 Project planning involves breaking down the work into
parts and assign these to project team members,
anticipate problems that might arise and prepare
tentative solutions to those problems.
 The project plan, which is created at the start of a
project, is used to communicate how the work will be
done to the project team and customers, and to help
assess progress on the project.
3
 At the proposal stage, when you are bidding for a
contract to develop or provide a software system.
 During the project startup phase, when you have to plan
who will work on the project, how the project will be
broken down into increments, how resources will be
allocated across your company, etc.
 Periodically throughout the project, when you modify
your plan in the light of experience gained and
information from monitoring the progress of the work.
4
 Planning may be necessary with only outline software
requirements.
 The aim of planning at this stage is to provide
information that will be used in setting a price for the
system to customers.
5
6
 Estimates are made to discover the cost, to the
developer, of producing a software system.
 You take into account hardware, software, travel, training
and effort costs.
 There is not a simple relationship between the
development cost and the price charged to the
customer.
 Broader organisational, economic, political and business
considerations influence the price charged.
7
Factor Description
Market opportunity
A development organization may quote a low price because it
wishes to move into a new segment of the software market.
Accepting a low profit on one project may give the organization the
opportunity to make a greater profit later. The experience gained
may also help it develop new products.
Cost estimate
uncertainty
If an organization is unsure of its cost estimate, it may increase its
price by a contingency over and above its normal profit.
Contractual terms
A customer may be willing to allow the developer to retain
ownership of the source code and reuse it in other projects. The
price charged may then be less than if the software source code is
handed over to the customer.
8
Factor Description
Requirements volatility
If the requirements are likely to change, an organization
may lower its price to win a contract. After the contract is
awarded, high prices can be charged for changes to the
requirements.
Financial health
Developers in financial difficulty may lower their price to
gain a contract. It is better to make a smaller than normal
profit or break even than to go out of business. Cash flow
is more important than profit in difficult economic times.
9
10
 Plan-driven or plan-based development is an approach
to software engineering where the development process
is planned in detail.
 Plan-driven development is based on engineering project
management techniques and is the ‘traditional’ way of
managing large software development projects.
 A project plan is created that records the work to be
done, who will do it, the development schedule and the
work products.
 Managers use the plan to support project decision
making and as a way of measuring progress.
11
 The arguments in favor of a plan-driven approach are
that early planning allows organizational issues
(availability of staff, other projects, etc.) to be closely
taken into account, and that potential problems and
dependencies are discovered before the project starts,
rather than once the project is underway.
 The principal argument against plan-driven development
is that many early decisions have to be revised because
of changes to the environment in which the software is
to be developed and used.
12
 In a plan-driven development project, a project plan
sets out the resources available to the project, the work
breakdown and a schedule for carrying out the work.
 Plan sections
 Introduction
 Project organization
 Risk analysis
 Hardware and software resource requirements
 Work breakdown
 Project schedule
 Monitoring and reporting mechanisms
13
Plan Description
Quality plan
Describes the quality procedures and standards that
will be used in a project.
Validation plan
Describes the approach, resources, and schedule used
for system validation.
Configuration management plan
Describes the configuration management procedures
and structures to be used.
Maintenance plan
Predicts the maintenance requirements, costs, and
effort.
Staff development plan
Describes how the skills and experience of the project
team members will be developed.
14
 Project planning is an iterative process that starts when
you create an initial project plan during the project
startup phase.
 Plan changes are inevitable.
 As more information about the system and the project
team becomes available during the project, you should
regularly revise the plan to reflect requirements, schedule
and risk changes.
 Changing business goals also leads to changes in project
plans. As business goals change, this could affect all
projects, which may then have to be re-planned.
15
16
17
 Project scheduling is the process of deciding how the
work in a project will be organized as separate tasks,
and when and how these tasks will be executed.
 You estimate the calendar time needed to complete
each task, the effort required and who will work on the
tasks that have been identified.
 You also have to estimate the resources needed to
complete each task, such as the disk space required on a
server, the time required on specialized hardware, such
as a simulator, and what the travel budget will be.
18
 Split project into tasks and estimate time and resources
required to complete each task.
 Organize tasks concurrently to make optimal
use of workforce.
 Minimize task dependencies to avoid delays
caused by one task waiting for another to complete.
 Dependent on project managers intuition and
experience.
19
 Milestones are points in the schedule against which you
can assess progress, for example, the handover of the
system for testing.
 Deliverables are work products that are delivered to the
customer, e.g. a requirements document for the system.
20
21
 Estimating the difficulty of problems and hence the cost
of developing a solution is hard.
 Productivity is not proportional to the number of people
working on a task.
 Adding people to a late project makes it later because
of communication overheads.
 The unexpected always happens. Always allow
contingency in planning.
22
 Graphical notations are normally used to illustrate the
project schedule.
 These show the project breakdown into tasks. Tasks
should not be too small. They should take about a week
or two.
 Bar charts are the most commonly used representation
for project schedules. They show the schedule as
activities or resources against time.
23
Task Effort (person-days) Duration (days) Dependencies
T1 15 10
T2 8 15
T3 20 15 T1 (M1)
T4 5 10
T5 5 10 T2, T4 (M3)
T6 10 5 T1, T2 (M4)
T7 25 20 T1 (M1)
T8 75 25 T4 (M2)
T9 10 15 T3, T6 (M5)
T10 20 15 T7, T8 (M6)
T11 10 10 T9 (M7)
T12 20 10 T10, T11 (M8)
24
25
26
27
 Agile methods of software development are iterative
approaches where the software is developed and
delivered to customers in increments.
 Unlike plan-driven approaches, the functionality of
these increments is not planned in advance but is
decided during the development.
 The decision on what to include in an increment depends
on progress and on the customer’s priorities.
 The customer’s priorities and requirements change so it
makes sense to have a flexible plan that can
accommodate these changes.
28
 Release planning, which looks ahead for several months
and decides on the features that should be included in a
release of a system.
 Iteration planning, which has a shorter term outlook,
and focuses on planning the next increment of a system.
This is typically 2-4 weeks of work for the team.
29
30
 The system specification in XP is based on user stories that reflect
the features that should be included in the system.
 The project team read and discuss the stories and rank them in
order of the amount of time they think it will take to implement the
story.
 Release planning involves selecting and refining the stories that will
reflect the features to be implemented in a release of a system and
the order in which the stories should be implemented.
 Stories to be implemented in each iteration are chosen, with the
number of stories reflecting the time to deliver an iteration (usually
2 or 3 weeks).
31
 The price charged for a system does not just depend on its
estimated development costs; it may be adjusted depending on the
market and organizational priorities.
 Plan-driven development is organized around a complete project
plan that defines the project activities, the planned effort, the
activity schedule and who is responsible for each activity.
 Project scheduling involves the creation of graphical
representations the project plan. Bar chartsshow the activity
duration and staffing timelines, are the most commonly used
schedule representations.
 The XP planning game involves the whole team in project planning.
The plan is developed incrementally and, if problems arise, is
adjusted. Software functionality is reduced instead of delaying
delivery of an increment.
32
33
 Organizations need to make software effort and cost
estimates. There are two types of technique that can be
used to do this:
 Experience-based techniques The estimate of future effort
requirements is based on the manager’s experience of past
projects and the application domain. Essentially, the
manager makes an informed judgment of what the effort
requirements are likely to be.
 Algorithmic cost modeling In this approach, a formulaic
approach is used to compute the project effort based on
estimates of product attributes, such as size, and process
characteristics, such as experience of staff involved.
34
 Experience-based techniques rely on judgments based
on experience of past projects and the effort expended
in these projects on software development activities.
 Typically, you identify the deliverables to be produced
in a project and the different software components or
systems that are to be developed.
 You document these in a spreadsheet, estimate them
individually and compute the total effort required.
 It usually helps to get a group of people involved in the
effort estimation and to ask each member of the group
to explain their estimate.
35
 Cost is estimated as a mathematical function of
product, project and process attributes whose
values are estimated by project managers:
 Effort = A ´ SizeB ´ M
 A is an organisation-dependent constant, B reflects the
disproportionate effort for large projects and M is a multiplier
reflecting product, process and people attributes.
 The most commonly used product attribute for cost
estimation is code size.
 Most models are similar but they use different values for
A, B and M.
36
 The size of a software system can only be known
accurately when it is finished.
 Several factors influence the final size
 Use of COTS and components;
 Programming language;
 Distribution of system.
 As the development process progresses then the size
estimate becomes more accurate.
 The estimates of the factors contributing to B and M are
subjective and vary according to the judgment of the
estimator.
37
38
 An empirical model based on project experience.
 Well-documented, ‘independent’ model which is not
tied to a specific software vendor.
 Long history from initial version published in 1981
(COCOMO-81) through various instantiations to COCOMO
2.
 COCOMO 2 takes into account different approaches to
software development, reuse, etc.
39
 COCOMO 2 incorporates a range of sub-models that
produce increasingly detailed software estimates.
 The sub-models in COCOMO 2 are:
 Application composition model. Used when software is
composed from existing parts.
 Early design model. Used when requirements are available but
design has not yet started.
 Reuse model. Used to compute the effort of integrating reusable
components.
 Post-architecture model. Used once the system architecture has
been designed and more information about the system is
available.
40
41
 Supports prototyping projects and projects where there
is extensive reuse.
 Based on standard estimates of developer productivity in
application (object) points/month.
 Takes CASE tool use into account.
 Formula is
 PM = ( NAP ´ (1 - %reuse/100 ) ) / PROD
 PM is the effort in person-months, NAP is the number of
application points and PROD is the productivity.
42
Developer’sْexperience
and capability
Very low Low Nominal High
Very
high
ICASE maturity and
capability
Very low Low Nominal High
Very
high
PROD (NAP/month) 4 7 13 25 50
43
 Estimates can be made after the requirements have
been agreed.
 Based on a standard formula for algorithmic models
 PM = A ´ SizeB ´ M where
 M = PERS ´ RCPX ´ RUSE ´ PDIF ´ PREX ´ FCIL ´ SCED;
 A = 2.94 in initial calibration, Size in KLOC, B varies from
1.1 to 1.24 depending on novelty of the project,
development flexibility, risk management approaches and
the process maturity.
44
 Multipliers reflect the capability of the developers, the
non-functional requirements, the familiarity with the
development platform, etc.
 RCPX - product reliability and complexity;
 RUSE - the reuse required;
 PDIF - platform difficulty;
 PREX - personnel experience;
 PERS - personnel capability;
 SCED - required schedule;
 FCIL - the team support facilities.
45
 Takes into account black-box code that is reused
without change and code that has to be adapted to
integrate it with new code.
 There are two versions:
 Black-box reuse where code is not modified. An effort
estimate (PM) is computed.
 White-box reuse where code is modified. A size estimate
equivalent to the number of lines of new source code is
computed. This then adjusts the size estimate for new
code.
46
 For generated code:
 PM = (ASLOC * AT/100)/ATPROD
 ASLOC is the number of lines of generated code
 AT is the percentage of code automatically generated.
 ATPROD is the productivity of engineers in integrating this
code.
47
 When code has to be understood and integrated:
 ESLOC = ASLOC * (1-AT/100) * AAM.
 ASLOC and AT as before.
 AAM is the adaptation adjustment multiplier computed
from the costs of changing the reused code, the costs of
understanding how to integrate the code and the costs of
reuse decision making.
48
 Uses the same formula as the early design model but
with 17 rather than 7 associated multipliers.
 The code size is estimated as:
 Number of lines of new code to be developed;
 Estimate of equivalent number of lines of new code
computed using the reuse model;
 An estimate of the number of lines of code that have to be
modified according to requirements changes.
49
 This depends on 5 scale factors (see next slide). Their
sum/100 is added to 1.01
 A company takes on a project in a new domain. The
client has not defined the process to be used and has
not allowed time for risk analysis. The company has a
CMM level 2 rating.
 Precedenteness - new project (4)
 Development flexibility - no client involvement - Very high (1)
 Architecture/risk resolution - No risk analysis - V. Low .(5)
 Team cohesion - new team - nominal (3)
 Process maturity - some control - nominal (3)
 Scale factor is therefore 1.17.
50
Scale factor Explanation
Precedentedness
Reflects the previous experience of the organization with this type of
project. Very low means no previous experience; extra-high means that
the organization is completely familiar with this application domain.
Development flexibility
Reflects the degree of flexibility in the development process. Very low
means a prescribed process is used; extra-high means that the client
sets only general goals.
Architecture/risk resolution
Reflects the extent of risk analysis carried out. Very low means little
analysis; extra-high means a complete and thorough risk analysis.
Team cohesion
Reflects how well the development team knows each other and work
together. Very low means very difficult interactions; extra-high means
an integrated and effective team with no communication problems.
Process maturity
Reflects the process maturity of the organization. The computation of
this value depends on the CMM Maturity Questionnaire, but an
estimate can be achieved by subtracting the CMM process maturity
level from 5.
51
 Product attributes
 Concerned with required characteristics of the software product
being developed.
 Computer attributes
 Constraints imposed on the software by the hardware platform.
 Personnel attributes
 Multipliers that take the experience and capabilities of the
people working on the project into account.
 Project attributes
 Concerned with the particular characteristics of the software
development project.
52
Exponent value 1.17
System size (including factors for reuse and
requirements volatility)
128,000 DSI
Initial COCOMO estimate without cost drivers 730 person-months
Reliability Very high, multiplier = 1.39
Complexity Very high, multiplier = 1.3
Memory constraint High, multiplier = 1.21
Tool use Low, multiplier = 1.12
Schedule Accelerated, multiplier = 1.29
Adjusted COCOMO estimate 2,306 person-months
53
Exponent value 1.17
Reliability Very low, multiplier = 0.75
Complexity Very low, multiplier = 0.75
Memory constraint None, multiplier = 1
Tool use Very high, multiplier = 0.72
Schedule Normal, multiplier = 1
Adjusted COCOMO estimate 295 person-months
54
 As well as effort estimation, managers must estimate
the calendar time required to complete a project and
when staff will be required.
 Calendar time can be estimated using a COCOMO 2
formula
 TDEV = 3 ´ (PM)(0.33+0.2*(B-1.01))
 PM is the effort computation and B is the exponent computed as
discussed above (B is 1 for the early prototyping model). This
computation predicts the nominal schedule for the project.
 The time required is independent of the number of
people working on the project.
55
 Staff required can’t be computed by diving the
development time by the required schedule.
 The number of people working on a project varies
depending on the phase of the project.
 The more people who work on the project, the more
total effort is usually required.
 A very rapid build-up of people often correlates with
schedule slippage.
56
 Estimation techniques for software may be experience-
based, where managers judge the effort required, or
algorithmic, where the effort required is computed from
other estimated project parameters.
 The COCOMO II costing model is an algorithmic cost
model that uses project, product, hardware and
personnel attributes as well as product size and
complexity attributes to derive a cost estimate.
57

More Related Content

PDF
SE18_SE_Lec 12_ Project Management 1
PDF
SE18_Lec 02_Software Life Cycle Model
PDF
SE18_Lec 05_Agile Software Development
PDF
SE2018_Lec 15_ Software Design
PDF
SE18_Lec 09_UML Use Cases
PDF
SE18_Lec 01_Introduction to Software Engineering
PDF
SE2_Lec 19_Design Principles and Design Patterns
PDF
SE2018_Lec 21_ Software Configuration Management (SCM)
SE18_SE_Lec 12_ Project Management 1
SE18_Lec 02_Software Life Cycle Model
SE18_Lec 05_Agile Software Development
SE2018_Lec 15_ Software Design
SE18_Lec 09_UML Use Cases
SE18_Lec 01_Introduction to Software Engineering
SE2_Lec 19_Design Principles and Design Patterns
SE2018_Lec 21_ Software Configuration Management (SCM)

What's hot (20)

PDF
SE18_Lec 00_Course Outline
PDF
SWE-401 - 3. Software Project Management
PDF
SE_Lec 01_ Introduction to Software Enginerring
DOCX
Software engg unit 4
PDF
SE2_Lec 23_Introduction to Cloud Computing
PDF
SE18_Lec 03_ RUP
PDF
Quality Attribute: Testability
PDF
SE2_Lec 18_ Coding
PDF
SWE-401 - 5. Software Design Basics
PDF
SE2018_Lec 14_ Process Modeling and Data Flow Diagram.pptx
PDF
10. Software testing overview
PDF
SE2018_Lec-22_-Continuous-Integration-Tools
DOCX
Software engineering Questions and Answers
PDF
SWE-401 - 4. Software Requirement Specifications
PDF
SWE-401 - 12. Software CASE Tools Overview
PDF
SWE-401 - 1. Introduction to Software Engineering
DOCX
Software engg unit 3
PPTX
Software engineering rogers pressman chapter 7
SE18_Lec 00_Course Outline
SWE-401 - 3. Software Project Management
SE_Lec 01_ Introduction to Software Enginerring
Software engg unit 4
SE2_Lec 23_Introduction to Cloud Computing
SE18_Lec 03_ RUP
Quality Attribute: Testability
SE2_Lec 18_ Coding
SWE-401 - 5. Software Design Basics
SE2018_Lec 14_ Process Modeling and Data Flow Diagram.pptx
10. Software testing overview
SE2018_Lec-22_-Continuous-Integration-Tools
Software engineering Questions and Answers
SWE-401 - 4. Software Requirement Specifications
SWE-401 - 12. Software CASE Tools Overview
SWE-401 - 1. Introduction to Software Engineering
Software engg unit 3
Software engineering rogers pressman chapter 7
Ad

Similar to SE18_Lec 13_ Project Planning (20)

PDF
SE_Lec 12_ Project Planning
PPTX
Chapter7 database management system.pptx
PPTX
7 Project planning for software engineering.pptx
PPTX
202004132159500111minsa_jafar_Project_Management.pptx
PDF
Software Project Management TestingNotes.pdf
PPTX
Ch23 - Project Planning
PPTX
Ch23 project planning
PPTX
Ch23-Software Engineering 9
PPTX
Ch23 Project planning preparation two.pptx
PPT
lecture16.ppt
PPTX
MIS Project management
PPT
5-ProjPlanning.ppthhjjjjhhhjjjjhgyhhjhggg
PPT
Project Planning
PPT
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
PPT
5-ProjPlanning.ppt
PPT
Planning.ppt
PPT
Lecture6
PPT
Software Project management
PPT
4-ProjectPlanning.ppt
SE_Lec 12_ Project Planning
Chapter7 database management system.pptx
7 Project planning for software engineering.pptx
202004132159500111minsa_jafar_Project_Management.pptx
Software Project Management TestingNotes.pdf
Ch23 - Project Planning
Ch23 project planning
Ch23-Software Engineering 9
Ch23 Project planning preparation two.pptx
lecture16.ppt
MIS Project management
5-ProjPlanning.ppthhjjjjhhhjjjjhgyhhjhggg
Project Planning
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
5-ProjPlanning.ppt
Planning.ppt
Lecture6
Software Project management
4-ProjectPlanning.ppt
Ad

More from Amr E. Mohamed (20)

PDF
Dsp 2018 foehu - lec 10 - multi-rate digital signal processing
PDF
Dcs lec03 - z-analysis of discrete time control systems
PDF
Dcs lec02 - z-transform
PDF
Dcs lec01 - introduction to discrete-time control systems
PDF
DDSP_2018_FOEHU - Lec 10 - Digital Signal Processing Applications
PDF
DSP_2018_FOEHU - Lec 07 - IIR Filter Design
PDF
DSP_2018_FOEHU - Lec 06 - FIR Filter Design
PDF
SE2018_Lec 17_ Coding
PDF
SE2018_Lec 18_ Design Principles and Design Patterns
PDF
Selenium - Introduction
PPTX
SE2018_Lec 20_ Test-Driven Development (TDD)
PDF
SE2018_Lec 19_ Software Testing
PDF
DSP_2018_FOEHU - Lec 08 - The Discrete Fourier Transform
PDF
DSP_2018_FOEHU - Lec 05 - Digital Filters
PDF
DSP_2018_FOEHU - Lec 04 - The z-Transform
PDF
DSP_2018_FOEHU - Lec 03 - Discrete-Time Signals and Systems
PDF
DSP_2018_FOEHU - Lec 02 - Sampling of Continuous Time Signals
PDF
DSP_2018_FOEHU - Lec 1 - Introduction to Digital Signal Processing
PDF
DSP_2018_FOEHU - Lec 0 - Course Outlines
PDF
SE18_Lec 10_ UML Behaviour and Interaction Diagrams
Dsp 2018 foehu - lec 10 - multi-rate digital signal processing
Dcs lec03 - z-analysis of discrete time control systems
Dcs lec02 - z-transform
Dcs lec01 - introduction to discrete-time control systems
DDSP_2018_FOEHU - Lec 10 - Digital Signal Processing Applications
DSP_2018_FOEHU - Lec 07 - IIR Filter Design
DSP_2018_FOEHU - Lec 06 - FIR Filter Design
SE2018_Lec 17_ Coding
SE2018_Lec 18_ Design Principles and Design Patterns
Selenium - Introduction
SE2018_Lec 20_ Test-Driven Development (TDD)
SE2018_Lec 19_ Software Testing
DSP_2018_FOEHU - Lec 08 - The Discrete Fourier Transform
DSP_2018_FOEHU - Lec 05 - Digital Filters
DSP_2018_FOEHU - Lec 04 - The z-Transform
DSP_2018_FOEHU - Lec 03 - Discrete-Time Signals and Systems
DSP_2018_FOEHU - Lec 02 - Sampling of Continuous Time Signals
DSP_2018_FOEHU - Lec 1 - Introduction to Digital Signal Processing
DSP_2018_FOEHU - Lec 0 - Course Outlines
SE18_Lec 10_ UML Behaviour and Interaction Diagrams

Recently uploaded (20)

PDF
Wondershare Recoverit Full Crack New Version (Latest 2025)
PPTX
Log360_SIEM_Solutions Overview PPT_Feb 2020.pptx
PPTX
Why Generative AI is the Future of Content, Code & Creativity?
PPTX
Computer Software and OS of computer science of grade 11.pptx
PDF
AI/ML Infra Meetup | LLM Agents and Implementation Challenges
PDF
EaseUS PDF Editor Pro 6.2.0.2 Crack with License Key 2025
PPTX
Trending Python Topics for Data Visualization in 2025
PDF
Topaz Photo AI Crack New Download (Latest 2025)
PDF
Types of Token_ From Utility to Security.pdf
PDF
iTop VPN Crack Latest Version Full Key 2025
PPTX
"Secure File Sharing Solutions on AWS".pptx
PPTX
Patient Appointment Booking in Odoo with online payment
PDF
AI Guide for Business Growth - Arna Softech
PDF
Multiverse AI Review 2025: Access All TOP AI Model-Versions!
PDF
DuckDuckGo Private Browser Premium APK for Android Crack Latest 2025
PDF
Cost to Outsource Software Development in 2025
PPTX
Monitoring Stack: Grafana, Loki & Promtail
PDF
Time Tracking Features That Teams and Organizations Actually Need
PDF
How to Make Money in the Metaverse_ Top Strategies for Beginners.pdf
DOCX
Modern SharePoint Intranet Templates That Boost Employee Engagement in 2025.docx
Wondershare Recoverit Full Crack New Version (Latest 2025)
Log360_SIEM_Solutions Overview PPT_Feb 2020.pptx
Why Generative AI is the Future of Content, Code & Creativity?
Computer Software and OS of computer science of grade 11.pptx
AI/ML Infra Meetup | LLM Agents and Implementation Challenges
EaseUS PDF Editor Pro 6.2.0.2 Crack with License Key 2025
Trending Python Topics for Data Visualization in 2025
Topaz Photo AI Crack New Download (Latest 2025)
Types of Token_ From Utility to Security.pdf
iTop VPN Crack Latest Version Full Key 2025
"Secure File Sharing Solutions on AWS".pptx
Patient Appointment Booking in Odoo with online payment
AI Guide for Business Growth - Arna Softech
Multiverse AI Review 2025: Access All TOP AI Model-Versions!
DuckDuckGo Private Browser Premium APK for Android Crack Latest 2025
Cost to Outsource Software Development in 2025
Monitoring Stack: Grafana, Loki & Promtail
Time Tracking Features That Teams and Organizations Actually Need
How to Make Money in the Metaverse_ Top Strategies for Beginners.pdf
Modern SharePoint Intranet Templates That Boost Employee Engagement in 2025.docx

SE18_Lec 13_ Project Planning

  • 2. 2  Project planning involves breaking down the work into parts and assign these to project team members, anticipate problems that might arise and prepare tentative solutions to those problems.  The project plan, which is created at the start of a project, is used to communicate how the work will be done to the project team and customers, and to help assess progress on the project.
  • 3. 3  At the proposal stage, when you are bidding for a contract to develop or provide a software system.  During the project startup phase, when you have to plan who will work on the project, how the project will be broken down into increments, how resources will be allocated across your company, etc.  Periodically throughout the project, when you modify your plan in the light of experience gained and information from monitoring the progress of the work.
  • 4. 4  Planning may be necessary with only outline software requirements.  The aim of planning at this stage is to provide information that will be used in setting a price for the system to customers.
  • 5. 5
  • 6. 6  Estimates are made to discover the cost, to the developer, of producing a software system.  You take into account hardware, software, travel, training and effort costs.  There is not a simple relationship between the development cost and the price charged to the customer.  Broader organisational, economic, political and business considerations influence the price charged.
  • 7. 7 Factor Description Market opportunity A development organization may quote a low price because it wishes to move into a new segment of the software market. Accepting a low profit on one project may give the organization the opportunity to make a greater profit later. The experience gained may also help it develop new products. Cost estimate uncertainty If an organization is unsure of its cost estimate, it may increase its price by a contingency over and above its normal profit. Contractual terms A customer may be willing to allow the developer to retain ownership of the source code and reuse it in other projects. The price charged may then be less than if the software source code is handed over to the customer.
  • 8. 8 Factor Description Requirements volatility If the requirements are likely to change, an organization may lower its price to win a contract. After the contract is awarded, high prices can be charged for changes to the requirements. Financial health Developers in financial difficulty may lower their price to gain a contract. It is better to make a smaller than normal profit or break even than to go out of business. Cash flow is more important than profit in difficult economic times.
  • 9. 9
  • 10. 10  Plan-driven or plan-based development is an approach to software engineering where the development process is planned in detail.  Plan-driven development is based on engineering project management techniques and is the ‘traditional’ way of managing large software development projects.  A project plan is created that records the work to be done, who will do it, the development schedule and the work products.  Managers use the plan to support project decision making and as a way of measuring progress.
  • 11. 11  The arguments in favor of a plan-driven approach are that early planning allows organizational issues (availability of staff, other projects, etc.) to be closely taken into account, and that potential problems and dependencies are discovered before the project starts, rather than once the project is underway.  The principal argument against plan-driven development is that many early decisions have to be revised because of changes to the environment in which the software is to be developed and used.
  • 12. 12  In a plan-driven development project, a project plan sets out the resources available to the project, the work breakdown and a schedule for carrying out the work.  Plan sections  Introduction  Project organization  Risk analysis  Hardware and software resource requirements  Work breakdown  Project schedule  Monitoring and reporting mechanisms
  • 13. 13 Plan Description Quality plan Describes the quality procedures and standards that will be used in a project. Validation plan Describes the approach, resources, and schedule used for system validation. Configuration management plan Describes the configuration management procedures and structures to be used. Maintenance plan Predicts the maintenance requirements, costs, and effort. Staff development plan Describes how the skills and experience of the project team members will be developed.
  • 14. 14  Project planning is an iterative process that starts when you create an initial project plan during the project startup phase.  Plan changes are inevitable.  As more information about the system and the project team becomes available during the project, you should regularly revise the plan to reflect requirements, schedule and risk changes.  Changing business goals also leads to changes in project plans. As business goals change, this could affect all projects, which may then have to be re-planned.
  • 15. 15
  • 16. 16
  • 17. 17  Project scheduling is the process of deciding how the work in a project will be organized as separate tasks, and when and how these tasks will be executed.  You estimate the calendar time needed to complete each task, the effort required and who will work on the tasks that have been identified.  You also have to estimate the resources needed to complete each task, such as the disk space required on a server, the time required on specialized hardware, such as a simulator, and what the travel budget will be.
  • 18. 18  Split project into tasks and estimate time and resources required to complete each task.  Organize tasks concurrently to make optimal use of workforce.  Minimize task dependencies to avoid delays caused by one task waiting for another to complete.  Dependent on project managers intuition and experience.
  • 19. 19  Milestones are points in the schedule against which you can assess progress, for example, the handover of the system for testing.  Deliverables are work products that are delivered to the customer, e.g. a requirements document for the system.
  • 20. 20
  • 21. 21  Estimating the difficulty of problems and hence the cost of developing a solution is hard.  Productivity is not proportional to the number of people working on a task.  Adding people to a late project makes it later because of communication overheads.  The unexpected always happens. Always allow contingency in planning.
  • 22. 22  Graphical notations are normally used to illustrate the project schedule.  These show the project breakdown into tasks. Tasks should not be too small. They should take about a week or two.  Bar charts are the most commonly used representation for project schedules. They show the schedule as activities or resources against time.
  • 23. 23 Task Effort (person-days) Duration (days) Dependencies T1 15 10 T2 8 15 T3 20 15 T1 (M1) T4 5 10 T5 5 10 T2, T4 (M3) T6 10 5 T1, T2 (M4) T7 25 20 T1 (M1) T8 75 25 T4 (M2) T9 10 15 T3, T6 (M5) T10 20 15 T7, T8 (M6) T11 10 10 T9 (M7) T12 20 10 T10, T11 (M8)
  • 24. 24
  • 25. 25
  • 26. 26
  • 27. 27  Agile methods of software development are iterative approaches where the software is developed and delivered to customers in increments.  Unlike plan-driven approaches, the functionality of these increments is not planned in advance but is decided during the development.  The decision on what to include in an increment depends on progress and on the customer’s priorities.  The customer’s priorities and requirements change so it makes sense to have a flexible plan that can accommodate these changes.
  • 28. 28  Release planning, which looks ahead for several months and decides on the features that should be included in a release of a system.  Iteration planning, which has a shorter term outlook, and focuses on planning the next increment of a system. This is typically 2-4 weeks of work for the team.
  • 29. 29
  • 30. 30  The system specification in XP is based on user stories that reflect the features that should be included in the system.  The project team read and discuss the stories and rank them in order of the amount of time they think it will take to implement the story.  Release planning involves selecting and refining the stories that will reflect the features to be implemented in a release of a system and the order in which the stories should be implemented.  Stories to be implemented in each iteration are chosen, with the number of stories reflecting the time to deliver an iteration (usually 2 or 3 weeks).
  • 31. 31  The price charged for a system does not just depend on its estimated development costs; it may be adjusted depending on the market and organizational priorities.  Plan-driven development is organized around a complete project plan that defines the project activities, the planned effort, the activity schedule and who is responsible for each activity.  Project scheduling involves the creation of graphical representations the project plan. Bar chartsshow the activity duration and staffing timelines, are the most commonly used schedule representations.  The XP planning game involves the whole team in project planning. The plan is developed incrementally and, if problems arise, is adjusted. Software functionality is reduced instead of delaying delivery of an increment.
  • 32. 32
  • 33. 33  Organizations need to make software effort and cost estimates. There are two types of technique that can be used to do this:  Experience-based techniques The estimate of future effort requirements is based on the manager’s experience of past projects and the application domain. Essentially, the manager makes an informed judgment of what the effort requirements are likely to be.  Algorithmic cost modeling In this approach, a formulaic approach is used to compute the project effort based on estimates of product attributes, such as size, and process characteristics, such as experience of staff involved.
  • 34. 34  Experience-based techniques rely on judgments based on experience of past projects and the effort expended in these projects on software development activities.  Typically, you identify the deliverables to be produced in a project and the different software components or systems that are to be developed.  You document these in a spreadsheet, estimate them individually and compute the total effort required.  It usually helps to get a group of people involved in the effort estimation and to ask each member of the group to explain their estimate.
  • 35. 35  Cost is estimated as a mathematical function of product, project and process attributes whose values are estimated by project managers:  Effort = A ´ SizeB ´ M  A is an organisation-dependent constant, B reflects the disproportionate effort for large projects and M is a multiplier reflecting product, process and people attributes.  The most commonly used product attribute for cost estimation is code size.  Most models are similar but they use different values for A, B and M.
  • 36. 36  The size of a software system can only be known accurately when it is finished.  Several factors influence the final size  Use of COTS and components;  Programming language;  Distribution of system.  As the development process progresses then the size estimate becomes more accurate.  The estimates of the factors contributing to B and M are subjective and vary according to the judgment of the estimator.
  • 37. 37
  • 38. 38  An empirical model based on project experience.  Well-documented, ‘independent’ model which is not tied to a specific software vendor.  Long history from initial version published in 1981 (COCOMO-81) through various instantiations to COCOMO 2.  COCOMO 2 takes into account different approaches to software development, reuse, etc.
  • 39. 39  COCOMO 2 incorporates a range of sub-models that produce increasingly detailed software estimates.  The sub-models in COCOMO 2 are:  Application composition model. Used when software is composed from existing parts.  Early design model. Used when requirements are available but design has not yet started.  Reuse model. Used to compute the effort of integrating reusable components.  Post-architecture model. Used once the system architecture has been designed and more information about the system is available.
  • 40. 40
  • 41. 41  Supports prototyping projects and projects where there is extensive reuse.  Based on standard estimates of developer productivity in application (object) points/month.  Takes CASE tool use into account.  Formula is  PM = ( NAP ´ (1 - %reuse/100 ) ) / PROD  PM is the effort in person-months, NAP is the number of application points and PROD is the productivity.
  • 42. 42 Developer’sْexperience and capability Very low Low Nominal High Very high ICASE maturity and capability Very low Low Nominal High Very high PROD (NAP/month) 4 7 13 25 50
  • 43. 43  Estimates can be made after the requirements have been agreed.  Based on a standard formula for algorithmic models  PM = A ´ SizeB ´ M where  M = PERS ´ RCPX ´ RUSE ´ PDIF ´ PREX ´ FCIL ´ SCED;  A = 2.94 in initial calibration, Size in KLOC, B varies from 1.1 to 1.24 depending on novelty of the project, development flexibility, risk management approaches and the process maturity.
  • 44. 44  Multipliers reflect the capability of the developers, the non-functional requirements, the familiarity with the development platform, etc.  RCPX - product reliability and complexity;  RUSE - the reuse required;  PDIF - platform difficulty;  PREX - personnel experience;  PERS - personnel capability;  SCED - required schedule;  FCIL - the team support facilities.
  • 45. 45  Takes into account black-box code that is reused without change and code that has to be adapted to integrate it with new code.  There are two versions:  Black-box reuse where code is not modified. An effort estimate (PM) is computed.  White-box reuse where code is modified. A size estimate equivalent to the number of lines of new source code is computed. This then adjusts the size estimate for new code.
  • 46. 46  For generated code:  PM = (ASLOC * AT/100)/ATPROD  ASLOC is the number of lines of generated code  AT is the percentage of code automatically generated.  ATPROD is the productivity of engineers in integrating this code.
  • 47. 47  When code has to be understood and integrated:  ESLOC = ASLOC * (1-AT/100) * AAM.  ASLOC and AT as before.  AAM is the adaptation adjustment multiplier computed from the costs of changing the reused code, the costs of understanding how to integrate the code and the costs of reuse decision making.
  • 48. 48  Uses the same formula as the early design model but with 17 rather than 7 associated multipliers.  The code size is estimated as:  Number of lines of new code to be developed;  Estimate of equivalent number of lines of new code computed using the reuse model;  An estimate of the number of lines of code that have to be modified according to requirements changes.
  • 49. 49  This depends on 5 scale factors (see next slide). Their sum/100 is added to 1.01  A company takes on a project in a new domain. The client has not defined the process to be used and has not allowed time for risk analysis. The company has a CMM level 2 rating.  Precedenteness - new project (4)  Development flexibility - no client involvement - Very high (1)  Architecture/risk resolution - No risk analysis - V. Low .(5)  Team cohesion - new team - nominal (3)  Process maturity - some control - nominal (3)  Scale factor is therefore 1.17.
  • 50. 50 Scale factor Explanation Precedentedness Reflects the previous experience of the organization with this type of project. Very low means no previous experience; extra-high means that the organization is completely familiar with this application domain. Development flexibility Reflects the degree of flexibility in the development process. Very low means a prescribed process is used; extra-high means that the client sets only general goals. Architecture/risk resolution Reflects the extent of risk analysis carried out. Very low means little analysis; extra-high means a complete and thorough risk analysis. Team cohesion Reflects how well the development team knows each other and work together. Very low means very difficult interactions; extra-high means an integrated and effective team with no communication problems. Process maturity Reflects the process maturity of the organization. The computation of this value depends on the CMM Maturity Questionnaire, but an estimate can be achieved by subtracting the CMM process maturity level from 5.
  • 51. 51  Product attributes  Concerned with required characteristics of the software product being developed.  Computer attributes  Constraints imposed on the software by the hardware platform.  Personnel attributes  Multipliers that take the experience and capabilities of the people working on the project into account.  Project attributes  Concerned with the particular characteristics of the software development project.
  • 52. 52 Exponent value 1.17 System size (including factors for reuse and requirements volatility) 128,000 DSI Initial COCOMO estimate without cost drivers 730 person-months Reliability Very high, multiplier = 1.39 Complexity Very high, multiplier = 1.3 Memory constraint High, multiplier = 1.21 Tool use Low, multiplier = 1.12 Schedule Accelerated, multiplier = 1.29 Adjusted COCOMO estimate 2,306 person-months
  • 53. 53 Exponent value 1.17 Reliability Very low, multiplier = 0.75 Complexity Very low, multiplier = 0.75 Memory constraint None, multiplier = 1 Tool use Very high, multiplier = 0.72 Schedule Normal, multiplier = 1 Adjusted COCOMO estimate 295 person-months
  • 54. 54  As well as effort estimation, managers must estimate the calendar time required to complete a project and when staff will be required.  Calendar time can be estimated using a COCOMO 2 formula  TDEV = 3 ´ (PM)(0.33+0.2*(B-1.01))  PM is the effort computation and B is the exponent computed as discussed above (B is 1 for the early prototyping model). This computation predicts the nominal schedule for the project.  The time required is independent of the number of people working on the project.
  • 55. 55  Staff required can’t be computed by diving the development time by the required schedule.  The number of people working on a project varies depending on the phase of the project.  The more people who work on the project, the more total effort is usually required.  A very rapid build-up of people often correlates with schedule slippage.
  • 56. 56  Estimation techniques for software may be experience- based, where managers judge the effort required, or algorithmic, where the effort required is computed from other estimated project parameters.  The COCOMO II costing model is an algorithmic cost model that uses project, product, hardware and personnel attributes as well as product size and complexity attributes to derive a cost estimate.
  • 57. 57