WATER SHUTOFF & ZONE
TRANSFER IN CAMBAY #15
WELL
ADJEI STEPHEN
MTECH PETROLEUM ENG
INDIAN SCHOOL OF MINES
1
CAMBAY #15 WELL
 Well was drilled by Cardwell- IX rig. After cumulative oil production of
11853.03 MT on self, water shut off by cement squeeze was carried out in
April 2006. After cumulative production of 40000MT again water shut off by
polymer gel followed by cement squeeze was carried out and well was put
on SRP mode in January 2012. After cumulative production of 42220 MT,
well is not operating due to 100% water cut.
 Drilled Depth; 1502m F/collar 1448 m well type vertical
 Casing; Conductor- 9 5/’’, 600m, N-80 & J-55, 40 ppf. Cement rise up to
surface
 Production- 5 ½ ‘’ shoe at 1470m N-80, 17ppf cement rise up to
960m
 F/collar - 1448m
 Wellbore clear; 1425m
 Interval open; 1400 – 1404.5m
 Tubing shoe; 1000.6m
 Last recorded reservoir pressure; 58.9 KSC at 1185m
 Last killed fluid; brine of sp. Gr 1.02
2
High Press Gas
Gas
Oil
Water
Oil
5 ½ ‘’Production Casing
9 5/8’’Conductor Casing
1400 – 1404.5m
tubing
Tubing shoe at 1000.6m
c/rise to 960m
950m
WELLBORE CLEAR AT 1425M
c/rise to surface
3
PROBLEM STATEMENT & SOLUTION
 THERE IS 100% WATER
CUT FROM THE
CAMBAY #15 WELL
 TO CURB THIS, A
SQUEEZE CEMENT JOB
WILL BE CARRIED OUT
IN THE OPEN INTERVAL
AND & ZONE
TRANSFERRED TO
UPPER SANDS
4
CAUSES OF EXCESS WATER
PRODUCTION
 CONING OR
CUSPING
 CHANNELING
 VISCOUR FINGERING
 WATER
ENCROACHMENT
5
WHY THE NEED TO CONTROL WATER
PRODUCTION
Corrosion of production facilities
Huge costs incurred in treating
produced water for disposal
Reduction in production rate
6
NEED FOR WORKOVER
workover refers
to any remedial
operation done
on a well to
restore, maintain
or enhance the
recovery from
the well
 Completing for
Production from a New
Reservoir
 Equipment failure (pump
failure)
 Wellbore problems
( sanding, formation
damage, paraffin
accumulation, water and
gas coning)
 Mechanical problems
(casing leaks, tubing
leaks, cement failure)
7
SQUEEZE CEMENTING
This refers to the process of injecting cement slurry
into a zone for purposes such as
 To abandon a zone
 To shutoff water or gas coning
 To repair casing leaks
 Seal off lost circulation zones
8
PROCEEDIA FOR SQUEEZE JOB ON
CAMBAY #15
1. Well volume was displaced with water and
subdued/KILLED with brine of specific gravity 1.02
2. Christmas tree was then nippled down and BOP
nippled up
3. Tubing was lowered from initial depth of 1000.6m to
wellbore clear (1425m) to confirm the wellbore clear
and reverse circulation of brine was carried out
9
4. Tubing shoe (Tubing) was then adjusted up by 2m to 1423m
5. Injectivity test was conducted (liter per minute)
injectivity test is conducted against the squeeze interval to
determine if and at what rate below the fracture gradient, fluid can
be placed against the formation.
Other reasons;
• To ensure that the perforations are open and ready to accept
fluids.
• To obtain an estimate of proper cement slurry injection rate
• To estimate the pressure at which the squeeze job will be
performed
• To estimate amount of slurry to be used
10
PUMPING SLURRY
5. Cement slurry was
then squeezed into the
existing interval and
cement top kept at
1380m
6. Tubing was pulled
out AND waiting on
cement was done for
24hours
11
7. TCR bit was then run on 2 3/8’’ drill pipe to tag
cement top ,plug was then tested at 100 KSC, then
drilled to 1390m and TCR bit pulled out
8. A scrapper was lowered to scrape the casing up
to 1390m and well circulated with brine.
Casing collar log was recorded for depth control
9. Cement plug was again drilled to 1395m and
scrapping done again. TCR bit pulled out
12
HERMETICAL TESTING & RE-PERFORATION
 11. Well was
hermetically tested to
check for leaks, brine
weight increased from
1.02 sp GR to 1.03 sp
GR
 12. New interval was
perforated at 1392-
1391m, 1390-
1388m,1386-1385m &
1381-1379m at 18 SPM
(shots per meter)
13
13. Tubing was returned with BB shoe up to 1364m.
Injectivity test was carried out. Test was less than 250
LPM at 700 psi so a well stimulation job with mud acid
was carried out.
14.BOP was nippled down and X-mas tree nippled up. Kill
fluid was displaced with water
Finally well was activated by air compressor
14
Thank You!
15

More Related Content

PPSX
Water coning in oil wells and DWS technology
PPTX
Pulsed neutron carbon oxygen logging
PPTX
Drilling fluids
PPT
introduction to completions and workovers (2)
PPTX
Sand Problem in Oil Wells
PPT
Well completion workshop april-2018
PPTX
Well intervention
PDF
Bond log theory and interpretation
Water coning in oil wells and DWS technology
Pulsed neutron carbon oxygen logging
Drilling fluids
introduction to completions and workovers (2)
Sand Problem in Oil Wells
Well completion workshop april-2018
Well intervention
Bond log theory and interpretation

What's hot (20)

PPTX
Factors effecting vertical lift performance
PDF
Subsurface safety valves
PPTX
Dst (Drill Stem Test)
PPT
Well completion fundamentals
PPT
Waterflood Design and Operational Best Practices
PPTX
Artificial lift method
PPTX
Intelligent well completion
PPTX
waterflooding
PDF
Production packer
PDF
One day gas lift system course
PPTX
Well Workover
PDF
Gas lift design
DOCX
Open Hole Completion Design
PPT
140717 artificial lift
PPTX
Basic Hydraulic Fracturing
PPTX
Well Stimulation
PPT
Formation Damage and Acid Stimulation Presentation 2.
PPT
Well completion and stimulation
PDF
Life Cycle of Oil & Gas Wells
PDF
Oil & Gas Production
Factors effecting vertical lift performance
Subsurface safety valves
Dst (Drill Stem Test)
Well completion fundamentals
Waterflood Design and Operational Best Practices
Artificial lift method
Intelligent well completion
waterflooding
Production packer
One day gas lift system course
Well Workover
Gas lift design
Open Hole Completion Design
140717 artificial lift
Basic Hydraulic Fracturing
Well Stimulation
Formation Damage and Acid Stimulation Presentation 2.
Well completion and stimulation
Life Cycle of Oil & Gas Wells
Oil & Gas Production
Ad

Viewers also liked (12)

PPSX
Depleted oil fields regeneration with water shutoff - euco group
PPTX
CONING CONTROL AND RECOVERY IMPROVEMENT IN BOTTOM WATER
PDF
PetroSync - IWCF Well Intervention Pressure Control 6.0
PPTX
Eclipse reservoir simulation project presentation slides team ucsi
PPTX
Produced water overview ppt, Oct 2011, M Rashid
PDF
Api standards for safe offshore operations brochure
PPTX
Produced Water | Session III - John Veil
PPTX
Geopolitics in oil and gas market
PPT
Produced water treatment_presentation
PDF
Q913 re1 w1 lec 4
PDF
Q913 re1 w2 lec 5
PDF
Q921 re1 lec6 v1
Depleted oil fields regeneration with water shutoff - euco group
CONING CONTROL AND RECOVERY IMPROVEMENT IN BOTTOM WATER
PetroSync - IWCF Well Intervention Pressure Control 6.0
Eclipse reservoir simulation project presentation slides team ucsi
Produced water overview ppt, Oct 2011, M Rashid
Api standards for safe offshore operations brochure
Produced Water | Session III - John Veil
Geopolitics in oil and gas market
Produced water treatment_presentation
Q913 re1 w1 lec 4
Q913 re1 w2 lec 5
Q921 re1 lec6 v1
Ad

Similar to Water shut off ppt (20)

DOC
Bj news cement squeeze job - vlc-1433
PDF
IJSRED-V2I3P90
PDF
IJSRED-V2I3P90
PPTX
Project 2
PPT
Cementation
PDF
Completion and work over well control .pdf
PPTX
Concrete retempering presentation
PPTX
nwosu chioma sylvia
PDF
Recap final celeus 1
PPT
Deep water drilling final
PDF
An experience of Loading pattern on Power supports with Sand stone roof in SCCL
PPT
PPTX
Blind Backfilling.pptx
PPTX
Polavaram internship
PPTX
Properties of concrete
PPTX
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
PDF
1. completion sequance
PDF
Well Hydraulics
PPTX
Presentation of CT unit1.1,1.2 &1.3NC.pptx
DOCX
Chenistry khan khan
Bj news cement squeeze job - vlc-1433
IJSRED-V2I3P90
IJSRED-V2I3P90
Project 2
Cementation
Completion and work over well control .pdf
Concrete retempering presentation
nwosu chioma sylvia
Recap final celeus 1
Deep water drilling final
An experience of Loading pattern on Power supports with Sand stone roof in SCCL
Blind Backfilling.pptx
Polavaram internship
Properties of concrete
Blind Backfilling of Goaf and Coal Extraction below Built-up Areas / Surface ...
1. completion sequance
Well Hydraulics
Presentation of CT unit1.1,1.2 &1.3NC.pptx
Chenistry khan khan

Recently uploaded (20)

PPTX
web development for engineering and engineering
PPTX
Geodesy 1.pptx...............................................
PPTX
additive manufacturing of ss316l using mig welding
PDF
Structs to JSON How Go Powers REST APIs.pdf
PPTX
Welding lecture in detail for understanding
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
Strings in CPP - Strings in C++ are sequences of characters used to store and...
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PDF
Well-logging-methods_new................
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PPTX
Sustainable Sites - Green Building Construction
PDF
Digital Logic Computer Design lecture notes
PDF
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
Lesson 3_Tessellation.pptx finite Mathematics
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
web development for engineering and engineering
Geodesy 1.pptx...............................................
additive manufacturing of ss316l using mig welding
Structs to JSON How Go Powers REST APIs.pdf
Welding lecture in detail for understanding
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Strings in CPP - Strings in C++ are sequences of characters used to store and...
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
UNIT-1 - COAL BASED THERMAL POWER PLANTS
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
Well-logging-methods_new................
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
Sustainable Sites - Green Building Construction
Digital Logic Computer Design lecture notes
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
Lesson 3_Tessellation.pptx finite Mathematics
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx

Water shut off ppt

  • 1. WATER SHUTOFF & ZONE TRANSFER IN CAMBAY #15 WELL ADJEI STEPHEN MTECH PETROLEUM ENG INDIAN SCHOOL OF MINES 1
  • 2. CAMBAY #15 WELL  Well was drilled by Cardwell- IX rig. After cumulative oil production of 11853.03 MT on self, water shut off by cement squeeze was carried out in April 2006. After cumulative production of 40000MT again water shut off by polymer gel followed by cement squeeze was carried out and well was put on SRP mode in January 2012. After cumulative production of 42220 MT, well is not operating due to 100% water cut.  Drilled Depth; 1502m F/collar 1448 m well type vertical  Casing; Conductor- 9 5/’’, 600m, N-80 & J-55, 40 ppf. Cement rise up to surface  Production- 5 ½ ‘’ shoe at 1470m N-80, 17ppf cement rise up to 960m  F/collar - 1448m  Wellbore clear; 1425m  Interval open; 1400 – 1404.5m  Tubing shoe; 1000.6m  Last recorded reservoir pressure; 58.9 KSC at 1185m  Last killed fluid; brine of sp. Gr 1.02 2
  • 3. High Press Gas Gas Oil Water Oil 5 ½ ‘’Production Casing 9 5/8’’Conductor Casing 1400 – 1404.5m tubing Tubing shoe at 1000.6m c/rise to 960m 950m WELLBORE CLEAR AT 1425M c/rise to surface 3
  • 4. PROBLEM STATEMENT & SOLUTION  THERE IS 100% WATER CUT FROM THE CAMBAY #15 WELL  TO CURB THIS, A SQUEEZE CEMENT JOB WILL BE CARRIED OUT IN THE OPEN INTERVAL AND & ZONE TRANSFERRED TO UPPER SANDS 4
  • 5. CAUSES OF EXCESS WATER PRODUCTION  CONING OR CUSPING  CHANNELING  VISCOUR FINGERING  WATER ENCROACHMENT 5
  • 6. WHY THE NEED TO CONTROL WATER PRODUCTION Corrosion of production facilities Huge costs incurred in treating produced water for disposal Reduction in production rate 6
  • 7. NEED FOR WORKOVER workover refers to any remedial operation done on a well to restore, maintain or enhance the recovery from the well  Completing for Production from a New Reservoir  Equipment failure (pump failure)  Wellbore problems ( sanding, formation damage, paraffin accumulation, water and gas coning)  Mechanical problems (casing leaks, tubing leaks, cement failure) 7
  • 8. SQUEEZE CEMENTING This refers to the process of injecting cement slurry into a zone for purposes such as  To abandon a zone  To shutoff water or gas coning  To repair casing leaks  Seal off lost circulation zones 8
  • 9. PROCEEDIA FOR SQUEEZE JOB ON CAMBAY #15 1. Well volume was displaced with water and subdued/KILLED with brine of specific gravity 1.02 2. Christmas tree was then nippled down and BOP nippled up 3. Tubing was lowered from initial depth of 1000.6m to wellbore clear (1425m) to confirm the wellbore clear and reverse circulation of brine was carried out 9
  • 10. 4. Tubing shoe (Tubing) was then adjusted up by 2m to 1423m 5. Injectivity test was conducted (liter per minute) injectivity test is conducted against the squeeze interval to determine if and at what rate below the fracture gradient, fluid can be placed against the formation. Other reasons; • To ensure that the perforations are open and ready to accept fluids. • To obtain an estimate of proper cement slurry injection rate • To estimate the pressure at which the squeeze job will be performed • To estimate amount of slurry to be used 10
  • 11. PUMPING SLURRY 5. Cement slurry was then squeezed into the existing interval and cement top kept at 1380m 6. Tubing was pulled out AND waiting on cement was done for 24hours 11
  • 12. 7. TCR bit was then run on 2 3/8’’ drill pipe to tag cement top ,plug was then tested at 100 KSC, then drilled to 1390m and TCR bit pulled out 8. A scrapper was lowered to scrape the casing up to 1390m and well circulated with brine. Casing collar log was recorded for depth control 9. Cement plug was again drilled to 1395m and scrapping done again. TCR bit pulled out 12
  • 13. HERMETICAL TESTING & RE-PERFORATION  11. Well was hermetically tested to check for leaks, brine weight increased from 1.02 sp GR to 1.03 sp GR  12. New interval was perforated at 1392- 1391m, 1390- 1388m,1386-1385m & 1381-1379m at 18 SPM (shots per meter) 13
  • 14. 13. Tubing was returned with BB shoe up to 1364m. Injectivity test was carried out. Test was less than 250 LPM at 700 psi so a well stimulation job with mud acid was carried out. 14.BOP was nippled down and X-mas tree nippled up. Kill fluid was displaced with water Finally well was activated by air compressor 14