SlideShare a Scribd company logo
Report on Solar Power Policies
&
Project Development in India
Sumit Mishra
Table of Content
I : Introduction…………………………………………………………… 3
II : Solar Technology …………………………………………………….. 3
1. Solar Photovoltaic (PV)……………………………………………. 3
2. Concentrating Solar Power System (CSP) …………………………. 4
3. Solar Heating & Cooling …………………………………………… 4
III : Working of solar PV ………………………………………………….. 4
IV : Photovoltaic Technologies ……………………………………………. 5
1. Crystalline Silicon …………………………………………………… 5
2. Thin Film ……………………………………………………………. 5
V : India’s Solar Market ……………………………………………………. 6
VI : Policy Initiative ………………………………………………………… 8
1. Jawaharlal Nehru National Solar Mission …………………………... 10
a. JNNSM Phase I…………………………………………………… 10
b. JNNSM Phase II ………………………………………………….. 11
c. JNNSM Phase II Batch I ………………………………………….. 12
d. JNNSM Phase II Batch II ………………………………………… 13
2. State Solar Policies ………………………………………………….. 13
3. Renewable Purchase Obligation …………………………………….. 16
4. Net Metering Policy ………………………………………………… 16
VII: Development of Solar PV Project ………………………………………. 18
1. Land/ Site selection …………………………………………………. 18
a. Solar Resources ………………………………………………….. 18
b. Available Area …………………………………………………... 19
c. Climate & topography …………………………………………… 19
d. Accessibility & RoW ……………………………………………. 20
e. Grid Connection …………………………………………………. 20
f. Water Availability ……………………………………………….. 20
2. Pre-Feasibility & Feasibility Study …………………………………. 20
3. Engineering, Procurement & Construction Contract …………….…. 20
4. Transmission Agreement ……………………………………………. 21
5. Clearances & Approvals …………………………………………….. 21
6. Operation & Maintenance Contract …………………………………. 22
VIII: Conclusion …………………………………………………………… 22
I: Introduction: Solar energy is the energy received from the Sun that sustains
life on Earth. For many decades solar has been considered to be a huge source
of energy & also economical one because it is freely available. However, it is
only now, after years of research that technology has made it possible to harness
solar energy. Key benefits of solar power is:
1. Freely available in abundant quantity.
2. Environment friendly
3. No fuel cost
4. Low operation & maintenance cost.
Basic principles of Solar Technology is that , the sun rays contains energy, and
normally when these rays hit an object that energy turns to heat but when these
rays hit silicon (Solar Cell), the energy becomes an electrical current that can be
harnessed for power. Silicon is the main ingredient in solar panels and is used to
capture the sun’s energy and turn it into electricity. This electricity is then
converted into clean, affordable power for your home. The whole process is
represented in Figure 1.
Figure 1: Generation of Solar Energy
II: Solar Technologies:
Solar energy is the cleanest, most abundant renewable energy source available.
Today's technology allows us to harness this resource in several ways. There are
three primary technologies by which solar energy is commonly harnessed:
1. Solar Photovoltaic (PV): These solar technologies directly produce
electricity which can be used, stored, or converted for long-distance
transmission. PV panels can be manufactured using a variety of materials
and processes and are widely-used for solar projects around the world.
2. Concentrating Solar Power system (CSP): Using reflective materials like
mirrors and lenses, these systems concentrate sunlight to generate thermal
energy, which is in turn used to generate electricity. Similar to traditional
power plants, many CSP plants are hundreds of megawatts (MW) in size
and some can continue to provide power after sunset
3. Solar Heating & Cooling: These technologies generate thermal (heat)
energy for water & pool heating and space heating. This type of
technology is generally used in houses for water heating.
III: Working of Solar PV: The main components of a PV power plants are:
1. Solar PV Modules: These convert solar radiation directly into electricity
through the photovoltaic effect in a silent and clean process that requires no
moving parts. The PV effect is a semiconductor effect whereby solar
radiation falling onto the semiconductor PV cells generates electron
movement. The output from a solar PV cell is direct current (DC) electricity.
A PV power plant contains many cells connected together in modules and
many modules connected together in strings to produce the required DC
power output.
2. Mounting Systems (Tracking –optional): These allows PV modules to be
securely attached to the ground at a fixed tilt angle or on sun tracking
frames.
3. Inverters: These are required to convert DC electricity to alternating current
AC for connection to the utility grid.
4. Step up Transformers: The output from the inverter generally requires a
further step-up in voltage to reach the AC grid voltage level.
5. Grid connection: This is where electricity is exported into the grid network.
Figure 2: Overview of Solar PV system
The above mentioned components collectively form a Solar PV system. The
complete assembly of solar power PV system is shown in figure 2.
A valuable feature of photovoltaic systems is the ability to connect with the
existing power grid which allows owners to sell excessive electricity back to the
utility with a plan known as Net Metering. At times when you are not using all
of the electricity produced by your system, your meter will spin backwards
selling the electricity back to the utility power grid.
IV: Photovoltaic Technologies:
The large variety of PV applications allow for a range of different technologies
to be present in the market , from low cost , lower efficiency technologies to
high efficiency technologies at high cost. Commercial PV modules may be
divided into two broad categories:
1. Wafer based Crystalline Silicon (C-Si) (Manufactured by cutting wafers
from solid ingot block of silicon). The Crystalline Silicon (C-Si) modules
represent 85-90% of the global annual market today. They are further
subdivided into Mono-crystalline silicon or Poly-crystalline silicon. Mono-
crystalline silicon cells are generally the most efficient, but are more costly
than poly—c-Si.
2. Thin films technologies (in which a thin layer of a semiconductor material is
deposited on low cost substrates).Thin films currently account for 10% to
15% of global PV module sales. Thin film cells provide a cheaper
alternative, but are less efficient. There are three main types of thin film
cells: Cadmium Telluride (CdTe), Copper Indium (Gallium) Di-Selenide
(CIGD/CIS) and Amorphous Silicon (a-Si).
Figure 3. Types of S-PV technologies
The efficiency of different PV technology commercial modules is as follows:
Figure 4. Efficiency Chart of PV cells
The cost of a project is highly dependent upon the type of PV technology
adopted because the total cost of the system /project are composed of the sum of
module cost , efficiency of module, land required , balance of system , inverter
etc. The better the efficiency of a solar PV system the lesser the land required
for installation of PV system.
V: India’s Solar Market:
India is located in the equatorial sun belt of the Earth & hence receives
abundant radiant energy from sun. India receives high Solar Irradiation in most
parts of the country – annual average Global Horizontal Irradiation of 5.1, with
large number of sunny days (approx. 330). Because of high GHI in some part of
the country we can achieve a Capacity Utilisation Factor (CUF) of 21-23 %.
This means that a 1 MW solar power plant can produce 1.85 million units of
electricity per year.
Solar PV
Technology
Crystalline
Silicon
Mono
Crystalline
Poly Crystalline
Thin Film
Amorphous
Cadmium
Telluride
(CdTe)
Copper Indium
Di-Selenide
CIS/CIGS
10-12%
CdTe
9-11%
a-Si;a-Si/µc-Si
6-9%
Wafer Based C-Si
Technology
Thin Films Technology
Considering the Solar ir-radiation data, available waste land & other factor, it is
estimated that our country has a solar potential of 748 GWp. The state wise
solar potential detail is presented in table 1 below:
State Solar
Potential
(GWp)
State Solar
Potential
(GWp)
State Solar
Potential
(GWp)
Rajasthan 142.31 Telangana 20.41 Nagaland 7.29
Jammu &
Kashmir
111.05 Chhattisgarh 18.27 West
Bengal
6.26
Maharashtra 64.32 Jharkhand 18.18 Kerala 6.11
Madhya
Pradesh
61.66 Tamil Nadu 17.67 Meghalaya 5.86
Andhra
Pradesh
38.44 Uttarakhand 16.80 Sikkim 4.94
Gujarat 35.77 Assam 13.76 Haryana 4.56
Himachal
Pradesh
33.84 Bihar 11.20 Punjab 2.81
Odisha 25.78 Manipur 10.63 Tripura 2.08
Karnataka 24.70 Mizoram 9.09 Delhi 2.05
Uttar
Pradesh
22.83 Arunachal
Pradesh
8.65 Goa & UT 1.67
Table 1: State wise Solar Potential
The outlook of solar sector in India is extremely positive, driven by powerful
underlying fundamentals such as rising cost of conventional power,
environmental concerns, falling costs of Solar power, high solar ir-radiation , a
high power deficit & the ability of solar to quickly bring power generation
capacity online. These fundamental coupled with several state & central
government initiatives should result in India becoming one of the largest solar
market in the world.
A SWOT analysis of Indian solar market is carried out for understanding the
strength, weakness, opportunity & threat to Indian Solar energy sector.
Figure 5: SWOT Analysis for developing Solar Project in India
VI: Policy Initiative: The Government of India (GoI) has taken several
initiative to promote solar energy market in India not only for energy security
but also for their commitment towards global warming.
Several policy at national & state level has been announced & highly ambitious
target has been set by the respective government. In the last 5 years India has
seen tremendous growth in its Solar installed capacity from a mere 22 MW in
2010 to 4011 MW by May 2015. This installed capacity is a result of
introduction of various policies viz. National solar Mission (Phase I & II) state
solar policies & REC mechanism etc. State wise solar installation detail is
presented in figure 6 below.
Strength
1. High Growth industry with significant future
potential.
2. Sunlight is available in sufficient quantity in
many regions.
3. Proven technology with low operation &
maintenance cost , which is also scalable.
4. Availability of Governmant incentives for
growth & expansions.
Weakness
1. Owing to high capital costs, the business
needs external incentives to be economical
feasible , thus increasing dependence on
Governmental policies.
2. The Capital intensive nature of the business
might favour larger business over smaller one.
3. The distributed & intermittent nature of solar
energy makes it difficult for utilities to rely on
Solar PV for their base load.
Opportunities
1. Government ambitious target & attractive
policies open up many avenues for
investment.
2. Opportunities exist all along the Solar PV
business value chain.
3. Entirely new opportunities could open up as
there is high innovation in technology,
especially with reduction in cost in future.
Threats
1. Off Peak season reduces cash flow.
2. Finding skilled manpower is a issue.
3. Solar Panels work only at 22% efficiency
therefore achieving solar targets could be
difficult despite scaling up .
SWOT Analysis
Figure 6: Utility Scale Solar Installed Capacity…as of May’15
Under National solar Mission GoI targets for setting up of 20,000MW (Revised
to 100,000 MW) solar capacity shows commitment of the government towards
development of solar market in India.
The announcement of various state level policies and the allocations under
NSM (Phase 1 &2) have brought fresh excitement to the market. Government
policies have so far been the prime driver for the solar energy sector in India
however there has been a gradual move from an incentive driven market to a
parity driven market. In addition to NSM and state policies developer also have
the option of setting solar power plant for captive purpose and avail benefit of
selling green attributes in the form of Renewable Energy Certificates (RECs) at
power exchanges.
Various states have now introduced their Net metering policies to attract
development of rooftop in their respective states. Net Metering is the regulatory
ability to get credit for electricity user generate with solar energy and send
backwards through their utility meter. Exact provisions vary with each state, but
the effect is to allow user to generate excess power during the day, and use it at
night, without needing batteries. For the injected quantity user will be
incentivise as per the rate fixed under the Net metering policy of their respective
states.
228
6
4
953
19
99
354
71
240
1128
164
5
68
18
637
7
5
2
1
2
0 200 400 600 800 1000 1200
Andhra Pradesh
Chhattisgarh
Delhi
Gujarat
Haryana
Karnataka
Maharashtra
Odisha
Punjab
Rajasthan
Tamil Nadu
Uttarakhand
Uttar Pradesh
Jharkhand
Madhya Pradesh
West Bengal
Andaman & Nicobar
Chandigarh
Lakshadweep
Other
Installed Capacity in MW
A detailed discussion on the respective policies is presented in the later part of
the report for better understanding.
Installed Solar Capacity in India under various policies:
Figure 7: India’s installed solar capacity under different policies
1. Jawaharlal Nehru National Solar Mission (JNNSM): The Jawaharlal
Nehru National Solar Mission (JNNSM) was the major initiative of
Government of India (GoI) and state government to promote ecologically
sustainable growth while addressing India’s energy security challenges. It
plays a prime role in India's contribution to the fight against issues of climate
change, which was the big concern across the globe. The launch of the
National Solar Mission (NSM) has given a big impetus to solar energy in
India. The Mission adopted a 3 phase approach, spanning the period of the
11th Five Year Plan and first year of the 12th Five Year Plan (up to FY2012-
Projects under NSM Projects under State Policy Projects under other policies
13) as Phase 1, the remaining 4 years of the 12th Plan (FY2013-17) as Phase
2 and the 13th Plan (FY17-22) as Phase 3.
To facilitate grid connected solar power generation under phase I without
any Government subsidy, GOI approved NTPC Vidyut Vyapar Nigam Ltd
(NVVN) as the nodal agency to purchase 1,000 MW from project developers
and sell this bundled power to the distribution utilities. The concept of
Bundling was introduced to select projects of 500 MW capacity each based
on solar thermal and PV technologies.
On 18th June 2015, in a major policy move, the government has announced
a massive scaling up of the targets for India's solar power capacity target
under Jawaharlal Nehru National Solar Mission (JNNSM) by five times,
reaching 1,00,000 MW by 2022.
The target will principally comprise of 40 GW (solar) rooftop & 60 GW
through large and medium scale grid connected solar power projects.
Toward achieving this target the government envisages a total investment in
setting up 100 GW will be around Rs 6, 00,000 crores. In the first phase, the
Government of India is providing Rs 15,050 crores as capital subsidy to
encourage solar energy based projects. This capital subsidy will be provided
for Rooftop Solar projects in various cities and towns, for Viability Gap
Funding (VGF) based projects to be developed through the Solar Energy
Corporation of India (SECI) and for decentralised generation through small
solar projects. The new solar target of 100 GW is expected to result in the
reduction of over 170 million tonnes of carbon dioxide, a gas contributing to
climate change.
a. JNNSM Phase 1: During Phase 1, a total of 1000MW of Solar Power
Projects were selected, with solar PV and Solar Thermal projects to be
allocated in the ration of 50:50. It was divided into batch 1 & 2 over FY
2010-11 & FY 2011-12, respectively. The highlight of Phase 1 is presented
in Table-2 below.
NSM Phase 1, Batch 1 NSM Phase 1, Batch 2
Managed by NVVN NVVN
Capacity
allocation
PV: 150 MW (PPA signed only
for 140MW)
CSP: 470 MW
PV: 350 MW (PPA signed
only for 340 MW)
CSP: Nil
Maximum &
Minimum
Project Capacity
PV: Min: 5 MW, Max: 5 MW.
CSP: Min: 5MW, Max:100 MW
(Max. of 3 project locations
Min: 5 MW,
Max: 20 MW
Maximum
capacity by a
bidder
PV: 5 MW,
CSP: 100 MW
50 MW
Domestic
Content
Requirement
(DCR)
PV: For projects based on c-Si
technology, the modules must
have been manufactured in India
CSP: 30% domestic content
mandatory
For Projects based on c-Si
technology, the modules
must have been
manufactured in India
Policy
Mechanism
Preferential feed-in tariff Preferential feed-in tariff
Allocation
Method
Reverse bidding on benchmark
tariff (per kWh): PV: INR
17.91/kWh, CSP: INR
15.31/kWh
Reverse bidding on
benchmark tariff (per
kWh): INR 15.39/kWh
Commissioning
time period
PV: 12 months, CSP: 28 months 13 months
Weighted
average of
winning bid
PV: INR 12.16/kWh ,
CSP: 11.48/kWh
PV: INR 8.77 / KWh
Project
Commissioned
PV: 140 MW,
CSP: 50 MW
PV: 330 MW
Technology
breakdown
Thin film: 55%, rest:
polycrystalline
Thin film: 75%, rest:
polycrystalline
Required bank
guarantee
INR 5 million/MW INR 5 million/MW
Table 2: Highlights of JNNSM Phase I
b. JNNSM Phase II : Out of the 60 GW of utility scale solar planned by 2022,
15 GW is expected to be developed under the National Solar Mission (NSM)
by 2019 using a combination of different structures including bundling of
Power , VGF, and interest rate subvention.
Proposed share of Solar PV and Solar Thermal at Central/State levels
during phase II:
Item
Description
Share Central Scheme State Scheme
Percentage
%
MW Percentage
%
MW Percentage
%
MW
Solar PV 70 10500 40 4200 60 6300
Solar
Thermal
30 4500 40 1800 60 2700
Total 100 15,000 - 6000 - 9000
Table 3: Proposed share of PV & CSP under Phase II at Central & State level
c. JNNSM Phase II Batch I: The total capacity targeted under this phase is
750 MW & all of the projects will use photovoltaic technology. The winners
were the project developer who sought the minimum possible funds to make
their projects viable to sell power to SECI at a tariff of Rs 5.45/kWh (Rs
4.75/kWh for project claiming accelerated depreciation) for 25 years. With
an object to promote local manufacturing, SECI invited bids in two separate
categories, reserving half of the projects under domestic content requirement
(DCR) restrictions.
Time Frame for JNNSM Phase II Batch I is as follows:
Sr. No Event Date
1 Approval of RfS documents by SECI Zero date
2 Issue of RfS documents (Sale of
Documents)
Zero date + 7 Days
3 Submission of Bids (Techno-
Commercial & Financial) Opening of
Techno-Commercial bids
Within 60 days from issue of
RfS
4 Evaluation of Techno-Commercial
bids & shortlisting of bidders
Within 60 days from
submission of bids
5 Opening of Financial bids Within 7 Days from
shortlisting of bidders
6 Issue of Letter of Intents ( LoI) Over a period of 15 days after
opening of financial bids
7 PPA Signing Within 30 days from the date
of signing of PPA
8 Financing arrangement Within 210 days from the date
of signing of PPA
9 Commissioning of Projects Within 13 months from the
date of signing of PPA
Table 4: Timeline for JNNSM Phase II batch I
d. JNNSM Phase II Batch II: MNRE proposed to add a total Solar PV
capacity of 15000 MW in three tranches to be implemented through NVVN
as part of Phase-II Batch-II. The scheme envisages setting up of Grid-
connected solar PV power plants of 15,000 MW aggregate capacity through
open competitive bidding as under:
(i) Tranche-I: 3,000 MW: 2014-15 to 2016-17 (Bundling with 1500 MW
unallocated NTPC Power from Coal Station allocated by MoP).
(ii) (ii) Tranche-II : 5,000 MW: 2015-16 to 2017-18 (selection mechanism
to be decided later)
(iii) (iii) Tranche-III : 7,000 MW: 2016-17 to 2018-19 ( selection
mechanism to be decided later)
2. State Solar Policies: In addition to the National Solar Policy, various states
have also announced State Level Policies aimed at encouraging investment
in their respective states. State Solar policies & capacity addition are usually
driven by three broad factors:
a. Renewable Purchase Obligation , (RPO)
b. Demand for new power generation capacity
c. Political commitment to the renewable sector.
States like Tamil Nadu, Andhra Pradesh, Karnataka, Jharkhand, Bihar and
Odisha etc. has come up with their solar policies. All these policies are more
concentrated towards the central agenda of reaching 100GW by 2022 and
thus almost all the policies have kept the provisions of various incentives and
benefits to the developer. A target of 50 GW has been set under the state
policies, a brief of various state policy is shown in table 5 below:
State PolicyTarget OffTaker Financialincentive ExemptionfromOAcharges OtherKeyBenefits DCR
AndhraSolarpolicy 5000MWby
2019
2GWtoState
Discoms
3rdPartyallowed
1.100%bankingforallcaptive&
OAduringall12monthsofthe
year.
2.Bankingcharge@2%of
energydeliveredwillbeadjusted.
Wheelingchargesexempted.
2.Distributionlossbelow
33KV-exempted.
4.CSSexemptedfor3rd
partysaleandcaptive
projectsfor5year
Exemptedfromobtaining
Pollutionclearances
EDexemptedfor3rdparty
sale,captiveconsumption
andsaletodiscom.
None
Table 5: Brief of State Solar Policies
Bihar Solar Policy 130 MW Captive , State
Discom & 3rd Party
No entry tax .
Incentive as per industry policy
applicable.
Wheeling & Transmission
charges as applicable.
ED exempted None
Chhattisgarh Solar
Policy
500 to 1000
MW by 2017
Captive & 3rd Party Stamp duty exempted.
Concession on land premium.
1. Not exempted (OA
Charges & losses applicable
as per CSERC order)
2. Wheeling & Transmission
charges applicable.
ED exempted on auxiliary
consumption & captive
consumption within the
state.
None
Gujarat Solar Policy Not defined Captive , State
Discom & 3rd Party
No additional financial incentive. No exemption ED exempted
CSS exempted
None
Haryana Solar Policy 100 MW State Discoms Incentive as applicable under
Industrial policy
No exemption Exemption from land use
charges
None
Jharkhand Solar Policy 2500 MW Captive , State
Discom & 3rd Party
100% Banking allowed.
VAT & Entry tax exempted.
Wheeling charge &
Distribution loss exempted.
ED Exempted , Pollution
clearance exempted.
None
Karnataka Solar Policy 2000 MW State Discoms , 3rd
Party , Captive
Concession on Stamp duty ,
registration charges & entry tax
as per industrial policy.
Banking charges waived.
Transmission charges ,
wheeling charges & CSS
waived for 10 Years.
ED exempted None
Kerala Solar Policy 500 MW by
2017
2500 MW by
2030
State Discoms , 3rd
Party , Captive
Banking facility available to
captive generator.
No OA Charges ED exempted.
Evacuation infrastructure
construction by state(for 10
MW below)
None
Maharashtra Solar
Policy
7500 MW by
2019
State Discoms , 3rd
Party , Captive
50% of transmission &
wheeling charges waived.
75% of CSS waived
ED exempted for 10 year.
Pollution clearance
exempted
None
MP Solar Policy 300 MW State Discoms , 3rd
Party , Captive
100% banking allowed in a FY @
2% of the banked energy.
VAT & entry tax exempted.
Transmission & Wheeling
charges reduced to 2% of
energy injected.
Wheeling Charges & CSS
waived
ED & Cess exempted for 10
year.
None
Odisha Solar Policy 135 MW by
2015
State Discoms , 3rd
Party , Captive
100 % banking allowed Wheeling & Transmission
charges applicable.
CSS waived.
ED exepmted None
Punjab Solar Policy 1000 MW by
2022
State Discoms , 3rd
Party , Captive
Banking Charges waived Transmission & Wheeling
charges reduced to 2% of
energy injected.
-
None
Rajasthan Solar Policy 25000 MW State Discoms , 3rd
Party , Captive
Banking allowed as per RERC
regulation.
OA charges applicable Pollution clearance not
required.
None
Tamil Nadu Solar
Policy
3000 MW by
2015
Obligated Entities
State Discoms
Preferential tariff based on
reverse bidding for a part of the
target
50% of transmission &
wheeling charges waived.
Single Window Clearance
GBI for residential
consumers
None
Telangana Solar Policy 5000 MW by
2019
State Discoms , 3rd
Party , Captive
100% Banking allowed. Wheeling charge exempted
for captive use within the
state.
CSS exempted for 3rd party
within the state.
ED Exempted , Pollution
clearance not required.
None
UP Solar Policy 500 MW by
2017
State Discoms Preferential tariff based on
reverse bidding
Wheeling & Transmission
charges exempted
Evacuation infrastructure
construction by state.
None
Uttarakhand Solar
Policy
500 MW by
2017
State Discoms , 3rd
Party , Captive
VAT & entry tax exempted. wheeling charges as per
state tariff.
Other OA charges as per
state tariff.
CSS waived None
West Bengal Solar
Policy
500 MW by
2022
Discoms LC from a nationalize bank as
apayment security.
Other concession and incentive
as per MNRE policy.
- -
None
As per the revised NSM target 60 GW of capacity should be utility scale A 60 GW
solar capacity should be from utility scale grid connected project and remaining 40
GW from off grid. To achieve that several states have revised their target under their
respective state policy. Figure 8 below shows the target set by the state under their
respective policies.
Figure 8: Targets set under state solar policies
3. Renewable Purchase Obligation (RPO): The Government of India (GoI),
through the central Electricity Regulatory Commission (CERC) has
introduced a Renewable Purchase Obligation (RPO’s) for all renewables as
per the requirement of the National Action Plan on Climate Change
(NAPCC). As per the RPO requirements, 15% of all power in the country
has to be sourced from renewable energy sources by 2020. For solar power
in particular, the RPO requirement is 3%. Individual state electricity
regulatory commission (SERC’s) have taken up this directive & have set
specific state targets. In addition, the government has introduced a market
tradable Renewable Energy Certificate (REC’s) for fulfilling Renewable
Purchase obligation. Under the REC mechanism developer are eligible to
receive one certificate for every 1000 kWh of renewable electricity fed into
the grid. Obligated Entities can buy these certificates to fulfil their
obligation.
4. Net Metering Policy: The concept of net metering involves recording the net
energy between export of generated energy and import of energy from
distribution licensee for a given period of time. This involves the usage of a
bi-directional meter which has the facility to record both import and export
values. Under the net metering system, the excess energy generated by the
solar photovoltaic plant at a given point of time is exported to the grid
instead of being stored using a battery. However when there is a deficit in
the power generated by the solar panels either during the night or a cloudy
day, energy is drawn from the grid. At the end of the billing period, if more
energy is exported to the grid than imported, then the distribution licensee
pays the consumer at a pre-determined price. On the other hand if more
energy is imported from the grid than exported, then the consumer pays the
distribution licensee at a predetermined price. These prices usually vary from
state to state.
As a part of the regulatory overhaul many state has come up with their Net
metering policy & brief of the respective state Net metering policy is
presented in table 6 below:
Table 6: Net metering policies of various state
State Cap on Solar
installation / injection
Grid penetration as
% of distribution
transformer capacity
Eligibility Excess
electricity
settlement
Project capacity
limit
Andhra Pradesh 100% of the electricity
consumption in a
billing month
Not mentioned Preferably allowed for 3
Phase service consumer
however single phase
consumer upto 3kW are alos
eligible.
As per APPC Upto 1 MW
Bihar Not Mentioned 15% Not Mentioned To be carried
forward to next
billing cycle
Maximum 1 MWp
Chhattisgarh Not Mentioned Annual energy
injection shall not
be more than 49% of
the annual net
generation
Not Mentioned To be billed at
50% of the
solar tariff (in
case energy
injected is less
than 49% of
annual net
generation)
50kWp to 1 MWp
capacity
Delhi system size less than
contracted load
20% All consumer As per APPC Above 1 kW
Goa & UT Not Mentioned 30% Consumer with single or
three phase supply
connection
As per Solar
tariff
1kWp to 1MWp
Haryana Injection < 90% of the
consumption in a year
15% All consumer To be carried
forward to next
billing cycle
1kWp to 1MWp
Himachal Pradesh Not Mentioned Not mentioned All consumer Not Mentioned Maximum 1 MWp
Karnataka Not Mentioned Not mentioned All consumer As per Solar
tariff (currently
9.56 /Unit
without
subsidy) & Rs
7.20 /Unit with
subsidy of 30%
Upto 500kWp
Kerala Not Mentioned 50% All consumer categories
availing electricity at
voltage level of and below
11kVA
As per APPC
(Rs. 1.99/Unit)
1kWp to 1MWp
Madhya Pradesh Not Mentioned Not mentioned All consumer Not Mentioned Not mentioned
Mahrashtra Not Mentioned Not mentioned Not Mentioned As per APPC Not mentioned
Meghalaya Not Mentioned Not mentioned All consumer Not Mentioned Maximum 1 MWp
Odisha Injection < 90% of the
consumption in a year
30% All consumer No Payment Not mentioned
Punjab System size < 80% of
the contracted load
30% All consumer As per retail
supply tariff of
that consumer
1kWp to 1MWp
Rajasthan System size < 80% of
the contracted load
30% All consumer As per Solar
tariff (currently
@ Rs 6.63/Unit)
1kWp to 1MWp
Tamil Nadu Injection < 90% of the
consumption in a year
30% Government run institution
& residential consumer
No Payment Not mentioned
Uttar Pradesh system size less than
contracted load
15% All consumer At Rs 0.50 /
Unit
More than 1 kW
Uttarakhand Not Mentioned Not mentioned All consumer As per Solar
tariff (currently
@ Rs 9.92/Unit)
5kW to 500kW
West Bengal Injection < 90% of the
consumption in a year
Not mentioned Institutional consumers like
Hospitals , Government
departments academic
institutions etc
As per APPC Upto 5 kW
VII: Development of Solar PV project:
The key steps for developing a solar PV project are well established & yet there
is no definitive detailed “road map” a developer can follow. The approach taken
in each project depends on site –specific parameters & the developer’s
priorities, risk appetite, regulatory requirement & the types of financing support
mechanism available in the given market. However in all cases certain activities
need to be completed that can be broadly be organized in the following 6 steps:
Figure 9: Steps for setting up of Solar Power Plant
1. Land /Site selection: Selecting a suitable site is a crucial part of developing a
viable project. In selecting a site the aim should be to maximise output and
minimise cost & the process of site selection must consider the constraints of
each site & the impact it will have on the cost of the electricity generated. The
main constraints that need to be assessed include:
a. Solar resources: The higher the resources the greater the energy yield per
kWp installed. When assessing the Global Horizontal Ir-radiation (GHI) at
site care must be taken to minimise any shading that will reduce the ir-
radiation received. Map showing India’s solar ir-radiation data is shown in
figure 10.
Land/Site
Selection
prefeasibility
& feasibility
study
Appointment
of EPC
contractors &
equipment
order.
Clearances &
approvals
Transmission
Agreement
O & M
Contractor
Figure 10: India’s solar Ir-radiation data
b. Available Area: The area required per kWp of installed capacity varies
with the technology chosen. Sites should be chosen with sufficient area to
allow the required capacity to be installed without having to reduce the
pitch (i.e. distance between rows of module) to levels that cause
unacceptable yield loss.
Depending upon the site location (altitude) the land required for a 1 MW
power plant setup is around 4.5-5 acres for crystalline technology and
around 6.5-7.5 acres for Thin-Film technology. This is only a rough
benchmark and may vary based on technology and efficiency of panels.
c. Climate & topography: In addition to a good solar resources, the climate
should not suffer from extremes of weather that will increase the risk of
damage or downtime.
Site should be flat or on a slight south facing slope in the northern
hemisphere or north facing slope in the southern hemisphere.
d. Accessibility & ROW: The site should allow access for trucks to deliver
plant & construction materials. The closer the site is to a main access road,
the lower the cost of adding this infrastructure. Row (i.e. access rights for
transmission lines on private land) should be exercised before finalising
the land.
e. Grid Connection: A grid connection of sufficient capacity is required to
enable the export of power. The viability of the grid connection will
depend on factors such as capacity, proximity, ROW, grid stability & grid
availability.
f. Water availability: Clean, low mineral content water is preferred for
cleaning modules. A reliable supply is required for module cleaning.
Other parameter which should be analysed before site selection are
geotechnical, geopolitical, module soiling & financial incentive etc.
2. Pre-feasibility & feasibility study: The aim of a prefeasibility study is to
develop a preliminary plant design & investment requirements, which allow
further assessment of the financial viability of the project. The prefeasibility
study should at minimum include an assessment of:
a. The project site & boundary area, ensuring access to the site is possible, both
legally & technically.
b. A conceptual design of the project giving different options of technology &
the financial impacts, including estimation of installed capacity.
c. Estimate cost of land & energy yield of the project.
d. A financial model to determine the commercial viability of the project for
further investment purposes.
e. Grid connection cost & likelihood of achieving a connection within the
required timeline.
f. Permitting requirements, costs, & likelihood of achieving consent.
The objective of the feasibility study is to provide more detailed information on
the potential project design, the investment requirements, and to plan for
financing and implementation. If the results of the study are favourable, the
developer should be prepared to invest more to advance the project to the
financing stage.
3. Engineering, Procurement, and Construction (EPC) contract:
Engineering, procurement and construction (EPC) contracts are the most
common form of contract for the construction of solar PV power plants. Under
an EPC contract, a principal contractor is engaged to carry out the detailed
engineering design of the project, procure all the equipment and materials
necessary, and then construct and commission the plant for the client.
The EPC contract for any project-financed solar PV power plant will typically
be held between a project company (the owner) and the EPC contractor (the
contractor). It is common practice to use a standard form of contract (sometimes
referred to as a “boilerplate contract”) as a template and basis for the EPC
contract.
The key clauses for a project owner in any construction contract are those that
relate to time, cost and quality. In the case of solar PV power plant construction,
a strong EPC contract will address the following areas:
 A “turnkey” scope of work.
 A fixed completion price.
 A fixed completion date.
 Restrictions on the ability of the contractor to claim extensions of time
and additional costs.
 A milestone payment profile that is suitably protective to the owner and
based upon the completion of predefined sub-tasks.
 Plant PR guarantees.
 LDs for both delay and performance.
 Financial security from the contractor and/or its parent organisation.
 A defects warranty.
4. Transmission agreement - The project developer will need to sign a
transmission agreement with the States respective STU.
5. Clearances & approvals: Clearances & approvals requirements for solar
PV power plants vary greatly from country to country and within different
country regions. It is important therefore to establish with the appropriate
planning/ government authority the relevant laws/ regulations and associated
clearances & approvals that will be required for the project. In some of the
states, State Nodal agency acts as a facilitator for getting clearances. Major
clearances which need to be obtained are:
a. Consent to Establish and Consent to Operate from State Pollution
Control Board
b. Import/License in case of import of plant and machinery.
c. No objection certificate from Civil Aviation Department.
d. No objection certificate from District Collector for setting up the project.
e. No objection certificate from the Panchayat under which the project area
is located.
f. Approval for water requirement in case of solar thermal projects.
g. Permission for laying power evacuation lines from Chief Electrical
Inspector.
h. No Objection Certificate from energy department.
i. Permission for 'Implementation of Metering Code', 'Protection System' to
be obtained from host Distribution Utility or the STU or the Central
Transmission Utility as the case may be.
6. Operation & Maintenance (O&M) contract: Compared to other power
generating technologies, solar PV power plants have low maintenance &
servicing requirements. However proper maintenance of a PV plant is
essential to maximise both energy yield & the plant’s useful life.
The presence of an operation & maintenance (O&M) contract is crucial to
define the parameter for the operation & maintenance of a project during its
life. The project developer shall appoint a private O&M contractor and enter
into an O&M contract. This shall specify details regarding project uptime,
personnel required, spare acquisition etc. for project operation and
management.

More Related Content

PDF
A Summer Internship report
PDF
Maximizing Output Power of a Solar Panel via Combination of Sun Tracking and ...
PDF
Report on the IMPROVING THE EFFICIENCY OF SOLAR PHOTOVOLTAIC POWER GENERATION...
PDF
IRJET- Design and Fabrication of Electric Scooter with Two Way Power Source
PPTX
PPT OF SOLAR NAVEEN' `11
DOC
Solar car full report
PPSX
Solar power plant Opportunity and Costing
PDF
The Efficiency of Solar PV System
A Summer Internship report
Maximizing Output Power of a Solar Panel via Combination of Sun Tracking and ...
Report on the IMPROVING THE EFFICIENCY OF SOLAR PHOTOVOLTAIC POWER GENERATION...
IRJET- Design and Fabrication of Electric Scooter with Two Way Power Source
PPT OF SOLAR NAVEEN' `11
Solar car full report
Solar power plant Opportunity and Costing
The Efficiency of Solar PV System

What's hot (20)

PDF
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
PDF
Solar Photovoltaic (PV) Grid Integration Issues
DOCX
PDF
IRJET-A Standalone Solar System
PDF
Design & estimation of rooftop grid tied solar pv system
PPTX
Financial viability of solar power plant in Tamil Nadu
PPTX
Dual axis solar tracker
PDF
PV Cottage Industry in Malaysia
PDF
Solar PV energy principles part 1
PDF
Lobel proposal for 1 mw crystalline pv solar power plant
PDF
Prototype solar power plant in laboratory electrical energy conversion
PDF
Making india non fossil fuel based
PPTX
Consumer perception towards solar products
PDF
Design and Development of Solar Two Wheeler
PPTX
Development of hybrid power generation model using system composed of rain wa...
PDF
Optimization towards cost effective solar mini grids in bangladesh
PPT
Mygen Training November 2010
PPTX
Financial analysis of 1 MW Solar PV plant
PPT
Solar technologies you can use in your Indian home
PDF
IRJET- A Study on Campus-Friendly Solar Powered Electric Vehicle
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
Solar Photovoltaic (PV) Grid Integration Issues
IRJET-A Standalone Solar System
Design & estimation of rooftop grid tied solar pv system
Financial viability of solar power plant in Tamil Nadu
Dual axis solar tracker
PV Cottage Industry in Malaysia
Solar PV energy principles part 1
Lobel proposal for 1 mw crystalline pv solar power plant
Prototype solar power plant in laboratory electrical energy conversion
Making india non fossil fuel based
Consumer perception towards solar products
Design and Development of Solar Two Wheeler
Development of hybrid power generation model using system composed of rain wa...
Optimization towards cost effective solar mini grids in bangladesh
Mygen Training November 2010
Financial analysis of 1 MW Solar PV plant
Solar technologies you can use in your Indian home
IRJET- A Study on Campus-Friendly Solar Powered Electric Vehicle
Ad

Similar to Solar policy &amp; project development (20)

PPTX
Photovoltaics
PPT
Photo
PPTX
solar photovoltaic system
PPSX
Solar photovoltaics
PPT
Chapter_2_part_D_Solar photovoltaics.ppt
PPT
Pv cell
PPT
JSJawa_Feb27.ppt
PDF
Shining Light on Photovoltaics
PPTX
Solar energy
PPTX
Solar energy.pptx
PDF
Photovoltaic Solar Energy Systems: Market Trends In The United States
DOCX
20201129 summarise photovoltaics topic nguyen thi thu
PPTX
Solar-101-workshop-midwest-2018-small (1).pptx
PPT
EcoOne - SolarEnergy Presentation 2014
PDF
IRJET- Design of Solar Rooftop Plant for JSSATEN
PDF
Sunny Days Ahead
 
PPT
IETE Institute Solar PPT
PPTX
Presentation1
PPTX
Presentation1
DOCX
English renwble-energy
Photovoltaics
Photo
solar photovoltaic system
Solar photovoltaics
Chapter_2_part_D_Solar photovoltaics.ppt
Pv cell
JSJawa_Feb27.ppt
Shining Light on Photovoltaics
Solar energy
Solar energy.pptx
Photovoltaic Solar Energy Systems: Market Trends In The United States
20201129 summarise photovoltaics topic nguyen thi thu
Solar-101-workshop-midwest-2018-small (1).pptx
EcoOne - SolarEnergy Presentation 2014
IRJET- Design of Solar Rooftop Plant for JSSATEN
Sunny Days Ahead
 
IETE Institute Solar PPT
Presentation1
Presentation1
English renwble-energy
Ad

Recently uploaded (20)

PDF
IWRM - City University Presentation 28 may 2018-v3.pdf
PPT
Environmental pollution for educational study
PDF
Biomass cookstoves: A review of technical aspects
PDF
PAKAM TECHNOLOGY LIMTED PITCH DECK pptx.pdf
PPTX
STL Academy - Highlights & Impact 2020-21-v2 (1).pptx
PPTX
Air_Pollution_Thesis_Presentation (1).pptx
PPTX
Plant Production 7.pptx in grade 7 students
PPTX
IMPACTS OF CHEMICAL FERTILIZERS -CHEMPROJ (11).pptx
PPTX
Biodiversity PPT by Gaithanlung Gonmei.pptx
PDF
The European Green Deal (EU Green Deal)
PPTX
EME Aerospace.pptx basics of mechanical engineering
DOCX
Double Membrane Roofs for Digester Tank Wastewater Treatment Integral to biog...
DOCX
Double Membrane Roofs for Biogas Digesters A sealed cover for biogas producti...
PPTX
Biodiversity of nature in environmental studies.pptx
PPTX
Afro-Asia Literature.pptxmmmmmmmmmmmmmmm
DOCX
Double Membrane Roofs for Biogas Tanks Securely store produced biogas.docx
PDF
FMM Slides For OSH Management Requirement
PDF
Effects of rice-husk biochar and aluminum sulfate application on rice grain q...
PPTX
Microbial-Pathogens-and-Parasites-Their-Impact-on-Plant-Health.pptx
PPTX
Untitled 1.pptxhhhhhhjjjbbbbb bikinis sis son ka s
IWRM - City University Presentation 28 may 2018-v3.pdf
Environmental pollution for educational study
Biomass cookstoves: A review of technical aspects
PAKAM TECHNOLOGY LIMTED PITCH DECK pptx.pdf
STL Academy - Highlights & Impact 2020-21-v2 (1).pptx
Air_Pollution_Thesis_Presentation (1).pptx
Plant Production 7.pptx in grade 7 students
IMPACTS OF CHEMICAL FERTILIZERS -CHEMPROJ (11).pptx
Biodiversity PPT by Gaithanlung Gonmei.pptx
The European Green Deal (EU Green Deal)
EME Aerospace.pptx basics of mechanical engineering
Double Membrane Roofs for Digester Tank Wastewater Treatment Integral to biog...
Double Membrane Roofs for Biogas Digesters A sealed cover for biogas producti...
Biodiversity of nature in environmental studies.pptx
Afro-Asia Literature.pptxmmmmmmmmmmmmmmm
Double Membrane Roofs for Biogas Tanks Securely store produced biogas.docx
FMM Slides For OSH Management Requirement
Effects of rice-husk biochar and aluminum sulfate application on rice grain q...
Microbial-Pathogens-and-Parasites-Their-Impact-on-Plant-Health.pptx
Untitled 1.pptxhhhhhhjjjbbbbb bikinis sis son ka s

Solar policy &amp; project development

  • 1. Report on Solar Power Policies & Project Development in India Sumit Mishra
  • 2. Table of Content I : Introduction…………………………………………………………… 3 II : Solar Technology …………………………………………………….. 3 1. Solar Photovoltaic (PV)……………………………………………. 3 2. Concentrating Solar Power System (CSP) …………………………. 4 3. Solar Heating & Cooling …………………………………………… 4 III : Working of solar PV ………………………………………………….. 4 IV : Photovoltaic Technologies ……………………………………………. 5 1. Crystalline Silicon …………………………………………………… 5 2. Thin Film ……………………………………………………………. 5 V : India’s Solar Market ……………………………………………………. 6 VI : Policy Initiative ………………………………………………………… 8 1. Jawaharlal Nehru National Solar Mission …………………………... 10 a. JNNSM Phase I…………………………………………………… 10 b. JNNSM Phase II ………………………………………………….. 11 c. JNNSM Phase II Batch I ………………………………………….. 12 d. JNNSM Phase II Batch II ………………………………………… 13 2. State Solar Policies ………………………………………………….. 13 3. Renewable Purchase Obligation …………………………………….. 16 4. Net Metering Policy ………………………………………………… 16 VII: Development of Solar PV Project ………………………………………. 18 1. Land/ Site selection …………………………………………………. 18 a. Solar Resources ………………………………………………….. 18 b. Available Area …………………………………………………... 19 c. Climate & topography …………………………………………… 19 d. Accessibility & RoW ……………………………………………. 20 e. Grid Connection …………………………………………………. 20 f. Water Availability ……………………………………………….. 20 2. Pre-Feasibility & Feasibility Study …………………………………. 20 3. Engineering, Procurement & Construction Contract …………….…. 20 4. Transmission Agreement ……………………………………………. 21 5. Clearances & Approvals …………………………………………….. 21 6. Operation & Maintenance Contract …………………………………. 22 VIII: Conclusion …………………………………………………………… 22
  • 3. I: Introduction: Solar energy is the energy received from the Sun that sustains life on Earth. For many decades solar has been considered to be a huge source of energy & also economical one because it is freely available. However, it is only now, after years of research that technology has made it possible to harness solar energy. Key benefits of solar power is: 1. Freely available in abundant quantity. 2. Environment friendly 3. No fuel cost 4. Low operation & maintenance cost. Basic principles of Solar Technology is that , the sun rays contains energy, and normally when these rays hit an object that energy turns to heat but when these rays hit silicon (Solar Cell), the energy becomes an electrical current that can be harnessed for power. Silicon is the main ingredient in solar panels and is used to capture the sun’s energy and turn it into electricity. This electricity is then converted into clean, affordable power for your home. The whole process is represented in Figure 1. Figure 1: Generation of Solar Energy II: Solar Technologies: Solar energy is the cleanest, most abundant renewable energy source available. Today's technology allows us to harness this resource in several ways. There are three primary technologies by which solar energy is commonly harnessed: 1. Solar Photovoltaic (PV): These solar technologies directly produce electricity which can be used, stored, or converted for long-distance transmission. PV panels can be manufactured using a variety of materials and processes and are widely-used for solar projects around the world.
  • 4. 2. Concentrating Solar Power system (CSP): Using reflective materials like mirrors and lenses, these systems concentrate sunlight to generate thermal energy, which is in turn used to generate electricity. Similar to traditional power plants, many CSP plants are hundreds of megawatts (MW) in size and some can continue to provide power after sunset 3. Solar Heating & Cooling: These technologies generate thermal (heat) energy for water & pool heating and space heating. This type of technology is generally used in houses for water heating. III: Working of Solar PV: The main components of a PV power plants are: 1. Solar PV Modules: These convert solar radiation directly into electricity through the photovoltaic effect in a silent and clean process that requires no moving parts. The PV effect is a semiconductor effect whereby solar radiation falling onto the semiconductor PV cells generates electron movement. The output from a solar PV cell is direct current (DC) electricity. A PV power plant contains many cells connected together in modules and many modules connected together in strings to produce the required DC power output. 2. Mounting Systems (Tracking –optional): These allows PV modules to be securely attached to the ground at a fixed tilt angle or on sun tracking frames. 3. Inverters: These are required to convert DC electricity to alternating current AC for connection to the utility grid. 4. Step up Transformers: The output from the inverter generally requires a further step-up in voltage to reach the AC grid voltage level. 5. Grid connection: This is where electricity is exported into the grid network.
  • 5. Figure 2: Overview of Solar PV system The above mentioned components collectively form a Solar PV system. The complete assembly of solar power PV system is shown in figure 2. A valuable feature of photovoltaic systems is the ability to connect with the existing power grid which allows owners to sell excessive electricity back to the utility with a plan known as Net Metering. At times when you are not using all of the electricity produced by your system, your meter will spin backwards selling the electricity back to the utility power grid. IV: Photovoltaic Technologies: The large variety of PV applications allow for a range of different technologies to be present in the market , from low cost , lower efficiency technologies to high efficiency technologies at high cost. Commercial PV modules may be divided into two broad categories: 1. Wafer based Crystalline Silicon (C-Si) (Manufactured by cutting wafers from solid ingot block of silicon). The Crystalline Silicon (C-Si) modules represent 85-90% of the global annual market today. They are further subdivided into Mono-crystalline silicon or Poly-crystalline silicon. Mono- crystalline silicon cells are generally the most efficient, but are more costly than poly—c-Si. 2. Thin films technologies (in which a thin layer of a semiconductor material is deposited on low cost substrates).Thin films currently account for 10% to 15% of global PV module sales. Thin film cells provide a cheaper alternative, but are less efficient. There are three main types of thin film cells: Cadmium Telluride (CdTe), Copper Indium (Gallium) Di-Selenide (CIGD/CIS) and Amorphous Silicon (a-Si).
  • 6. Figure 3. Types of S-PV technologies The efficiency of different PV technology commercial modules is as follows: Figure 4. Efficiency Chart of PV cells The cost of a project is highly dependent upon the type of PV technology adopted because the total cost of the system /project are composed of the sum of module cost , efficiency of module, land required , balance of system , inverter etc. The better the efficiency of a solar PV system the lesser the land required for installation of PV system. V: India’s Solar Market: India is located in the equatorial sun belt of the Earth & hence receives abundant radiant energy from sun. India receives high Solar Irradiation in most parts of the country – annual average Global Horizontal Irradiation of 5.1, with large number of sunny days (approx. 330). Because of high GHI in some part of the country we can achieve a Capacity Utilisation Factor (CUF) of 21-23 %. This means that a 1 MW solar power plant can produce 1.85 million units of electricity per year. Solar PV Technology Crystalline Silicon Mono Crystalline Poly Crystalline Thin Film Amorphous Cadmium Telluride (CdTe) Copper Indium Di-Selenide CIS/CIGS 10-12% CdTe 9-11% a-Si;a-Si/µc-Si 6-9% Wafer Based C-Si Technology Thin Films Technology
  • 7. Considering the Solar ir-radiation data, available waste land & other factor, it is estimated that our country has a solar potential of 748 GWp. The state wise solar potential detail is presented in table 1 below: State Solar Potential (GWp) State Solar Potential (GWp) State Solar Potential (GWp) Rajasthan 142.31 Telangana 20.41 Nagaland 7.29 Jammu & Kashmir 111.05 Chhattisgarh 18.27 West Bengal 6.26 Maharashtra 64.32 Jharkhand 18.18 Kerala 6.11 Madhya Pradesh 61.66 Tamil Nadu 17.67 Meghalaya 5.86 Andhra Pradesh 38.44 Uttarakhand 16.80 Sikkim 4.94 Gujarat 35.77 Assam 13.76 Haryana 4.56 Himachal Pradesh 33.84 Bihar 11.20 Punjab 2.81 Odisha 25.78 Manipur 10.63 Tripura 2.08 Karnataka 24.70 Mizoram 9.09 Delhi 2.05 Uttar Pradesh 22.83 Arunachal Pradesh 8.65 Goa & UT 1.67 Table 1: State wise Solar Potential The outlook of solar sector in India is extremely positive, driven by powerful underlying fundamentals such as rising cost of conventional power, environmental concerns, falling costs of Solar power, high solar ir-radiation , a high power deficit & the ability of solar to quickly bring power generation capacity online. These fundamental coupled with several state & central government initiatives should result in India becoming one of the largest solar market in the world. A SWOT analysis of Indian solar market is carried out for understanding the strength, weakness, opportunity & threat to Indian Solar energy sector.
  • 8. Figure 5: SWOT Analysis for developing Solar Project in India VI: Policy Initiative: The Government of India (GoI) has taken several initiative to promote solar energy market in India not only for energy security but also for their commitment towards global warming. Several policy at national & state level has been announced & highly ambitious target has been set by the respective government. In the last 5 years India has seen tremendous growth in its Solar installed capacity from a mere 22 MW in 2010 to 4011 MW by May 2015. This installed capacity is a result of introduction of various policies viz. National solar Mission (Phase I & II) state solar policies & REC mechanism etc. State wise solar installation detail is presented in figure 6 below. Strength 1. High Growth industry with significant future potential. 2. Sunlight is available in sufficient quantity in many regions. 3. Proven technology with low operation & maintenance cost , which is also scalable. 4. Availability of Governmant incentives for growth & expansions. Weakness 1. Owing to high capital costs, the business needs external incentives to be economical feasible , thus increasing dependence on Governmental policies. 2. The Capital intensive nature of the business might favour larger business over smaller one. 3. The distributed & intermittent nature of solar energy makes it difficult for utilities to rely on Solar PV for their base load. Opportunities 1. Government ambitious target & attractive policies open up many avenues for investment. 2. Opportunities exist all along the Solar PV business value chain. 3. Entirely new opportunities could open up as there is high innovation in technology, especially with reduction in cost in future. Threats 1. Off Peak season reduces cash flow. 2. Finding skilled manpower is a issue. 3. Solar Panels work only at 22% efficiency therefore achieving solar targets could be difficult despite scaling up . SWOT Analysis
  • 9. Figure 6: Utility Scale Solar Installed Capacity…as of May’15 Under National solar Mission GoI targets for setting up of 20,000MW (Revised to 100,000 MW) solar capacity shows commitment of the government towards development of solar market in India. The announcement of various state level policies and the allocations under NSM (Phase 1 &2) have brought fresh excitement to the market. Government policies have so far been the prime driver for the solar energy sector in India however there has been a gradual move from an incentive driven market to a parity driven market. In addition to NSM and state policies developer also have the option of setting solar power plant for captive purpose and avail benefit of selling green attributes in the form of Renewable Energy Certificates (RECs) at power exchanges. Various states have now introduced their Net metering policies to attract development of rooftop in their respective states. Net Metering is the regulatory ability to get credit for electricity user generate with solar energy and send backwards through their utility meter. Exact provisions vary with each state, but the effect is to allow user to generate excess power during the day, and use it at night, without needing batteries. For the injected quantity user will be incentivise as per the rate fixed under the Net metering policy of their respective states. 228 6 4 953 19 99 354 71 240 1128 164 5 68 18 637 7 5 2 1 2 0 200 400 600 800 1000 1200 Andhra Pradesh Chhattisgarh Delhi Gujarat Haryana Karnataka Maharashtra Odisha Punjab Rajasthan Tamil Nadu Uttarakhand Uttar Pradesh Jharkhand Madhya Pradesh West Bengal Andaman & Nicobar Chandigarh Lakshadweep Other Installed Capacity in MW
  • 10. A detailed discussion on the respective policies is presented in the later part of the report for better understanding. Installed Solar Capacity in India under various policies: Figure 7: India’s installed solar capacity under different policies 1. Jawaharlal Nehru National Solar Mission (JNNSM): The Jawaharlal Nehru National Solar Mission (JNNSM) was the major initiative of Government of India (GoI) and state government to promote ecologically sustainable growth while addressing India’s energy security challenges. It plays a prime role in India's contribution to the fight against issues of climate change, which was the big concern across the globe. The launch of the National Solar Mission (NSM) has given a big impetus to solar energy in India. The Mission adopted a 3 phase approach, spanning the period of the 11th Five Year Plan and first year of the 12th Five Year Plan (up to FY2012- Projects under NSM Projects under State Policy Projects under other policies
  • 11. 13) as Phase 1, the remaining 4 years of the 12th Plan (FY2013-17) as Phase 2 and the 13th Plan (FY17-22) as Phase 3. To facilitate grid connected solar power generation under phase I without any Government subsidy, GOI approved NTPC Vidyut Vyapar Nigam Ltd (NVVN) as the nodal agency to purchase 1,000 MW from project developers and sell this bundled power to the distribution utilities. The concept of Bundling was introduced to select projects of 500 MW capacity each based on solar thermal and PV technologies. On 18th June 2015, in a major policy move, the government has announced a massive scaling up of the targets for India's solar power capacity target under Jawaharlal Nehru National Solar Mission (JNNSM) by five times, reaching 1,00,000 MW by 2022. The target will principally comprise of 40 GW (solar) rooftop & 60 GW through large and medium scale grid connected solar power projects. Toward achieving this target the government envisages a total investment in setting up 100 GW will be around Rs 6, 00,000 crores. In the first phase, the Government of India is providing Rs 15,050 crores as capital subsidy to encourage solar energy based projects. This capital subsidy will be provided for Rooftop Solar projects in various cities and towns, for Viability Gap Funding (VGF) based projects to be developed through the Solar Energy Corporation of India (SECI) and for decentralised generation through small solar projects. The new solar target of 100 GW is expected to result in the reduction of over 170 million tonnes of carbon dioxide, a gas contributing to climate change. a. JNNSM Phase 1: During Phase 1, a total of 1000MW of Solar Power Projects were selected, with solar PV and Solar Thermal projects to be allocated in the ration of 50:50. It was divided into batch 1 & 2 over FY 2010-11 & FY 2011-12, respectively. The highlight of Phase 1 is presented in Table-2 below. NSM Phase 1, Batch 1 NSM Phase 1, Batch 2 Managed by NVVN NVVN Capacity allocation PV: 150 MW (PPA signed only for 140MW) CSP: 470 MW PV: 350 MW (PPA signed only for 340 MW) CSP: Nil
  • 12. Maximum & Minimum Project Capacity PV: Min: 5 MW, Max: 5 MW. CSP: Min: 5MW, Max:100 MW (Max. of 3 project locations Min: 5 MW, Max: 20 MW Maximum capacity by a bidder PV: 5 MW, CSP: 100 MW 50 MW Domestic Content Requirement (DCR) PV: For projects based on c-Si technology, the modules must have been manufactured in India CSP: 30% domestic content mandatory For Projects based on c-Si technology, the modules must have been manufactured in India Policy Mechanism Preferential feed-in tariff Preferential feed-in tariff Allocation Method Reverse bidding on benchmark tariff (per kWh): PV: INR 17.91/kWh, CSP: INR 15.31/kWh Reverse bidding on benchmark tariff (per kWh): INR 15.39/kWh Commissioning time period PV: 12 months, CSP: 28 months 13 months Weighted average of winning bid PV: INR 12.16/kWh , CSP: 11.48/kWh PV: INR 8.77 / KWh Project Commissioned PV: 140 MW, CSP: 50 MW PV: 330 MW Technology breakdown Thin film: 55%, rest: polycrystalline Thin film: 75%, rest: polycrystalline Required bank guarantee INR 5 million/MW INR 5 million/MW Table 2: Highlights of JNNSM Phase I b. JNNSM Phase II : Out of the 60 GW of utility scale solar planned by 2022, 15 GW is expected to be developed under the National Solar Mission (NSM) by 2019 using a combination of different structures including bundling of Power , VGF, and interest rate subvention. Proposed share of Solar PV and Solar Thermal at Central/State levels during phase II: Item Description Share Central Scheme State Scheme Percentage % MW Percentage % MW Percentage % MW Solar PV 70 10500 40 4200 60 6300
  • 13. Solar Thermal 30 4500 40 1800 60 2700 Total 100 15,000 - 6000 - 9000 Table 3: Proposed share of PV & CSP under Phase II at Central & State level c. JNNSM Phase II Batch I: The total capacity targeted under this phase is 750 MW & all of the projects will use photovoltaic technology. The winners were the project developer who sought the minimum possible funds to make their projects viable to sell power to SECI at a tariff of Rs 5.45/kWh (Rs 4.75/kWh for project claiming accelerated depreciation) for 25 years. With an object to promote local manufacturing, SECI invited bids in two separate categories, reserving half of the projects under domestic content requirement (DCR) restrictions. Time Frame for JNNSM Phase II Batch I is as follows: Sr. No Event Date 1 Approval of RfS documents by SECI Zero date 2 Issue of RfS documents (Sale of Documents) Zero date + 7 Days 3 Submission of Bids (Techno- Commercial & Financial) Opening of Techno-Commercial bids Within 60 days from issue of RfS 4 Evaluation of Techno-Commercial bids & shortlisting of bidders Within 60 days from submission of bids 5 Opening of Financial bids Within 7 Days from shortlisting of bidders 6 Issue of Letter of Intents ( LoI) Over a period of 15 days after opening of financial bids 7 PPA Signing Within 30 days from the date of signing of PPA 8 Financing arrangement Within 210 days from the date of signing of PPA 9 Commissioning of Projects Within 13 months from the date of signing of PPA Table 4: Timeline for JNNSM Phase II batch I d. JNNSM Phase II Batch II: MNRE proposed to add a total Solar PV capacity of 15000 MW in three tranches to be implemented through NVVN as part of Phase-II Batch-II. The scheme envisages setting up of Grid- connected solar PV power plants of 15,000 MW aggregate capacity through open competitive bidding as under:
  • 14. (i) Tranche-I: 3,000 MW: 2014-15 to 2016-17 (Bundling with 1500 MW unallocated NTPC Power from Coal Station allocated by MoP). (ii) (ii) Tranche-II : 5,000 MW: 2015-16 to 2017-18 (selection mechanism to be decided later) (iii) (iii) Tranche-III : 7,000 MW: 2016-17 to 2018-19 ( selection mechanism to be decided later) 2. State Solar Policies: In addition to the National Solar Policy, various states have also announced State Level Policies aimed at encouraging investment in their respective states. State Solar policies & capacity addition are usually driven by three broad factors: a. Renewable Purchase Obligation , (RPO) b. Demand for new power generation capacity c. Political commitment to the renewable sector. States like Tamil Nadu, Andhra Pradesh, Karnataka, Jharkhand, Bihar and Odisha etc. has come up with their solar policies. All these policies are more concentrated towards the central agenda of reaching 100GW by 2022 and thus almost all the policies have kept the provisions of various incentives and benefits to the developer. A target of 50 GW has been set under the state policies, a brief of various state policy is shown in table 5 below: State PolicyTarget OffTaker Financialincentive ExemptionfromOAcharges OtherKeyBenefits DCR AndhraSolarpolicy 5000MWby 2019 2GWtoState Discoms 3rdPartyallowed 1.100%bankingforallcaptive& OAduringall12monthsofthe year. 2.Bankingcharge@2%of energydeliveredwillbeadjusted. Wheelingchargesexempted. 2.Distributionlossbelow 33KV-exempted. 4.CSSexemptedfor3rd partysaleandcaptive projectsfor5year Exemptedfromobtaining Pollutionclearances EDexemptedfor3rdparty sale,captiveconsumption andsaletodiscom. None
  • 15. Table 5: Brief of State Solar Policies Bihar Solar Policy 130 MW Captive , State Discom & 3rd Party No entry tax . Incentive as per industry policy applicable. Wheeling & Transmission charges as applicable. ED exempted None Chhattisgarh Solar Policy 500 to 1000 MW by 2017 Captive & 3rd Party Stamp duty exempted. Concession on land premium. 1. Not exempted (OA Charges & losses applicable as per CSERC order) 2. Wheeling & Transmission charges applicable. ED exempted on auxiliary consumption & captive consumption within the state. None Gujarat Solar Policy Not defined Captive , State Discom & 3rd Party No additional financial incentive. No exemption ED exempted CSS exempted None Haryana Solar Policy 100 MW State Discoms Incentive as applicable under Industrial policy No exemption Exemption from land use charges None Jharkhand Solar Policy 2500 MW Captive , State Discom & 3rd Party 100% Banking allowed. VAT & Entry tax exempted. Wheeling charge & Distribution loss exempted. ED Exempted , Pollution clearance exempted. None Karnataka Solar Policy 2000 MW State Discoms , 3rd Party , Captive Concession on Stamp duty , registration charges & entry tax as per industrial policy. Banking charges waived. Transmission charges , wheeling charges & CSS waived for 10 Years. ED exempted None Kerala Solar Policy 500 MW by 2017 2500 MW by 2030 State Discoms , 3rd Party , Captive Banking facility available to captive generator. No OA Charges ED exempted. Evacuation infrastructure construction by state(for 10 MW below) None Maharashtra Solar Policy 7500 MW by 2019 State Discoms , 3rd Party , Captive 50% of transmission & wheeling charges waived. 75% of CSS waived ED exempted for 10 year. Pollution clearance exempted None MP Solar Policy 300 MW State Discoms , 3rd Party , Captive 100% banking allowed in a FY @ 2% of the banked energy. VAT & entry tax exempted. Transmission & Wheeling charges reduced to 2% of energy injected. Wheeling Charges & CSS waived ED & Cess exempted for 10 year. None Odisha Solar Policy 135 MW by 2015 State Discoms , 3rd Party , Captive 100 % banking allowed Wheeling & Transmission charges applicable. CSS waived. ED exepmted None Punjab Solar Policy 1000 MW by 2022 State Discoms , 3rd Party , Captive Banking Charges waived Transmission & Wheeling charges reduced to 2% of energy injected. - None Rajasthan Solar Policy 25000 MW State Discoms , 3rd Party , Captive Banking allowed as per RERC regulation. OA charges applicable Pollution clearance not required. None Tamil Nadu Solar Policy 3000 MW by 2015 Obligated Entities State Discoms Preferential tariff based on reverse bidding for a part of the target 50% of transmission & wheeling charges waived. Single Window Clearance GBI for residential consumers None Telangana Solar Policy 5000 MW by 2019 State Discoms , 3rd Party , Captive 100% Banking allowed. Wheeling charge exempted for captive use within the state. CSS exempted for 3rd party within the state. ED Exempted , Pollution clearance not required. None UP Solar Policy 500 MW by 2017 State Discoms Preferential tariff based on reverse bidding Wheeling & Transmission charges exempted Evacuation infrastructure construction by state. None Uttarakhand Solar Policy 500 MW by 2017 State Discoms , 3rd Party , Captive VAT & entry tax exempted. wheeling charges as per state tariff. Other OA charges as per state tariff. CSS waived None West Bengal Solar Policy 500 MW by 2022 Discoms LC from a nationalize bank as apayment security. Other concession and incentive as per MNRE policy. - - None
  • 16. As per the revised NSM target 60 GW of capacity should be utility scale A 60 GW solar capacity should be from utility scale grid connected project and remaining 40 GW from off grid. To achieve that several states have revised their target under their respective state policy. Figure 8 below shows the target set by the state under their respective policies. Figure 8: Targets set under state solar policies
  • 17. 3. Renewable Purchase Obligation (RPO): The Government of India (GoI), through the central Electricity Regulatory Commission (CERC) has introduced a Renewable Purchase Obligation (RPO’s) for all renewables as per the requirement of the National Action Plan on Climate Change (NAPCC). As per the RPO requirements, 15% of all power in the country has to be sourced from renewable energy sources by 2020. For solar power in particular, the RPO requirement is 3%. Individual state electricity regulatory commission (SERC’s) have taken up this directive & have set specific state targets. In addition, the government has introduced a market tradable Renewable Energy Certificate (REC’s) for fulfilling Renewable Purchase obligation. Under the REC mechanism developer are eligible to receive one certificate for every 1000 kWh of renewable electricity fed into the grid. Obligated Entities can buy these certificates to fulfil their obligation. 4. Net Metering Policy: The concept of net metering involves recording the net energy between export of generated energy and import of energy from distribution licensee for a given period of time. This involves the usage of a bi-directional meter which has the facility to record both import and export values. Under the net metering system, the excess energy generated by the solar photovoltaic plant at a given point of time is exported to the grid instead of being stored using a battery. However when there is a deficit in the power generated by the solar panels either during the night or a cloudy day, energy is drawn from the grid. At the end of the billing period, if more energy is exported to the grid than imported, then the distribution licensee pays the consumer at a pre-determined price. On the other hand if more energy is imported from the grid than exported, then the consumer pays the distribution licensee at a predetermined price. These prices usually vary from state to state. As a part of the regulatory overhaul many state has come up with their Net metering policy & brief of the respective state Net metering policy is presented in table 6 below:
  • 18. Table 6: Net metering policies of various state State Cap on Solar installation / injection Grid penetration as % of distribution transformer capacity Eligibility Excess electricity settlement Project capacity limit Andhra Pradesh 100% of the electricity consumption in a billing month Not mentioned Preferably allowed for 3 Phase service consumer however single phase consumer upto 3kW are alos eligible. As per APPC Upto 1 MW Bihar Not Mentioned 15% Not Mentioned To be carried forward to next billing cycle Maximum 1 MWp Chhattisgarh Not Mentioned Annual energy injection shall not be more than 49% of the annual net generation Not Mentioned To be billed at 50% of the solar tariff (in case energy injected is less than 49% of annual net generation) 50kWp to 1 MWp capacity Delhi system size less than contracted load 20% All consumer As per APPC Above 1 kW Goa & UT Not Mentioned 30% Consumer with single or three phase supply connection As per Solar tariff 1kWp to 1MWp Haryana Injection < 90% of the consumption in a year 15% All consumer To be carried forward to next billing cycle 1kWp to 1MWp Himachal Pradesh Not Mentioned Not mentioned All consumer Not Mentioned Maximum 1 MWp Karnataka Not Mentioned Not mentioned All consumer As per Solar tariff (currently 9.56 /Unit without subsidy) & Rs 7.20 /Unit with subsidy of 30% Upto 500kWp Kerala Not Mentioned 50% All consumer categories availing electricity at voltage level of and below 11kVA As per APPC (Rs. 1.99/Unit) 1kWp to 1MWp Madhya Pradesh Not Mentioned Not mentioned All consumer Not Mentioned Not mentioned Mahrashtra Not Mentioned Not mentioned Not Mentioned As per APPC Not mentioned Meghalaya Not Mentioned Not mentioned All consumer Not Mentioned Maximum 1 MWp Odisha Injection < 90% of the consumption in a year 30% All consumer No Payment Not mentioned Punjab System size < 80% of the contracted load 30% All consumer As per retail supply tariff of that consumer 1kWp to 1MWp Rajasthan System size < 80% of the contracted load 30% All consumer As per Solar tariff (currently @ Rs 6.63/Unit) 1kWp to 1MWp Tamil Nadu Injection < 90% of the consumption in a year 30% Government run institution & residential consumer No Payment Not mentioned Uttar Pradesh system size less than contracted load 15% All consumer At Rs 0.50 / Unit More than 1 kW Uttarakhand Not Mentioned Not mentioned All consumer As per Solar tariff (currently @ Rs 9.92/Unit) 5kW to 500kW West Bengal Injection < 90% of the consumption in a year Not mentioned Institutional consumers like Hospitals , Government departments academic institutions etc As per APPC Upto 5 kW
  • 19. VII: Development of Solar PV project: The key steps for developing a solar PV project are well established & yet there is no definitive detailed “road map” a developer can follow. The approach taken in each project depends on site –specific parameters & the developer’s priorities, risk appetite, regulatory requirement & the types of financing support mechanism available in the given market. However in all cases certain activities need to be completed that can be broadly be organized in the following 6 steps: Figure 9: Steps for setting up of Solar Power Plant 1. Land /Site selection: Selecting a suitable site is a crucial part of developing a viable project. In selecting a site the aim should be to maximise output and minimise cost & the process of site selection must consider the constraints of each site & the impact it will have on the cost of the electricity generated. The main constraints that need to be assessed include: a. Solar resources: The higher the resources the greater the energy yield per kWp installed. When assessing the Global Horizontal Ir-radiation (GHI) at site care must be taken to minimise any shading that will reduce the ir- radiation received. Map showing India’s solar ir-radiation data is shown in figure 10. Land/Site Selection prefeasibility & feasibility study Appointment of EPC contractors & equipment order. Clearances & approvals Transmission Agreement O & M Contractor
  • 20. Figure 10: India’s solar Ir-radiation data b. Available Area: The area required per kWp of installed capacity varies with the technology chosen. Sites should be chosen with sufficient area to allow the required capacity to be installed without having to reduce the pitch (i.e. distance between rows of module) to levels that cause unacceptable yield loss. Depending upon the site location (altitude) the land required for a 1 MW power plant setup is around 4.5-5 acres for crystalline technology and around 6.5-7.5 acres for Thin-Film technology. This is only a rough benchmark and may vary based on technology and efficiency of panels. c. Climate & topography: In addition to a good solar resources, the climate should not suffer from extremes of weather that will increase the risk of damage or downtime.
  • 21. Site should be flat or on a slight south facing slope in the northern hemisphere or north facing slope in the southern hemisphere. d. Accessibility & ROW: The site should allow access for trucks to deliver plant & construction materials. The closer the site is to a main access road, the lower the cost of adding this infrastructure. Row (i.e. access rights for transmission lines on private land) should be exercised before finalising the land. e. Grid Connection: A grid connection of sufficient capacity is required to enable the export of power. The viability of the grid connection will depend on factors such as capacity, proximity, ROW, grid stability & grid availability. f. Water availability: Clean, low mineral content water is preferred for cleaning modules. A reliable supply is required for module cleaning. Other parameter which should be analysed before site selection are geotechnical, geopolitical, module soiling & financial incentive etc. 2. Pre-feasibility & feasibility study: The aim of a prefeasibility study is to develop a preliminary plant design & investment requirements, which allow further assessment of the financial viability of the project. The prefeasibility study should at minimum include an assessment of: a. The project site & boundary area, ensuring access to the site is possible, both legally & technically. b. A conceptual design of the project giving different options of technology & the financial impacts, including estimation of installed capacity. c. Estimate cost of land & energy yield of the project. d. A financial model to determine the commercial viability of the project for further investment purposes. e. Grid connection cost & likelihood of achieving a connection within the required timeline. f. Permitting requirements, costs, & likelihood of achieving consent. The objective of the feasibility study is to provide more detailed information on the potential project design, the investment requirements, and to plan for financing and implementation. If the results of the study are favourable, the developer should be prepared to invest more to advance the project to the financing stage. 3. Engineering, Procurement, and Construction (EPC) contract: Engineering, procurement and construction (EPC) contracts are the most common form of contract for the construction of solar PV power plants. Under an EPC contract, a principal contractor is engaged to carry out the detailed
  • 22. engineering design of the project, procure all the equipment and materials necessary, and then construct and commission the plant for the client. The EPC contract for any project-financed solar PV power plant will typically be held between a project company (the owner) and the EPC contractor (the contractor). It is common practice to use a standard form of contract (sometimes referred to as a “boilerplate contract”) as a template and basis for the EPC contract. The key clauses for a project owner in any construction contract are those that relate to time, cost and quality. In the case of solar PV power plant construction, a strong EPC contract will address the following areas:  A “turnkey” scope of work.  A fixed completion price.  A fixed completion date.  Restrictions on the ability of the contractor to claim extensions of time and additional costs.  A milestone payment profile that is suitably protective to the owner and based upon the completion of predefined sub-tasks.  Plant PR guarantees.  LDs for both delay and performance.  Financial security from the contractor and/or its parent organisation.  A defects warranty. 4. Transmission agreement - The project developer will need to sign a transmission agreement with the States respective STU. 5. Clearances & approvals: Clearances & approvals requirements for solar PV power plants vary greatly from country to country and within different country regions. It is important therefore to establish with the appropriate planning/ government authority the relevant laws/ regulations and associated clearances & approvals that will be required for the project. In some of the states, State Nodal agency acts as a facilitator for getting clearances. Major clearances which need to be obtained are: a. Consent to Establish and Consent to Operate from State Pollution Control Board b. Import/License in case of import of plant and machinery. c. No objection certificate from Civil Aviation Department. d. No objection certificate from District Collector for setting up the project. e. No objection certificate from the Panchayat under which the project area is located. f. Approval for water requirement in case of solar thermal projects.
  • 23. g. Permission for laying power evacuation lines from Chief Electrical Inspector. h. No Objection Certificate from energy department. i. Permission for 'Implementation of Metering Code', 'Protection System' to be obtained from host Distribution Utility or the STU or the Central Transmission Utility as the case may be. 6. Operation & Maintenance (O&M) contract: Compared to other power generating technologies, solar PV power plants have low maintenance & servicing requirements. However proper maintenance of a PV plant is essential to maximise both energy yield & the plant’s useful life. The presence of an operation & maintenance (O&M) contract is crucial to define the parameter for the operation & maintenance of a project during its life. The project developer shall appoint a private O&M contractor and enter into an O&M contract. This shall specify details regarding project uptime, personnel required, spare acquisition etc. for project operation and management.