Michael A. Schwartz, P.E.




Time Dose vs. “Pump & Dump”
This is what we want to avoid, right!?
So here’s what we’ll learn about:
  Basic System Layout
  Operations
  Major Components of Each System
  •Identify differences for each system
  •Design criteria (engineering standpoint)
  •Examples
  Field Example - Conversion
Background




• Major Components of a Traditional Gravity System
   • Septic Tank         • Drain field (Disposal Area)
   • Distribution Box
Background




• Major Components of a Pump System
  • Septic Tank     • Pump
  • Dose Chamber    • Drainfield (Disposal Area)
Types of Pump Systems
“Pump & Dump”




•   Septic Tank                  • Raised or at Grade
•   Dosing Chamber               • Traditional Trench or Bed
•   Pump                         • Containing 4” PVC Diameter
•   Conventional Disposal Area     Laterals (Non-pressurized)

Types
Time Dose




• Septic Tank                  • Traditional Trench or Bed
• Dosing Tank                  • Containing Small Diameter
• Pump                           Laterals (1”-2”)
• Conventional Disposal Area   • Lateral with Orifices (small holes)
• Raised or at Grade           • Pressurized System
 Types
Typical Trench Cross-Section




                  Types
Float Operation Comparison
    “Pump & Dump”                 Time Dose
  • Float 1 – High Water     • Float 1 – Lag Pump –
    Alarm                      Timer Over-Ride (HWA)
  • Float 2 – Lag Pump On    • Float 2 – Lead Pump -
  • Float 3 – Lead Pump On     Timer Over-Ride (HWA)
  • Float 4 – Pumps Off      • Float 3 – Pumps Off /
  • Float 5 – Redundant        Timer Enable
    Off / Low level Alarm    • Float 4 – Redundant
                               Off / Low level Alarm
Major Components
Septic Tank
• Remains the same size for the 3 systems
   • Traditional Gravity
   • Pump & Dump
   • Time Dose                                 Septic Tank
• Sizing is currently based on hold time
                        Major Components       Dosing Tank
• 24-hours or 72-hours (food service)
• Exception (minimal size –typically 1,000        Pump

  gals)
                                               Disposal Area
• Purpose – Pretreatment (separate - solids,
  FOG, liquid)


           Major Components
Septic Tank
• Example #1
  • 2,400 gallons per day
  • Non-Food Service Establishment
  • Loamy Sand                                   Septic Tank
  • Typically perform topographic and
                                                 Dosing Tank
    boundary survey, soils evaluation and flow
    determination to determine constraints
                                                    Pump
  • Septic Tank Size = 24-hour flow
  • Therefore minimum tank size = 2,400          Disposal Area
    gallons



          Major Components
Major Components
“Pump & Dump”:
Dose Tank & Pump
“Pump & Dump”
• Sizing
   • Dosing Chamber
      • The liquid capacity of the dosing tank must
        be sufficient to dose the soil absorption
                                                       Septic Tank
        field or bed no more than three (3) to four
        (4) times a day at design flow.
                                                      Dosing Tank
   • Pump
      • Pumps should be sized to empty the dosing        Pump
        tank in no more than 20 minutes.
      • Automatic alternating pumps shall be          Disposal Area
        provided in all systems where design flow
        exceeds 2,000 gallons/day and in locations
        where continuous reliability is essential.

            Major Components
“Pump & Dump”
• Example #2
  •   2,400 gallons per day
  •   Non-Food Service Establishment
  •   Loamy Sand                                    Septic Tank
  •   Since Flow > 2,000 gallons per day, design
                                                   Dosing Tank
      system with 2 pumps
                                                      Pump

                                                   Disposal Area




            Major Components
“Pump & Dump”
• Example #3
  •   2 Pumps to 1 Disposal Area
  •   Dose Chamber = 2,400 / 3 = 800 gal
  •   Dose Chamber = 2,400 / 4 = 600 gal         Septic Tank
  •   Dosing Tank Size = 1,000 gallon – 1,200
                                                Dosing Tank
      gallon
                                                   Pump

                                                Disposal Area




            Major Components
“Pump & Dump”
• Example #4
  •   2 Pumps to ½ of the disposal area each
  •   Dose Chamber = 2,400 / 6 = 400 gal
  •   Dose Chamber = 2,400 / 8 = 300 gal        Septic Tank
  •   Dosing Tank Size about 500-750 gallon
                                               Dosing Tank

                                                  Pump

                                               Disposal Area




            Major Components
“Pump & Dump”
• Example #5
  • Pumps should be sized to empty the
    dosing tank in no more than 20 minutes.
  • 300 gallons / 20 minutes = 15 gpm                       Septic Tank
    (minimum)
  • Pumps need 2 items to specify                          Dosing Tank
     • GPM
                                                              Pump
     • TDH (Total Dynamic Head)
         • TDH = Static Lift + Friction Lost               Disposal Area
         • Friction Loss also known as “head lost” is
           divided into two main categories, "major
           losses" associated with energy loss per
           length of pipe, and "minor losses"
           associated with bends, fittings, valves, etc.
          Major Components
Major Components
 “Pump & Dump”:
     Disposal Area
“Pump & Dump”
• Disposal Area Sizing
   • Absorption systems shall be sized on the
     basis of the maximum daily sewage flows,
     according to the following table:
                                                 Septic Tank

                                                Dosing Tank

                                                   Pump

                                                Disposal Area




           Major Components
“Pump & Dump”
• Example #6
  • 2,400 gallons/day
  • Non-Food Service Establishment
  • Loamy Sand                                       Septic Tank
  • Assuming a trench layout:
                                                    Dosing Tank
  • Loamy Sand = 0.75 gal per day / square
    foot                                               Pump
  • 2,400 g.p.d. / 0.75 g.p.d./sq.ft. = 3,200 sq.
    ft.                                             Disposal Area




          Major Components
“Pump & Dump”
• Example #7 – Network Layout
   • 3,200 sq. ft. bottom area required
   • Assume trench is 3’ wide: 3,200 / 3’ =
     1,070 LF of trench required                  Septic Tank
   • Probably use 12 trenches that are 90 feet
     long x 3’ wide with 4’ undisturbed earth    Dosing Tank
     between trenches.
                                                    Pump
   • With 2 pumps, each pump would
     discharge to 6 of the 12 trenches.          Disposal Area




           Major Components
Time Dose
Time Dose




•   Septic Tank                  • Traditional Trench or Bed
•   Dosing Tank                  • Containing Small Diameter
•   Pump                           Laterals (1”-2”)
•   Conventional Disposal Area   • Lateral with Orifices (small holes)
•   Raised or at Grade           • Pressurized System

             Major Components
Time Dose
• Why Time Dose?
  • Pressure distribution is a recent modification to the
    conventional dosed sewage system. Uniform distribution
    over the bottom area of the drain field is achieved and
    provides certain advantages over conventional systems as
    follows:
     1. Formation of the clogging mat is substantially delayed.
     2. System provides for unsaturated flow into underlying soil.
     3. System design is not limited to rectangular configuration.




          Major Components
Time Dose
• Why Time Dose?
                                               Same   Different
  Septic Tank                                   x
  Conventional Disposal Area                    x
  Raised or at Grade                            x
  Traditional Trench or Bed                     x
  Containing Small Diameter Laterals (1”-2”)             x
  Lateral with Orifices (small holes)                    x
  Pump                                                   x
  Dosing Tank                                            x




             Major Components
Time Dose
• Order of Design
   • Septic Tank – Same (based on retention time)
   • Disposal Area Network
      • Orifices (small holes) – Spacing & Size
      • Laterals Diameter
   • Pump
   • Dosing Tank




           Major Components
Major Components
       Time Dose:
     Disposal Area
Time Dose
1. Configure Disposal Area Network
2. Determine Length of Lateral
  • Example: 2,400 gallons per day, Non-Food
    Service Establishment, Loamy Sand                   Septic Tank
  • Assuming a trench layout:
     • Loamy Sand = 0.75 gal per day / sq. foot        Disposal Area

     • 2,400 g.p.d. / 0.75 g.p.d./sq.ft. = 3,200 sq.      Pump
       ft.
  • Assume trench is 3’ wide:                          Dosing Tank
     • 3,200 / 3’ = 1070 LF of trench required
     • Use 12 trenches that are 90 feet long x 3’
       wide with 4’ undisturbed earth between
       trenches
          Major Components
Time Dose
3. Determine “orifice” spacing and size
  • Michigan Criteria for Subsurface Sewage Disposal
    reference “Pressure Distribution Network Design
    Manual,” Technical Guide for Pressure Mound Systems
    (June 2003 MDEQ)
      • Pressure distribution system design should generally comply with        Septic Tank
        currently accepted design practice including the following features:
      • Design shall provide uniform doses with no more than 0.5 gallons
        per orifice per dose.
                                                                               Disposal Area
      • Distribution cell area per orifice shall not exceed 12 sq.ft.
      • To reduce orifice plugging, high head pumps are recommended.              Pump
      • Orifice shields should be provided.
      • Provisions for flushing must be incorporated at the ends of all
        laterals.                                                              Dosing Tank
      • Geotextile fabric which prevents the downward migration of fine
        materials but allows for free passage of air and water should be
        placed over the stone in the distribution cell prior to placement of
        final cover.




              Major Components
Time Dose
3. Determine “orifice” spacing and size
  • Distribution cell area per orifice shall not
    exceed 12 sq.ft.
     • Spacing is typically 3-5 feet apart (some
                                                       Septic Tank
       health department code books dictate
       spacing.                                       Disposal Area
     • If the trench is 3’ wide and each orifice is
       to “distribute” effluent to 12 sq.ft. than        Pump
       spacing is 4’ apart
                                                      Dosing Tank




           Major Components
Time Dose
3. Determine “orifice” spacing and size
  • Orifice sizes can range from 1/8” diameter
    to 5/8” diameter.
  • Typically 1/8”, 3/16” or 1/4” diameter         Septic Tank
  • 3/16” diameter is most common sized
    used                                          Disposal Area

  • Larger holes will be problematic on finding
                                                     Pump
    a pump to produce adequate design flow
  • Some health departments provides              Dosing Tank
    recommended size
  • Ultimately up to the design engineer


          Major Components
Time Dose
4. Determine lateral pipe diameter



                                                                          Septic Tank

                                                                         Disposal Area

                                                                            Pump

                                                                         Dosing Tank



    Want the 1st orifice to distribute approximately equal to the last
                 orifice (this table is for 3/16” orifices)


               Major Components
Time Dose
5. Determine Number of Orifices/Lateral
  •   # of orifices = Length of Lateral / Spacing
      of orifice
  •   Example: 90 ft lateral / 4 ft spacing = 23     Septic Tank
      orifices
                                                    Disposal Area

                                                       Pump

                                                    Dosing Tank




           Major Components
Major Components
       Time Dose:
            Pump
Time Dose
6. Determine Lateral Discharge Rate



                                                                   Septic Tank

                                                                  Disposal Area

                                                                     Pump

                                                                  Dosing Tank



    If 3/16” orifice with 4 ft pressure = 0.83 gal/orifice
    23 orifice / lateral x 0.83 gal/orifice = 19.09 gal/lateral


              Major Components
Time Dose
7. Determine Network Discharge Rate (zone)
   • Determine how many laterals are in the
     network (per pump or zone) and multiple
     by GPM per lateral
                                                     Septic Tank
   • 12 trenches (laterals) with each pump
     utilizing 6 laterals each (network has 2       Disposal Area
     zones)
   • 6 laterals x 19.09 gal / lateral = 114.5 gpm      Pump

   • This is the minimum pump flow required         Dosing Tank




           Major Components
Time Dose
• Pump Comparison Sizing
   • Pump & Dump”
      • 20 minutes to empty septic tank
   • Time Dose                                           Septic Tank
      • # of orifices (more orifices = more gpm)
      • Size of Orifices (larger orifices = more gpm)   Disposal Area

      • Spacing of orifices (closer space = more
                                                           Pump
        gpm)
   • Example: 15 gpm vs. 114.5 (6 – 90’                 Dosing Tank
     trenches per pump)
      • Each on is dosing 1,600 sq ft of area
      • “Pump & Dump” = 20 minutes
      • Time Dose = very short timeframe
           Major Components
Time Dose
8. Calculate Manifold Size
9. Determine the Total Dynamic Head
   • TDH = Static Lift + Friction Lost +
     Perforation Head                           Septic Tank
   • Perforation head = 1.3(Q/(11.79*d^2))^2
                                               Disposal Area
   • Perforation head = 1.3(squirt height)
10. Select Pump                                   Pump
   • Pumps need 2 items to specify (GPM &
                                               Dosing Tank
     TDH)
   • Repeat if necessary



           Major Components
Major Components: Time Dose




                              Pump Curve
Major Components
       Time Dose:
    Dose Chamber
Time Dose
11. Determine Dose Volume
   • Technical Guide for Pressure Mound
     Systems (June 2003 MDEQ)
      • Design shall provide uniform doses with no
                                                          Septic Tank
        more than 0.5 gallons per orifice per dose.
      • Example: 6 laterals with 23 orifices per         Disposal Area
        lateral = 138 orifices
      • 138 orifices x 0.5 gal per orifice dose rate =      Pump
        69 gals per dose
                                                         Dosing Tank




           Major Components
Time Dose
12. Calculate Run Time of Pump
   • Run Time = (Dose Volume + “Empty” Pipe
     Volume) / Pump Rate
   • Example:                                          Septic Tank
      •   Dose Volume = 69 gallons
      •   Volume to “fill” pipe = 17 gallons          Disposal Area
      •   Pump Rate = 114.5 gpm
                                                         Pump
      •   Run Time = (69 gal +17 gal) / 114.5 gpm =
          0.75 minutes = 45 seconds                   Dosing Tank




             Major Components
Time Dose
13. Calculate Number of Doses/Day
   •   Gallons per day = 2,400
   •   Gallons per dose = 69
   •   Doses per day = 2400 / 69 = 34 doses    Septic Tank
   •   Therefore each pump will operate 17
                                              Disposal Area
       times per day
                                                 Pump

                                              Dosing Tank




            Major Components
Time Dose
  • Calculation Check
     • Dose = 0.5 gallons / dose / orifice
     • # of doses per day = 17
     • Gallons per day / orifice = 8.5 gallons     Septic Tank
     • Soil Load Rate 0.75 gal/sq. ft.
                                                  Disposal Area
     • Each orifice is dosing 12 sq. ft.
     • Dose < 0.75 gal/sq. ft. x 12 sq. ft. = 9      Pump
       gallons
                                                  Dosing Tank
     • Numbers check




          Major Components
Time Dose
14. Calculate Programmable Timer Settings
   • Previous step determined number times a
     pump turns on (34 times)
   • If want to equal dose over 22 hours         Septic Tank
     (account for peak days)
   • Duration is up to the design engineer      Disposal Area

   • 22 hours x 60 min/hour = 1320 minutes
                                                   Pump
   • 1320 minutes / 34 times = 38.8 minutes
   • Therefore a pump will run 45 seconds and   Dosing Tank
     no pump will run for 38 minutes
   • (76 minutes off time per pump)


           Major Components
Time Dose
15. Size the Dose Chamber
   • Up to the judgment of the engineer
   • Based on off time and timing of incoming
     flow                                        Septic Tank

                                                Disposal Area

                                                   Pump

                                                Dosing Tank




           Major Components
System Conversion
• Conversion of a “Pump & Dump” to a Time Dose System
• Flushing Elementary, Flushing, MI


                       System Conversion
Existing Drain Field




                 System Conversion
Drawing




          System Conversion
Existing Septic Tank /Pump
Chamber




                System Conversion
Existing Septic Tank /Pump
Chamber




                System Conversion
Existing Septic Tank /Pump
Chamber




                System Conversion
Existing Septic Tank /Pump
Chamber




                System Conversion
Proposed Drain Field




                 System Conversion
System Conversion
System Conversion
System Conversion
Construction




               System Conversion
Construction




               System Conversion
System Conversion
System Conversion
Construction




               System Conversion
Construction




               System Conversion
System Conversion
System Conversion
Construction




               System Conversion
Construction




               System Conversion
Construction




               System Conversion
Construction




               System Conversion
Final Site Photos




                    System Conversion
Final Site Photos




                    System Conversion
Thank you.
             Do You Have Questions?

                    E-mail Mike:
                    Michael A. Schwartz, P.E.
                    mschwartz@preinnewhof.com

More Related Content

PPT
Pressure mound system: Septic Installers - Mike Schwartz, P.E.
PPTX
Septic Systems for Homeowners
PPT
Homeowners guide to septic systems
PDF
Water Pumps - Public Health Engineering
PDF
Wastewater pump station_design_problems_and_solutions
PPT
Pipex Pumping Stations, Chambers & Catchpits
PPTX
Pumping Stations
PPTX
Mine dewatering techniques
Pressure mound system: Septic Installers - Mike Schwartz, P.E.
Septic Systems for Homeowners
Homeowners guide to septic systems
Water Pumps - Public Health Engineering
Wastewater pump station_design_problems_and_solutions
Pipex Pumping Stations, Chambers & Catchpits
Pumping Stations
Mine dewatering techniques

What's hot (20)

PDF
L 9 pumping stations
PPT
Oil Sands Water Management Initiative Notes
PPTX
Multi slot divisor
PPTX
Design and Construction of Sewers And Sewer Appurtenances
PPTX
ESTIMATION OF SOIL LOSS BY USING MULTISLOT DEVISOR
PPTX
Sewerage System
PPTX
Micro irrigation systems- at field level
PPTX
PROCEDURE FOR MAINTENANCE OF SEWAGE SYSTEM
PPTX
Low Cost Sanitation Systems
PDF
Mining Operations Optimize Dewatering Processes
PPTX
PDF
Rational Artificial Lift Selection by Mike Berry
PPT
Sistem bekalan air di dalam bangunan
PPTX
UNCONVENTIONAL GAS- DRILLING FOOTPRINT REDUCTION CHALLENGE
PDF
LARGE SCALE INSTALLATION OF SUBSURFACE DRAINAGE SYSTEM
PPTX
Collection of sewage & estimation of its discharge
DOCX
Sewer Appurtenances
PPT
Drainage
PPTX
Hydraulicdesignofsewer
PPTX
Design and construction of sewer
L 9 pumping stations
Oil Sands Water Management Initiative Notes
Multi slot divisor
Design and Construction of Sewers And Sewer Appurtenances
ESTIMATION OF SOIL LOSS BY USING MULTISLOT DEVISOR
Sewerage System
Micro irrigation systems- at field level
PROCEDURE FOR MAINTENANCE OF SEWAGE SYSTEM
Low Cost Sanitation Systems
Mining Operations Optimize Dewatering Processes
Rational Artificial Lift Selection by Mike Berry
Sistem bekalan air di dalam bangunan
UNCONVENTIONAL GAS- DRILLING FOOTPRINT REDUCTION CHALLENGE
LARGE SCALE INSTALLATION OF SUBSURFACE DRAINAGE SYSTEM
Collection of sewage & estimation of its discharge
Sewer Appurtenances
Drainage
Hydraulicdesignofsewer
Design and construction of sewer
Ad

Viewers also liked (15)

PDF
National building code for residential apartments in india
DOCX
Septic tank,soak pit and gi sheet design
PPT
National building code
PDF
NSCP 2010 , Volume 1
PDF
Simple Piping design
PPTX
Septic tank process&design
PPTX
Building bye laws
PPS
Piping basics knowledge
PDF
national builiding codes
PPTX
Building bye laws CIVIL ENGINEERING DRAWING
DOC
Question bank
PDF
Bhutan septic-system-manual
PDF
PDF
Piping engineering guide
PDF
Piping components, materials, codes and standards part 1- pipe
National building code for residential apartments in india
Septic tank,soak pit and gi sheet design
National building code
NSCP 2010 , Volume 1
Simple Piping design
Septic tank process&design
Building bye laws
Piping basics knowledge
national builiding codes
Building bye laws CIVIL ENGINEERING DRAWING
Question bank
Bhutan septic-system-manual
Piping engineering guide
Piping components, materials, codes and standards part 1- pipe
Ad

Similar to Time dose vs. Pump & Dump - Mike Schwartz (20)

PPTX
Septic Tank
PDF
septic_tank_concept_and_design.pdf
PPT
Presentation for safegard septic tank
PPTX
2.Design of On-site Sanitation systems.pptx
PPTX
Septictankprocessdesign
PPTX
Septic tank
PDF
Septictank 150312104320-conversion-gate01
PDF
PDF
Bulletin 829_1
PDF
septic tank design manual or how to design septic tank.pdf
PDF
TOPIC: EXCRETA DISPOSAL-NEED OF THE HOUR
PPTX
371754892-Group-1-Chapter-4-the-Sewage-Disposal.pptx
PPTX
Evs ppt avinash
PDF
A Homeowners Guide To On-Site Sewage Management Systems
PPTX
1. Onsite sanitation system and disposal of sludge slide series (1) septic tank
PDF
Septic Pumping North Hills
PPTX
UASB reactors
PPTX
Sewage disposal
PPTX
Disposal of excreta
PDF
Hire-Unit-Data-Sheet-1
Septic Tank
septic_tank_concept_and_design.pdf
Presentation for safegard septic tank
2.Design of On-site Sanitation systems.pptx
Septictankprocessdesign
Septic tank
Septictank 150312104320-conversion-gate01
Bulletin 829_1
septic tank design manual or how to design septic tank.pdf
TOPIC: EXCRETA DISPOSAL-NEED OF THE HOUR
371754892-Group-1-Chapter-4-the-Sewage-Disposal.pptx
Evs ppt avinash
A Homeowners Guide To On-Site Sewage Management Systems
1. Onsite sanitation system and disposal of sludge slide series (1) septic tank
Septic Pumping North Hills
UASB reactors
Sewage disposal
Disposal of excreta
Hire-Unit-Data-Sheet-1

Time dose vs. Pump & Dump - Mike Schwartz

  • 1. Michael A. Schwartz, P.E. Time Dose vs. “Pump & Dump”
  • 2. This is what we want to avoid, right!?
  • 3. So here’s what we’ll learn about: Basic System Layout Operations Major Components of Each System •Identify differences for each system •Design criteria (engineering standpoint) •Examples Field Example - Conversion
  • 4. Background • Major Components of a Traditional Gravity System • Septic Tank • Drain field (Disposal Area) • Distribution Box
  • 5. Background • Major Components of a Pump System • Septic Tank • Pump • Dose Chamber • Drainfield (Disposal Area)
  • 6. Types of Pump Systems
  • 7. “Pump & Dump” • Septic Tank • Raised or at Grade • Dosing Chamber • Traditional Trench or Bed • Pump • Containing 4” PVC Diameter • Conventional Disposal Area Laterals (Non-pressurized) Types
  • 8. Time Dose • Septic Tank • Traditional Trench or Bed • Dosing Tank • Containing Small Diameter • Pump Laterals (1”-2”) • Conventional Disposal Area • Lateral with Orifices (small holes) • Raised or at Grade • Pressurized System Types
  • 10. Float Operation Comparison “Pump & Dump” Time Dose • Float 1 – High Water • Float 1 – Lag Pump – Alarm Timer Over-Ride (HWA) • Float 2 – Lag Pump On • Float 2 – Lead Pump - • Float 3 – Lead Pump On Timer Over-Ride (HWA) • Float 4 – Pumps Off • Float 3 – Pumps Off / • Float 5 – Redundant Timer Enable Off / Low level Alarm • Float 4 – Redundant Off / Low level Alarm
  • 12. Septic Tank • Remains the same size for the 3 systems • Traditional Gravity • Pump & Dump • Time Dose Septic Tank • Sizing is currently based on hold time Major Components Dosing Tank • 24-hours or 72-hours (food service) • Exception (minimal size –typically 1,000 Pump gals) Disposal Area • Purpose – Pretreatment (separate - solids, FOG, liquid) Major Components
  • 13. Septic Tank • Example #1 • 2,400 gallons per day • Non-Food Service Establishment • Loamy Sand Septic Tank • Typically perform topographic and Dosing Tank boundary survey, soils evaluation and flow determination to determine constraints Pump • Septic Tank Size = 24-hour flow • Therefore minimum tank size = 2,400 Disposal Area gallons Major Components
  • 14. Major Components “Pump & Dump”: Dose Tank & Pump
  • 15. “Pump & Dump” • Sizing • Dosing Chamber • The liquid capacity of the dosing tank must be sufficient to dose the soil absorption Septic Tank field or bed no more than three (3) to four (4) times a day at design flow. Dosing Tank • Pump • Pumps should be sized to empty the dosing Pump tank in no more than 20 minutes. • Automatic alternating pumps shall be Disposal Area provided in all systems where design flow exceeds 2,000 gallons/day and in locations where continuous reliability is essential. Major Components
  • 16. “Pump & Dump” • Example #2 • 2,400 gallons per day • Non-Food Service Establishment • Loamy Sand Septic Tank • Since Flow > 2,000 gallons per day, design Dosing Tank system with 2 pumps Pump Disposal Area Major Components
  • 17. “Pump & Dump” • Example #3 • 2 Pumps to 1 Disposal Area • Dose Chamber = 2,400 / 3 = 800 gal • Dose Chamber = 2,400 / 4 = 600 gal Septic Tank • Dosing Tank Size = 1,000 gallon – 1,200 Dosing Tank gallon Pump Disposal Area Major Components
  • 18. “Pump & Dump” • Example #4 • 2 Pumps to ½ of the disposal area each • Dose Chamber = 2,400 / 6 = 400 gal • Dose Chamber = 2,400 / 8 = 300 gal Septic Tank • Dosing Tank Size about 500-750 gallon Dosing Tank Pump Disposal Area Major Components
  • 19. “Pump & Dump” • Example #5 • Pumps should be sized to empty the dosing tank in no more than 20 minutes. • 300 gallons / 20 minutes = 15 gpm Septic Tank (minimum) • Pumps need 2 items to specify Dosing Tank • GPM Pump • TDH (Total Dynamic Head) • TDH = Static Lift + Friction Lost Disposal Area • Friction Loss also known as “head lost” is divided into two main categories, "major losses" associated with energy loss per length of pipe, and "minor losses" associated with bends, fittings, valves, etc. Major Components
  • 20. Major Components “Pump & Dump”: Disposal Area
  • 21. “Pump & Dump” • Disposal Area Sizing • Absorption systems shall be sized on the basis of the maximum daily sewage flows, according to the following table: Septic Tank Dosing Tank Pump Disposal Area Major Components
  • 22. “Pump & Dump” • Example #6 • 2,400 gallons/day • Non-Food Service Establishment • Loamy Sand Septic Tank • Assuming a trench layout: Dosing Tank • Loamy Sand = 0.75 gal per day / square foot Pump • 2,400 g.p.d. / 0.75 g.p.d./sq.ft. = 3,200 sq. ft. Disposal Area Major Components
  • 23. “Pump & Dump” • Example #7 – Network Layout • 3,200 sq. ft. bottom area required • Assume trench is 3’ wide: 3,200 / 3’ = 1,070 LF of trench required Septic Tank • Probably use 12 trenches that are 90 feet long x 3’ wide with 4’ undisturbed earth Dosing Tank between trenches. Pump • With 2 pumps, each pump would discharge to 6 of the 12 trenches. Disposal Area Major Components
  • 25. Time Dose • Septic Tank • Traditional Trench or Bed • Dosing Tank • Containing Small Diameter • Pump Laterals (1”-2”) • Conventional Disposal Area • Lateral with Orifices (small holes) • Raised or at Grade • Pressurized System Major Components
  • 26. Time Dose • Why Time Dose? • Pressure distribution is a recent modification to the conventional dosed sewage system. Uniform distribution over the bottom area of the drain field is achieved and provides certain advantages over conventional systems as follows: 1. Formation of the clogging mat is substantially delayed. 2. System provides for unsaturated flow into underlying soil. 3. System design is not limited to rectangular configuration. Major Components
  • 27. Time Dose • Why Time Dose? Same Different Septic Tank x Conventional Disposal Area x Raised or at Grade x Traditional Trench or Bed x Containing Small Diameter Laterals (1”-2”) x Lateral with Orifices (small holes) x Pump x Dosing Tank x Major Components
  • 28. Time Dose • Order of Design • Septic Tank – Same (based on retention time) • Disposal Area Network • Orifices (small holes) – Spacing & Size • Laterals Diameter • Pump • Dosing Tank Major Components
  • 29. Major Components Time Dose: Disposal Area
  • 30. Time Dose 1. Configure Disposal Area Network 2. Determine Length of Lateral • Example: 2,400 gallons per day, Non-Food Service Establishment, Loamy Sand Septic Tank • Assuming a trench layout: • Loamy Sand = 0.75 gal per day / sq. foot Disposal Area • 2,400 g.p.d. / 0.75 g.p.d./sq.ft. = 3,200 sq. Pump ft. • Assume trench is 3’ wide: Dosing Tank • 3,200 / 3’ = 1070 LF of trench required • Use 12 trenches that are 90 feet long x 3’ wide with 4’ undisturbed earth between trenches Major Components
  • 31. Time Dose 3. Determine “orifice” spacing and size • Michigan Criteria for Subsurface Sewage Disposal reference “Pressure Distribution Network Design Manual,” Technical Guide for Pressure Mound Systems (June 2003 MDEQ) • Pressure distribution system design should generally comply with Septic Tank currently accepted design practice including the following features: • Design shall provide uniform doses with no more than 0.5 gallons per orifice per dose. Disposal Area • Distribution cell area per orifice shall not exceed 12 sq.ft. • To reduce orifice plugging, high head pumps are recommended. Pump • Orifice shields should be provided. • Provisions for flushing must be incorporated at the ends of all laterals. Dosing Tank • Geotextile fabric which prevents the downward migration of fine materials but allows for free passage of air and water should be placed over the stone in the distribution cell prior to placement of final cover. Major Components
  • 32. Time Dose 3. Determine “orifice” spacing and size • Distribution cell area per orifice shall not exceed 12 sq.ft. • Spacing is typically 3-5 feet apart (some Septic Tank health department code books dictate spacing. Disposal Area • If the trench is 3’ wide and each orifice is to “distribute” effluent to 12 sq.ft. than Pump spacing is 4’ apart Dosing Tank Major Components
  • 33. Time Dose 3. Determine “orifice” spacing and size • Orifice sizes can range from 1/8” diameter to 5/8” diameter. • Typically 1/8”, 3/16” or 1/4” diameter Septic Tank • 3/16” diameter is most common sized used Disposal Area • Larger holes will be problematic on finding Pump a pump to produce adequate design flow • Some health departments provides Dosing Tank recommended size • Ultimately up to the design engineer Major Components
  • 34. Time Dose 4. Determine lateral pipe diameter Septic Tank Disposal Area Pump Dosing Tank Want the 1st orifice to distribute approximately equal to the last orifice (this table is for 3/16” orifices) Major Components
  • 35. Time Dose 5. Determine Number of Orifices/Lateral • # of orifices = Length of Lateral / Spacing of orifice • Example: 90 ft lateral / 4 ft spacing = 23 Septic Tank orifices Disposal Area Pump Dosing Tank Major Components
  • 36. Major Components Time Dose: Pump
  • 37. Time Dose 6. Determine Lateral Discharge Rate Septic Tank Disposal Area Pump Dosing Tank If 3/16” orifice with 4 ft pressure = 0.83 gal/orifice 23 orifice / lateral x 0.83 gal/orifice = 19.09 gal/lateral Major Components
  • 38. Time Dose 7. Determine Network Discharge Rate (zone) • Determine how many laterals are in the network (per pump or zone) and multiple by GPM per lateral Septic Tank • 12 trenches (laterals) with each pump utilizing 6 laterals each (network has 2 Disposal Area zones) • 6 laterals x 19.09 gal / lateral = 114.5 gpm Pump • This is the minimum pump flow required Dosing Tank Major Components
  • 39. Time Dose • Pump Comparison Sizing • Pump & Dump” • 20 minutes to empty septic tank • Time Dose Septic Tank • # of orifices (more orifices = more gpm) • Size of Orifices (larger orifices = more gpm) Disposal Area • Spacing of orifices (closer space = more Pump gpm) • Example: 15 gpm vs. 114.5 (6 – 90’ Dosing Tank trenches per pump) • Each on is dosing 1,600 sq ft of area • “Pump & Dump” = 20 minutes • Time Dose = very short timeframe Major Components
  • 40. Time Dose 8. Calculate Manifold Size 9. Determine the Total Dynamic Head • TDH = Static Lift + Friction Lost + Perforation Head Septic Tank • Perforation head = 1.3(Q/(11.79*d^2))^2 Disposal Area • Perforation head = 1.3(squirt height) 10. Select Pump Pump • Pumps need 2 items to specify (GPM & Dosing Tank TDH) • Repeat if necessary Major Components
  • 41. Major Components: Time Dose Pump Curve
  • 42. Major Components Time Dose: Dose Chamber
  • 43. Time Dose 11. Determine Dose Volume • Technical Guide for Pressure Mound Systems (June 2003 MDEQ) • Design shall provide uniform doses with no Septic Tank more than 0.5 gallons per orifice per dose. • Example: 6 laterals with 23 orifices per Disposal Area lateral = 138 orifices • 138 orifices x 0.5 gal per orifice dose rate = Pump 69 gals per dose Dosing Tank Major Components
  • 44. Time Dose 12. Calculate Run Time of Pump • Run Time = (Dose Volume + “Empty” Pipe Volume) / Pump Rate • Example: Septic Tank • Dose Volume = 69 gallons • Volume to “fill” pipe = 17 gallons Disposal Area • Pump Rate = 114.5 gpm Pump • Run Time = (69 gal +17 gal) / 114.5 gpm = 0.75 minutes = 45 seconds Dosing Tank Major Components
  • 45. Time Dose 13. Calculate Number of Doses/Day • Gallons per day = 2,400 • Gallons per dose = 69 • Doses per day = 2400 / 69 = 34 doses Septic Tank • Therefore each pump will operate 17 Disposal Area times per day Pump Dosing Tank Major Components
  • 46. Time Dose • Calculation Check • Dose = 0.5 gallons / dose / orifice • # of doses per day = 17 • Gallons per day / orifice = 8.5 gallons Septic Tank • Soil Load Rate 0.75 gal/sq. ft. Disposal Area • Each orifice is dosing 12 sq. ft. • Dose < 0.75 gal/sq. ft. x 12 sq. ft. = 9 Pump gallons Dosing Tank • Numbers check Major Components
  • 47. Time Dose 14. Calculate Programmable Timer Settings • Previous step determined number times a pump turns on (34 times) • If want to equal dose over 22 hours Septic Tank (account for peak days) • Duration is up to the design engineer Disposal Area • 22 hours x 60 min/hour = 1320 minutes Pump • 1320 minutes / 34 times = 38.8 minutes • Therefore a pump will run 45 seconds and Dosing Tank no pump will run for 38 minutes • (76 minutes off time per pump) Major Components
  • 48. Time Dose 15. Size the Dose Chamber • Up to the judgment of the engineer • Based on off time and timing of incoming flow Septic Tank Disposal Area Pump Dosing Tank Major Components
  • 50. • Conversion of a “Pump & Dump” to a Time Dose System • Flushing Elementary, Flushing, MI System Conversion
  • 51. Existing Drain Field System Conversion
  • 52. Drawing System Conversion
  • 53. Existing Septic Tank /Pump Chamber System Conversion
  • 54. Existing Septic Tank /Pump Chamber System Conversion
  • 55. Existing Septic Tank /Pump Chamber System Conversion
  • 56. Existing Septic Tank /Pump Chamber System Conversion
  • 57. Proposed Drain Field System Conversion
  • 61. Construction System Conversion
  • 62. Construction System Conversion
  • 65. Construction System Conversion
  • 66. Construction System Conversion
  • 69. Construction System Conversion
  • 70. Construction System Conversion
  • 71. Construction System Conversion
  • 72. Construction System Conversion
  • 73. Final Site Photos System Conversion
  • 74. Final Site Photos System Conversion
  • 75. Thank you. Do You Have Questions? E-mail Mike: Michael A. Schwartz, P.E. mschwartz@preinnewhof.com