H, I
Source - Another student's paper
j 6 days H, I
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
AN ACTIVITY PRECEDENCE DIAGRAM
Source - Another student's paper
· An activity precedence diagram
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
THE TOTAL PATHS CAN BE CALCULATED
THERE THE FIRST DIAGRAM CAN BE
DEFINED THE OVERALL PATHS WHICH
ARE GIVEN BELOW
Source - Another student's paper
The total paths can be calculated there the first
diagram can be defined the overall paths which
are given below
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
ABEFIJ=5+10+5+10+12+6=48
ABEFGHJ=5+10+5+10+14+3+6=53
Source - Another student's paper
ABEFIJ=5+10+5+10+12+6=48
ABEFGHJ=5+10+5+10+14+3+6=53
ACEFIJ=5+8+5+10+12+6=46
ACEFGHJ=5+10+5+10+14+3+6=51
ADFIJ=5+1+10+12+6=34
ADFGHJ=5+1+10+14+3+6=39
ACEFIJ=5+8+5+10+12+6=46
ACEFGHJ=5+10+5+10+14+3+6=51
ADFIJ=5+1+10+12+6=34
ADFGHJ=5+1+10+14+3+6=39
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
THE 2ND PATH CAN BE CONSTRUCTED
FOR THE CRITICAL PATH WHICH HAVE THE
LONGEST PATH DURATION
Source - Another student's paper
The 2nd path can be constructed for the critical
path which have the longest path duration
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
ABEFGHJ=5+10+5+10+14+3+6=53 ITS
KNOWN AS A CRITICAL PATH FOR THE
GIVEN ACTIVITY
Source - Another student's paper
ABEFGHJ=5+10+5+10+14+3+6=53 Its known
as a critical path for the given activity
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
PRECEDENCE DIAGRAM AND CRITICAL
PATH
Source - Another student's paper
Precedence diagram and critical path
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
END H J G F E B A A J H G E F I START D C
B J END START END END
Source - Another student's paper
end H j G F E B A A J H G E F I START D C B
J END START end END
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx Source - Another student's paper
USING THE INFORMATION PROVIDED IN
THE GANTT CHART BELOW, CONSTRUCT
THE PROJECT ACTIVITY NETWORK USING
THE ACTIVITY-ON-NODE (AON)
METHODOLOGY, AND LABEL EACH NODE
Using the information provided in the Gantt
chart below, construct the project activity
network using the activity-on-node (AON)
methodology, and label each node
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
IDENTIFY THE CRITICAL PATH AND OTHER
PATHS THROUGH THE NETWORK
Source - Another student's paper
Identify the critical path and other paths through
the network
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
E, F, G
Source - Another student's paper
E, F, G
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
ACTIVITY DURATION ES EF LS
Source - Another student's paper
Activity Duration ES EF LS
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
A 3 0 3 0
Source - Another student's paper
A 3 0 3 0
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
B 5 3 8 8
Source - Another student's paper
B 5 3 8 8
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
C 7 3 10 3
Source - Another student's paper
C 7 3 10 3
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
D 3 10 13 13
Source - Another student's paper
D 3 10 13 13
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
E 5 8 13 13
Source - Another student's paper
E 5 8 13 13
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
F 4 13 17 13
Source - Another student's paper
F 4 13 17 13
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
G 2 10 12 15
Source - Another student's paper
G 2 10 12 15
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
H 5 17 22 17
Source - Another student's paper
H 5 17 22 17
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
1 PART 1
Source - Another student's paper
1 Part 1
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
0 3 0
Source - Another student's paper
0 3 0
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
8 5 13
Source - Another student's paper
8 5 13
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
3 5 17
Source - Another student's paper
3 5 17
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
13 3 13
Source - Another student's paper
13 3 13
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
17 5 22
Source - Another student's paper
17 5 22
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
13 4 17
Source - Another student's paper
13 4 17
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
3 7 10
Source - Another student's paper
3 7 10
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
15 2 17
Source - Another student's paper
15 2 17
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
ES ID EF
Source - Another student's paper
ES ID EF
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
LS DURATION LF
Source - Another student's paper
LS DURATION LF
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
THE CRITICAL PATH CAN BE CHOOSE
WHICH HAVE THE MINIMUM SLACK AND
THEN FIND THE DURATION OR DELAY OF
CRITICAL PATH FIRST OF ALL WE FIND
THE CRITICAL PATH OF GIVEN ACTIVITY
THE CRITICAL PATH HAVE MINIMUM
SLACK BUT DELAY SHOULD BE
MAXIMUM ,WHICH ARE GIVEN BELOW
Source - Another student's paper
The critical path can be choose which have the
minimum slack and then find the duration or
delay of critical path first of all we find the critical
path of given activity the critical path have
minimum slack but delay should be maximum,
which are given below
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
ACDFH=3+7+3+4+5=22DAYS/MIN WITH THE
CRITICAL POINT OF SLACK THE
FLEXIBILITY OF THE PROJECT IS LIMITED
Source - Another student's paper
ACDFH=3+7+3+4+5=22days/min With the
critical point of slack, the flexibility of the project
is limited
Running head: UNIT VI PROJECT
1
Part 1:
UNIT VI PROJECT 6
Unit VI Project
Your Name
Columbia Southern University
Part 1
Develop an in-depth schedule for the project you selected and
used to develop the statement of work and work breakdown
structure in Unit III. Please refer to the Integrated Project in
Chapter 10 on page 363 (Project Scheduling) of the textbook for
more information. Be sure to include the following components:
· an activity precedence diagram,
· an activity duration table, and
· a network diagram and Gantt charts.
Part 2
Please complete Case Study 10.1: Project Scheduling at Blanque
Check Construction on page 360 of the textbook, and answer the
three questions at the end.
Part 3
Develop a network activity chart, and identify the critical path
for a project based on the information provided in the Gantt
chart below. Draw the activity network as a Gantt chart. What is
the expected duration of the project?
Activity
Expected Duration
Predecessor
A
5 days
----
B
10 days
A
C
8 days
A
D
1 day
A
E
5 days
B, C
F
10 days
D, E
G
14 days
F
H
3 days
G
I
12 days
F
j
6 days
H, I
Part 4
Using the information provided in the Gantt chart below,
construct the project activity network using the activity-on-node
(AON) methodology, and label each node. Identify the critical
path and other paths through the network.
Activity
Duration
Predecessors
A
3
--
B
5
A
C
7
A
D
3
B, C
E
5
B
F
4
D
G
2
C
H
5
E, F, G
Activity
Duration
ES
EF
LS
LF
Slack
A
3
0
3
0
0
--
B
5
3
8
8
13
5
C
7
3
10
3
10
--
D
3
10
13
13
13
--
E
5
8
12
13
17
5
F
4
13
17
13
17
G
2
10
12
15
17
5
H
5
17
22
17
22
--
References

More Related Content

PPT
OPM101Chapter16_001 (2).ppt
PPT
cpm pert.ppt isbsk kshvs sjskdb dnksshgs nj
PPT
cpm pert which is good jsonsk kejd gis s kso
PDF
Chapter Five project management in operations research .pdf
PPT
MGT-Ch07.ppt
PPT
Comparative characteristics of pert and cpm
PPT
Pert cpm
PPT
Pert cpm
OPM101Chapter16_001 (2).ppt
cpm pert.ppt isbsk kshvs sjskdb dnksshgs nj
cpm pert which is good jsonsk kejd gis s kso
Chapter Five project management in operations research .pdf
MGT-Ch07.ppt
Comparative characteristics of pert and cpm
Pert cpm
Pert cpm

Similar to SAFEASSIGNCHECKTEST - CSU SAFEASSIGN PLAGIARISM CHECK TOOL.docx (20)

PPT
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
PDF
Initial Project Meeting Agenda PowerPoint Presentation Slides
PDF
Bballard2000 dissertation
PDF
Project Management The Managerial Process 5th Edition Larson Solutions Manual
PDF
Project Management The Managerial Process 5th Edition Larson Solutions Manual
PDF
Lecture 2 PERT-CPM.pdf
PDF
Student Research Award
PPTX
best note.pptx
DOCX
Uav Dissertation
PDF
ntcir14centre-overview
PDF
IT6511 Networks Laboratory
PPT
EO notes Lecture 27 Project Management 2.ppt
DOCX
Bus 517 final exam – strayer new
DOCX
Bus 517 final exam – strayer new
DOCX
Bus 517 final exam – strayer new
DOCX
Bus 517 final exam – strayer new
DOCX
Bus 517 final exam – strayer new
DOCX
Bus 517 final exam – strayer new
DOCX
Bus 517 final exam – strayer new
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
Initial Project Meeting Agenda PowerPoint Presentation Slides
Bballard2000 dissertation
Project Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions Manual
Lecture 2 PERT-CPM.pdf
Student Research Award
best note.pptx
Uav Dissertation
ntcir14centre-overview
IT6511 Networks Laboratory
EO notes Lecture 27 Project Management 2.ppt
Bus 517 final exam – strayer new
Bus 517 final exam – strayer new
Bus 517 final exam – strayer new
Bus 517 final exam – strayer new
Bus 517 final exam – strayer new
Bus 517 final exam – strayer new
Bus 517 final exam – strayer new
Ad

More from rtodd599 (20)

DOCX
SAGE was founded in 1965 by Sa.docx
DOCX
SafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docx
DOCX
Safety Management System1SMS-1Jeffrey D Carpenter, CSP.docx
DOCX
Sajan Thapa1) Allegory suggests that enlightenment or educatio.docx
DOCX
Safety and Health Providing a safe and secure environment for emplo.docx
DOCX
SAGE OpenJuly-September 2013 1 –10© The Author(s) 2013D.docx
DOCX
Safeby Rachael FabelurinSubmission dat e 07 - Jan- 201.docx
DOCX
Safe Work Environment  Please respond to the followingRecommen.docx
DOCX
Sadder and Less Accurate False Memory for NegativeMaterial .docx
DOCX
Safe Work Environment  Please respond to the followingRecomme.docx
DOCX
Safe Work Environment  Please respond to the followingRecomme.docx
DOCX
S216 MAN506 ORGANISATIONAL BEHAVIOUR httpsonline.cdu.edu..docx
DOCX
SAAD COLLEGE OF NURSING AND ALLIED HEALTH SCIENCESUNIVERSI.docx
DOCX
S18SOCI111SocialNetworksHomework4DUE66198.docx
DOCX
SAAD COLLEGE OF NURSING AND ALLIED HEALTH SC.docx
DOCX
Sadly today police are not often viewed in the best light. Not a.docx
DOCX
S w 909E24 ENGRO CHEMICALS PAKISTAN LIMITED — .docx
DOCX
SA #1 What is Ekman Divergence Wherewhat are three location.docx
DOCX
S&J Plumbing, Inc.s 2010 income statement shows a net profit before.docx
DOCX
S2021Instructions In describing your pro and con arguments, be sure.docx
SAGE was founded in 1965 by Sa.docx
SafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docx
Safety Management System1SMS-1Jeffrey D Carpenter, CSP.docx
Sajan Thapa1) Allegory suggests that enlightenment or educatio.docx
Safety and Health Providing a safe and secure environment for emplo.docx
SAGE OpenJuly-September 2013 1 –10© The Author(s) 2013D.docx
Safeby Rachael FabelurinSubmission dat e 07 - Jan- 201.docx
Safe Work Environment  Please respond to the followingRecommen.docx
Sadder and Less Accurate False Memory for NegativeMaterial .docx
Safe Work Environment  Please respond to the followingRecomme.docx
Safe Work Environment  Please respond to the followingRecomme.docx
S216 MAN506 ORGANISATIONAL BEHAVIOUR httpsonline.cdu.edu..docx
SAAD COLLEGE OF NURSING AND ALLIED HEALTH SCIENCESUNIVERSI.docx
S18SOCI111SocialNetworksHomework4DUE66198.docx
SAAD COLLEGE OF NURSING AND ALLIED HEALTH SC.docx
Sadly today police are not often viewed in the best light. Not a.docx
S w 909E24 ENGRO CHEMICALS PAKISTAN LIMITED — .docx
SA #1 What is Ekman Divergence Wherewhat are three location.docx
S&J Plumbing, Inc.s 2010 income statement shows a net profit before.docx
S2021Instructions In describing your pro and con arguments, be sure.docx
Ad

Recently uploaded (20)

PPTX
Institutional Correction lecture only . . .
PDF
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
PDF
Sports Quiz easy sports quiz sports quiz
PDF
O7-L3 Supply Chain Operations - ICLT Program
PPTX
master seminar digital applications in india
PDF
STATICS OF THE RIGID BODIES Hibbelers.pdf
PPTX
Introduction_to_Human_Anatomy_and_Physiology_for_B.Pharm.pptx
PDF
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
PDF
Anesthesia in Laparoscopic Surgery in India
PDF
Basic Mud Logging Guide for educational purpose
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PPTX
Microbial diseases, their pathogenesis and prophylaxis
PPTX
GDM (1) (1).pptx small presentation for students
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
2.FourierTransform-ShortQuestionswithAnswers.pdf
PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PDF
Microbial disease of the cardiovascular and lymphatic systems
PPTX
Cell Structure & Organelles in detailed.
PDF
Abdominal Access Techniques with Prof. Dr. R K Mishra
PPTX
human mycosis Human fungal infections are called human mycosis..pptx
Institutional Correction lecture only . . .
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
Sports Quiz easy sports quiz sports quiz
O7-L3 Supply Chain Operations - ICLT Program
master seminar digital applications in india
STATICS OF THE RIGID BODIES Hibbelers.pdf
Introduction_to_Human_Anatomy_and_Physiology_for_B.Pharm.pptx
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
Anesthesia in Laparoscopic Surgery in India
Basic Mud Logging Guide for educational purpose
Final Presentation General Medicine 03-08-2024.pptx
Microbial diseases, their pathogenesis and prophylaxis
GDM (1) (1).pptx small presentation for students
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
2.FourierTransform-ShortQuestionswithAnswers.pdf
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
Microbial disease of the cardiovascular and lymphatic systems
Cell Structure & Organelles in detailed.
Abdominal Access Techniques with Prof. Dr. R K Mishra
human mycosis Human fungal infections are called human mycosis..pptx

SAFEASSIGNCHECKTEST - CSU SAFEASSIGN PLAGIARISM CHECK TOOL.docx

  • 1. SAFEASSIGNCHECKTEST - CSU SAFEASSIGN PLAGIARISM CHECK TOOL SafeAssign Originality Report Generator I Odell Kruah on Fri, Nov 30 2018, 4:44 PM 100% highest match Submission ID: d0da8619-c56f-4e34-9af1-6edd71018503 Attachments (1) PROJECT VI.docx 1 ODELL KRUAH PROJECT MANAGEMENT UNIT VI NOVEMBER 30, 2018 Part 1 1 DEVELOP AN IN-DEPTH SCHEDULE FOR THE PROJECT YOU SELECTED AND USED TO DEVELOP THE STATEMENT OF WORK AND WORK BREAKDOWN STRUCTURE IN UNIT III. PLEASE REFER TO THE INTEGRATED PROJECT IN CHAPTER 10 ON PAGE 363
  • 2. (PROJECT SCHEDULING) OF THE TEXTBOOK FOR MORE INFORMATION. BE SURE TO INCLUDE THE FOLLOWING COMPONENTS: · AN ACTIVITY PRECEDENCE DIAGRAM, · AN ACTIVITY DURATION TABLE, AND · A NETWORK DIAGRAM AND GANTT CHARTS. · AN ACTIVITY PRECEDENCE DIAGRAM: (http://safeassign.blackboard.com/) PROJECT VI.docx Word Count: 862 Attachment ID: 244309330 100% ACTIVITY DURATION TABLE: ACTIVITY EXPECTED DURATION PREDECESSOR A 5 DAYS ---- B 10 DAYS A C 8 DAYS A D 1 DAY A
  • 3. E 5 DAYS B, C F 10 DAYS D, E G 14 DAYS F H 3 DAYS G I 12 DAYS F J 6 DAYS H, I A NETWORK DIAGRAM AND GANTT CHARTS: A B C D E F G H I J
  • 4. Part 2 1 PLEASE COMPLETE CASE STUDY 10.1: PROJECT SCHEDULING AT BLANQUE CHECK CONSTRUCTION ON PAGE 360 OF THE TEXTBOOK, AND ANSWER THE THREE QUESTIONS AT THE END. Q1(ANS) PRECEDENCE DIAGRAM: 1 C=DIFFERENT CONSRUCTION TYPES OF SCHEDULING METHODS TYPE FROM 1 TO 9 P= DIFFERENT CONSRUCTION PROJECTS WHICH SHOW THE TYPES OF SCHEDULING METHODS TYPE FROM 1 TO 9 O1=ORGANIZATION ONE O2= ORGANIZATION 2 S E C4 C5 O1 P9 P8 O2 P7 P6 P5 P4 P3 P2 C9 C8 C7 C6 C1 C2 C3 P1 Q2(ANS) ACCORDING TO MY RESEARCH LEVEL AND LITERATURE REVIEW THE EXPERT OPINION AND PAST HISTORY BOTH ARE THE BEST TO SOLVE PROBLEM FOR CALCULATING THE
  • 5. CRITICAL PATH ,WHICH MAY ALSO TELL US THE DURATION OR PROJECT DELAY TO HANDLE OR RUN OUR CONSTRUCTION COMPANY. Q3(ANS) THESE BOTH HAVE SOME STRENGTHENS AND WEAKNESSES AND BOTH GIVE THE RESULTS PROBABLY SAME , BUT ACCORDING TO LITERATURE AOA IS THE BENEFICIAL FOR MODELING IT WILL BE HELPFUL AND IN THE BUSINESS FIELD IT WILL BE IMPORTANT AON WILL BE LESS WIDELY USED , IN CASE OF LARGE AND COMPLEX PROJECTS IT IS EASIER TO EMPLOY THE PATH PROCESS USED IN THE AOA. ACCORDING TO AOA WE ACHIEVE THE EVERY MILESTONE AND PARTICULARLY USED THE DUMMY PROJECTS OR ACTIVITIES THE CONCEPT OF DUMMY
  • 6. PROJECT IS NOT SIMPLE AND EASY IT REQUIRE MORE TRAINING AND PRACTICE. AON CONVENTION ,AOA NETWORK USED BOTH NODES AND ARROW TO LABEL THE PROJECT. Part 3 1 DEVELOP A NETWORK ACTIVITY CHART, AND IDENTIFY THE CRITICAL PATH FOR A PROJECT BASED ON THE INFORMATION PROVIDED IN THE GANTT CHART BELOW. DRAW THE ACTIVITY NETWORK AS A GANTT CHART. WHAT IS THE EXPECTED DURATION OF THE PROJECT? ACTIVITY EXPECTED DURATION PREDECESSOR A 5 DAYS ---- B 10 DAYS A C 8 DAYS A D 1 DAY A E 5 DAYS B, C
  • 7. F 10 DAYS D, E G 14 DAYS F H 3 DAYS G I 12 DAYS F J 6 DAYS H, I AN ACTIVITY PRECEDENCE DIAGRAM: THE TOTAL PATHS CAN BE CALCULATED THERE THE FIRST DIAGRAM CAN BE DEFINED THE OVERALL PATHS WHICH ARE GIVEN BELOW ABEFIJ=5+10+5+10+12+6=48 ABEFGHJ=5+10+5+10+14+3+6=53 ACEFIJ=5+8+5+10+12+6=46 ACEFGHJ=5+10+5+10+14+3+6=51 ADFIJ=5+1+10+12+6=34 ADFGHJ=5+1+10+14+3+6=39 Critical path: 1 THE 2ND PATH CAN BE CONSTRUCTED FOR THE CRITICAL PATH WHICH HAVE THE LONGEST PATH DURATION
  • 8. ABEFGHJ=5+10+5+10+14+3+6=53 ITS KNOWN AS A CRITICAL PATH FOR THE GIVEN ACTIVITY. PRECEDENCE DIAGRAM AND CRITICAL PATH END H J G F E B A A J H G E F I START D C B J END START END END Part 4 1 USING THE INFORMATION PROVIDED IN THE GANTT CHART BELOW, CONSTRUCT THE PROJECT ACTIVITY NETWORK USING THE ACTIVITY-ON-NODE (AON) METHODOLOGY, AND LABEL EACH NODE. IDENTIFY THE CRITICAL PATH AND OTHER PATHS THROUGH THE NETWORK. Activity Duration Predecessors A
  • 10. G 2 C H 5 1 E, F, G ACTIVITY DURATION ES EF LS LF Slack 1 A 3 0 3 0 0 -- 1 B 5 3 8 8 13 5 1 C 7 3 10 3 10 -- 1 D 3 10 13 13 13 -- 1 E 5 8 13 13 17 5
  • 11. 1 F 4 13 17 13 17 1 G 2 10 12 15 17 5 1 H 5 17 22 17 22 -- SOLUTION: 1 1 PART 1: 6 0 3 3 8 8 13 0 A 5 B
  • 12. 10 13 5 E 3 D 1 0 3 0 8 5 13 3 5 17 17 22 1 13 3 13 0 H END 13 17 3 10 0 F
  • 13. 1 17 5 22 0 C 1 13 4 17 3 7 10 10 12 5 G LEGEND 1 15 2 17 ES ID EF SL DISCRIPTION 1 LS DURATION LF THE CRITICAL PATH CAN BE CHOOSE WHICH HAVE THE MINIMUM SLACK AND THEN FIND THE DURATION OR DELAY OF CRITICAL PATH FIRST OF ALL WE FIND THE CRITICAL PATH OF GIVEN
  • 14. ACTIVITY THE CRITICAL PATH HAVE MINIMUM SLACK BUT DELAY SHOULD BE MAXIMUM ,WHICH ARE GIVEN BELOW ACDFH=3+7+3+4+5=22DAYS/MIN WITH THE CRITICAL POINT OF SLACK THE FLEXIBILITY OF THE PROJECT IS LIMITED G Citations (1/1) Matched Text 1 Another student's paper Suspected Entry: 62% match Uploaded - PROJECT VI.docx ODELL KRUAH PROJECT MANAGEMENT UNIT VI NOVEMBER 30, 2018 Source - Another student's paper Unit VI Project Odell Kruah Columbia Southern University 11/18/2018 Suspected Entry: 100% match
  • 15. Uploaded - PROJECT VI.docx DEVELOP AN IN-DEPTH SCHEDULE FOR THE PROJECT YOU SELECTED AND USED TO DEVELOP THE STATEMENT OF WORK AND WORK BREAKDOWN STRUCTURE IN UNIT III Source - Another student's paper Develop an in-depth schedule for the project you selected and used to develop the statement of work and work breakdown structure in Unit III Suspected Entry: 100% match Uploaded - PROJECT VI.docx PLEASE REFER TO THE INTEGRATED PROJECT IN CHAPTER 10 ON PAGE 363 (PROJECT SCHEDULING) OF THE TEXTBOOK FOR MORE INFORMATION Source - Another student's paper Please refer to the Integrated Project in Chapter
  • 16. 10 on page 363 (Project Scheduling) of the textbook for more information Suspected Entry: 100% match Uploaded - PROJECT VI.docx BE SURE TO INCLUDE THE FOLLOWING COMPONENTS Source - Another student's paper Be sure to include the following components Suspected Entry: 100% match Uploaded - PROJECT VI.docx · AN ACTIVITY PRECEDENCE DIAGRAM, · AN ACTIVITY DURATION TABLE, AND · A NETWORK DIAGRAM AND GANTT CHARTS Source - Another student's paper · an activity precedence diagram, · an activity duration table, and · a network diagram and Gantt charts Suspected Entry: 100% match
  • 17. Uploaded - PROJECT VI.docx · AN ACTIVITY PRECEDENCE DIAGRAM Source - Another student's paper · An activity precedence diagram Suspected Entry: 100% match Uploaded - PROJECT VI.docx ACTIVITY DURATION TABLE Source - Another student's paper Activity duration table Suspected Entry: 100% match Uploaded - PROJECT VI.docx ACTIVITY EXPECTED DURATION PREDECESSOR Source - Another student's paper Activity Expected Duration Predecessor Suspected Entry: 100% match Uploaded - PROJECT VI.docx
  • 18. A 5 DAYS ---- Source - Another student's paper A 5 days ---- Suspected Entry: 99% match Uploaded - PROJECT VI.docx B 10 DAYS A Source - Another student's paper B 10 days A Suspected Entry: 99% match Uploaded - PROJECT VI.docx C 8 DAYS A Source - Another student's paper C 8 days A Suspected Entry: 100% match Uploaded - PROJECT VI.docx D 1 DAY A Source - Another student's paper D 1 day A
  • 19. Suspected Entry: 100% match Uploaded - PROJECT VI.docx E 5 DAYS B, C Source - Another student's paper E 5 days B, C Suspected Entry: 99% match Uploaded - PROJECT VI.docx F 10 DAYS D, E Source - Another student's paper F 10 days D, E Suspected Entry: 99% match Uploaded - PROJECT VI.docx G 14 DAYS F Source - Another student's paper G 14 days F Suspected Entry: 99% match Uploaded - PROJECT VI.docx
  • 20. H 3 DAYS G Source - Another student's paper H 3 days G Suspected Entry: 100% match Uploaded - PROJECT VI.docx I 12 DAYS F Source - Another student's paper I 12 days F Suspected Entry: 100% match Uploaded - PROJECT VI.docx J 6 DAYS H, I Source - Another student's paper j 6 days H, I Suspected Entry: 100% match Uploaded - PROJECT VI.docx A NETWORK DIAGRAM AND GANTT CHARTS
  • 21. Source - Another student's paper A network diagram and Gantt charts Suspected Entry: 100% match Uploaded - PROJECT VI.docx PLEASE COMPLETE CASE STUDY 10.1 Source - Another student's paper Please complete Case Study 10.1 Suspected Entry: 99% match Uploaded - PROJECT VI.docx PROJECT SCHEDULING AT BLANQUE CHECK CONSTRUCTION ON PAGE 360 OF THE TEXTBOOK, AND ANSWER THE THREE QUESTIONS AT THE END Source - Another student's paper Project Scheduling at Blanque Check Construction on page 360 of the textbook and answer the three questions at the end Suspected Entry: 100% match
  • 22. Uploaded - PROJECT VI.docx C=DIFFERENT CONSRUCTION TYPES OF SCHEDULING METHODS TYPE FROM 1 TO 9 P= DIFFERENT CONSRUCTION PROJECTS WHICH SHOW THE TYPES OF SCHEDULING METHODS TYPE FROM 1 TO 9 O1=ORGANIZATION ONE O2= ORGANIZATION 2 Source - Another student's paper C=DIFFERENT CONSRUCTION TYPES OF SCHEDULING METHODS TYPE FROM 1 TO 9 P= DIFFERENT CONSRUCTION PROJECTS WHICH SHOW THE TYPES OF SCHEDULING METHODS TYPE FROM 1 TO 9 O1=ORGANIZATION ONE O2= ORGANIZATION 2 Suspected Entry: 100% match Uploaded - PROJECT VI.docx
  • 23. S E C4 C5 O1 P9 P8 O2 P7 P6 P5 P4 P3 P2 C9 C8 C7 C6 C1 C2 C3 P1 Source - Another student's paper S E C4 C5 O1 P9 P8 O2 P7 P6 P5 P4 P3 P2 C9 C8 C7 C6 C1 C2 C3 P1 Suspected Entry: 100% match Uploaded - PROJECT VI.docx Q2(ANS) ACCORDING TO MY RESEARCH LEVEL AND LITERATURE REVIEW THE EXPERT OPINION AND PAST HISTORY BOTH ARE THE BEST TO SOLVE PROBLEM FOR CALCULATING THE CRITICAL PATH ,WHICH MAY ALSO TELL US THE DURATION OR PROJECT DELAY TO HANDLE OR RUN OUR CONSTRUCTION COMPANY Source - Another student's paper
  • 24. Q2(ANS) According to my research level and literature review the expert opinion and past history both are the best to solve problem for calculating the critical path ,which may also tell us the duration or project delay to handle or run our construction company Suspected Entry: 100% match Uploaded - PROJECT VI.docx Q3(ANS) THESE BOTH HAVE SOME STRENGTHENS AND WEAKNESSES AND BOTH GIVE THE RESULTS PROBABLY SAME , BUT ACCORDING TO LITERATURE AOA IS THE BENEFICIAL FOR MODELING IT WILL BE HELPFUL AND IN THE BUSINESS FIELD IT WILL BE IMPORTANT AON WILL BE LESS WIDELY USED , IN CASE OF LARGE AND COMPLEX PROJECTS IT IS EASIER TO EMPLOY THE PATH PROCESS
  • 25. USED IN THE AOA Source - Another student's paper Q3(ANS) These both have some strengthens and weaknesses and both give the results probably same , but according to literature AOA is the beneficial for modeling it will be helpful and in the business field it will be important AON will be less widely used , in case of large and complex projects it is easier to employ the path process used in the AOA Suspected Entry: 100% match Uploaded - PROJECT VI.docx ACCORDING TO AOA WE ACHIEVE THE EVERY MILESTONE AND PARTICULARLY USED THE DUMMY PROJECTS OR ACTIVITIES THE CONCEPT OF DUMMY PROJECT IS NOT SIMPLE AND EASY IT REQUIRE MORE TRAINING AND PRACTICE
  • 26. Source - Another student's paper according to AOA we achieve the every milestone and particularly used the dummy projects or activities the concept of dummy project is not simple and easy it require more training and practice Suspected Entry: 100% match Uploaded - PROJECT VI.docx AON CONVENTION ,AOA NETWORK USED BOTH NODES AND ARROW TO LABEL THE PROJECT Source - Another student's paper AON Convention ,AOA network used both nodes and arrow to label the project Suspected Entry: 100% match Uploaded - PROJECT VI.docx DEVELOP A NETWORK ACTIVITY CHART,
  • 27. AND IDENTIFY THE CRITICAL PATH FOR A PROJECT BASED ON THE INFORMATION PROVIDED IN THE GANTT CHART BELOW Source - Another student's paper Develop a network activity chart and identify the critical path for a project based on the information provided in the Gantt chart below Suspected Entry: 100% match Uploaded - PROJECT VI.docx DRAW THE ACTIVITY NETWORK AS A GANTT CHART Source - Another student's paper Draw the activity network as a Gantt chart Suspected Entry: 100% match Uploaded - PROJECT VI.docx WHAT IS THE EXPECTED DURATION OF THE PROJECT Source - Another student's paper
  • 28. What is the expected duration of the project Suspected Entry: 100% match Uploaded - PROJECT VI.docx ACTIVITY EXPECTED DURATION PREDECESSOR Source - Another student's paper Activity Expected Duration Predecessor Suspected Entry: 100% match Uploaded - PROJECT VI.docx Source - Another student's paper A 5 DAYS ---- A 5 days ---- Suspected Entry: 99% match Uploaded - PROJECT VI.docx B 10 DAYS A Source - Another student's paper B 10 days A Suspected Entry: 99% match Uploaded - PROJECT VI.docx
  • 29. C 8 DAYS A Source - Another student's paper C 8 days A Suspected Entry: 100% match Uploaded - PROJECT VI.docx D 1 DAY A Source - Another student's paper D 1 day A Suspected Entry: 100% match Uploaded - PROJECT VI.docx E 5 DAYS B, C Source - Another student's paper E 5 days B, C Suspected Entry: 99% match Uploaded - PROJECT VI.docx F 10 DAYS D, E Source - Another student's paper F 10 days D, E
  • 30. Suspected Entry: 99% match Uploaded - PROJECT VI.docx G 14 DAYS F Source - Another student's paper G 14 days F Suspected Entry: 99% match Uploaded - PROJECT VI.docx H 3 DAYS G Source - Another student's paper H 3 days G Suspected Entry: 100% match Uploaded - PROJECT VI.docx I 12 DAYS F Source - Another student's paper I 12 days F Suspected Entry: 100% match Uploaded - PROJECT VI.docx
  • 31. J 6 DAYS H, I Source - Another student's paper j 6 days H, I Suspected Entry: 100% match Uploaded - PROJECT VI.docx AN ACTIVITY PRECEDENCE DIAGRAM Source - Another student's paper · An activity precedence diagram Suspected Entry: 99% match Uploaded - PROJECT VI.docx THE TOTAL PATHS CAN BE CALCULATED THERE THE FIRST DIAGRAM CAN BE DEFINED THE OVERALL PATHS WHICH ARE GIVEN BELOW Source - Another student's paper The total paths can be calculated there the first diagram can be defined the overall paths which are given below
  • 32. Suspected Entry: 100% match Uploaded - PROJECT VI.docx ABEFIJ=5+10+5+10+12+6=48 ABEFGHJ=5+10+5+10+14+3+6=53 Source - Another student's paper ABEFIJ=5+10+5+10+12+6=48 ABEFGHJ=5+10+5+10+14+3+6=53 ACEFIJ=5+8+5+10+12+6=46 ACEFGHJ=5+10+5+10+14+3+6=51 ADFIJ=5+1+10+12+6=34 ADFGHJ=5+1+10+14+3+6=39 ACEFIJ=5+8+5+10+12+6=46 ACEFGHJ=5+10+5+10+14+3+6=51 ADFIJ=5+1+10+12+6=34 ADFGHJ=5+1+10+14+3+6=39 Suspected Entry: 99% match Uploaded - PROJECT VI.docx
  • 33. THE 2ND PATH CAN BE CONSTRUCTED FOR THE CRITICAL PATH WHICH HAVE THE LONGEST PATH DURATION Source - Another student's paper The 2nd path can be constructed for the critical path which have the longest path duration Suspected Entry: 99% match Uploaded - PROJECT VI.docx ABEFGHJ=5+10+5+10+14+3+6=53 ITS KNOWN AS A CRITICAL PATH FOR THE GIVEN ACTIVITY Source - Another student's paper ABEFGHJ=5+10+5+10+14+3+6=53 Its known as a critical path for the given activity Suspected Entry: 99% match Uploaded - PROJECT VI.docx PRECEDENCE DIAGRAM AND CRITICAL PATH
  • 34. Source - Another student's paper Precedence diagram and critical path Suspected Entry: 100% match Uploaded - PROJECT VI.docx END H J G F E B A A J H G E F I START D C B J END START END END Source - Another student's paper end H j G F E B A A J H G E F I START D C B J END START end END Suspected Entry: 100% match Uploaded - PROJECT VI.docx Source - Another student's paper USING THE INFORMATION PROVIDED IN THE GANTT CHART BELOW, CONSTRUCT THE PROJECT ACTIVITY NETWORK USING THE ACTIVITY-ON-NODE (AON) METHODOLOGY, AND LABEL EACH NODE Using the information provided in the Gantt
  • 35. chart below, construct the project activity network using the activity-on-node (AON) methodology, and label each node Suspected Entry: 100% match Uploaded - PROJECT VI.docx IDENTIFY THE CRITICAL PATH AND OTHER PATHS THROUGH THE NETWORK Source - Another student's paper Identify the critical path and other paths through the network Suspected Entry: 100% match Uploaded - PROJECT VI.docx E, F, G Source - Another student's paper E, F, G Suspected Entry: 100% match Uploaded - PROJECT VI.docx ACTIVITY DURATION ES EF LS
  • 36. Source - Another student's paper Activity Duration ES EF LS Suspected Entry: 100% match Uploaded - PROJECT VI.docx A 3 0 3 0 Source - Another student's paper A 3 0 3 0 Suspected Entry: 100% match Uploaded - PROJECT VI.docx B 5 3 8 8 Source - Another student's paper B 5 3 8 8 Suspected Entry: 100% match Uploaded - PROJECT VI.docx C 7 3 10 3 Source - Another student's paper C 7 3 10 3
  • 37. Suspected Entry: 100% match Uploaded - PROJECT VI.docx D 3 10 13 13 Source - Another student's paper D 3 10 13 13 Suspected Entry: 100% match Uploaded - PROJECT VI.docx E 5 8 13 13 Source - Another student's paper E 5 8 13 13 Suspected Entry: 100% match Uploaded - PROJECT VI.docx F 4 13 17 13 Source - Another student's paper F 4 13 17 13 Suspected Entry: 100% match Uploaded - PROJECT VI.docx G 2 10 12 15
  • 38. Source - Another student's paper G 2 10 12 15 Suspected Entry: 99% match Uploaded - PROJECT VI.docx H 5 17 22 17 Source - Another student's paper H 5 17 22 17 Suspected Entry: 100% match Uploaded - PROJECT VI.docx 1 PART 1 Source - Another student's paper 1 Part 1 Suspected Entry: 100% match Uploaded - PROJECT VI.docx 0 3 0 Source - Another student's paper 0 3 0
  • 39. Suspected Entry: 100% match Uploaded - PROJECT VI.docx 8 5 13 Source - Another student's paper 8 5 13 Suspected Entry: 100% match Uploaded - PROJECT VI.docx 3 5 17 Source - Another student's paper 3 5 17 Suspected Entry: 100% match Uploaded - PROJECT VI.docx 13 3 13 Source - Another student's paper 13 3 13 Suspected Entry: 100% match Uploaded - PROJECT VI.docx 17 5 22
  • 40. Source - Another student's paper 17 5 22 Suspected Entry: 100% match Uploaded - PROJECT VI.docx 13 4 17 Source - Another student's paper 13 4 17 Suspected Entry: 100% match Uploaded - PROJECT VI.docx 3 7 10 Source - Another student's paper 3 7 10 Suspected Entry: 100% match Uploaded - PROJECT VI.docx 15 2 17 Source - Another student's paper 15 2 17
  • 41. Suspected Entry: 100% match Uploaded - PROJECT VI.docx ES ID EF Source - Another student's paper ES ID EF Suspected Entry: 100% match Uploaded - PROJECT VI.docx LS DURATION LF Source - Another student's paper LS DURATION LF Suspected Entry: 99% match Uploaded - PROJECT VI.docx THE CRITICAL PATH CAN BE CHOOSE WHICH HAVE THE MINIMUM SLACK AND THEN FIND THE DURATION OR DELAY OF CRITICAL PATH FIRST OF ALL WE FIND THE CRITICAL PATH OF GIVEN ACTIVITY THE CRITICAL PATH HAVE MINIMUM
  • 42. SLACK BUT DELAY SHOULD BE MAXIMUM ,WHICH ARE GIVEN BELOW Source - Another student's paper The critical path can be choose which have the minimum slack and then find the duration or delay of critical path first of all we find the critical path of given activity the critical path have minimum slack but delay should be maximum, which are given below Suspected Entry: 100% match Uploaded - PROJECT VI.docx ACDFH=3+7+3+4+5=22DAYS/MIN WITH THE CRITICAL POINT OF SLACK THE FLEXIBILITY OF THE PROJECT IS LIMITED Source - Another student's paper ACDFH=3+7+3+4+5=22days/min With the critical point of slack, the flexibility of the project
  • 43. is limited Running head: UNIT VI PROJECT 1 Part 1: UNIT VI PROJECT 6 Unit VI Project Your Name Columbia Southern University Part 1 Develop an in-depth schedule for the project you selected and used to develop the statement of work and work breakdown structure in Unit III. Please refer to the Integrated Project in Chapter 10 on page 363 (Project Scheduling) of the textbook for more information. Be sure to include the following components: · an activity precedence diagram, · an activity duration table, and · a network diagram and Gantt charts. Part 2 Please complete Case Study 10.1: Project Scheduling at Blanque
  • 44. Check Construction on page 360 of the textbook, and answer the three questions at the end. Part 3 Develop a network activity chart, and identify the critical path for a project based on the information provided in the Gantt chart below. Draw the activity network as a Gantt chart. What is the expected duration of the project? Activity Expected Duration Predecessor A 5 days ---- B 10 days A C 8 days A D 1 day A E 5 days B, C F 10 days D, E G 14 days F H
  • 45. 3 days G I 12 days F j 6 days H, I Part 4 Using the information provided in the Gantt chart below, construct the project activity network using the activity-on-node (AON) methodology, and label each node. Identify the critical path and other paths through the network. Activity Duration Predecessors A 3 -- B 5 A C