Barracks Upgrades
Advance Efficiency
For decades, Starship military barracks in locations including Fort
Benning, GA and Fort Jackson, SC have provided housing, instruction
and training for recruits on their way to becoming combat-ready
soldiers.
To ensure the facilities measure up to their sterling reputations, the
military posts needed to renovate these older barracks. With a primary
goal of upgrading soldiers’ living quarters, and a secondary goal of
improving energy efficiency and pursuing LEED® accreditation, the US
Army Corps of Engineers (USACE) and its general contractors, architects
and engineers rely on McKenney’s Building Performance Solutions
team to design and install the plumbing and HVAC systems that serves
the barracks.
Starship barracks renovations, which fall under the military’s Training
Barracks Upgrade Program (TBUP), have strict design and budget
requirements. In addition, they are large, horizontal, complex
renovation projects on very tight schedules. This creates the potential
for contractors to spread out and work in areas out of sequence, which
can, in turn, negatively impact the project.
Drawing from its experience on 14 similar TBUP renovation projects,
the McKenney’s team collaborates with the MATOC (Multiple Award
Task Order Contract) general contractor and other trades in developing
the overall project design schedule and sequence. By doing this, the
team is able to create a workable schedule that meets the USACE’s
goals— then focus on short-term planning, on-time deliveries and
meeting milestones to direct the project.
In addition, to minimize time onsite and further compress the schedule
during the construction phase, McKenney’s prefabricates the plumbing
and HVAC components in its shops and makes just-in-time deliveries of
the components to the jobsite.
McKenney’s has proven time and again that it is a valuable partner and
resource when it comes to complicated TBUP barracks renovation
projects. By adding value from the beginning stages of design all the
way through completion, the McKenney’s team is able to avoid
problems and help keep these complex projects on track.
All the while supporting energy efficiency goals of consuming 30
percent less energy, putting any TBUP renovation on a firm footing to
pursue LEED® Silver certification.
The content of this document is not intended as an endorsement.
`
Keeping trades and contractors
sequenced and on schedule
The Challenge
Achieving greater energy efficiency
Enlisted design/assist expertise
where needed
The Solution
Pre-fabricated plumbing and
HVAC components offsite
Drove the schedule through
short-term planning and
on-time deliveries
Reduced energy consumption
The Results
Positioned Starship barracks
for LEED® Silver certification
Specializations
Design/Assist
BIM
LEED® Certification
Plumbing, Pipe and Sheet Shops
Energy Management
Phase I Starship: Fort Benning
Buildings 3105, 3335, 3505,
3210
TBUP Renovations Completed
Phase II Starship: Fort Benning
Buildings 3240, 3210
Phase II Starship: Fort Jackson
Buildings 11000, 12000
Phase I Starship: Fort Jackson
Building 11000
Rolling Pin: Fort Gordon Buildings
25718, 25720, 25721, 29702
1056 Moreland Industrial Boulevard
Atlanta, GA 30316
P: 404-622-5000
sales@mckenneys.com
www.mckenneys.com
3601 Performance Road
Charlotte, North Carolina 28214
P: 704-357-1200
Atlanta Office:
Charlotte Office:

More Related Content

PDF
Deploying Expertise and Skill - HVAC and Plumbing Systems Upgrade in Augusta, GA
PDF
10 nysdot chapt 5 final
PPTX
Mission Critical Data Center Retrofit Project - Catawaba County, NC
PDF
A Central District Water Plant
PDF
Precise Planning, Staged Installation
PDF
Soaring Past Obstacles - Design-Assist Services in Davidson, NC
DOCX
Dfuson Resume log
PDF
Expediting a Smooth Move - Design Assist Services in Norcross, GA
Deploying Expertise and Skill - HVAC and Plumbing Systems Upgrade in Augusta, GA
10 nysdot chapt 5 final
Mission Critical Data Center Retrofit Project - Catawaba County, NC
A Central District Water Plant
Precise Planning, Staged Installation
Soaring Past Obstacles - Design-Assist Services in Davidson, NC
Dfuson Resume log
Expediting a Smooth Move - Design Assist Services in Norcross, GA

Viewers also liked (7)

PDF
Barracks Upgrades Advance Efficiency
PPT
Corps of Engineers - Savannah District
PDF
2014 Delucchi Brochure
PDF
شهادة الخبرة النهائية
PPTX
Nader khalili
PDF
Prefabrication
PPTX
My school 16
Barracks Upgrades Advance Efficiency
Corps of Engineers - Savannah District
2014 Delucchi Brochure
شهادة الخبرة النهائية
Nader khalili
Prefabrication
My school 16
Ad

More from McKenney's Inc (20)

PPTX
CRAC Units Installation for a Data Center Project in Alpharetta, GA
PDF
Generating a Reliable Backup Plan - Data Center Retrofit Project
PDF
Performing a Cooling Transplant in Braselton, Georgia
PDF
Lab Installation Cools Concerns - Federal Laboratory Renovation
PDF
Blowing the Lid Off City Hall - Energy Savings Performance Contracting
PPTX
Design/Build Mechanical Systems Projects - Atlanta, GA
PDF
Building Relationships on the Double - Design/Build Mechanical Systems Projects
PDF
Keeping the Fans Waving - Cooling Systems Replacement
PDF
A Breakout Turnkey HVAC Conversion - Turnkey Design/Build
PPTX
Installation of Plumbing and HVAC systems - Hospitality Construction
PDF
Covering All the Bases - Plumbing and HVAC Systems Installation
PPT
Reducing Building Energy Consumption in Zero Energy Buildings (ZEB)
PPT
Turnkey Solution for an ESPC (Energy Savings Performance Contract) Project
PPT
McKenney’s, Inc. Critical Systems - High-Quality Mechanical Services for Miss...
PPT
Efficient Solutions for Rainwater and Condensate Harvesting
PPT
Plumbing Preventive Maintenance in Commercial Buildings
PPT
McKenney’s, Inc. Interiors & Special Projects - Your Single Source for High-q...
PDF
Creating a Showstopper in Charlotte - Mechanical Systems Installation
PDF
A Greener Hospital by Design
PDF
Playing Multiple Roles - Hospitality Construction
CRAC Units Installation for a Data Center Project in Alpharetta, GA
Generating a Reliable Backup Plan - Data Center Retrofit Project
Performing a Cooling Transplant in Braselton, Georgia
Lab Installation Cools Concerns - Federal Laboratory Renovation
Blowing the Lid Off City Hall - Energy Savings Performance Contracting
Design/Build Mechanical Systems Projects - Atlanta, GA
Building Relationships on the Double - Design/Build Mechanical Systems Projects
Keeping the Fans Waving - Cooling Systems Replacement
A Breakout Turnkey HVAC Conversion - Turnkey Design/Build
Installation of Plumbing and HVAC systems - Hospitality Construction
Covering All the Bases - Plumbing and HVAC Systems Installation
Reducing Building Energy Consumption in Zero Energy Buildings (ZEB)
Turnkey Solution for an ESPC (Energy Savings Performance Contract) Project
McKenney’s, Inc. Critical Systems - High-Quality Mechanical Services for Miss...
Efficient Solutions for Rainwater and Condensate Harvesting
Plumbing Preventive Maintenance in Commercial Buildings
McKenney’s, Inc. Interiors & Special Projects - Your Single Source for High-q...
Creating a Showstopper in Charlotte - Mechanical Systems Installation
A Greener Hospital by Design
Playing Multiple Roles - Hospitality Construction
Ad

Recently uploaded (20)

PDF
Immigration Law and Communication: Challenges and Solutions {www.kiu.ac.ug)
PPTX
df0ee68f89e1a869be4bff9b80a7 business 79f0.pptx
PPTX
BUSINESS CYCLE_INFLATION AND UNEMPLOYMENT.pptx
PPTX
Transportation in Logistics management.pptx
PPTX
IITM - FINAL Option - 01 - 12.08.25.pptx
PDF
MBA2024 CGE 1.pdf file presentation 2025
PPTX
Understanding Procurement Strategies.pptx Your score increases as you pick a ...
PDF
Comments on Clouds that Assimilate Parts I&II.pdf
PDF
Second Hand Fashion Call to Action March 2025
PPTX
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
PDF
533158074-Saudi-Arabia-Companies-List-Contact.pdf
PPTX
Market and Demand Analysis.pptx for Management students
PDF
HQ #118 / 'Building Resilience While Climbing the Event Mountain
PDF
income tax laws notes important pakistan
PDF
Middle East's Most Impactful Business Leaders to Follow in 2025
PPTX
CTG - Business Update 2Q2025 & 6M2025.pptx
DOCX
Emerging Dubai Investment Opportunities in 2025.docx
PPTX
2 - Self & Personality 587689213yiuedhwejbmansbeakjrk
DOCX
80 DE ÔN VÀO 10 NĂM 2023vhkkkjjhhhhjjjj
PPT
Retail Management and Retail Markets and Concepts
Immigration Law and Communication: Challenges and Solutions {www.kiu.ac.ug)
df0ee68f89e1a869be4bff9b80a7 business 79f0.pptx
BUSINESS CYCLE_INFLATION AND UNEMPLOYMENT.pptx
Transportation in Logistics management.pptx
IITM - FINAL Option - 01 - 12.08.25.pptx
MBA2024 CGE 1.pdf file presentation 2025
Understanding Procurement Strategies.pptx Your score increases as you pick a ...
Comments on Clouds that Assimilate Parts I&II.pdf
Second Hand Fashion Call to Action March 2025
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
533158074-Saudi-Arabia-Companies-List-Contact.pdf
Market and Demand Analysis.pptx for Management students
HQ #118 / 'Building Resilience While Climbing the Event Mountain
income tax laws notes important pakistan
Middle East's Most Impactful Business Leaders to Follow in 2025
CTG - Business Update 2Q2025 & 6M2025.pptx
Emerging Dubai Investment Opportunities in 2025.docx
2 - Self & Personality 587689213yiuedhwejbmansbeakjrk
80 DE ÔN VÀO 10 NĂM 2023vhkkkjjhhhhjjjj
Retail Management and Retail Markets and Concepts

Training Barracks Upgrade Program

  • 2. For decades, Starship military barracks in locations including Fort Benning, GA and Fort Jackson, SC have provided housing, instruction and training for recruits on their way to becoming combat-ready soldiers.
  • 3. To ensure the facilities measure up to their sterling reputations, the military posts needed to renovate these older barracks. With a primary goal of upgrading soldiers’ living quarters, and a secondary goal of improving energy efficiency and pursuing LEED® accreditation, the US Army Corps of Engineers (USACE) and its general contractors, architects and engineers rely on McKenney’s Building Performance Solutions team to design and install the plumbing and HVAC systems that serves the barracks. Starship barracks renovations, which fall under the military’s Training Barracks Upgrade Program (TBUP), have strict design and budget requirements. In addition, they are large, horizontal, complex renovation projects on very tight schedules. This creates the potential for contractors to spread out and work in areas out of sequence, which can, in turn, negatively impact the project.
  • 4. Drawing from its experience on 14 similar TBUP renovation projects, the McKenney’s team collaborates with the MATOC (Multiple Award Task Order Contract) general contractor and other trades in developing the overall project design schedule and sequence. By doing this, the team is able to create a workable schedule that meets the USACE’s goals— then focus on short-term planning, on-time deliveries and meeting milestones to direct the project. In addition, to minimize time onsite and further compress the schedule during the construction phase, McKenney’s prefabricates the plumbing and HVAC components in its shops and makes just-in-time deliveries of the components to the jobsite.
  • 5. McKenney’s has proven time and again that it is a valuable partner and resource when it comes to complicated TBUP barracks renovation projects. By adding value from the beginning stages of design all the way through completion, the McKenney’s team is able to avoid problems and help keep these complex projects on track. All the while supporting energy efficiency goals of consuming 30 percent less energy, putting any TBUP renovation on a firm footing to pursue LEED® Silver certification. The content of this document is not intended as an endorsement.
  • 6. ` Keeping trades and contractors sequenced and on schedule The Challenge Achieving greater energy efficiency Enlisted design/assist expertise where needed The Solution Pre-fabricated plumbing and HVAC components offsite Drove the schedule through short-term planning and on-time deliveries Reduced energy consumption The Results Positioned Starship barracks for LEED® Silver certification Specializations Design/Assist BIM LEED® Certification Plumbing, Pipe and Sheet Shops Energy Management Phase I Starship: Fort Benning Buildings 3105, 3335, 3505, 3210 TBUP Renovations Completed Phase II Starship: Fort Benning Buildings 3240, 3210 Phase II Starship: Fort Jackson Buildings 11000, 12000 Phase I Starship: Fort Jackson Building 11000 Rolling Pin: Fort Gordon Buildings 25718, 25720, 25721, 29702
  • 7. 1056 Moreland Industrial Boulevard Atlanta, GA 30316 P: 404-622-5000 sales@mckenneys.com www.mckenneys.com 3601 Performance Road Charlotte, North Carolina 28214 P: 704-357-1200 Atlanta Office: Charlotte Office: