The importance of 3 Core NEC Time Clauses when submitting a programme
 27th January 2022
 SiteAdmin
 Cost Control Management, NEC, Project Planning
https://www.big-dada.co.uk/2022/01/27/3-core-nec-time-
clauses/?MC=1&FirstName=Andrew&LastName=Ng&Email=Andrewngadelaide@outlook.com&ut
m_source=Fellow+Conference+Exhibitors+List&utm_campaign=d18258ff08-
Fellow_Conference_Exhibitors_List_19042022&utm_medium=email&utm_term=0_aa06dea8f4-
d18258ff08-443207378&ct=t(Fellow_Conference_Exhibitors_List_19042022)
Via our chat function we received an interesting question…
Morning , just a quick query under NEC4 when you submit a clause 32 programme do you use the
clause 31 or last accepted clause 32 as Baseline. Many planners are using different methods I use
the accepted Clause 31 and add CE’s to accepted Clause 32 and then add to Clause 31 is this
correct ?
Regards Mr J [real name redacted]
Unfortunately Mr J (real name anonymised) was in a rush and did not provide their e-mail address for
us to post an answer, but we still thought it was a cracking question…
So we thought we would do it here!
Programme Acceptance
It is important to first explain the key differences in Programme Acceptance between NEC3 and NEC4
Contract Types.
As covered in our past article, within NEC3 in the absence of a Project Manager’s response, the contract
provided that the programme was simply ‘not accepted’, putting all the risk ontothe Contractor in
allowing the Project Managerto to withhold 25% of the price of work done to date if the
Contractor does not provide a programme in accordance with Cl.31.
Within NEC4 the position is improved and the contract includes a provision whereby in the absence of a
Project Manager’s response to the submitted programme within two weeks, the Contractor can
serve notice of a further week. After this, if there is still no response then the contractor’s
programme is ‘deemed accepted’ under the contract.
Preparation of Compensation Events Costs
Another key difference between NEC3 and NEC4, is that the newer version allows recovery of costs
even where the Project Manager proposes an instruction which is not accepted. The past exclusion
for the cost of preparing compensation events has been deleted and is now recoverable underall
Options. There is now the introduction of new CE clause 60(1)(20) (“where the PM notifies the
Contractor that a quotation for a proposed instruction is not accepted”).
3 Core Time Clauses
Within NEC Professional Services Contract, there are 3 core Schedule related clauses within the
Professional Services Contract which we shall use to answer the original question posed:
 Clause 30 Starting, Completion and Key Dates
 Clause 31 The programme
 Clause 32 Revising the programme
To answer Mr J’s question the two key concept to understand is that there is a “Planned Completion
Date” and the ‘Completion Date’.
Under Clause 31.2 the programme issued for acceptance will show the “Planned Completion Date”,
which will be driven by the any event that affects the criticalpath.
The other is the “Completion Date“, which can only be changed ‘in accordance with the Contract. This
reflecting that the contractoris contractually obliged to achieve ‘Completion’ on or before the
‘Completion Date’, under clause 30.1.
So under Clause 14.1 “acceptance of a programme” cannot and will not change that responsibility of
meeting the ‘Completion Date’ in Clause 11.2(3), that being ‘Completion Date’ in the contract data.
NEC contract documentation does set out when the date can be changed (eg., 44.2, 36.3 and 65.4),
however acceptance of the programme, does not by itself change the “Completion Date”.
As covered under clause 31.3 the Project Manager has to accept or not accept a programme within two
weeks of submission. Any non-acceptance having to be communicated backto the Contractor in
sufficient detail to Contactor tocorrect the submission (via a separate response under Clause 13.7).
The four reasons reasons for non-acceptance are:
1. Contractor’s plans shown are not practicable
2. It does not show the information which this contract requires
3. It does not represent the Contractors plans realistically
4. It does not comply with the Scope
As such the programme should show the starting date, access dates, key dates and completion dates
when the Contractor plans to meet each condition stated for the Key Dates. It should also show the
Planned dates when the contractor plans to complete work required to allow others to carry out
works. It also needs to show the dates when the Contractor needs access to the site if this is later
than their planned access dates. Acceptances, plant, materials and other things to be provided by
the Client should also be identified. Finally for each operation, a statement of how the Contractor
plans to do the work should be given.
If not met, the Project Manager can respond under Clause 13.7 on the reason for non-acceptance. If the
Project Manager chooses not to accept for any other reason, then by default that would be a
compensation event under 60.1(9).
In revising the programme under Clause 32.1, to update the accepted programme under Clause 31, Mr
J should remember…that the acceptance of a programme does not change the responsibility to
‘Provide the Works’ in clause 11.2(13).
However it should be borne in mind that Clause (14.1) states that acceptance of any communication
does not transfer liability away from the Contractor to comply with their obligations underthe
contract. And so, the “Completion Date” as defined by 11.2 remains. That said, acceptance of the
programme is still significant as it recognises that the Client has given affirmation that from their
perspective that the programme is realistic, practicable and shows the information that the
contract requires.
The “Accepted Programme” as laid out under Clause 31, and defined under 11.2, is thereby the
reference point for all compensation events and change that occur. If there is no recent “Accepted
Programme” then commercial resolution is made the more difficult as reference will have to be
made to the last “Accepted Programme”, which will inevitably differ from the latest “Revised
Programme” under 32.1.
The workflow below can be used to explain a scenario how the under 32.1 the Contractor is responsible
for correcting all Work which the Client has found to be defective or which fails to conform to the
Contract Documents whetherobserved before or after Substantial Completion.
NECProject ManagementProject Portfolio Management (PPM)
Share This

More Related Content

PDF
PDF
Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...
PDF
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
PDF
NEC Contracts - Programmes under ECC and PSC webinar
PDF
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
PPTX
CFW NEC Management of change under the NEC3
PPTX
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
PDF
From NEC3 to NEC4 ECC
Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
NEC Contracts - Programmes under ECC and PSC webinar
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
CFW NEC Management of change under the NEC3
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
From NEC3 to NEC4 ECC

Similar to The importance of 3 Core NEC Time Clauses when submitting a programme.docx (9)

PPT
20090714 Contracts Workshop
PDF
NEC4 overview: key changes and impacts - Nottingham, September 2017
PDF
NEC4 overview: key changes and impacts - Birmingham, September 2017
PDF
NEC4 overview: key changes and impacts - London, September 2017
PDF
pdfsecret.com_nec3-engineering-construction-contract-acoste.pdf
PPTX
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
PDF
The people factor in contracts and procurement, Barry Trebes, 16th June 2016
PDF
Baseline Schedules 2
PPTX
C. Site managment chapter 5.pptx
20090714 Contracts Workshop
NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - London, September 2017
pdfsecret.com_nec3-engineering-construction-contract-acoste.pdf
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
The people factor in contracts and procurement, Barry Trebes, 16th June 2016
Baseline Schedules 2
C. Site managment chapter 5.pptx
Ad

More from My own (17)

PDF
eBook_ Digitizing and Automating Work Packaging (3).pdf
DOCX
Procurement and Contract Management Strategy-1.docx
PDF
AWP-Education-Primer.pdf
PDF
ENR Sep 2018 - Best Global Project Award - Sidra Citation -w Picture.pdf
PDF
Andrew 2008 Ipma Assessor Certificate
PDF
2008 Ipma Pe Training Beijing
PDF
2007 Advanced Primavera Project Management Module 6.0 Training
PDF
Cipa 2009 Contract Master Class
PDF
2010 Ipma Pe Training Beijing
PDF
120606 Contract Management Skill Checklist & Experience Grid Andrew Ng
PPT
Countries at the Forefronts of Project Management Excellence
PPT
Aw Award Marketing Presentation 2012
PDF
110801Proposed Fidic Contract Framework For Complex Epc Projects
PDF
Beyond Contract Series Article One
PDF
Skills & Experience Compared with Planning Fraternity
PDF
Ipma Proj Excel Mtg09
PPT
Ipma Pe Draf Tnewassessmenttables Tm 20090515
eBook_ Digitizing and Automating Work Packaging (3).pdf
Procurement and Contract Management Strategy-1.docx
AWP-Education-Primer.pdf
ENR Sep 2018 - Best Global Project Award - Sidra Citation -w Picture.pdf
Andrew 2008 Ipma Assessor Certificate
2008 Ipma Pe Training Beijing
2007 Advanced Primavera Project Management Module 6.0 Training
Cipa 2009 Contract Master Class
2010 Ipma Pe Training Beijing
120606 Contract Management Skill Checklist & Experience Grid Andrew Ng
Countries at the Forefronts of Project Management Excellence
Aw Award Marketing Presentation 2012
110801Proposed Fidic Contract Framework For Complex Epc Projects
Beyond Contract Series Article One
Skills & Experience Compared with Planning Fraternity
Ipma Proj Excel Mtg09
Ipma Pe Draf Tnewassessmenttables Tm 20090515
Ad

Recently uploaded (20)

PPTX
Lecture Notes Electrical Wiring System Components
PPTX
additive manufacturing of ss316l using mig welding
PDF
composite construction of structures.pdf
PPTX
Strings in CPP - Strings in C++ are sequences of characters used to store and...
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPT
Project quality management in manufacturing
PPTX
OOP with Java - Java Introduction (Basics)
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PDF
Well-logging-methods_new................
PPT
Mechanical Engineering MATERIALS Selection
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PDF
Digital Logic Computer Design lecture notes
PPTX
CH1 Production IntroductoryConcepts.pptx
PPTX
bas. eng. economics group 4 presentation 1.pptx
PPTX
UNIT 4 Total Quality Management .pptx
PPTX
Lesson 3_Tessellation.pptx finite Mathematics
Lecture Notes Electrical Wiring System Components
additive manufacturing of ss316l using mig welding
composite construction of structures.pdf
Strings in CPP - Strings in C++ are sequences of characters used to store and...
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Project quality management in manufacturing
OOP with Java - Java Introduction (Basics)
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
Well-logging-methods_new................
Mechanical Engineering MATERIALS Selection
Foundation to blockchain - A guide to Blockchain Tech
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Digital Logic Computer Design lecture notes
CH1 Production IntroductoryConcepts.pptx
bas. eng. economics group 4 presentation 1.pptx
UNIT 4 Total Quality Management .pptx
Lesson 3_Tessellation.pptx finite Mathematics

The importance of 3 Core NEC Time Clauses when submitting a programme.docx

  • 1. The importance of 3 Core NEC Time Clauses when submitting a programme  27th January 2022  SiteAdmin  Cost Control Management, NEC, Project Planning https://www.big-dada.co.uk/2022/01/27/3-core-nec-time- clauses/?MC=1&FirstName=Andrew&LastName=Ng&Email=Andrewngadelaide@outlook.com&ut m_source=Fellow+Conference+Exhibitors+List&utm_campaign=d18258ff08- Fellow_Conference_Exhibitors_List_19042022&utm_medium=email&utm_term=0_aa06dea8f4- d18258ff08-443207378&ct=t(Fellow_Conference_Exhibitors_List_19042022) Via our chat function we received an interesting question… Morning , just a quick query under NEC4 when you submit a clause 32 programme do you use the clause 31 or last accepted clause 32 as Baseline. Many planners are using different methods I use the accepted Clause 31 and add CE’s to accepted Clause 32 and then add to Clause 31 is this correct ? Regards Mr J [real name redacted] Unfortunately Mr J (real name anonymised) was in a rush and did not provide their e-mail address for us to post an answer, but we still thought it was a cracking question… So we thought we would do it here! Programme Acceptance It is important to first explain the key differences in Programme Acceptance between NEC3 and NEC4 Contract Types. As covered in our past article, within NEC3 in the absence of a Project Manager’s response, the contract provided that the programme was simply ‘not accepted’, putting all the risk ontothe Contractor in allowing the Project Managerto to withhold 25% of the price of work done to date if the Contractor does not provide a programme in accordance with Cl.31. Within NEC4 the position is improved and the contract includes a provision whereby in the absence of a Project Manager’s response to the submitted programme within two weeks, the Contractor can serve notice of a further week. After this, if there is still no response then the contractor’s programme is ‘deemed accepted’ under the contract. Preparation of Compensation Events Costs Another key difference between NEC3 and NEC4, is that the newer version allows recovery of costs even where the Project Manager proposes an instruction which is not accepted. The past exclusion for the cost of preparing compensation events has been deleted and is now recoverable underall Options. There is now the introduction of new CE clause 60(1)(20) (“where the PM notifies the Contractor that a quotation for a proposed instruction is not accepted”). 3 Core Time Clauses Within NEC Professional Services Contract, there are 3 core Schedule related clauses within the Professional Services Contract which we shall use to answer the original question posed:  Clause 30 Starting, Completion and Key Dates  Clause 31 The programme  Clause 32 Revising the programme To answer Mr J’s question the two key concept to understand is that there is a “Planned Completion Date” and the ‘Completion Date’. Under Clause 31.2 the programme issued for acceptance will show the “Planned Completion Date”, which will be driven by the any event that affects the criticalpath. The other is the “Completion Date“, which can only be changed ‘in accordance with the Contract. This reflecting that the contractoris contractually obliged to achieve ‘Completion’ on or before the ‘Completion Date’, under clause 30.1.
  • 2. So under Clause 14.1 “acceptance of a programme” cannot and will not change that responsibility of meeting the ‘Completion Date’ in Clause 11.2(3), that being ‘Completion Date’ in the contract data. NEC contract documentation does set out when the date can be changed (eg., 44.2, 36.3 and 65.4), however acceptance of the programme, does not by itself change the “Completion Date”.
  • 3. As covered under clause 31.3 the Project Manager has to accept or not accept a programme within two weeks of submission. Any non-acceptance having to be communicated backto the Contractor in sufficient detail to Contactor tocorrect the submission (via a separate response under Clause 13.7). The four reasons reasons for non-acceptance are: 1. Contractor’s plans shown are not practicable 2. It does not show the information which this contract requires 3. It does not represent the Contractors plans realistically 4. It does not comply with the Scope As such the programme should show the starting date, access dates, key dates and completion dates when the Contractor plans to meet each condition stated for the Key Dates. It should also show the Planned dates when the contractor plans to complete work required to allow others to carry out
  • 4. works. It also needs to show the dates when the Contractor needs access to the site if this is later than their planned access dates. Acceptances, plant, materials and other things to be provided by the Client should also be identified. Finally for each operation, a statement of how the Contractor plans to do the work should be given. If not met, the Project Manager can respond under Clause 13.7 on the reason for non-acceptance. If the Project Manager chooses not to accept for any other reason, then by default that would be a compensation event under 60.1(9). In revising the programme under Clause 32.1, to update the accepted programme under Clause 31, Mr J should remember…that the acceptance of a programme does not change the responsibility to ‘Provide the Works’ in clause 11.2(13). However it should be borne in mind that Clause (14.1) states that acceptance of any communication does not transfer liability away from the Contractor to comply with their obligations underthe contract. And so, the “Completion Date” as defined by 11.2 remains. That said, acceptance of the programme is still significant as it recognises that the Client has given affirmation that from their perspective that the programme is realistic, practicable and shows the information that the contract requires. The “Accepted Programme” as laid out under Clause 31, and defined under 11.2, is thereby the reference point for all compensation events and change that occur. If there is no recent “Accepted Programme” then commercial resolution is made the more difficult as reference will have to be made to the last “Accepted Programme”, which will inevitably differ from the latest “Revised Programme” under 32.1. The workflow below can be used to explain a scenario how the under 32.1 the Contractor is responsible for correcting all Work which the Client has found to be defective or which fails to conform to the Contract Documents whetherobserved before or after Substantial Completion.
  • 5. NECProject ManagementProject Portfolio Management (PPM) Share This