SPLOST PROJECTS 2008 City of Duluth, Georgia June 19, 2008
Introduction The City of Duluth is continuing to make an extensive effort to create a vibrant  Downtown through the development of access corridors and gateways to the newly created and beautiful Town Green.  As a result, of the need to create these new gateways, the City of Duluth has participated in the development of multiple road and sidewalk projects that would create efficient and attractive gateways into the downtown corridor while promoting a pedestrian friendly environment.  The various projects, that have been selected by the City of Duluth, have traditionally been funded through various grants and funds such as LCI, CMAQ, SPLOST & GDOT funds.  However, the cost of development, match requirements and funding restrictions requires  that the City of Duluth peruse alternative sources of funding.  In addition to downtown needs the City hopes to implement many of the recommendations identified in the recently completed Master Park Plan. The City’s road resurfacing needs have grown beyond the City’s ability to handle from property taxes above.
Projected SPLOST Transportation Project  The City of Duluth is seeking SPLOST funds to finance Transportation Improvement projects that would fall under three separate categories. Road Improvements  – These are projects that include the extension and creation of public Right-of-Ways that can be utilized to assist in alleviating traffic congestion throughout targeted areas in the City. (Can include Land Acquisitions) Sidewalk Improvements - These are projects that construct or improve public sidewalks that can be utilized to promote a pedestrian friendly neighborhood environment. (Can include Land Acquisition). Street Resurfacing  – The resurfacing  and maintenance of existing public streets.
SPLOST FUNDS NEEDED For Road Improvements  Although the City has LCI funds available for a portion of the aforementioned projects there is a need for SPLOST funds to assist in the financing.  As a result, the City of Duluth is seeking 2008 SPLOST funds to finance the following three road projects that were identified as being key components to the development of a gateway to downtown. Three primary projects targeted for SPLOST funds include; Davenport Road Extension Ridgeway Road Extension Hospital Connector
History of Road Improvement Project’s The City of Duluth and its citizens have recognized the need to develop a coordinated plan to alleviate traffic throughout downtown and address the following concerns identified in past community workshops:  Use of Highway 120 as a pass-through by commuters “ Traffic-choked” downtown Limited number of options to W. Lawrenceville Street and Highway 120 Intersection Deficiencies Unsafe Pedestrian Environment Lack of good sidewalks  Lack of connections between neighborhoods and downtown Buford Highway is unsightly and dangerous for pedestrians. As a result, the City of Duluth sought LCI funding to finance four primary road projects that included ; Davenport Road Extension SR 120 Realignment Ridgeway Road Extension Hospital Connector
Hospital Connecter Description: This project involves the design and construction of a new connecting street from West  Lawrenceville Street to Abbotts Bridge Road.  In addition, the newly created connector  street will also align the new intersection at SR 120 with the new Duluth High School Entrance. Purpose: As stated above, the newly constructed Right-of-Way will tie into West Lawrenceville  Street at the intersection of McClure Bridge Road with the proposed development of a  traffic control round-a-bout.  As a result, this newly created intersection should provide  a functional connector that improves safety, reduces congestion while maintaining a  cost effective solution.
Hospital Connector North
Hospital Connector As previously stated, this project involves a newly constructed Right-of-Way that will tie into West Lawrenceville Street at the intersection of McClure Bridge Road with the proposed development of a traffic control round-a-bout. In addition, the newly created connector street will also align the new intersection at SR 120 with the new Duluth High School Entrance. The City is seeking $500,000 in SPLOST funds to finance the following components of the project. $500,000 (Additional Construction Costs) Status:   This total estimated project cost is $3,800,000  and has been primarily funded by 2004 LCI and 2005 SPLOST funds.  The funds committed to this project total approximately $3,300,000 based on the following: 1) LCI Funds  ($2,400,000 LCI + $316,500 Transferred from Ridgeway LCI = $2,716,500) 2) 2001 & 2005 SPLOST = $577,000. The environmental clearance is almost complete and Right-of-Way acquisition should begin this summer.  Construction plans will be completed prior to ROW acquisition. Project should be ready for construction in Spring 2009 and completed by early 2010.
Ridgeway Road Extension Description: This project involves the extension of Ridgeway Road from the current termination  point on to McClure Bridge Road at the intersection of West Lawrenceville Street.  Purpose: As stated above, the newly constructed Right-of-Way will extend Ridgeway Road to West Lawrenceville Street at the intersection of McClure Bridge Road at the  aforementioned proposed traffic control round-a-bout.  As a result, this newly created  intersection and extension should provide a functional connector that improves safety,  reduces congestion while maintaining a cost effective solution.
Ridgeway Road Extension North
Ridgeway Road Extension As previously stated this project involves the extension of Ridgeway Road from the current termination point on to McClure Bridge Road at the intersection of West Lawrenceville Street. This newly created intersection and extension should provide a functional connector that improves safety, reduces congestion while maintaining a cost effective solution. The City is seeking $2,000,000 in SPLOST funds to finance the following components of the project. $1,500,000 (Road Construction) $500,000 (Right-of-Way Acquisition) Status:   This project was originally to be funded by LCI funds but has been determined to be ineligible.  As a result, the existing LCI funds have been transferred to the Hospital Connector Project.  Federal Highway Administration approval is no longer required so ROW acquisition can proceed without further delay.  The Engineering and Design of the project is completed and construction can begin once ROW  is acquired. Expected start of construction is Spring 2009 and completion of project should be early 2010.
Davenport Road Extension Description: This project involves the construction of Davenport Road from the intersection of Main  Street and Buford Highway to the intersection of Hill Street and Hardy Street. Purpose: This project will connect by new construction the extension of Hill Street looping back  to connect with the new location of Main Street.  The project will continue by  extending from Hill Street to cross over the Norfolk Southern railroad tracks and  connect to Buford Highway at the Davenport Road intersection. As a result, this newly created intersection and extension should provide a functional connector that  improves safety, reduces congestion while maintaining a cost effective solution.
Davenport Road Extension North
SR 120 Realignment Description: This project involves the widening of SR 120 from Hill Street to Buford Highway.  The  project will tie into the SR 120 Gateway development. Purpose: This project will widen the existing SR 120 from Hill Street to Buford Highway.  The  completion of this project will include additional lanes, traffic control devices and  sidewalks that will contribute to more efficient traffic flow patterns throughout the  downtown area while promoting a more pedestrian friendly environment.
SR 120 Realignment North
Sidewalk Improvement Project’s The City of Duluth has set a goal to identify, repair and replace hazardous sidewalks and to construct incomplete sections of the sidewalk system over time in a continuous effort to promote a safe and pedestrian friendly environment for its citizens.  As a result, the City has identified multiple sidewalk improvement projects that will be completed in addition to the aforementioned Road Improvement projects. The City is working towards achieving the goals of sidewalk construction and maintenance through the development of a “Master Sidewalk Plan”.
Master Sidewalk Plan The City of Duluth’s  “Master Sidewalk Plan” is a long range multi-year plan for the construction of sidewalks throughout the city.  The sidewalk plan has prioritized sidewalks based on safety and need along with the following guidelines: Priority Guidelines: Sidewalks serving schools are given the highest priority. Sidewalks serving parks, hospitals, libraries, and other public buildings are given next highest  priority. Sidewalks serving higher density residential areas in close proximity to shopping is given the next highest priority. Residential neighborhoods fronting along high traffic streets are given the next highest priority. Linkage of neighborhoods and existing sidewalks within neighborhoods to the above listed sidewalk system is the next highest priority of sidewalks. Current Improvement Projects meeting the criteria of the City’s Master Sidewalk Plan and are targeted for SPLOST 08 funds include:  - W. Lawrenceville - McClure Bridge Road - Other pending funds   a) Pine Needle   b) Howell Ferry
W. Lawrenceville/McClure Bridge Sidewalks Description:  The proposed sidewalk improvements, which are being proposed, along West Lawrenceville and McClure Bridge Road will be in conjunction with the proposed Road  Improvements previously identified.  The need for the improvements will be the result  of both new construction and the replacement of existing sidewalks throughout the  targeted area.  The total estimated cost for the projects, in which SPLOST funds are  being requested, is $1,250,000. Purpose: The completion of the sidewalk projects will provide a safe and pedestrian friendly  neighborhood environment while meeting the goals and objective’s set forth in the  City of Duluth’s “Master Sidewalk Plan”.
Street Resurfacing The City of Duluth’s  Public Work’s Department continuously works to keep City streets in a condition similar to the original condition that was present when they were constructed. As a result, the City’s Public Works Department will be utilizing SPLOST funds to fund the following projects: 1) - W. Lawrenceville / McClure Bridge -  This project will consist of resurfacing the  remaining portions of W. Lawrenceville Street and McClure Bridge Road to  complete the aforementioned Road Improvement Projects. ($1,250,000)   - Primarily be Grinding & Resurfacing - Yearly Resurfacing ( 5-year period) -  This project will consist of yearly resurfacing  of multiple City Street’s that are in need of maintenance. ($1,000,000)
Rogers Bridge Scott Hudgens W.P. Jones Taylor Park Church Street Central City It Starts in the Parks
Proposed SPLOST Projects as recommended by the Parks & Recreation Advisory Board Green space Park Land Rogers Bridge W.P. Jones Taylor Park
Rogers Bridge Park
Rogers Bridge Park Slide #1
Rogers Bridge Park Slide #2
Rogers Bridge Park – Master Park Plan Concept
Rogers Bridge/Dog Park (Projected Goal)
Scott Hudgens Park
Scott Hudgens Park Slide #1
Scott Hudgens Park – Master Park Plan Concept
W.P. Jones Park
W.P. Jones Park Slide #1
W.P. Jones Park Slide #2
W.P. Jones Park – Master Park Plan Concept
W.P. Jones Depot Replacement (Projected Goal)
Taylor Park
Taylor Park Slide #1
Taylor Park- Playground (Projected Goal)
Church Street Park
Church St. Park Slide #1
Church Street Park – Master Park Plan Concept
Central City Bikeway
Project Costs Projected Costs for Park ($5,800,000) Dog Park ($50,000) Depot Replacement ($500,000) Taylor Park Playground ($250,000)
Other Targeted SPLOST Projects Stormwater - Repair & Replace Storm Water Pipes. ($250,000) - Backhoe for Storm Water Work ($50,000) Downtown Parking (Library)   - Library Land Acquisition. ($1,510,000) Public Safety - Police Vehicles 5 years ($1,000,000) - Police Radio Replacements ($500,000) - Police & Court Software ($265,000) Historical & Cultural - Renovation of Methodists Church ($250,000) Roads & Sidewalks - Multiple Projects ($5,677,424)
TOTAL 2008 SPLOST  The total projected costs of SPLOST projects is $16,000,000. The total SPLOST funds available is $23,000,000

More Related Content

PPT
Splost Presentation 2008
PPT
Delivering the Rehabilitation of the F.G. Gardiner Expressway
PDF
Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...
PDF
APWA mid atlantic awards
PDF
Planning Department Response to Primary Questions re: Johnwoods
PDF
Section 2 Inventory and Assessment
PDF
Belcrest Road Phasing Program
PDF
Gardiner East EA Public Forum 3 (Feb062014) - panels
Splost Presentation 2008
Delivering the Rehabilitation of the F.G. Gardiner Expressway
Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...
APWA mid atlantic awards
Planning Department Response to Primary Questions re: Johnwoods
Section 2 Inventory and Assessment
Belcrest Road Phasing Program
Gardiner East EA Public Forum 3 (Feb062014) - panels

What's hot (20)

PDF
PALM BAY HANDS CDBG EXPO SLIDE SHOW FINAL
PDF
Oakwood Avenue Bump-outs (panels)
PDF
Nicholas DiFrank - Professional Portfolio 2015
PPT
Sectors 2 & 3 Charrette Closing Presentation
PDF
New Street Typologies/New Street Types - Getting more out of the same R.O.W.:...
PDF
PIS Uyo - Ring Road Phases I
PDF
Lynée Russell - Previous DUDC Projects
PPT
Beaufort-Sector1-Charrette-FinalPresentation
PPT
May 4 presentation re: Johnwoods closure
PPTX
South Lakes Drive Sidewalk
PDF
Walton Boulevard Reconstruction, APWA Project of the Year
PDF
EIR Scoping Meeting 7 18-17 presentation
PDF
Clairemont CPG Ad Hoc Subcommittee Meeting
PDF
SmartTrack Public Meeting Presentation
PDF
Gardiner East EA - Public Forum 5 Panels
PDF
DC Buys 2018 - DDOT Infrastructure Project Management Division - Full Present...
PDF
FG Gardiner New Simcoe Ramp - display boards
PDF
AH City Council Meeting 12.14.15 - Item #10 - 6116 Broadway & 213 Henderson
PPTX
Sunset Hills Road Walkway
PPTX
Lee Highway, U.S. Route 29 Phase III Widening
PALM BAY HANDS CDBG EXPO SLIDE SHOW FINAL
Oakwood Avenue Bump-outs (panels)
Nicholas DiFrank - Professional Portfolio 2015
Sectors 2 & 3 Charrette Closing Presentation
New Street Typologies/New Street Types - Getting more out of the same R.O.W.:...
PIS Uyo - Ring Road Phases I
Lynée Russell - Previous DUDC Projects
Beaufort-Sector1-Charrette-FinalPresentation
May 4 presentation re: Johnwoods closure
South Lakes Drive Sidewalk
Walton Boulevard Reconstruction, APWA Project of the Year
EIR Scoping Meeting 7 18-17 presentation
Clairemont CPG Ad Hoc Subcommittee Meeting
SmartTrack Public Meeting Presentation
Gardiner East EA - Public Forum 5 Panels
DC Buys 2018 - DDOT Infrastructure Project Management Division - Full Present...
FG Gardiner New Simcoe Ramp - display boards
AH City Council Meeting 12.14.15 - Item #10 - 6116 Broadway & 213 Henderson
Sunset Hills Road Walkway
Lee Highway, U.S. Route 29 Phase III Widening
Ad

Viewers also liked (8)

PPT
Occupational Tax Amendments
PPT
香港六合彩
PDF
Memoria2007
PPT
State of the City 2009
PPTX
CIty of Duluth State of the City 2010
PPT
Adding Music To Power Point
PPT
Budget Committee Presentation March 19
PPT
2nd Honor Ride
Occupational Tax Amendments
香港六合彩
Memoria2007
State of the City 2009
CIty of Duluth State of the City 2010
Adding Music To Power Point
Budget Committee Presentation March 19
2nd Honor Ride
Ad

Similar to Splost Projects (9)

PDF
2011 State of the City
PDF
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
PDF
2010 Caroline, VA Economic Report
PPT
Accomplishments 2011
PPT
Wilton Walking Audit
PDF
2012 annual report
PDF
Capital Improvement Project Highlights for Downtown Merchants
DOCX
respond to this discussion answerHamilton Crossing is a sm.docx
PPT
City of LaSalle 2008 Annual Report
2011 State of the City
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
2010 Caroline, VA Economic Report
Accomplishments 2011
Wilton Walking Audit
2012 annual report
Capital Improvement Project Highlights for Downtown Merchants
respond to this discussion answerHamilton Crossing is a sm.docx
City of LaSalle 2008 Annual Report

Recently uploaded (20)

PDF
Tortilla Mexican Grill 发射点犯得上发射点发生发射点犯得上发生
PDF
Consumer Behavior in the Digital Age (www.kiu.ac.ug)
PDF
Middle East's Most Impactful Business Leaders to Follow in 2025
PDF
Comments on Clouds that Assimilate Parts I&II.pdf
PPT
Retail Management and Retail Markets and Concepts
DOCX
Center Enamel Powering Innovation and Resilience in the Italian Chemical Indu...
PPTX
33ABJFA6556B1ZP researhchzfrsdfasdfsadzd
PPTX
operations management : demand supply ch
PDF
Immigration Law and Communication: Challenges and Solutions {www.kiu.ac.ug)
DOCX
Handbook of Entrepreneurship- Chapter 5: Identifying business opportunity.docx
PPTX
IITM - FINAL Option - 01 - 12.08.25.pptx
PDF
income tax laws notes important pakistan
DOCX
Hand book of Entrepreneurship 4 Chapters.docx
PDF
Business Communication for MBA Students.
PPTX
chapter 2 entrepreneurship full lecture ppt
PPTX
Market and Demand Analysis.pptx for Management students
PDF
Vinod Bhatt - Most Inspiring Supply Chain Leader in India 2025.pdf
PDF
Highest-Paid CEO in 2025_ You Won’t Believe Who Tops the List.pdf
PPTX
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
DOCX
Handbook of entrepreneurship- Chapter 7- Types of business organisations
Tortilla Mexican Grill 发射点犯得上发射点发生发射点犯得上发生
Consumer Behavior in the Digital Age (www.kiu.ac.ug)
Middle East's Most Impactful Business Leaders to Follow in 2025
Comments on Clouds that Assimilate Parts I&II.pdf
Retail Management and Retail Markets and Concepts
Center Enamel Powering Innovation and Resilience in the Italian Chemical Indu...
33ABJFA6556B1ZP researhchzfrsdfasdfsadzd
operations management : demand supply ch
Immigration Law and Communication: Challenges and Solutions {www.kiu.ac.ug)
Handbook of Entrepreneurship- Chapter 5: Identifying business opportunity.docx
IITM - FINAL Option - 01 - 12.08.25.pptx
income tax laws notes important pakistan
Hand book of Entrepreneurship 4 Chapters.docx
Business Communication for MBA Students.
chapter 2 entrepreneurship full lecture ppt
Market and Demand Analysis.pptx for Management students
Vinod Bhatt - Most Inspiring Supply Chain Leader in India 2025.pdf
Highest-Paid CEO in 2025_ You Won’t Believe Who Tops the List.pdf
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
Handbook of entrepreneurship- Chapter 7- Types of business organisations

Splost Projects

  • 1. SPLOST PROJECTS 2008 City of Duluth, Georgia June 19, 2008
  • 2. Introduction The City of Duluth is continuing to make an extensive effort to create a vibrant Downtown through the development of access corridors and gateways to the newly created and beautiful Town Green. As a result, of the need to create these new gateways, the City of Duluth has participated in the development of multiple road and sidewalk projects that would create efficient and attractive gateways into the downtown corridor while promoting a pedestrian friendly environment. The various projects, that have been selected by the City of Duluth, have traditionally been funded through various grants and funds such as LCI, CMAQ, SPLOST & GDOT funds. However, the cost of development, match requirements and funding restrictions requires that the City of Duluth peruse alternative sources of funding. In addition to downtown needs the City hopes to implement many of the recommendations identified in the recently completed Master Park Plan. The City’s road resurfacing needs have grown beyond the City’s ability to handle from property taxes above.
  • 3. Projected SPLOST Transportation Project The City of Duluth is seeking SPLOST funds to finance Transportation Improvement projects that would fall under three separate categories. Road Improvements – These are projects that include the extension and creation of public Right-of-Ways that can be utilized to assist in alleviating traffic congestion throughout targeted areas in the City. (Can include Land Acquisitions) Sidewalk Improvements - These are projects that construct or improve public sidewalks that can be utilized to promote a pedestrian friendly neighborhood environment. (Can include Land Acquisition). Street Resurfacing – The resurfacing and maintenance of existing public streets.
  • 4. SPLOST FUNDS NEEDED For Road Improvements Although the City has LCI funds available for a portion of the aforementioned projects there is a need for SPLOST funds to assist in the financing. As a result, the City of Duluth is seeking 2008 SPLOST funds to finance the following three road projects that were identified as being key components to the development of a gateway to downtown. Three primary projects targeted for SPLOST funds include; Davenport Road Extension Ridgeway Road Extension Hospital Connector
  • 5. History of Road Improvement Project’s The City of Duluth and its citizens have recognized the need to develop a coordinated plan to alleviate traffic throughout downtown and address the following concerns identified in past community workshops: Use of Highway 120 as a pass-through by commuters “ Traffic-choked” downtown Limited number of options to W. Lawrenceville Street and Highway 120 Intersection Deficiencies Unsafe Pedestrian Environment Lack of good sidewalks Lack of connections between neighborhoods and downtown Buford Highway is unsightly and dangerous for pedestrians. As a result, the City of Duluth sought LCI funding to finance four primary road projects that included ; Davenport Road Extension SR 120 Realignment Ridgeway Road Extension Hospital Connector
  • 6. Hospital Connecter Description: This project involves the design and construction of a new connecting street from West Lawrenceville Street to Abbotts Bridge Road. In addition, the newly created connector street will also align the new intersection at SR 120 with the new Duluth High School Entrance. Purpose: As stated above, the newly constructed Right-of-Way will tie into West Lawrenceville Street at the intersection of McClure Bridge Road with the proposed development of a traffic control round-a-bout. As a result, this newly created intersection should provide a functional connector that improves safety, reduces congestion while maintaining a cost effective solution.
  • 8. Hospital Connector As previously stated, this project involves a newly constructed Right-of-Way that will tie into West Lawrenceville Street at the intersection of McClure Bridge Road with the proposed development of a traffic control round-a-bout. In addition, the newly created connector street will also align the new intersection at SR 120 with the new Duluth High School Entrance. The City is seeking $500,000 in SPLOST funds to finance the following components of the project. $500,000 (Additional Construction Costs) Status: This total estimated project cost is $3,800,000 and has been primarily funded by 2004 LCI and 2005 SPLOST funds. The funds committed to this project total approximately $3,300,000 based on the following: 1) LCI Funds ($2,400,000 LCI + $316,500 Transferred from Ridgeway LCI = $2,716,500) 2) 2001 & 2005 SPLOST = $577,000. The environmental clearance is almost complete and Right-of-Way acquisition should begin this summer. Construction plans will be completed prior to ROW acquisition. Project should be ready for construction in Spring 2009 and completed by early 2010.
  • 9. Ridgeway Road Extension Description: This project involves the extension of Ridgeway Road from the current termination point on to McClure Bridge Road at the intersection of West Lawrenceville Street. Purpose: As stated above, the newly constructed Right-of-Way will extend Ridgeway Road to West Lawrenceville Street at the intersection of McClure Bridge Road at the aforementioned proposed traffic control round-a-bout. As a result, this newly created intersection and extension should provide a functional connector that improves safety, reduces congestion while maintaining a cost effective solution.
  • 11. Ridgeway Road Extension As previously stated this project involves the extension of Ridgeway Road from the current termination point on to McClure Bridge Road at the intersection of West Lawrenceville Street. This newly created intersection and extension should provide a functional connector that improves safety, reduces congestion while maintaining a cost effective solution. The City is seeking $2,000,000 in SPLOST funds to finance the following components of the project. $1,500,000 (Road Construction) $500,000 (Right-of-Way Acquisition) Status: This project was originally to be funded by LCI funds but has been determined to be ineligible. As a result, the existing LCI funds have been transferred to the Hospital Connector Project. Federal Highway Administration approval is no longer required so ROW acquisition can proceed without further delay. The Engineering and Design of the project is completed and construction can begin once ROW is acquired. Expected start of construction is Spring 2009 and completion of project should be early 2010.
  • 12. Davenport Road Extension Description: This project involves the construction of Davenport Road from the intersection of Main Street and Buford Highway to the intersection of Hill Street and Hardy Street. Purpose: This project will connect by new construction the extension of Hill Street looping back to connect with the new location of Main Street. The project will continue by extending from Hill Street to cross over the Norfolk Southern railroad tracks and connect to Buford Highway at the Davenport Road intersection. As a result, this newly created intersection and extension should provide a functional connector that improves safety, reduces congestion while maintaining a cost effective solution.
  • 14. SR 120 Realignment Description: This project involves the widening of SR 120 from Hill Street to Buford Highway. The project will tie into the SR 120 Gateway development. Purpose: This project will widen the existing SR 120 from Hill Street to Buford Highway. The completion of this project will include additional lanes, traffic control devices and sidewalks that will contribute to more efficient traffic flow patterns throughout the downtown area while promoting a more pedestrian friendly environment.
  • 16. Sidewalk Improvement Project’s The City of Duluth has set a goal to identify, repair and replace hazardous sidewalks and to construct incomplete sections of the sidewalk system over time in a continuous effort to promote a safe and pedestrian friendly environment for its citizens. As a result, the City has identified multiple sidewalk improvement projects that will be completed in addition to the aforementioned Road Improvement projects. The City is working towards achieving the goals of sidewalk construction and maintenance through the development of a “Master Sidewalk Plan”.
  • 17. Master Sidewalk Plan The City of Duluth’s “Master Sidewalk Plan” is a long range multi-year plan for the construction of sidewalks throughout the city. The sidewalk plan has prioritized sidewalks based on safety and need along with the following guidelines: Priority Guidelines: Sidewalks serving schools are given the highest priority. Sidewalks serving parks, hospitals, libraries, and other public buildings are given next highest priority. Sidewalks serving higher density residential areas in close proximity to shopping is given the next highest priority. Residential neighborhoods fronting along high traffic streets are given the next highest priority. Linkage of neighborhoods and existing sidewalks within neighborhoods to the above listed sidewalk system is the next highest priority of sidewalks. Current Improvement Projects meeting the criteria of the City’s Master Sidewalk Plan and are targeted for SPLOST 08 funds include: - W. Lawrenceville - McClure Bridge Road - Other pending funds a) Pine Needle b) Howell Ferry
  • 18. W. Lawrenceville/McClure Bridge Sidewalks Description: The proposed sidewalk improvements, which are being proposed, along West Lawrenceville and McClure Bridge Road will be in conjunction with the proposed Road Improvements previously identified. The need for the improvements will be the result of both new construction and the replacement of existing sidewalks throughout the targeted area. The total estimated cost for the projects, in which SPLOST funds are being requested, is $1,250,000. Purpose: The completion of the sidewalk projects will provide a safe and pedestrian friendly neighborhood environment while meeting the goals and objective’s set forth in the City of Duluth’s “Master Sidewalk Plan”.
  • 19. Street Resurfacing The City of Duluth’s Public Work’s Department continuously works to keep City streets in a condition similar to the original condition that was present when they were constructed. As a result, the City’s Public Works Department will be utilizing SPLOST funds to fund the following projects: 1) - W. Lawrenceville / McClure Bridge - This project will consist of resurfacing the remaining portions of W. Lawrenceville Street and McClure Bridge Road to complete the aforementioned Road Improvement Projects. ($1,250,000) - Primarily be Grinding & Resurfacing - Yearly Resurfacing ( 5-year period) - This project will consist of yearly resurfacing of multiple City Street’s that are in need of maintenance. ($1,000,000)
  • 20. Rogers Bridge Scott Hudgens W.P. Jones Taylor Park Church Street Central City It Starts in the Parks
  • 21. Proposed SPLOST Projects as recommended by the Parks & Recreation Advisory Board Green space Park Land Rogers Bridge W.P. Jones Taylor Park
  • 23. Rogers Bridge Park Slide #1
  • 24. Rogers Bridge Park Slide #2
  • 25. Rogers Bridge Park – Master Park Plan Concept
  • 26. Rogers Bridge/Dog Park (Projected Goal)
  • 28. Scott Hudgens Park Slide #1
  • 29. Scott Hudgens Park – Master Park Plan Concept
  • 31. W.P. Jones Park Slide #1
  • 32. W.P. Jones Park Slide #2
  • 33. W.P. Jones Park – Master Park Plan Concept
  • 34. W.P. Jones Depot Replacement (Projected Goal)
  • 37. Taylor Park- Playground (Projected Goal)
  • 39. Church St. Park Slide #1
  • 40. Church Street Park – Master Park Plan Concept
  • 42. Project Costs Projected Costs for Park ($5,800,000) Dog Park ($50,000) Depot Replacement ($500,000) Taylor Park Playground ($250,000)
  • 43. Other Targeted SPLOST Projects Stormwater - Repair & Replace Storm Water Pipes. ($250,000) - Backhoe for Storm Water Work ($50,000) Downtown Parking (Library) - Library Land Acquisition. ($1,510,000) Public Safety - Police Vehicles 5 years ($1,000,000) - Police Radio Replacements ($500,000) - Police & Court Software ($265,000) Historical & Cultural - Renovation of Methodists Church ($250,000) Roads & Sidewalks - Multiple Projects ($5,677,424)
  • 44. TOTAL 2008 SPLOST The total projected costs of SPLOST projects is $16,000,000. The total SPLOST funds available is $23,000,000