SlideShare a Scribd company logo
An Overview of
NEW STORMWATER RULES
(PENDING June adoption)
Evan N. Pratt, P.E.
Water Resources Commissioner
OUTLINE
A. Why Change?
B. Value of Infiltration
C. 3 Main Changes
D. Development Benefits and Concerns
E. Community Benefits and Concerns
F. Case/Cost Studies and Examples
G. Summary Talking Points – Let’s be consistent
WHY ARE WE HERE?
THESE PEOPLE CAN’T CHANGE POLICY – BUT HAVE TO LIVE WITH IT
WHY CHANGE?
WHY CHANGE?
WHY CHANGE?
Green infrastructure policy for stormwater infiltration
Green infrastructure policy for stormwater infiltration
IT ALL
ADDS UP
Q: Why Infiltration?
A: TSS Removal Efficiencies
SOURCE: 2005 DATA REPORT, UNH STORMWATER CENTER
Top 5 TSS Removal Efficiencies
 POROUS PAVEMENT– 100%
 GRAVEL WETLAND – 100%
 STORAGE BASIN INFILTRATION– 100%
 TREE FILTER – 93%
 BIORETENTION – 92%
 RETENTION POND – 65%
 SWALE – 55+%
WCWRC RULES:
WHAT IS CHANGING?
3 KEY CHANGES
1. PROCESS: MANDATORY PRE-APPLICATION MEETING
2. TECHNICAL APPROACH
a. METHOD OF CALCULATING RUNOFF: NO IMPACT
b. STORMS HAVE GOTTEN BIGGER
3. INFILTRATION REQUIREMENT
a. First 1”, OR
b. Must prove that soils are unsuitable for infiltration
OVERVIEW OF CHANGES
1. PROCESS:
PRE-APPLICATION MEETING
GENERAL EVALUATION
Purpose: Engage Owner, clarify changes and benefits
Soil types
Information on geology and hydrology including estimate
of groundwater table elevation
Topography
Land cover
Other pertinent natural or man-made features
Potential locations for infiltration BMPs
2. TECHNICAL: 1% STORM
 Current MDEQ 24 hour 1% storm = 4.36 inches
 NOAA Atlas 14, Volume 8
 Published 2013
 Provides data for discreet locations
 Ann Arbor, Milan & Ypsilanti Stations
 Range for the 24 hour 1% storm at these stations varies minimally
 All indicate the 24 hour 1% storm = 5.11 inches
 Chelsea Station
 24 hour 1 % storm = 5.21
 New WCWRC Rules 24 hour 1 % storm = 5.11 inches
2. TECHNICAL: Method of Calculation
SUMMARY: Method yields about the same results for
detention on several sites.
 “The Oakland County Method” vs. “NRCS Curve Number”
 Peer Review Comparisons
 WCWRC Deputy WRC -- Dennis Wojcik, P.E. verifications
 705 N. Zeeb Road
 Two Other Site Developments
3. INFILTRATION
 MDEQ NPDES Permit Application
 Require that post-construction runoff rate and volume of
discharges not exceed the pre-development rate and
volume for all storms up to the two-year, 24 hour storm at
the site. At a minimum, pre-development is the last land
use prior to the planned new development or
redevelopment.
 WCWRC Rules will require infiltration of the greater of the
first flush volume or difference between pre-settlement
and post-development 24 hour 50% storm.
HOW DOES DEVELOPMENT BENEFIT?
Many developers are finding lower cost for GI when used in
greenfields. Case studies at http://tinyurl.com/streetrunoff
 Less concrete infrastructure needed.
 Less surface area of storage needed if doing infiltration
 Less impact to developable area with co-location
 It will always be more costly to develop unsuitable land
 This is why poorly suited land (soils, etc) is cheaper
 Public cost of developing poorly suited land
 Whose job is it to look at total cost of a site?
COMMUNITY BENEFITS and CONCERNS
 Reduction in community costs related to development
 Soils have always been integral to land use decisions.
Now on County GIS – NRCS Soils layer under “Soils”
 Collaboration during pre-application process
 HOW WILL YOUR COMMUNITY FUND LEGACY COSTS OF
DEVELOPMENT? 35% GENERAL FUND (OLD WAY) OR
MORE LIKE WCRC?
DEVELOPER CASE STUDY:
GI COST SAVINGS
Case Study: Boulder Hills
Pelham, NH
 2009 -- 900’ OF PRIVATE RESIDENTIAL PAVING IN NE
 SITE GOAL OF ZERO DISCHARGE
 55+ ACTIVE ADULT COMMUNITY
 SANDY SOILS (NOT A MUST)
COST AVOIDANCE
 1616’ CONCRETE CURB
 785’ PIPE
 8 CATCHBASINS
 2 DETENTION BASINS & 2 OUTLET STRUCTURES
 SAVED 1.3 ACRES IN LAND CLEARING/CONSUMPTION
 CONVENTIONAL = $789,500 vs. LID SWM= $740,300
 INFILTRATION COST SAVINGS = $49,000 = (6.2%)
 O/M DISCUSSION LATER – ALSO LESS
Comparison of Unit Costs
HOW POROUS O/M IS MUCH LESS
WHAT IF PAVEMENT NEVER CRACKED?
HOW POROUS O/M IS MUCH LESS
…AND IS SUPPOSED TO HAVE WATER IN THE BASE
HOW POROUS O/M IS MUCH LESS
$-
$10,000
$20,000
$30,000
$40,000
$50,000
$60,000
$70,000
$80,000
$90,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
HMA Maintenance With Sweeping
Cumulative Porous Sweeping Costs
WHY CHANGE:
LET’S ALL GIVE THE SAME ANSWERS
SOAKING WATER INTO THE GROUND IS SIMPLER AND
CAN COST LESS
WCWRC WILL WORK WITH OWNERS BEFORE A
PURCHASE DECISION. OWNER’S RESPONSIBILITY TO
EVALUATE DEVELOPMENT COSTS OF CHEAPER PROPERTY.
GOVERNMENT AGENCIES ARE ALREADY INVESTING
GOVERNMENT AGENCIES ALREADY
INVEST IN GREEN INFRASTRUCTURE
WCWRC OFFICE – 705 N. ZEEB
 13 years old
 42,000+ sft.
 Detention (2)
 Bioswales
 Level Spreader
 Infiltration Bed
 Solar Panels
 Native Veg.
BUT
 No Credit
WASHTENAW COUNTY BUILDING
 Current method detention volume = 45,000 c.f.
 Revised method detention volume = 60,000 c.f.
 Reduction in volume utilizing BMPs installed = 11,000 c.f.
 Revised method required detention volume = 49,000 c.f.
705 ZEEB ROAD
REDUCED CONSTRUCTION COST
 8 structures @ $2,000 ea. = $16,000
 425 ft.-12in. RCP @ $40/ft. = $17,000
 265 ft.-15 in. RCP @ $50/ft. = $13,250
 Savings = $46,250 (FIRST FLUSH ONLY)
 BUT SOILS ARE SUITABLE FOR 100% INFILTRATION
 Extra Savings: 1,950 cyd earthwork @ $10/cyd = $19,500
 NET SAVINGS = at least $65,750
(plus additional pipe savings, offset by need to add bioswale)
-Will be estimating porous asphalt option in future version
EMU Student Housing
After planting – still standing water
Eastern Michigan University, InSite Design Studio
Plants mature – no standing water
InSite Design Studio, Inc.
IT’S SIMPLE:
WHICH IS
BETTER??
http://tinyurl.com/streetrunoff
TAKE AWAY MESSAGES
1. Human activity is the #1 cause of many problems. The
purpose of the New Rules is to:
A. Reduce long term cost impacts to communities and taxpayers
B. Reduce water quality and flooding impacts of development
2. Good sites with good soils will result in less costly projects –
Owners’ responsibility during site selection & due diligence.
3. WCWRC is available to work with communities and the
Owner on challenging sites.
QUESTIONS?

More Related Content

PDF
PPTX
Matt MacConnell, Lehigh River Stocking Association, “Lausanne Tunnel Remediat...
PPTX
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
PDF
Chemung Landfill Expansion - The Facts
PPT
Assessment Of Permeable Pavement In High Volume Urban Flooding
PDF
Acf environmental 2016 apwa fl expo - integrated infrastructure-an innovati...
PPTX
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
PDF
Managing Stormwater in the Hudson Valley: A Cost-Benefit Analysis of Permeabl...
Matt MacConnell, Lehigh River Stocking Association, “Lausanne Tunnel Remediat...
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
Chemung Landfill Expansion - The Facts
Assessment Of Permeable Pavement In High Volume Urban Flooding
Acf environmental 2016 apwa fl expo - integrated infrastructure-an innovati...
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
Managing Stormwater in the Hudson Valley: A Cost-Benefit Analysis of Permeabl...

What's hot (20)

PPTX
Delivering Mitigation Solutions for Natural Resource Extraction Projects: Ins...
PPTX
Hydrology Final Poster
PDF
DSD-INT 2019 Regional groundwater and geological voxel models for the Cauca V...
PDF
Urban Design Solutions for Ameliorating Urban Heat Island in Ipswich, Queensland
PPTX
George Ellis, ARIPPA, “Economic & Environmental Benefits of the PA Coal Refus...
PDF
Green Infrastructure in Omaha 4 22-15
PPT
2011 6 14 Home Builders of MD Environmental Site Design Introduction
PPTX
Desal in Texas: Past, Present and Future - Kyle Frazier
PDF
Dr. Kevin King - Impacting Water Quality Through Drainage Water Management
PPT
Maryland Environmental Site Design Presentation
PPTX
Water Resources Department 5 Year Capital Improvement Plan
PPT
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]
PPTX
Charleston midterm
PPTX
Design build strategies to optimize cost effectiveness in aml v2
PPT
Sustainable Water Savings for Irrigation Systems
PDF
CCUS_Mobile
PDF
Renting GAC Systems for Municipal Drinking Water Purification
PDF
Soil Moisture 102: Water Content Methods–Demystified
PDF
5 Reasons You’re Getting Less Accurate Soil Moisture Release Curves
PDF
Soil Moisture 201: Moisture Release Curves
Delivering Mitigation Solutions for Natural Resource Extraction Projects: Ins...
Hydrology Final Poster
DSD-INT 2019 Regional groundwater and geological voxel models for the Cauca V...
Urban Design Solutions for Ameliorating Urban Heat Island in Ipswich, Queensland
George Ellis, ARIPPA, “Economic & Environmental Benefits of the PA Coal Refus...
Green Infrastructure in Omaha 4 22-15
2011 6 14 Home Builders of MD Environmental Site Design Introduction
Desal in Texas: Past, Present and Future - Kyle Frazier
Dr. Kevin King - Impacting Water Quality Through Drainage Water Management
Maryland Environmental Site Design Presentation
Water Resources Department 5 Year Capital Improvement Plan
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]
Charleston midterm
Design build strategies to optimize cost effectiveness in aml v2
Sustainable Water Savings for Irrigation Systems
CCUS_Mobile
Renting GAC Systems for Municipal Drinking Water Purification
Soil Moisture 102: Water Content Methods–Demystified
5 Reasons You’re Getting Less Accurate Soil Moisture Release Curves
Soil Moisture 201: Moisture Release Curves
Ad

Viewers also liked (16)

PDF
UXSG User Experience Singapore 2013
PPT
Asset Management presented at Tennessee APWA
PDF
The tension theorm By tension Disciple Ganesh Prasad Rana
PPTX
Televisions maria
PPT
Sustainable Roundabouts presented to Michigan Association of Planning in a Pe...
PPTX
Televisions maria
DOCX
Campbell
KEY
Sizemore evan visual speech
PPT
Asset Management Doing More With Less
PPT
Presentacion total
PPTX
Presentación1
PPTX
Conklin
PPT
深蓝
PDF
NUS IPS Young Singaporeans Conference 2012 : Are Young Singaporeans Happy?
PDF
TYPO San Francisco 2013
PDF
Pecha Kucha Singapore
UXSG User Experience Singapore 2013
Asset Management presented at Tennessee APWA
The tension theorm By tension Disciple Ganesh Prasad Rana
Televisions maria
Sustainable Roundabouts presented to Michigan Association of Planning in a Pe...
Televisions maria
Campbell
Sizemore evan visual speech
Asset Management Doing More With Less
Presentacion total
Presentación1
Conklin
深蓝
NUS IPS Young Singaporeans Conference 2012 : Are Young Singaporeans Happy?
TYPO San Francisco 2013
Pecha Kucha Singapore
Ad

Similar to Green infrastructure policy for stormwater infiltration (20)

PPS
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
PPTX
Capstone Midterm
PDF
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
PDF
WET Feature 4 - Building bigger and better - Jan_16
PDF
Permitting potable water from rainwater- AIA Houston- September 2014
PDF
The Toolbox for Clean Water Construction
PPT
Managing stormwater in the Hudson Valley: a cost benefit analysis of permeabl...
PPTX
Louisville MSD
PPTX
Final poster final
PPTX
Pioneer Turbine
PPTX
Pvr presentation 20150707
PPTX
Pvr presentation 20150707
PDF
Transbay Presentation Sustainable Silicon Valley
PPTX
August 24 Clean Water Facility Planning Public Forum
PPT
Stormwater Management Bylaw
PDF
GIS Presentation_BDH
PPTX
"We've got to do what now?" Webinar
PPTX
Resource Recovery Panel
PPT
Steve_Wielebski_(Developer_perspective).ppt
PPT
Lisa stormcon presentation number one ieca
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
Capstone Midterm
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
WET Feature 4 - Building bigger and better - Jan_16
Permitting potable water from rainwater- AIA Houston- September 2014
The Toolbox for Clean Water Construction
Managing stormwater in the Hudson Valley: a cost benefit analysis of permeabl...
Louisville MSD
Final poster final
Pioneer Turbine
Pvr presentation 20150707
Pvr presentation 20150707
Transbay Presentation Sustainable Silicon Valley
August 24 Clean Water Facility Planning Public Forum
Stormwater Management Bylaw
GIS Presentation_BDH
"We've got to do what now?" Webinar
Resource Recovery Panel
Steve_Wielebski_(Developer_perspective).ppt
Lisa stormcon presentation number one ieca

Recently uploaded (20)

DOCX
Double Membrane Roofs for Bio-gas Tanks Reliable containment for biofuel gas....
DOCX
Biogas Balloon for Bio CNG Plants An efficient solution for biogas storage..docx
PPTX
EME Aerospace.pptx basics of mechanical engineering
PPTX
Importance of good air quality and different pollutants.
PDF
The European Green Deal (EU Green Deal)
PPTX
Environmental pollutants for natural res
PDF
1748933543SJA_41_2_826-834 SJA Ihsan ullha.pdf
PPTX
Biodiversity PPT by Gaithanlung Gonmei.pptx
PPTX
STL Academy - Highlights & Impact 2020-21-v2 (1).pptx
PPTX
Untitled 1.pptxhhhhhhjjjbbbbb bikinis sis son ka s
PPTX
Unit 1 - Environmental management, politics and.pptx
PDF
IWRM - City University Presentation 28 may 2018-v3.pdf
DOCX
Double Membrane Roofs for Cassava Wastewater Treatment Captures biogas from i...
DOCX
Double Membrane Roofs for Biomethane Storage Holds upgraded biomethane fuel.docx
PPTX
Definition, Causes And Effects Of Greenhouse.pptx
PDF
Biomass cookstoves: A review of technical aspects
PDF
Cave Diggers Simplified cave survey methods and mapping
PPTX
IMPACTS OF CHEMICAL FERTILIZERS -CHEMPROJ (11).pptx
PPTX
102602734019608717246081273460745534.pptx
PDF
BD4E4- DISASTER MANAGEMENT BY A.R.SIVANESH.pdf
Double Membrane Roofs for Bio-gas Tanks Reliable containment for biofuel gas....
Biogas Balloon for Bio CNG Plants An efficient solution for biogas storage..docx
EME Aerospace.pptx basics of mechanical engineering
Importance of good air quality and different pollutants.
The European Green Deal (EU Green Deal)
Environmental pollutants for natural res
1748933543SJA_41_2_826-834 SJA Ihsan ullha.pdf
Biodiversity PPT by Gaithanlung Gonmei.pptx
STL Academy - Highlights & Impact 2020-21-v2 (1).pptx
Untitled 1.pptxhhhhhhjjjbbbbb bikinis sis son ka s
Unit 1 - Environmental management, politics and.pptx
IWRM - City University Presentation 28 may 2018-v3.pdf
Double Membrane Roofs for Cassava Wastewater Treatment Captures biogas from i...
Double Membrane Roofs for Biomethane Storage Holds upgraded biomethane fuel.docx
Definition, Causes And Effects Of Greenhouse.pptx
Biomass cookstoves: A review of technical aspects
Cave Diggers Simplified cave survey methods and mapping
IMPACTS OF CHEMICAL FERTILIZERS -CHEMPROJ (11).pptx
102602734019608717246081273460745534.pptx
BD4E4- DISASTER MANAGEMENT BY A.R.SIVANESH.pdf

Green infrastructure policy for stormwater infiltration

  • 1. An Overview of NEW STORMWATER RULES (PENDING June adoption) Evan N. Pratt, P.E. Water Resources Commissioner
  • 2. OUTLINE A. Why Change? B. Value of Infiltration C. 3 Main Changes D. Development Benefits and Concerns E. Community Benefits and Concerns F. Case/Cost Studies and Examples G. Summary Talking Points – Let’s be consistent
  • 3. WHY ARE WE HERE? THESE PEOPLE CAN’T CHANGE POLICY – BUT HAVE TO LIVE WITH IT
  • 10. Q: Why Infiltration? A: TSS Removal Efficiencies SOURCE: 2005 DATA REPORT, UNH STORMWATER CENTER
  • 11. Top 5 TSS Removal Efficiencies  POROUS PAVEMENT– 100%  GRAVEL WETLAND – 100%  STORAGE BASIN INFILTRATION– 100%  TREE FILTER – 93%  BIORETENTION – 92%  RETENTION POND – 65%  SWALE – 55+%
  • 12. WCWRC RULES: WHAT IS CHANGING? 3 KEY CHANGES 1. PROCESS: MANDATORY PRE-APPLICATION MEETING 2. TECHNICAL APPROACH a. METHOD OF CALCULATING RUNOFF: NO IMPACT b. STORMS HAVE GOTTEN BIGGER 3. INFILTRATION REQUIREMENT a. First 1”, OR b. Must prove that soils are unsuitable for infiltration
  • 14. 1. PROCESS: PRE-APPLICATION MEETING GENERAL EVALUATION Purpose: Engage Owner, clarify changes and benefits Soil types Information on geology and hydrology including estimate of groundwater table elevation Topography Land cover Other pertinent natural or man-made features Potential locations for infiltration BMPs
  • 15. 2. TECHNICAL: 1% STORM  Current MDEQ 24 hour 1% storm = 4.36 inches  NOAA Atlas 14, Volume 8  Published 2013  Provides data for discreet locations  Ann Arbor, Milan & Ypsilanti Stations  Range for the 24 hour 1% storm at these stations varies minimally  All indicate the 24 hour 1% storm = 5.11 inches  Chelsea Station  24 hour 1 % storm = 5.21  New WCWRC Rules 24 hour 1 % storm = 5.11 inches
  • 16. 2. TECHNICAL: Method of Calculation SUMMARY: Method yields about the same results for detention on several sites.  “The Oakland County Method” vs. “NRCS Curve Number”  Peer Review Comparisons  WCWRC Deputy WRC -- Dennis Wojcik, P.E. verifications  705 N. Zeeb Road  Two Other Site Developments
  • 17. 3. INFILTRATION  MDEQ NPDES Permit Application  Require that post-construction runoff rate and volume of discharges not exceed the pre-development rate and volume for all storms up to the two-year, 24 hour storm at the site. At a minimum, pre-development is the last land use prior to the planned new development or redevelopment.  WCWRC Rules will require infiltration of the greater of the first flush volume or difference between pre-settlement and post-development 24 hour 50% storm.
  • 18. HOW DOES DEVELOPMENT BENEFIT? Many developers are finding lower cost for GI when used in greenfields. Case studies at http://tinyurl.com/streetrunoff  Less concrete infrastructure needed.  Less surface area of storage needed if doing infiltration  Less impact to developable area with co-location  It will always be more costly to develop unsuitable land  This is why poorly suited land (soils, etc) is cheaper  Public cost of developing poorly suited land  Whose job is it to look at total cost of a site?
  • 19. COMMUNITY BENEFITS and CONCERNS  Reduction in community costs related to development  Soils have always been integral to land use decisions. Now on County GIS – NRCS Soils layer under “Soils”  Collaboration during pre-application process  HOW WILL YOUR COMMUNITY FUND LEGACY COSTS OF DEVELOPMENT? 35% GENERAL FUND (OLD WAY) OR MORE LIKE WCRC?
  • 20. DEVELOPER CASE STUDY: GI COST SAVINGS
  • 21. Case Study: Boulder Hills Pelham, NH  2009 -- 900’ OF PRIVATE RESIDENTIAL PAVING IN NE  SITE GOAL OF ZERO DISCHARGE  55+ ACTIVE ADULT COMMUNITY  SANDY SOILS (NOT A MUST)
  • 22. COST AVOIDANCE  1616’ CONCRETE CURB  785’ PIPE  8 CATCHBASINS  2 DETENTION BASINS & 2 OUTLET STRUCTURES  SAVED 1.3 ACRES IN LAND CLEARING/CONSUMPTION  CONVENTIONAL = $789,500 vs. LID SWM= $740,300  INFILTRATION COST SAVINGS = $49,000 = (6.2%)  O/M DISCUSSION LATER – ALSO LESS
  • 24. HOW POROUS O/M IS MUCH LESS WHAT IF PAVEMENT NEVER CRACKED?
  • 25. HOW POROUS O/M IS MUCH LESS …AND IS SUPPOSED TO HAVE WATER IN THE BASE
  • 26. HOW POROUS O/M IS MUCH LESS $- $10,000 $20,000 $30,000 $40,000 $50,000 $60,000 $70,000 $80,000 $90,000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 HMA Maintenance With Sweeping Cumulative Porous Sweeping Costs
  • 27. WHY CHANGE: LET’S ALL GIVE THE SAME ANSWERS SOAKING WATER INTO THE GROUND IS SIMPLER AND CAN COST LESS WCWRC WILL WORK WITH OWNERS BEFORE A PURCHASE DECISION. OWNER’S RESPONSIBILITY TO EVALUATE DEVELOPMENT COSTS OF CHEAPER PROPERTY. GOVERNMENT AGENCIES ARE ALREADY INVESTING
  • 28. GOVERNMENT AGENCIES ALREADY INVEST IN GREEN INFRASTRUCTURE
  • 29. WCWRC OFFICE – 705 N. ZEEB  13 years old  42,000+ sft.  Detention (2)  Bioswales  Level Spreader  Infiltration Bed  Solar Panels  Native Veg. BUT  No Credit
  • 30. WASHTENAW COUNTY BUILDING  Current method detention volume = 45,000 c.f.  Revised method detention volume = 60,000 c.f.  Reduction in volume utilizing BMPs installed = 11,000 c.f.  Revised method required detention volume = 49,000 c.f.
  • 31. 705 ZEEB ROAD REDUCED CONSTRUCTION COST  8 structures @ $2,000 ea. = $16,000  425 ft.-12in. RCP @ $40/ft. = $17,000  265 ft.-15 in. RCP @ $50/ft. = $13,250  Savings = $46,250 (FIRST FLUSH ONLY)  BUT SOILS ARE SUITABLE FOR 100% INFILTRATION  Extra Savings: 1,950 cyd earthwork @ $10/cyd = $19,500  NET SAVINGS = at least $65,750 (plus additional pipe savings, offset by need to add bioswale) -Will be estimating porous asphalt option in future version
  • 33. After planting – still standing water
  • 34. Eastern Michigan University, InSite Design Studio Plants mature – no standing water
  • 37. http://tinyurl.com/streetrunoff TAKE AWAY MESSAGES 1. Human activity is the #1 cause of many problems. The purpose of the New Rules is to: A. Reduce long term cost impacts to communities and taxpayers B. Reduce water quality and flooding impacts of development 2. Good sites with good soils will result in less costly projects – Owners’ responsibility during site selection & due diligence. 3. WCWRC is available to work with communities and the Owner on challenging sites.