SPM-UNIT III
RISK MANAGEMENT
MONITORING & CONTROL
Prof. Kanchana Devi
Introduction
 After scheduling , project will start and then
attention must be focused on progress.
 Progress needs monitoring
 What is happening
 Comparison of actual achievement against the schedule
 Revision of plans and schedules (wherever necessary)
2
Prof. Kanchana Devi
Creating Framework
Prof. Kanchana Devi
3
 Exercising control over a project and ensuring
that targets are met is a matter of regular
monitoring.
 Finding out what is happening and comparing
it with targets
 Re-planning also sometimes required
Project control cycle
Prof. Kanchana Devi
4
Responsibility
Prof. Kanchana Devi
5
 The overall responsibility
 Ensuring satisfactory progress on a project
 It is the role of “Steering Committee”, project
management board or Project Board.
Project Reporting Structure
Prof. Kanchana Devi
6
Reporting
Prof. Kanchana Devi
7
 Reporting may be
 Oral/Written
 Formal/Informal
 Regular/Ad-hoc
Assessing Progress
Prof. Kanchana Devi
8
 Information should be collected routinely
 Information should be objective and tangible
 Whether or not a particular report has been delivered
 Sometimes the assessment depends on
estimates of proportion of current activity that
has been completed
Setting Checkpoints
Prof. Kanchana Devi
9
 Necessary to set a series of check points in
the initial activity plan.
 Checkpoints may be:
 Regular(Monthly)
 Tied to specific events (production of report)
Collecting the Data
Prof. Kanchana Devi
10
 Rule: Manager will breakdown the long
activities into more controllable tasks of one or
two weeks.
 It is necessary to gather information about
partially completed activities, forecasts of how
much work is left to be completed.
Example of partial completion reporting
Prof. Kanchana Devi
11
Risk Reporting
Prof. Kanchana Devi
12
 One way to overcome the objections of partial
completion report is to avoid asking for
completion dates. (instead ask for likelihood of meeting the
target)
 Called “Traffic Light Method”.
Consists of following steps
Prof. Kanchana Devi
13
 Identify the key elements for assessment in a piece of
work
 Break these key elements into constituent element
 Assess each of the second level element on the scale
 Green for target,
 Amber for ‘not on target but recoverable’
 Red for ‘not on target and recoverable only with
difficulty’
 Review second level assessment to arrive at first level
 Review first level assessment to produce an overall
assessment
Example
Prof. Kanchana Devi
14
Visualizing Progress
Prof. Kanchana Devi
15
 Gantt Chart
 Slip Chart
 Ball Chart
 Timeline Chart
Cost Monitoring
Prof. Kanchana Devi
16
 Expenditure monitoring is an important
component of project control
 A project might be on time but only because
more money has been spent on activities than
originally budgeted
Tracking cumulative expenditure
Prof. Kanchana Devi
17
Cumulative Expenditure Chart
Prof. Kanchana Devi
18
Earned Value
Prof. Kanchana Devi
19
 Analysis is based on assigning a ‘value’ to each
task or work package based on expenditure
forecasts.
 The assigned value is the original budgeted cost
for the item and is known as the ‘baseline budget’
or ‘budgeted cost of work scheduled’(BCWS)
 The total value credited to a project at any point is
known as the ‘earned value’ or ‘budgeted cost of
the work performed’(BCWP)
Actual Cost
Prof. Kanchana Devi
20
 By recording the “Earned Value”, the actual
cost of each task can be collected as “Actual
Cost” or ACWP-Actual Cost of Work
Performed.
 There are three types of Variance:
 Schedule Variance(SV)
 Time Variance(TV)
 Cost Variance(CV)
Schedule Variance(SV)
Prof. Kanchana Devi
21
 The Schedule Variance is measured in
cost terms as EV-PV
 It indicates the degree to which the value
of the completed work differs from the
planned work.
Example:
Prof. Kanchana Devi
22
 A work with a PV of $40,000 should have
been completed by now. In fact, some of that
work has not been done so that the EV is only
$35,000. Calculate SV.
 SV=EV-PV
 35000-40000= - 5000
 A negative SV means the project is behind
schedule
Time Variance (TV)
Prof. Kanchana Devi
23
 Difference between the time when the
achievement of the current earned value was
planned to occur and the time now.
 Eg:
 The current EV should have been achieved in the
early part of month 9 and as the time now is end
of month 11, the TV is about -1.75 months from
graph.
Cost Variance (CV)
Prof. Kanchana Devi
24
 This is calculated as EV-AC.
 It indicates the difference between the earned
value or budgeted cost and the actual cost of the
completed work.
 Let Actual Cost for previous example is $ 55,000
 CV=35000-55000
 = -20000
 A negative CV means that the project is over cost
Prioritizing Monitoring
Prof. Kanchana Devi
25
 List of priorities
 Critical Path Activities
 Activities with no free float
 Activities with less than a specified float
 High Risk Activities
 Activities using critical resources

More Related Content

PPTX
SPM_UNIT-1(1).pptx
PPT
Spm unit 4
PDF
MG6088 SOFTWARE PROJECT MANAGEMENT
PPTX
Unit 7 performing user interface design
PPTX
#1 formal methods – introduction for software engineering
PDF
Data Versioning and Reproducible ML with DVC and MLflow
PDF
MG6088 SOFTWARE PROJECT MANAGEMENT
PPTX
Software Reliability
SPM_UNIT-1(1).pptx
Spm unit 4
MG6088 SOFTWARE PROJECT MANAGEMENT
Unit 7 performing user interface design
#1 formal methods – introduction for software engineering
Data Versioning and Reproducible ML with DVC and MLflow
MG6088 SOFTWARE PROJECT MANAGEMENT
Software Reliability

What's hot (20)

PDF
Requirements Validation
PPTX
Project Scheduling
PPT
Unit 2 spm
PPT
Lecture 2
PPT
Software Engineering (Project Scheduling)
PPTX
source code metrics and other maintenance tools and techniques
PDF
Spm ap-network model-
PPTX
SPM Activity Planning Introduction
PPT
Managing contracts
PDF
Introducción a la Ingenieria de Software
PPTX
software project management Artifact set(spm)
PPTX
Software development process models
PDF
Capability maturity model
PDF
MG6088 SOFTWARE PROJECT MANAGEMENT
PPTX
Walkthroughs
PPT
Managing the information system project
PPT
Pressman ch-21-project-management-concepts
PPT
Software effort estimation
PPTX
Checkpoints of the Process
ODP
Software Measurement: Lecture 1. Measures and Metrics
Requirements Validation
Project Scheduling
Unit 2 spm
Lecture 2
Software Engineering (Project Scheduling)
source code metrics and other maintenance tools and techniques
Spm ap-network model-
SPM Activity Planning Introduction
Managing contracts
Introducción a la Ingenieria de Software
software project management Artifact set(spm)
Software development process models
Capability maturity model
MG6088 SOFTWARE PROJECT MANAGEMENT
Walkthroughs
Managing the information system project
Pressman ch-21-project-management-concepts
Software effort estimation
Checkpoints of the Process
Software Measurement: Lecture 1. Measures and Metrics
Ad

Viewers also liked (20)

PPTX
Spm unit iii-risk-resource allocation
PPTX
Risk management
PPTX
Risk Management
PDF
Spm unit iii-risk-pert
PPT
Spm chapter 8
PPTX
Spm unit iii-risk-working in teams
PPT
List of 10 Sales Performance Management (SPM) Vendors
PDF
Spm project planning
PPTX
Monitoring the control
PDF
160155061 project-monitoring-control
PPT
Ch 9 project monitoring & control updated
PDF
How to monitor your project progress
PPTX
Bank risk management
PDF
Effective Risk Mgmt Kylucas (C) 2009 All Rights Reserved
PPT
Spm unit 1
PPTX
Project Monitoring and Control
ZIP
Project Monitoring and Control
PDF
Risk management in banks
PPSX
Leadership In Project Management
PPT
Spm unit 3
Spm unit iii-risk-resource allocation
Risk management
Risk Management
Spm unit iii-risk-pert
Spm chapter 8
Spm unit iii-risk-working in teams
List of 10 Sales Performance Management (SPM) Vendors
Spm project planning
Monitoring the control
160155061 project-monitoring-control
Ch 9 project monitoring & control updated
How to monitor your project progress
Bank risk management
Effective Risk Mgmt Kylucas (C) 2009 All Rights Reserved
Spm unit 1
Project Monitoring and Control
Project Monitoring and Control
Risk management in banks
Leadership In Project Management
Spm unit 3
Ad

Similar to Spm unit iii-risk-monitoring & control1 (20)

PPTX
Project monitoring & Earned Value Analysis
PPTX
Project monitoring lecture 1
PPT
Project Planning and Excution chapter 4.ppt
PDF
Project monitoring and controlling with earned value management
PPTX
Projects Control Using Earned Value Techniques - Part One
PPTX
project control using earned value analysis - Part 01
PPT
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
PPTX
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PDF
Earned value analysis
PDF
An introduction to project accounting
PPTX
Earned value analysis (1)
PDF
Primavera Calender and Earned Value.pdf..
PPT
The Project Management Process - Week 9 Performance Management
PPT
EVA - Metrics.ppt
PPTX
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
PPTX
Earned Value Analysis in construction projects
PDF
Project managment 6 (a)
PPT
Earned value Project Management (evpm)
DOCX
Summer Internship Report by waqar ahmed javed
PPTX
Earned Value Management - Leading & Misleading in Project Control
Project monitoring & Earned Value Analysis
Project monitoring lecture 1
Project Planning and Excution chapter 4.ppt
Project monitoring and controlling with earned value management
Projects Control Using Earned Value Techniques - Part One
project control using earned value analysis - Part 01
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
Earned value analysis
An introduction to project accounting
Earned value analysis (1)
Primavera Calender and Earned Value.pdf..
The Project Management Process - Week 9 Performance Management
EVA - Metrics.ppt
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Earned Value Analysis in construction projects
Project managment 6 (a)
Earned value Project Management (evpm)
Summer Internship Report by waqar ahmed javed
Earned Value Management - Leading & Misleading in Project Control

More from Kanchana Devi (9)

PPTX
Spm unit v-software reliability-
PPTX
Spm unit v-software maintenance-intro
PDF
Spm unit iii-configuration mgmt-responsibilities
PPTX
Spm unit iii-configuration mgmt-intro
PPTX
Spm unit iii-risk-intro
PDF
Spm software effort estimation
PPTX
SPM Evaluation
PPTX
Open source spm tools
PPTX
Software project management introduction
Spm unit v-software reliability-
Spm unit v-software maintenance-intro
Spm unit iii-configuration mgmt-responsibilities
Spm unit iii-configuration mgmt-intro
Spm unit iii-risk-intro
Spm software effort estimation
SPM Evaluation
Open source spm tools
Software project management introduction

Recently uploaded (20)

PPTX
Current and future trends in Computer Vision.pptx
PPTX
Artificial Intelligence
PDF
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
PDF
737-MAX_SRG.pdf student reference guides
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PPTX
UNIT 4 Total Quality Management .pptx
PPT
Total quality management ppt for engineering students
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PDF
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
PPTX
Fundamentals of Mechanical Engineering.pptx
PDF
Categorization of Factors Affecting Classification Algorithms Selection
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
Current and future trends in Computer Vision.pptx
Artificial Intelligence
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
737-MAX_SRG.pdf student reference guides
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
Fundamentals of safety and accident prevention -final (1).pptx
Foundation to blockchain - A guide to Blockchain Tech
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
UNIT 4 Total Quality Management .pptx
Total quality management ppt for engineering students
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
Fundamentals of Mechanical Engineering.pptx
Categorization of Factors Affecting Classification Algorithms Selection
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk

Spm unit iii-risk-monitoring & control1

  • 1. SPM-UNIT III RISK MANAGEMENT MONITORING & CONTROL Prof. Kanchana Devi
  • 2. Introduction  After scheduling , project will start and then attention must be focused on progress.  Progress needs monitoring  What is happening  Comparison of actual achievement against the schedule  Revision of plans and schedules (wherever necessary) 2 Prof. Kanchana Devi
  • 3. Creating Framework Prof. Kanchana Devi 3  Exercising control over a project and ensuring that targets are met is a matter of regular monitoring.  Finding out what is happening and comparing it with targets  Re-planning also sometimes required
  • 4. Project control cycle Prof. Kanchana Devi 4
  • 5. Responsibility Prof. Kanchana Devi 5  The overall responsibility  Ensuring satisfactory progress on a project  It is the role of “Steering Committee”, project management board or Project Board.
  • 7. Reporting Prof. Kanchana Devi 7  Reporting may be  Oral/Written  Formal/Informal  Regular/Ad-hoc
  • 8. Assessing Progress Prof. Kanchana Devi 8  Information should be collected routinely  Information should be objective and tangible  Whether or not a particular report has been delivered  Sometimes the assessment depends on estimates of proportion of current activity that has been completed
  • 9. Setting Checkpoints Prof. Kanchana Devi 9  Necessary to set a series of check points in the initial activity plan.  Checkpoints may be:  Regular(Monthly)  Tied to specific events (production of report)
  • 10. Collecting the Data Prof. Kanchana Devi 10  Rule: Manager will breakdown the long activities into more controllable tasks of one or two weeks.  It is necessary to gather information about partially completed activities, forecasts of how much work is left to be completed.
  • 11. Example of partial completion reporting Prof. Kanchana Devi 11
  • 12. Risk Reporting Prof. Kanchana Devi 12  One way to overcome the objections of partial completion report is to avoid asking for completion dates. (instead ask for likelihood of meeting the target)  Called “Traffic Light Method”.
  • 13. Consists of following steps Prof. Kanchana Devi 13  Identify the key elements for assessment in a piece of work  Break these key elements into constituent element  Assess each of the second level element on the scale  Green for target,  Amber for ‘not on target but recoverable’  Red for ‘not on target and recoverable only with difficulty’  Review second level assessment to arrive at first level  Review first level assessment to produce an overall assessment
  • 15. Visualizing Progress Prof. Kanchana Devi 15  Gantt Chart  Slip Chart  Ball Chart  Timeline Chart
  • 16. Cost Monitoring Prof. Kanchana Devi 16  Expenditure monitoring is an important component of project control  A project might be on time but only because more money has been spent on activities than originally budgeted
  • 19. Earned Value Prof. Kanchana Devi 19  Analysis is based on assigning a ‘value’ to each task or work package based on expenditure forecasts.  The assigned value is the original budgeted cost for the item and is known as the ‘baseline budget’ or ‘budgeted cost of work scheduled’(BCWS)  The total value credited to a project at any point is known as the ‘earned value’ or ‘budgeted cost of the work performed’(BCWP)
  • 20. Actual Cost Prof. Kanchana Devi 20  By recording the “Earned Value”, the actual cost of each task can be collected as “Actual Cost” or ACWP-Actual Cost of Work Performed.  There are three types of Variance:  Schedule Variance(SV)  Time Variance(TV)  Cost Variance(CV)
  • 21. Schedule Variance(SV) Prof. Kanchana Devi 21  The Schedule Variance is measured in cost terms as EV-PV  It indicates the degree to which the value of the completed work differs from the planned work.
  • 22. Example: Prof. Kanchana Devi 22  A work with a PV of $40,000 should have been completed by now. In fact, some of that work has not been done so that the EV is only $35,000. Calculate SV.  SV=EV-PV  35000-40000= - 5000  A negative SV means the project is behind schedule
  • 23. Time Variance (TV) Prof. Kanchana Devi 23  Difference between the time when the achievement of the current earned value was planned to occur and the time now.  Eg:  The current EV should have been achieved in the early part of month 9 and as the time now is end of month 11, the TV is about -1.75 months from graph.
  • 24. Cost Variance (CV) Prof. Kanchana Devi 24  This is calculated as EV-AC.  It indicates the difference between the earned value or budgeted cost and the actual cost of the completed work.  Let Actual Cost for previous example is $ 55,000  CV=35000-55000  = -20000  A negative CV means that the project is over cost
  • 25. Prioritizing Monitoring Prof. Kanchana Devi 25  List of priorities  Critical Path Activities  Activities with no free float  Activities with less than a specified float  High Risk Activities  Activities using critical resources