SlideShare a Scribd company logo
CIVIL ENGINEERING
COURSE
CONSTRUCTION TECHNOLOGY I
ChAPTER 2: FOUNDATION
PRESENTER:
ENG ABDIQANI FAARAH ABDILLE
2.4 DEEP FOUNDATIONS
2.4.1 What is the deep foundation?
Deep foundations are founded too deeply
below the finished ground surface for
their base bearing capacity to be affected
by surface conditions, this is usually at
depths >3 m below finished ground level.
Deep foundation can be used to transfer
the loading to a deeper, more competent
strata at depth if unsuitable soils are
present near the surface.
2.4.2 TYPES OF DEEP FOUNDATION
1. Piles
2. Piers
3. Caissons
4. Compensated foundations
PILE FOUNDATION
Piles are relatively long, slender members that
transmit foundation loads through soil strata of
low bearing capacity to deeper soil or rock strata
having a high bearing capacity. They are used
when for economic, constructional or soil
condition considerations it is desirable to transmit
loads to strata beyond the practical reach of
shallow foundations. In addition to supporting
structures, piles are also used to anchor
structures against uplift forces and to assist
structures in resisting lateral and overturning
forces.
PIERS
Piers are foundations for carrying a heavy
structural load which is constructed
insitu in a deep excavation.
CAISSONS
Caissons are a form of deep foundation
which are constructed above ground
level, then sunk to the required level by
excavating or dredging material from
within the caisson
COMPENSATED FOUNDATIONS
Compensated foundations are
deep foundations in which the
relief of stress due to excavation
is approximately balanced by
the applied stress due to the
foundation. The net stress
applied is therefore very small. A
compensated foundation
normally comprises a deep
PILES
Types of pile
Type of construction
Factors influencing choice
Pile groups
TYPES OF PILE
Piled foundations can be classified
according to:
a) The type of pile: (Different
structures to be supported, and
different ground conditions, require
different types of resistance) and
b) The type of construction:( different
materials, structures and process
can be used).
types of pile
1. End bearing pile
End bearing piles are those which
terminate in hard, relatively
impenetrable material such as
rock or very dense sand and
gravel.
They derive most of their carrying
capacity from the resistance of
the stratum at the toe of the pile.
2. Friction piles
Friction piles obtain a greater part of
their carrying capacity by skin
friction or adhesion. This tends to
occur when pile do not reach an
impenetrable stratum but are driven
for some distance into a penetrable
soil, their carrying capacity is derived
partly from end bearing and partly
from skin friction between the
embedded surface of the soil and
the surrounding soil.
3. Settlement reducing piles
Settlement reducing piles are usually
incorporated beneath the central part
of raft foundation in order to reduce
differential settlement to an
acceptable level. Such piles act to
reinforce the soil beneath the raft and
help to prevent dishing of rafr in the
centre.
4. Tension piles
Structures such as tall chimneys, transmission
towers and jetties can be subject to large
overturning moments and so piles are often
used to resist the resulting uplift forces at
the foundations. In such cases the resulting
forces are transmitted to the soil along the
embedded length of the pile. The resisting
force can be increased in the case of bored
piles by under-reaming. In the design of
tension piles the effect of radial contraction
of the pile must be taken into account as this
can cause about a 10% - 20% reduction in
shaft resistance.
5. Laterally loaded piles
Almost all piled foundations are subjected to at least
some degree of horizontal loading. The
magnitude of the loads in relation to the
applied vertical axial loading will generally
be small and no additional design
calculations will normally be necessary.
However, in the case of wharves and jetties
carrying the impact forces of berthing ships,
piled foundations to bridge piers, trestles to
overhead cranes, tall chimneys and
retaining walls, the horizontal component is
relatively large and may prove critical in
design.
Traditionally piles have been installed at an angle
to the vertical in such cases, providing
sufficient horizontal resistance by virtue of the
component of axial capacity of the pile which
acts horizontally. However the capacity of a
vertical pile to resist loads applied normally to
the axis, although significantly smaller than
the axial capacity of that pile, may be
sufficient to avoid the need for such 'raking' or
'battered' piles which are more expensive to
install. When designing piles to take lateral
forces it is therefore important to take this
into account.
2.5 SETTING OUT OF FOUNDATION TRENCHES
Setting out of foundation trenches done by the following
steps:
a) First of all. The corners of the building are marked and
then the length of the sides are checked by diagonal
measurements.
b) The axial lines (center lines) of the trenches are marked
with the help of profiles, sighting rails, strings and pegs.
c) The off-sets are measured from axial lines and the
frontage lines are placed in their correct position relative
to local requirements.
d) The position of cross walls should be measured along
the main walls and squared from these walls if desired,
the total width of trenches being carefully outlined.
The following points should be observed while
setting out trenches:
a) profiles, nails, strings and lime are used for
setting out foundation plan.
b) Sight rails may be erected at the corners of
a building to determine the correct position
of trenches.
c) A theodolite may be used for marking
accurately the axial lines or center lines.
d) Strings are tied and stretched to the nails on
profile or on pegs for horizontal control of
dimensions.
e) Vertical reference pillars are erected at a
distance of 1 meter from the edges of
excavation for vertical control of building
during construction.
f) All the levels on site should be obtained
from a fixed datum previously determined by
the surveyor. The depth of trenches and
other levels should also be regulated by
measurements from this point.
g) The bottom of all trenches should be well
rammed before placing the concrete in
position.
2.6 Timbering to excavations
When earth has been excavated to a
considerable depth the vertical faces of the
excavations need supporting by means of
timber, to prevent the soil from falling in and
injuring the workmen or the work upon
which they are engaged.
The strength of the timbering used for this
purpose necessarily depends upon the nature
of the soil, the depth of the excavations, and
the length of time it is likely to be kept open.
2.6.1 Excavation in firms soil
The method of timbering a trench in firm ground,
in which case short deal and batten ends,
varying from 1 by 4 ½ inches to 1 ½ by 9
inches, and about 3 feet long, called politics or
poling boards, are placed in pairs opposite one
another against either side of the trench, and
are held in position by means of struts, these
struts, which are usually short length of 4
inches diameter scaffold poles, or 4 by 4 inch
squared timbers, and cut about inch longer than
the clear distance between a pair of poling
boards,
Are fixed in position in the following
manner: one end of the strut is placed
against the middle of one poling board,
and the other end is swung vertically
downwards against the opposite poling
board, and forced tightly against it by
means of a few downward taps with a
mallet.
2.7 Excavation
What is an excavation or a trench?
OSHA defines as an excavation as any man
made cut, cavity, trench, or depression in
the earth’s surface formed by earth
removal. A trench is defined as a narrow
underground excavation that is deeper
than it is wide, and is no wider than
15feet (4.5m)
What are the competent person responsibilities?
OSHA’s trenching and excavation standard requires that a
competent person inspect job site trenches daily, as the
conditions change such as a rainstorm occurring, and
before a worker enters the trench, to ensure elimination of
excavation hazards. A competent person is knowledgeable
about excavation hazards and has the authority to fix
those hazards.
How to protect workers in excavation or trench?
All workers who enter a trench or excavation more than 5ft
deep must be protected by benching or sloping of the
earth, shoring, or shielding (trench boxes) to the dirction
of the competent person.
Protective systems
Benching: means a method of protecting
workers from cave-ins by excavating the
sides of an excavation to form one or
series of horizontal levels or steps, Usually
with vertical or near vertical surfaces
between levels. Note: benching can not be
done in type c soil, which is the least
stable soil type.
Sloping: involves cutting back the trench
wall at an angle inclined away from the
excavation.
Shoring: requires installing aluminum
hydraulic or other type of supports to
prevent soil movement and cave-ins.
Shielding: protects workers by using
trench boxes or other types of supports to
prevent soil cave-ins.
What are the general trenching and
excavation requirement?
Call before you dig. Request utility
companies or owners to determine the
location of underground utility
installations before excavating.
Ensure that underground installations are
protected, supported, or removed while the
excavation is open.
Keep heavy equipment away from trench
edges and identify other sources that
might affect trench stability.
Keep all spoils piles and equipment at least
2ft away from the edge of the excavation.
Use stairs, ladders, and ramps every 2ft, to
exit the excavation.
Do not stand beneath loads handled by
lifting or digging equipment.
 Do not work in excavations where water is standing
or accumulating unless special supports are used to
prevent cave-ins.
 Inspect excavations, adjacent area, and protective
systems for evidence of possible cave-ins,
indications of failure of protective systems,
hazardous atmospheres, other hazardous
conditions at the beginning of each workday or if
the stability of the excavation cold change.
 Test for atmospheric hazards such as low oxygen,
hazardous fumes and toxic gases hen greater than
4ft deep.
 Wear warning vests or other high visibility materials
when working near moving equipment or vehicles
THANK YOU

More Related Content

PPTX
Construction of substructure
PDF
ABC 1st Week(2hrs
PPT
FOUNDATION 13-02-14 (1).ppt,TYPES,PROCESS
PDF
Piles and drilled shaft - Deep Foundations
PPTX
foundation.pptx
PPTX
Building Constructure(CE3G) for construction work.pptx
PPTX
2 Foundations.pptx
PPT
Foundation Transfers building loads to ground
Construction of substructure
ABC 1st Week(2hrs
FOUNDATION 13-02-14 (1).ppt,TYPES,PROCESS
Piles and drilled shaft - Deep Foundations
foundation.pptx
Building Constructure(CE3G) for construction work.pptx
2 Foundations.pptx
Foundation Transfers building loads to ground

Similar to topic four.pptx foundation Engineering f (20)

PPTX
pilefoundationbypratiksolanki-171018083759.pptx
PPTX
Pile foundations Case Study Delhi Metro Site Visit
PPT
ALL ABOUT DEEP FOUNDATIONS
PPTX
Bcon final
PDF
PPT
Pile foundation ppt 2 (usefulsearch.org) (useful search)
PPT
Chapter 4 deep foundation ( bi )
PPT
Excav & Deep Foundations Fall 09
PPT
Foundation
PPTX
design of pile foundation anna university syllabus
PPTX
Pile foundation
PDF
Foundations
PPTX
Chapter 11 temporary works
PPTX
footing for construction technology.pptx
PDF
LECT 6 UPDATE.pdf
PPT
Deep Foundation
PPTX
CONSTRUCTION OF MULTI STOREY BUILDING.pptx
PPTX
Foundations
pilefoundationbypratiksolanki-171018083759.pptx
Pile foundations Case Study Delhi Metro Site Visit
ALL ABOUT DEEP FOUNDATIONS
Bcon final
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Chapter 4 deep foundation ( bi )
Excav & Deep Foundations Fall 09
Foundation
design of pile foundation anna university syllabus
Pile foundation
Foundations
Chapter 11 temporary works
footing for construction technology.pptx
LECT 6 UPDATE.pdf
Deep Foundation
CONSTRUCTION OF MULTI STOREY BUILDING.pptx
Foundations
Ad

More from abdi beder (20)

PPTX
Lecture 7 - Introdn_to_statistical_analysis_variables.pptx
PPTX
HR Policies Chapter 4_Stakeholders in HR Policy Formulation.pptx
PPTX
HR Policies Chapter 3_Essentials of a HR Policy Statement.pptx
PPTX
Chapter 5 Industrial Management and Labor Relations.pptx
PPTX
chapter 5 Environmental Impact Assessement v.pptx
PPTX
chapter 2 Human resource Procurement.pptx
PPTX
chapter 44. Industrial Management and Labor Relations.pptx
PPTX
structural analysis two .powerpoint presentation
PPTX
chapter five soil compaction.powerpoint presentation
PPT
Chapter 1 Introduction fgdgdfgdfgdgd
PPT
442695204-01-Introduction-to-surveying-ppt.ppt
PPTX
introduction surveybasic-191018120837 (1).pptx
PPTX
Introduction of surveybasic-191018120837.pptx1
PPTX
Full Project ministry of public work and Transportation
PPTX
islamicarchitecturefinal-150825161135-lva1-app6891.pptx
PPT
Environmental Impact Assessement13164243.ppt
PPT
ex1uxosws4w99hhoaohc-signature-132c2b3937a787aed48364a3f2c88d8b7a1e758a5b6889...
PPTX
ex1uxosws4w99hhoaohc-signature-132c2b3937a787aed48364a3f2c88d8b7a1e758a5b6889...
PPT
chapter 4 history of modern African architecture
PPTX
chapter three topic2.pptx construction tech II
Lecture 7 - Introdn_to_statistical_analysis_variables.pptx
HR Policies Chapter 4_Stakeholders in HR Policy Formulation.pptx
HR Policies Chapter 3_Essentials of a HR Policy Statement.pptx
Chapter 5 Industrial Management and Labor Relations.pptx
chapter 5 Environmental Impact Assessement v.pptx
chapter 2 Human resource Procurement.pptx
chapter 44. Industrial Management and Labor Relations.pptx
structural analysis two .powerpoint presentation
chapter five soil compaction.powerpoint presentation
Chapter 1 Introduction fgdgdfgdfgdgd
442695204-01-Introduction-to-surveying-ppt.ppt
introduction surveybasic-191018120837 (1).pptx
Introduction of surveybasic-191018120837.pptx1
Full Project ministry of public work and Transportation
islamicarchitecturefinal-150825161135-lva1-app6891.pptx
Environmental Impact Assessement13164243.ppt
ex1uxosws4w99hhoaohc-signature-132c2b3937a787aed48364a3f2c88d8b7a1e758a5b6889...
ex1uxosws4w99hhoaohc-signature-132c2b3937a787aed48364a3f2c88d8b7a1e758a5b6889...
chapter 4 history of modern African architecture
chapter three topic2.pptx construction tech II
Ad

Recently uploaded (20)

DOCX
Double Membrane Roofs for Bio CNG Plants Stores biogas.docx
DOCX
Double Membrane Roofs for Cassava Wastewater Treatment Captures biogas from i...
PPTX
Importance of good air quality and different pollutants.
PPT
PPTPresentation3 jhsvdasvdjhavsdhsvjcksjbc.jasb..ppt
PDF
The European Green Deal (EU Green Deal)
PPTX
Lecture-05-Audio-lingual. Method & Appro
DOCX
Double Membrane Roofs for Digester Tank Wastewater Treatment Integral to biog...
PDF
1748933543SJA_41_2_826-834 SJA Ihsan ullha.pdf
PDF
Global Natural Disasters in H1 2025 by Beinsure
PDF
Effects of rice-husk biochar and aluminum sulfate application on rice grain q...
DOCX
The Ripple Effect: Understanding Extreme Weather Patterns and Geomagnetic Dyn...
PPTX
Microbial-Pathogens-and-Parasites-Their-Impact-on-Plant-Health.pptx
PPTX
Corporate Social Responsibility & Governance
PPTX
the solar system janDNsdnfanscssfsaaansf
PDF
Cave Diggers Simplified cave survey methods and mapping
DOCX
Double Membrane Roofs for Agricultural Waste Biogas Digesters Turns various f...
PPTX
Biodiversity.udfnfndrijfreniufrnsiufnriufrenfuiernfuire
PPT
Environmental pollution for educational study
PPTX
Afro-Asia Literature.pptxmmmmmmmmmmmmmmm
DOCX
Double Membrane Roofs for Biomethane Storage Holds upgraded biomethane fuel.docx
Double Membrane Roofs for Bio CNG Plants Stores biogas.docx
Double Membrane Roofs for Cassava Wastewater Treatment Captures biogas from i...
Importance of good air quality and different pollutants.
PPTPresentation3 jhsvdasvdjhavsdhsvjcksjbc.jasb..ppt
The European Green Deal (EU Green Deal)
Lecture-05-Audio-lingual. Method & Appro
Double Membrane Roofs for Digester Tank Wastewater Treatment Integral to biog...
1748933543SJA_41_2_826-834 SJA Ihsan ullha.pdf
Global Natural Disasters in H1 2025 by Beinsure
Effects of rice-husk biochar and aluminum sulfate application on rice grain q...
The Ripple Effect: Understanding Extreme Weather Patterns and Geomagnetic Dyn...
Microbial-Pathogens-and-Parasites-Their-Impact-on-Plant-Health.pptx
Corporate Social Responsibility & Governance
the solar system janDNsdnfanscssfsaaansf
Cave Diggers Simplified cave survey methods and mapping
Double Membrane Roofs for Agricultural Waste Biogas Digesters Turns various f...
Biodiversity.udfnfndrijfreniufrnsiufnriufrenfuiernfuire
Environmental pollution for educational study
Afro-Asia Literature.pptxmmmmmmmmmmmmmmm
Double Membrane Roofs for Biomethane Storage Holds upgraded biomethane fuel.docx

topic four.pptx foundation Engineering f

  • 1. CIVIL ENGINEERING COURSE CONSTRUCTION TECHNOLOGY I ChAPTER 2: FOUNDATION PRESENTER: ENG ABDIQANI FAARAH ABDILLE
  • 2. 2.4 DEEP FOUNDATIONS 2.4.1 What is the deep foundation? Deep foundations are founded too deeply below the finished ground surface for their base bearing capacity to be affected by surface conditions, this is usually at depths >3 m below finished ground level. Deep foundation can be used to transfer the loading to a deeper, more competent strata at depth if unsuitable soils are present near the surface.
  • 3. 2.4.2 TYPES OF DEEP FOUNDATION 1. Piles 2. Piers 3. Caissons 4. Compensated foundations
  • 4. PILE FOUNDATION Piles are relatively long, slender members that transmit foundation loads through soil strata of low bearing capacity to deeper soil or rock strata having a high bearing capacity. They are used when for economic, constructional or soil condition considerations it is desirable to transmit loads to strata beyond the practical reach of shallow foundations. In addition to supporting structures, piles are also used to anchor structures against uplift forces and to assist structures in resisting lateral and overturning forces.
  • 5. PIERS Piers are foundations for carrying a heavy structural load which is constructed insitu in a deep excavation. CAISSONS Caissons are a form of deep foundation which are constructed above ground level, then sunk to the required level by excavating or dredging material from within the caisson
  • 6. COMPENSATED FOUNDATIONS Compensated foundations are deep foundations in which the relief of stress due to excavation is approximately balanced by the applied stress due to the foundation. The net stress applied is therefore very small. A compensated foundation normally comprises a deep
  • 7. PILES Types of pile Type of construction Factors influencing choice Pile groups
  • 8. TYPES OF PILE Piled foundations can be classified according to: a) The type of pile: (Different structures to be supported, and different ground conditions, require different types of resistance) and b) The type of construction:( different materials, structures and process can be used).
  • 9. types of pile 1. End bearing pile End bearing piles are those which terminate in hard, relatively impenetrable material such as rock or very dense sand and gravel. They derive most of their carrying capacity from the resistance of the stratum at the toe of the pile.
  • 10. 2. Friction piles Friction piles obtain a greater part of their carrying capacity by skin friction or adhesion. This tends to occur when pile do not reach an impenetrable stratum but are driven for some distance into a penetrable soil, their carrying capacity is derived partly from end bearing and partly from skin friction between the embedded surface of the soil and the surrounding soil.
  • 11. 3. Settlement reducing piles Settlement reducing piles are usually incorporated beneath the central part of raft foundation in order to reduce differential settlement to an acceptable level. Such piles act to reinforce the soil beneath the raft and help to prevent dishing of rafr in the centre.
  • 12. 4. Tension piles Structures such as tall chimneys, transmission towers and jetties can be subject to large overturning moments and so piles are often used to resist the resulting uplift forces at the foundations. In such cases the resulting forces are transmitted to the soil along the embedded length of the pile. The resisting force can be increased in the case of bored piles by under-reaming. In the design of tension piles the effect of radial contraction of the pile must be taken into account as this can cause about a 10% - 20% reduction in shaft resistance.
  • 13. 5. Laterally loaded piles Almost all piled foundations are subjected to at least some degree of horizontal loading. The magnitude of the loads in relation to the applied vertical axial loading will generally be small and no additional design calculations will normally be necessary. However, in the case of wharves and jetties carrying the impact forces of berthing ships, piled foundations to bridge piers, trestles to overhead cranes, tall chimneys and retaining walls, the horizontal component is relatively large and may prove critical in design.
  • 14. Traditionally piles have been installed at an angle to the vertical in such cases, providing sufficient horizontal resistance by virtue of the component of axial capacity of the pile which acts horizontally. However the capacity of a vertical pile to resist loads applied normally to the axis, although significantly smaller than the axial capacity of that pile, may be sufficient to avoid the need for such 'raking' or 'battered' piles which are more expensive to install. When designing piles to take lateral forces it is therefore important to take this into account.
  • 15. 2.5 SETTING OUT OF FOUNDATION TRENCHES Setting out of foundation trenches done by the following steps: a) First of all. The corners of the building are marked and then the length of the sides are checked by diagonal measurements. b) The axial lines (center lines) of the trenches are marked with the help of profiles, sighting rails, strings and pegs. c) The off-sets are measured from axial lines and the frontage lines are placed in their correct position relative to local requirements. d) The position of cross walls should be measured along the main walls and squared from these walls if desired, the total width of trenches being carefully outlined.
  • 16. The following points should be observed while setting out trenches: a) profiles, nails, strings and lime are used for setting out foundation plan. b) Sight rails may be erected at the corners of a building to determine the correct position of trenches. c) A theodolite may be used for marking accurately the axial lines or center lines. d) Strings are tied and stretched to the nails on profile or on pegs for horizontal control of dimensions.
  • 17. e) Vertical reference pillars are erected at a distance of 1 meter from the edges of excavation for vertical control of building during construction. f) All the levels on site should be obtained from a fixed datum previously determined by the surveyor. The depth of trenches and other levels should also be regulated by measurements from this point. g) The bottom of all trenches should be well rammed before placing the concrete in position.
  • 18. 2.6 Timbering to excavations When earth has been excavated to a considerable depth the vertical faces of the excavations need supporting by means of timber, to prevent the soil from falling in and injuring the workmen or the work upon which they are engaged. The strength of the timbering used for this purpose necessarily depends upon the nature of the soil, the depth of the excavations, and the length of time it is likely to be kept open.
  • 19. 2.6.1 Excavation in firms soil The method of timbering a trench in firm ground, in which case short deal and batten ends, varying from 1 by 4 ½ inches to 1 ½ by 9 inches, and about 3 feet long, called politics or poling boards, are placed in pairs opposite one another against either side of the trench, and are held in position by means of struts, these struts, which are usually short length of 4 inches diameter scaffold poles, or 4 by 4 inch squared timbers, and cut about inch longer than the clear distance between a pair of poling boards,
  • 20. Are fixed in position in the following manner: one end of the strut is placed against the middle of one poling board, and the other end is swung vertically downwards against the opposite poling board, and forced tightly against it by means of a few downward taps with a mallet.
  • 21. 2.7 Excavation What is an excavation or a trench? OSHA defines as an excavation as any man made cut, cavity, trench, or depression in the earth’s surface formed by earth removal. A trench is defined as a narrow underground excavation that is deeper than it is wide, and is no wider than 15feet (4.5m)
  • 22. What are the competent person responsibilities? OSHA’s trenching and excavation standard requires that a competent person inspect job site trenches daily, as the conditions change such as a rainstorm occurring, and before a worker enters the trench, to ensure elimination of excavation hazards. A competent person is knowledgeable about excavation hazards and has the authority to fix those hazards. How to protect workers in excavation or trench? All workers who enter a trench or excavation more than 5ft deep must be protected by benching or sloping of the earth, shoring, or shielding (trench boxes) to the dirction of the competent person.
  • 23. Protective systems Benching: means a method of protecting workers from cave-ins by excavating the sides of an excavation to form one or series of horizontal levels or steps, Usually with vertical or near vertical surfaces between levels. Note: benching can not be done in type c soil, which is the least stable soil type. Sloping: involves cutting back the trench wall at an angle inclined away from the excavation.
  • 24. Shoring: requires installing aluminum hydraulic or other type of supports to prevent soil movement and cave-ins. Shielding: protects workers by using trench boxes or other types of supports to prevent soil cave-ins. What are the general trenching and excavation requirement? Call before you dig. Request utility companies or owners to determine the location of underground utility installations before excavating.
  • 25. Ensure that underground installations are protected, supported, or removed while the excavation is open. Keep heavy equipment away from trench edges and identify other sources that might affect trench stability. Keep all spoils piles and equipment at least 2ft away from the edge of the excavation. Use stairs, ladders, and ramps every 2ft, to exit the excavation. Do not stand beneath loads handled by lifting or digging equipment.
  • 26.  Do not work in excavations where water is standing or accumulating unless special supports are used to prevent cave-ins.  Inspect excavations, adjacent area, and protective systems for evidence of possible cave-ins, indications of failure of protective systems, hazardous atmospheres, other hazardous conditions at the beginning of each workday or if the stability of the excavation cold change.  Test for atmospheric hazards such as low oxygen, hazardous fumes and toxic gases hen greater than 4ft deep.  Wear warning vests or other high visibility materials when working near moving equipment or vehicles