A stamping operation involves two cylinders A and B working in
sequence.
 Cylinder A extends and brings a job under a stamping cylinder B.
 Cylinder B then extends and stamps the job
 Cylinder A can return back only after cylinder B has retracted fully .
 A pneumatic circuit has to be developed for realizing this control task.
Multiple Actuator Control
Week # 7
Displacement–Event
Diagram
A+ B+ B- A-
 A+ action generates sensor signal a1, which is used for B+ action.
 B+ action generates sensor signal b1, which is used for B- action.
 B+ action generates sensor signal b0, which is used for A- action.
 A- action generates sensor signal a0, which is used for A+ action.
Week # 7 Multiple Actuator Control
A start signal is also required along with a0 signal
for obtaining A+ action. (Signal generated due to
the last control action in the sequence)
Week # 7 Multiple Actuator Control
Week # 7 Multiple Actuator Control
 When the start push button is pressed, signal
appears at port 14 of valve through sensor a0
 Signal is also present at port 12 of valve,
resulting in a signal conflict.
 When cylinder B extends fully, sensor b1
generates an output signal at port 12 of valve
 Signal is also present at port 12 of valve,
resulting in a signal conflict.
Look for signal conflicts
Week # 7 Multiple Actuator Control
 Idle-return Rollers
 Reversing valves (memory valves)
 Modules as combination of valves
Elimination of signal conflicts
Idle-return Rollers
Week # 7 Multiple Actuator Control
 This method is not reliable
 The end position cannot be sensed accurately.
 Fast control system cannot be setup.
Elimination of signal conflicts
Week # 7 Multiple Actuator Control
Two of the possible designs used to remove signal conflicts through reversing valves are
 Cascade Method
 Shift-Register Method
Elimination of signal conflicts
Cascade Method
Sequence of operation of cylinders can be divided into appropriate number of groups
 There is a possibility of signals conflicts If any cylinder happen to appear twice in a group
 Hence, sequence is divided in such a way that A+ and A- fall into different groups
A+ B+ B- A-
Week # 7 Multiple Actuator Control
Two of the possible designs used to remove signal conflicts through reversing valves are
 Cascade Method
 Shift-Register Method
Elimination of signal conflicts
Cascade Method
Sequence of operation of cylinders can be divided into appropriate number of groups
 There is a possibility of signals conflicts If any cylinder happen to appear twice in a group
 Hence, sequence is divided in such a way that A+ and A- fall into different groups
A+ B+ B- A-
Group 1 Group 2
Week # 7 Multiple Actuator Control
Cascade Method
Number of groups increases, the number of
valves required also increases
Next is to divide the power supply for the control circuit into the same number of groups as for the
sequence of the operation
• Only one group will have supply with all other groups connected to the exhaust
Week # 7 Multiple Actuator Control
Cascade Method
Initially the supply is in the last group
Week # 7 Multiple Actuator Control
Week # 7 Multiple Actuator Control
END

More Related Content

PDF
Pneumatic control MCQ
PDF
Project Report - Spring 2014
DOCX
ControlsLab2
PDF
Korg sq 10 owners manual (users)
PDF
Week 7 3_design_of_advanced_pneumatics
DOC
Basic Control System unit2
DOCX
ECET 402 Entire Course NEW
PPTX
CONTROL SYSTEMS AND MEASUREMENTS
Pneumatic control MCQ
Project Report - Spring 2014
ControlsLab2
Korg sq 10 owners manual (users)
Week 7 3_design_of_advanced_pneumatics
Basic Control System unit2
ECET 402 Entire Course NEW
CONTROL SYSTEMS AND MEASUREMENTS

Similar to Week7_Chap7_multi actutaor control cylinder control (20)

PDF
Digital Control Systems
PDF
Real-time PID control of an inverted pendulum
PPTX
QuadcopterControllnnnnnnnnnnnnnnner.pptx
PDF
Control_System_Lab.pdf
PDF
Week 5 1_advance_electro_hydraulics_design1
PDF
IRJET- PLC based Washing Machine
PDF
E05222936
PPTX
ELEN601_Project
DOCX
Sop 6.6 kv switchboard edited
PDF
Pneumatics Circuits Components (Circuit details)
 
PPTX
speed governer characteristics and classfication
PPTX
Basic hydraulic circuit
PPTX
Automatic Generation Control
PDF
INSTRUMENTATION AND PROCESS CONTROL - BOILER CONTROL
DOCX
Sop 6.6 kv switchboard
PDF
Time Response
PPT
condition monitoring and Fault diagnostics of centrifugal pump using data acq...
PDF
Manual english new material OT III 962-0512.pdf
PPT
Fundamental process control system Chapter2.ppt
PDF
Condition monitoring of screw compressors and induction motors in a food proc...
Digital Control Systems
Real-time PID control of an inverted pendulum
QuadcopterControllnnnnnnnnnnnnnnner.pptx
Control_System_Lab.pdf
Week 5 1_advance_electro_hydraulics_design1
IRJET- PLC based Washing Machine
E05222936
ELEN601_Project
Sop 6.6 kv switchboard edited
Pneumatics Circuits Components (Circuit details)
 
speed governer characteristics and classfication
Basic hydraulic circuit
Automatic Generation Control
INSTRUMENTATION AND PROCESS CONTROL - BOILER CONTROL
Sop 6.6 kv switchboard
Time Response
condition monitoring and Fault diagnostics of centrifugal pump using data acq...
Manual english new material OT III 962-0512.pdf
Fundamental process control system Chapter2.ppt
Condition monitoring of screw compressors and induction motors in a food proc...
Ad

Recently uploaded (20)

PPTX
Construction Project Organization Group 2.pptx
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PPTX
Sustainable Sites - Green Building Construction
PDF
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PPTX
OOP with Java - Java Introduction (Basics)
PPTX
bas. eng. economics group 4 presentation 1.pptx
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PDF
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PPTX
CH1 Production IntroductoryConcepts.pptx
PDF
PPT on Performance Review to get promotions
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
DOCX
573137875-Attendance-Management-System-original
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
Construction Project Organization Group 2.pptx
Embodied AI: Ushering in the Next Era of Intelligent Systems
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
Sustainable Sites - Green Building Construction
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
CYBER-CRIMES AND SECURITY A guide to understanding
OOP with Java - Java Introduction (Basics)
bas. eng. economics group 4 presentation 1.pptx
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
Model Code of Practice - Construction Work - 21102022 .pdf
CH1 Production IntroductoryConcepts.pptx
PPT on Performance Review to get promotions
Foundation to blockchain - A guide to Blockchain Tech
Operating System & Kernel Study Guide-1 - converted.pdf
573137875-Attendance-Management-System-original
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
Ad

Week7_Chap7_multi actutaor control cylinder control

  • 1. Hydraulics & Pneumatics MCT-313 Fall 2023 – Session 2021 by Dr. Muhammad Awais Hafeez Chapter # 7 Week # 7
  • 2. A stamping operation involves two cylinders A and B working in sequence.  Cylinder A extends and brings a job under a stamping cylinder B.  Cylinder B then extends and stamps the job  Cylinder A can return back only after cylinder B has retracted fully .  A pneumatic circuit has to be developed for realizing this control task. Multiple Actuator Control Week # 7 Displacement–Event Diagram A+ B+ B- A-
  • 3.  A+ action generates sensor signal a1, which is used for B+ action.  B+ action generates sensor signal b1, which is used for B- action.  B+ action generates sensor signal b0, which is used for A- action.  A- action generates sensor signal a0, which is used for A+ action. Week # 7 Multiple Actuator Control A start signal is also required along with a0 signal for obtaining A+ action. (Signal generated due to the last control action in the sequence)
  • 4. Week # 7 Multiple Actuator Control
  • 5. Week # 7 Multiple Actuator Control  When the start push button is pressed, signal appears at port 14 of valve through sensor a0  Signal is also present at port 12 of valve, resulting in a signal conflict.  When cylinder B extends fully, sensor b1 generates an output signal at port 12 of valve  Signal is also present at port 12 of valve, resulting in a signal conflict. Look for signal conflicts
  • 6. Week # 7 Multiple Actuator Control  Idle-return Rollers  Reversing valves (memory valves)  Modules as combination of valves Elimination of signal conflicts Idle-return Rollers
  • 7. Week # 7 Multiple Actuator Control  This method is not reliable  The end position cannot be sensed accurately.  Fast control system cannot be setup. Elimination of signal conflicts
  • 8. Week # 7 Multiple Actuator Control Two of the possible designs used to remove signal conflicts through reversing valves are  Cascade Method  Shift-Register Method Elimination of signal conflicts Cascade Method Sequence of operation of cylinders can be divided into appropriate number of groups  There is a possibility of signals conflicts If any cylinder happen to appear twice in a group  Hence, sequence is divided in such a way that A+ and A- fall into different groups A+ B+ B- A-
  • 9. Week # 7 Multiple Actuator Control Two of the possible designs used to remove signal conflicts through reversing valves are  Cascade Method  Shift-Register Method Elimination of signal conflicts Cascade Method Sequence of operation of cylinders can be divided into appropriate number of groups  There is a possibility of signals conflicts If any cylinder happen to appear twice in a group  Hence, sequence is divided in such a way that A+ and A- fall into different groups A+ B+ B- A- Group 1 Group 2
  • 10. Week # 7 Multiple Actuator Control Cascade Method Number of groups increases, the number of valves required also increases Next is to divide the power supply for the control circuit into the same number of groups as for the sequence of the operation • Only one group will have supply with all other groups connected to the exhaust
  • 11. Week # 7 Multiple Actuator Control Cascade Method Initially the supply is in the last group
  • 12. Week # 7 Multiple Actuator Control
  • 13. Week # 7 Multiple Actuator Control
  • 14. END