SlideShare a Scribd company logo
Well Completion and
Intervention
Operations Training(RTC)
After the well is drilled, casing ran and cemented
in place, the well is ready for the completion
process to begin.
Well completion may be performed by the larger
drilling rig or by a smaller less expensive
completion/workover rig. Rig type would be
determined by availability and project economics.
The uncompleted well is not perforated
and is left with the casing full of liquid.
It is capped off with a valve.
To complete the well, it must be
perforated, sand control installed if
required, the tubing installed, tubing
auxiliaries and packers installed and
the tree installed.
The first step in the completion process
is to remove the valve and flange and
install the workover BOP on the well.
Operations Training(RTC)
A completion/workover rig is similar to a drilling
rig but on a reduced scale. Completion/workover
rigs have four basic systems.
1. Power System
2. Rotating System
3. Hoisting
4. Circulating System
Operations Training(RTC)
Shale Shaker
Diesel Tank-Skid Beams
Engines
Derrick
Skid-Beam
Draw Works
Work String
Elevators
Operations Training(RTC)
Cameron
Type U
Preventer
with Blind
Rams
Cameron
Type U
Preventer
with Pipe
Rams
Preparation Steps Completing a well:
1. Installing the blowout preventer
2. Filling the well with proper completion fluid
3. Perforating the well
4. Installing sand control equipment if
required
5. Running product tubing with its auxiliary
components
6. Pumping inhibited fluid in to the annulus
when required
7. Removal of the BOP stack and installing
and testing the Christmas Tree.
7 1/16”/179 mm
Hydril Annular
Preventer
Blind Rams
Pipe Rams
Cameron Type U Preventer
The type of well completion needed is dependent on several
factors.
•Zone Thickness: A few feet to hundreds of feet/hundreds of
meters.
•Reservoir Pressure: Almost zero to more than 20,000 psi
(1,406kg/cm2
).
•Reservoir Temperature: 60 ° F (16 °C) to 600 °F (315 °C) or more.
•Contaminants: Compounds like H2S and CO2 are annoying in
small amounts. In higher volumes it may require special
equipment and procedures. Above a certain point, it may not be
economically feasible to produce some zones, because of these
components.
•Unconsolidated Sand
•Water production
Operations Training(RTC)
Wells that are completed in hard rock formations or sands that
are naturally cemented together do not require sand control.
Well completed in a sand zone that has not been naturally
cemented together, (unconsolidated sand) would flow to the
surface with the produced fluids and cause serious problems.
Sand control, usually in the form of a gravel pack or pre-pack
screens are used to keep the sand in place.
• After a well is drilled and cased, equipment is installed to flow oil
and gas from the reservoir to the separation equipment. The
“completion” procedure varies with depth, pressure, expected
flow rates and other factors.
• A successful well is the result of a combination of good drilling,
completion, and production practices. Failure in any one of these
area’s could affect present or future project development.
• Poor drilling practices could result in formation damage, reduced
flow rates and possibly premature well abandonment, which in
turn would effect ultimate recovery.
Operations Training(RTC)
Completion Steps
A bit and scraper run is made to insure no cement deposits were left on
the interior walls of the casing.
If drilling mud was left in the well after the drilling process, it is replaced
with completion fluid.
If the well is not to be an open hole completion, the next step may be to
perforate the well and run the production packer.
If the well is to be a gravel pack completion, a sump packer set , the
casing perforated, a screen and packer installed, and gravel pumped.
Open hole completion wells are completed by drilling out of the end of
the casing. The target zone is penetrated, a pre-pack screen is installed
in the un-cased hole which is anchored and sealed in the casing.
Work String Or Drill String
Scraper
Bit
The rig will pick up a drill string
or a work string and make a bit
and scraper run to TD. This is
to ensure that the well bore
and casing is clean to TD.
At this point, the liquid left in
the casing by the drilling rig
will be displaced with a
specified completion fluid.
Casing Scraper
Loose unconsolidated reservoir sand will flow up
the tubing string along with reservoir fluids unless
restricted from doing so. Unconsolidated reservoirs
requires some type of sand control.
There are typically three types of sand control.
Sand consolidation - gluing of reservoir sand grains together.
Gravel pack - filter system usually required in high volume wells
with large producing intervals. A gravel pack is designed for the
sand characteristics of a specific reservoir. This system prevents
loose reservoir sand from flowing into the well.
Pre-pack screen - This system incorporates a sand
filtering material which is wrapped between an
inter and outer layer of the screen.
HES
Pre-pack
Screen
The first step in a gravel pack
completion is to set the sump packer.
This packer is set for two reasons.
1. It will be the basis for proper
placement of the gravel pack screen
across the perforations. For
accuracy in packer placement, an
electric line unit is used to set this
packer.
2. Sand grains and/or other particles
that pass through the screen fall
through the bottom of the gravel
pack assembly into a sump or rat
hole. This lessens the chances of
plugging the tubing.
Locating Device
Packer Setting
Tool
Sump Packer
Sump/Rat Hole
Perm. Packer
Packer Seal
Assemblies
Once the sump packer is set, the well
will be perforated. This may be done
with tubing conveyed guns or guns run
on electric line units. Perforating guns
are designed to penetrate the casing,
the surrounding cement, and go into
the formation, opening the reservoir to
the well bore. Perforating guns
usually do their job by means of a
shaped explosive charge.
Caution: Perforating is a critical
and potentially dangerous operation,
all guide lines must be followed.
This process may leave behind
undesired material that could impede
flow into the well bore.
Sump
Packer
Perforations
Locating
Device
r
Operations Training(RTC)
Perforation Guns
Pictured to the right are
casing and tubing
perforators.
Tubing conveyed
perforating gun
Wireline conveyed
perforating guns
Operations Training(RTC)
Perferation:
After casing is set and
cemented, the well must
be opened to the
producing zone.
Necessary holes are
opened through the
casing and cement into
the producing zone.
The perforating process may leave material
behind which may affect production
volumes, the well is usually back surged to
remove this material.
A back surge tool is run and set above the
perforations.
The back surge process causes a sudden
short term decrease in pressure at the
perforations. Damaged material in the
perforated areas caused by the shaped
charges are pulled into the casing by the
reduced pressure.
This material is circulated out of the well,
it’s volume measured and an equal volume
of clean gravel pumped into the well.
Next, the screen and gravel pack setting
and crossover tool are run. The gravel pack
sand is pumped in a gel type solution. This
solution is designed to keep sand volumes
consistent as it is pumped down the work
string.
Once the sand /gel slurry is pumped below
the screen liner hanger, it goes through a
port in the crossover tool into the annular
space between the screen and production
casing. The gel minus the sand returns to
the surface through a port in the gravel
pack assembly by crossing over into the
production casing /tubing annulus.
Pumping continues until pack sand fills the
annulus between the production casing
and the screen to a predetermined height.
The gravel packing is now complete.
The liner setting device and gravel pack
tool are pulled out of the hole.
Sump Packer
Perforations
Screen
Liner Hanger
Gravel Pack
Crossover
Tool
Screen
Liner
Hanger
Packer
After the gravel pack running
equipment is removed, the
complete gravel pack assembly
including the sump packer,
sand screen, sand and liner
hanger/packer will be in place.
The well is now ready for the
production tubing and its
components to be installed.
The production tubing which carries
fluids from the reservoir to the
christmas tree is now installed. Tubing
strings generally run from 2 3/8 “ to
5 1/2” in diameter. The tubing string
contains a number of auxiliary devices
which provide safety and environmental
protection and assist in producing and
maintaining the well.
Landing
Nipple
Gas Lift
Valves
Landing
Nipple
Surface
Controlled
Subsurface
Safety Valve
And
Hydraulic
Control Line
Proposed Completion Sketch
Auxiliary Tubing Devices
Landing nipples - Equipped with a polished
bore and internal profiles cut into the I.D., these
devices allow locking mandrels and the
attached devices to be locked and sealed in the
tubing.
Locking mandrel are flow through devices.
Landing nipples and Locking Mandrels may be
used to:
•Check tubing integrity.
•Install a down hole choke.
•Install a subsurface controlled safety valve.
•Hang off a BHP device.
Landing
Nipple
Gas Lift
Valves
Landing
Nipple
Surface
Controlled
Subsurface
Safety Valve
And
Hydraulic
Control Line
Landing
Nipple
Locking
Mandrel
Auxiliary Tubing Devices
Gas Lift Mandrels: High pressure
compressed gas from the production
casing is injected through the
mandrel and gas lift valve into the
tubing.
Gas injection lightens the
hydrostatic fluid column in the
tubing, allowing the well to flow.
Some wells are kicked off on gas lift,
others require gas lift continuously.
To date Shell has not used gas lift in
any deepwater or subsea wells.
Other methods of artificial lift are:
•Rod pumping
•Hydraulic down hole pumping
•Electrical down hole pumping
Landing
Nipple
Gas Lift
Mandrels
Landing
Nipple
Surface
Controlled
Subsurface
Safety Valve
And
Hydraulic
Control Line
Landing
Nipple
Gas Lift
Valves
Landing
Nipple
Subsurface
Safety Valve
And
Hydraulic
Control Line
Rod Pump
Hydraulic
Pumping
Systems
Surface controlled subsurface
safety valves:
Usually part of the tubing
Automatically closes if a undesirable
event or catastrophe occurs.
Set at least 100’ below the mud line
(MMS). Fail safe; normally closed
valve
Operates automatically or manually
Controlled by a small stainless steel
hydraulic line which allows hydraulic
pressure from the surface to operate
the valve.
The valve must be checked for holding
every 6 months (MMS).
Chemical injection Nipples:
Allows injection of chemical down hole
into the tubing.
If necessary, injection of hydrate
inhibition chemicals, asphaltine
inhibition chemicals, wax (paraffin)
control chemicals, and corrosion
inhibitors can be injected into the
tubing.
Down hole pressure /temperature
devices:
Provide real time wellbore pressures and
temperatures.
Auxiliary Tubing Devices
Down hole volume measurement devices:
- Usually run in high volume subsea or TLPs wells.
- Permits down-hole measurement of produced fluids.
- Eliminates large heavy top side measurement equipment.
- In multiple subsea systems, will reduce down time due to testing.
- Allows measurement before commingling subsea wells
Operations Training(RTC)
Surface Casing
Landing Base
Conductor Casing
Production Casing
Slip and seal
assembly
Production Tubing
VR Plug
Valve Removal
Tubing Hanger
Spool
Tubing Hanger
SC-SSSV Hydraulic
Control Line
Drive Pipe
Hanger Pins
Guide Pins
Christmas Tree
Well_Completion introduction an general .ppt
Operations Training(RTC)
Typical Solid Block (OCS) Tree
Tree Cap
Wireline Valve
SSV
Master Valve
Tubing Hanger Spool
Casing Valve
Choke Body
Needle Valve
Wing Valve
Subsea Tree
•Choke
•POD (Subsea Control
Module)
•Tree Valves
•Production
•Chemical
•Annulus
Tree
Wellhead
ROV Access Panel
POD (Control Module)
Subsea Tree
Tubing Head
Assembly
Tree Cap
Tubing Hanger
Tubing Hanger
ROV Tree Cap
ROV Tree Cap
Insert Choke
Insert Choke
Tree Assembly
Tree Assembly
Tubing Hanger
Tubing Hanger
Vertical Hub
Vertical Hub
for Well Jumper
for Well Jumper
Tubing Head
Tubing Head
Assembly
Assembly
Operations Training(RTC)
After a well has produced for a time, mechanical may develop.
Problems may include:
A. Damaged Tubing
•Collapsed and plugged
•Holes and split
•Parted and corroded
•Leaking Packers
B. Damaged gravel pack screens
• Collapsed
• Washed out
C. Damaged Casing
• Collapsed
• Split
• Eroded
• Parted
• Corroded
Remedial Well Operations
Remedial well work will be
required at some point in the
life of a well.
Re-completions requires a workover
rig.
If the job does not require pulling of
the tubing, through tubing equipment
may be used.
Problems may include:
•The reservoir is depleted
•Excessive gas or water production
•Mechanical problems
•The well is plugged up
Operations Training(RTC)
Mechanical problems (Tubular Damage) usually require pulling the
tubing string and its components, necessary repair’s or replacement
made and the well returned to production. With this type of
workover, the well continues to produce from the same reservoir.
Examples of non-mechanical well problems:
1. Excessive water production (expected or unexpected)
2. Excessive gas production
3. Restricted production due to formation damage
4. Increase/decrease in reservoir pressure
5. Depleted reservoir
Operations Training(RTC)
Conventional Workover/Intervention Methods:
• Require removal of Christmas tree, tubing, and other
mechanical components in the well
• In many instances, workover/intervention on a well with
reservoir problems will require completing the well in a
different reservoir
These projects must be justified, cost to do the work is
estimated, economics of the project are then determined.
Based upon this evaluation, the project is approved or
rejected.
After completion, the well is turned over to production for
unloading and bringing to full potential.
Coiled Tubing Units
A continuous small diameter tubing (generally on the
order of 1/2” to 1 1/4”/12.5mm to 31.25 mm in
diameter) which is inserted into and removed from the
well bore by means of a tubing injector and BOP which
is mounted on the christmas tree.
Designed to do remedial work on wells without
removing the christmas tree or production tubing from
the well.
They are limited in the following ways:
•Depth and pulling capabilities
•Pressure handling capabilities
•Inability to rotate the work string
•They must use down hole mud motors to drill
•Do not work well in highly deviated wells
•Not well suited for minor drilling or fishing operations
Courtesy of Halliburton Energy
Services
Courtesy of Halliburton Energy
Services
Snubbing Units
Designed to do remedial work on a well without
removal of the Christmas tree or production tubing.
This kind of a project is called a through tubing job.
Pipe, generally about 1”/ 25 mm in diameter is
inserted into and removed from the well by means of
a hydraulic ram. A small BOP is placed on top of the
tree to ensure proper well control while working is
being conducted. Snubbing operations are suited for
work on fairly deep high pressure wells.
Snubbers are capable of:
•Acidizing wells
•Drilling or washing sanded out of the tubing
•Fishing operations including milling
•Minor drilling operations by means of a hydraulic
rotating system or a down hole mud motor.
•Operating in deviated wells.
•Unloading wells by means of gas injection
•Spotting cement and doing minor squeeze jobs
Courtesy of Halliburton Energy Services
Down Hole
Mud Motor
To recomplete this well to another zone:
•A workover rig would be moved on
location
•The well would be killed and prepared
for the workover
•The tubing would be removed
•If the zone to be completed were below
the existing zone, the gravel pack would
have to be removed using typical fishing
techniques to clean out the hole.
•The perforations would be squeeze
cemented
•The new zone would be perforated and
gravel packed
•Production tubulars would be run in the
well
•The christmas tree installed and the well
would be turned over to production
personnel to be put on production
If the zone to be completed were above
the existing zone, the gravel pack would
be squeeze cemented and abandoned
using typical cementing techniques.
The new zone located above the original
zone would be perforated and gravel
packed
•Production tubulars would be run in
the well
•The christmas tree installed and the
well would be turned over to production
personnel to be put on production
Squeeze
Tool
Packer
Mill and
Spear
Box and
Tapered Taps
Junk and
Tapered
Mills
Rotary
Shoe
Surface Controlled Subsurface
Safety Valve System
SC-SSSV
Surface Controlled Subsurface
Safety Valve System
• Surface controlled subsurface safety valves
are controlled (opened & closed) from the
surface by applying and releasing hydraulic
pressure to the valve.
Surface Controlled Subsurface
Safety Valve System
• The Surface Controlled Subsurface Safety
Valve is a device installed in a well to
prevent uncontrolled well flow when
actuated.
• This type valve can be tubing or wireline
retrievable.
Surface Controlled Subsurface
Safety Valve System
• Each well has both a surface safety valve
(SSV) and a surface controlled subsurface
safety valve (SC-SSSV)
• The SSV is the primary means of shutting in
the well
• The SC-SSSV is the secondary means of
shut in
Surface Controlled Subsurface
Safety Valve System
Regulations concerning subsurface valves
• All tubing installations open to hydrocarbon-
bearing zones shall be equipped with
subsurface safety valves
• All tubing installations which are capable of
natural flow shall be equipped with a surface
control SSSV
Surface Controlled Subsurface
Safety Valve System
• Test frequencies: Every six months
• Leakage rates: 200 cc’s liquid per min. or 5
scfm gas
• The SC-SSSV shall close in not more than 2
minutes after the shut in signal has closed
the SSV
Surface Safety Valve System
Surface Controlled Subsurface
Safety Valve System
Subsurface Safety Valve
Subsurface Controlled
Subsurface Safety
Valves
SSSV
Subsurface Safety Valve
The subsurface controlled subsurface safety
valve (SSCSV) is a device installed in a well,
below the well-head, with the designed
function to prevent uncontrolled well flow
when actuated.
Subsurface Safety Valve
• These devices can be installed and retrieved
by wire-line (wire-line retrievable) and/or
pump down methods (TFL Thru-Flowline)
or be an integral part of the tubing string
(Tubing retrievable).
Subsurface Safety Valve
• The most common type in our operation is
the wire-line retrievable, which is set in a
landing nipple or on a slip lock device.
The landing nipple is generally used. The
subsurface safety valve is attached to a
mandrel which is located, locked, and
sealed inside the landing nipple. A flow
coupling should extend a min. of 3 feet
above and below the landing nipple.
Subsurface Safety Valve
• Other names given this valve are “storm
choke” or “velocity valve”. The general
principle of operation is an increased
pressure drop across the choke or
decreased tubing pressure that will cause
the valve to shut.
Subsurface Safety Valve
• These valves are set to close on velocities
higher than normal production rates. This
is generally done by installing spacers and
chokes in the valve. If improper spacers or
chokes are installed, the valve will not close
at the desired velocity.
Subsurface Safety Valve
• Leakage Rates: 200 cc liquid or 5 scfm
• Test Frequency: Every six months if not
installed in a landing and once a year for
those valves that are installed in a landing
nipple.

More Related Content

PPTX
Sand control
PDF
Chapter 10 Well Completion.pdf
PDF
Chapter_6-OCW.pdf
PDF
Chapter_6hdhdvd-OCW.pdf
PPTX
WELL COMPLETIONS.pptx
PDF
Defining Well completion
PPTX
Fundamentals of Petroleum Engineering Module 6
PPT
Section 5 - Well Completion for drilling .ppt
Sand control
Chapter 10 Well Completion.pdf
Chapter_6-OCW.pdf
Chapter_6hdhdvd-OCW.pdf
WELL COMPLETIONS.pptx
Defining Well completion
Fundamentals of Petroleum Engineering Module 6
Section 5 - Well Completion for drilling .ppt

Similar to Well_Completion introduction an general .ppt (20)

PPT
Well completion and stimulation
PDF
Sequence of well completion part 1
PDF
Sequence of well completion part 1
PDF
468288879-completion-design-apparatus tag
PPT
vdocuments.mx_well-completion-petronas.ppt
PDF
Well Completion Design.pdf
PPTX
TCD2011 - Kunne bedre kompetanse avverget Macondo-ulykken i Mexico-gulfen? v/...
PPT
introduction to completions and workovers (2)
PDF
Petroleum well completion overview
PDF
An Introduction to Well Completion Design.pdf
PPTX
Well Complection - Basic-1.pptx
PDF
Sand Control Course Version.pdf
PPTX
PTP 224 Oil & Gas Wells Production Operations and Well Testing ( LO1).pptx
PPTX
Detailed drilling
PDF
Completion and work over well control .pdf
PPTX
Lecture05.pptxfor oil and gas engineers in oil and gas industry
PDF
Baker Hughes Completion Programme Manual
PDF
1. completion sequance
PDF
Cementing well
Well completion and stimulation
Sequence of well completion part 1
Sequence of well completion part 1
468288879-completion-design-apparatus tag
vdocuments.mx_well-completion-petronas.ppt
Well Completion Design.pdf
TCD2011 - Kunne bedre kompetanse avverget Macondo-ulykken i Mexico-gulfen? v/...
introduction to completions and workovers (2)
Petroleum well completion overview
An Introduction to Well Completion Design.pdf
Well Complection - Basic-1.pptx
Sand Control Course Version.pdf
PTP 224 Oil & Gas Wells Production Operations and Well Testing ( LO1).pptx
Detailed drilling
Completion and work over well control .pdf
Lecture05.pptxfor oil and gas engineers in oil and gas industry
Baker Hughes Completion Programme Manual
1. completion sequance
Cementing well
Ad

Recently uploaded (20)

PDF
Looking into the jet cone of the neutrino-associated very high-energy blazar ...
PDF
lecture 2026 of Sjogren's syndrome l .pdf
PPTX
Science Quipper for lesson in grade 8 Matatag Curriculum
PPTX
2. Earth - The Living Planet earth and life
PDF
The scientific heritage No 166 (166) (2025)
PPTX
EPIDURAL ANESTHESIA ANATOMY AND PHYSIOLOGY.pptx
PPTX
ECG_Course_Presentation د.محمد صقران ppt
PDF
Sciences of Europe No 170 (2025)
PPTX
Vitamins & Minerals: Complete Guide to Functions, Food Sources, Deficiency Si...
PDF
Warm, water-depleted rocky exoplanets with surfaceionic liquids: A proposed c...
PDF
ELS_Q1_Module-11_Formation-of-Rock-Layers_v2.pdf
PDF
An interstellar mission to test astrophysical black holes
PDF
Biophysics 2.pdffffffffffffffffffffffffff
PPTX
famous lake in india and its disturibution and importance
DOCX
Q1_LE_Mathematics 8_Lesson 5_Week 5.docx
PPTX
POULTRY PRODUCTION AND MANAGEMENTNNN.pptx
PDF
Mastering Bioreactors and Media Sterilization: A Complete Guide to Sterile Fe...
PPTX
Pharmacology of Autonomic nervous system
PPTX
Application of enzymes in medicine (2).pptx
PPT
protein biochemistry.ppt for university classes
Looking into the jet cone of the neutrino-associated very high-energy blazar ...
lecture 2026 of Sjogren's syndrome l .pdf
Science Quipper for lesson in grade 8 Matatag Curriculum
2. Earth - The Living Planet earth and life
The scientific heritage No 166 (166) (2025)
EPIDURAL ANESTHESIA ANATOMY AND PHYSIOLOGY.pptx
ECG_Course_Presentation د.محمد صقران ppt
Sciences of Europe No 170 (2025)
Vitamins & Minerals: Complete Guide to Functions, Food Sources, Deficiency Si...
Warm, water-depleted rocky exoplanets with surfaceionic liquids: A proposed c...
ELS_Q1_Module-11_Formation-of-Rock-Layers_v2.pdf
An interstellar mission to test astrophysical black holes
Biophysics 2.pdffffffffffffffffffffffffff
famous lake in india and its disturibution and importance
Q1_LE_Mathematics 8_Lesson 5_Week 5.docx
POULTRY PRODUCTION AND MANAGEMENTNNN.pptx
Mastering Bioreactors and Media Sterilization: A Complete Guide to Sterile Fe...
Pharmacology of Autonomic nervous system
Application of enzymes in medicine (2).pptx
protein biochemistry.ppt for university classes
Ad

Well_Completion introduction an general .ppt

  • 2. Operations Training(RTC) After the well is drilled, casing ran and cemented in place, the well is ready for the completion process to begin. Well completion may be performed by the larger drilling rig or by a smaller less expensive completion/workover rig. Rig type would be determined by availability and project economics.
  • 3. The uncompleted well is not perforated and is left with the casing full of liquid. It is capped off with a valve. To complete the well, it must be perforated, sand control installed if required, the tubing installed, tubing auxiliaries and packers installed and the tree installed. The first step in the completion process is to remove the valve and flange and install the workover BOP on the well.
  • 4. Operations Training(RTC) A completion/workover rig is similar to a drilling rig but on a reduced scale. Completion/workover rigs have four basic systems. 1. Power System 2. Rotating System 3. Hoisting 4. Circulating System
  • 5. Operations Training(RTC) Shale Shaker Diesel Tank-Skid Beams Engines Derrick Skid-Beam Draw Works Work String Elevators
  • 6. Operations Training(RTC) Cameron Type U Preventer with Blind Rams Cameron Type U Preventer with Pipe Rams Preparation Steps Completing a well: 1. Installing the blowout preventer 2. Filling the well with proper completion fluid 3. Perforating the well 4. Installing sand control equipment if required 5. Running product tubing with its auxiliary components 6. Pumping inhibited fluid in to the annulus when required 7. Removal of the BOP stack and installing and testing the Christmas Tree. 7 1/16”/179 mm Hydril Annular Preventer Blind Rams Pipe Rams Cameron Type U Preventer
  • 7. The type of well completion needed is dependent on several factors. •Zone Thickness: A few feet to hundreds of feet/hundreds of meters. •Reservoir Pressure: Almost zero to more than 20,000 psi (1,406kg/cm2 ). •Reservoir Temperature: 60 ° F (16 °C) to 600 °F (315 °C) or more. •Contaminants: Compounds like H2S and CO2 are annoying in small amounts. In higher volumes it may require special equipment and procedures. Above a certain point, it may not be economically feasible to produce some zones, because of these components. •Unconsolidated Sand •Water production Operations Training(RTC)
  • 8. Wells that are completed in hard rock formations or sands that are naturally cemented together do not require sand control. Well completed in a sand zone that has not been naturally cemented together, (unconsolidated sand) would flow to the surface with the produced fluids and cause serious problems. Sand control, usually in the form of a gravel pack or pre-pack screens are used to keep the sand in place.
  • 9. • After a well is drilled and cased, equipment is installed to flow oil and gas from the reservoir to the separation equipment. The “completion” procedure varies with depth, pressure, expected flow rates and other factors. • A successful well is the result of a combination of good drilling, completion, and production practices. Failure in any one of these area’s could affect present or future project development. • Poor drilling practices could result in formation damage, reduced flow rates and possibly premature well abandonment, which in turn would effect ultimate recovery. Operations Training(RTC)
  • 10. Completion Steps A bit and scraper run is made to insure no cement deposits were left on the interior walls of the casing. If drilling mud was left in the well after the drilling process, it is replaced with completion fluid. If the well is not to be an open hole completion, the next step may be to perforate the well and run the production packer. If the well is to be a gravel pack completion, a sump packer set , the casing perforated, a screen and packer installed, and gravel pumped. Open hole completion wells are completed by drilling out of the end of the casing. The target zone is penetrated, a pre-pack screen is installed in the un-cased hole which is anchored and sealed in the casing.
  • 11. Work String Or Drill String Scraper Bit The rig will pick up a drill string or a work string and make a bit and scraper run to TD. This is to ensure that the well bore and casing is clean to TD. At this point, the liquid left in the casing by the drilling rig will be displaced with a specified completion fluid. Casing Scraper
  • 12. Loose unconsolidated reservoir sand will flow up the tubing string along with reservoir fluids unless restricted from doing so. Unconsolidated reservoirs requires some type of sand control. There are typically three types of sand control. Sand consolidation - gluing of reservoir sand grains together. Gravel pack - filter system usually required in high volume wells with large producing intervals. A gravel pack is designed for the sand characteristics of a specific reservoir. This system prevents loose reservoir sand from flowing into the well. Pre-pack screen - This system incorporates a sand filtering material which is wrapped between an inter and outer layer of the screen. HES Pre-pack Screen
  • 13. The first step in a gravel pack completion is to set the sump packer. This packer is set for two reasons. 1. It will be the basis for proper placement of the gravel pack screen across the perforations. For accuracy in packer placement, an electric line unit is used to set this packer. 2. Sand grains and/or other particles that pass through the screen fall through the bottom of the gravel pack assembly into a sump or rat hole. This lessens the chances of plugging the tubing. Locating Device Packer Setting Tool Sump Packer Sump/Rat Hole Perm. Packer Packer Seal Assemblies
  • 14. Once the sump packer is set, the well will be perforated. This may be done with tubing conveyed guns or guns run on electric line units. Perforating guns are designed to penetrate the casing, the surrounding cement, and go into the formation, opening the reservoir to the well bore. Perforating guns usually do their job by means of a shaped explosive charge. Caution: Perforating is a critical and potentially dangerous operation, all guide lines must be followed. This process may leave behind undesired material that could impede flow into the well bore. Sump Packer Perforations Locating Device
  • 15. r Operations Training(RTC) Perforation Guns Pictured to the right are casing and tubing perforators. Tubing conveyed perforating gun Wireline conveyed perforating guns
  • 16. Operations Training(RTC) Perferation: After casing is set and cemented, the well must be opened to the producing zone. Necessary holes are opened through the casing and cement into the producing zone.
  • 17. The perforating process may leave material behind which may affect production volumes, the well is usually back surged to remove this material. A back surge tool is run and set above the perforations. The back surge process causes a sudden short term decrease in pressure at the perforations. Damaged material in the perforated areas caused by the shaped charges are pulled into the casing by the reduced pressure. This material is circulated out of the well, it’s volume measured and an equal volume of clean gravel pumped into the well.
  • 18. Next, the screen and gravel pack setting and crossover tool are run. The gravel pack sand is pumped in a gel type solution. This solution is designed to keep sand volumes consistent as it is pumped down the work string. Once the sand /gel slurry is pumped below the screen liner hanger, it goes through a port in the crossover tool into the annular space between the screen and production casing. The gel minus the sand returns to the surface through a port in the gravel pack assembly by crossing over into the production casing /tubing annulus. Pumping continues until pack sand fills the annulus between the production casing and the screen to a predetermined height. The gravel packing is now complete. The liner setting device and gravel pack tool are pulled out of the hole. Sump Packer Perforations Screen Liner Hanger Gravel Pack Crossover Tool Screen Liner Hanger Packer
  • 19. After the gravel pack running equipment is removed, the complete gravel pack assembly including the sump packer, sand screen, sand and liner hanger/packer will be in place. The well is now ready for the production tubing and its components to be installed.
  • 20. The production tubing which carries fluids from the reservoir to the christmas tree is now installed. Tubing strings generally run from 2 3/8 “ to 5 1/2” in diameter. The tubing string contains a number of auxiliary devices which provide safety and environmental protection and assist in producing and maintaining the well. Landing Nipple Gas Lift Valves Landing Nipple Surface Controlled Subsurface Safety Valve And Hydraulic Control Line
  • 22. Auxiliary Tubing Devices Landing nipples - Equipped with a polished bore and internal profiles cut into the I.D., these devices allow locking mandrels and the attached devices to be locked and sealed in the tubing. Locking mandrel are flow through devices. Landing nipples and Locking Mandrels may be used to: •Check tubing integrity. •Install a down hole choke. •Install a subsurface controlled safety valve. •Hang off a BHP device. Landing Nipple Gas Lift Valves Landing Nipple Surface Controlled Subsurface Safety Valve And Hydraulic Control Line Landing Nipple Locking Mandrel
  • 23. Auxiliary Tubing Devices Gas Lift Mandrels: High pressure compressed gas from the production casing is injected through the mandrel and gas lift valve into the tubing. Gas injection lightens the hydrostatic fluid column in the tubing, allowing the well to flow. Some wells are kicked off on gas lift, others require gas lift continuously. To date Shell has not used gas lift in any deepwater or subsea wells. Other methods of artificial lift are: •Rod pumping •Hydraulic down hole pumping •Electrical down hole pumping Landing Nipple Gas Lift Mandrels Landing Nipple Surface Controlled Subsurface Safety Valve And Hydraulic Control Line
  • 25. Surface controlled subsurface safety valves: Usually part of the tubing Automatically closes if a undesirable event or catastrophe occurs. Set at least 100’ below the mud line (MMS). Fail safe; normally closed valve Operates automatically or manually Controlled by a small stainless steel hydraulic line which allows hydraulic pressure from the surface to operate the valve. The valve must be checked for holding every 6 months (MMS).
  • 26. Chemical injection Nipples: Allows injection of chemical down hole into the tubing. If necessary, injection of hydrate inhibition chemicals, asphaltine inhibition chemicals, wax (paraffin) control chemicals, and corrosion inhibitors can be injected into the tubing. Down hole pressure /temperature devices: Provide real time wellbore pressures and temperatures.
  • 27. Auxiliary Tubing Devices Down hole volume measurement devices: - Usually run in high volume subsea or TLPs wells. - Permits down-hole measurement of produced fluids. - Eliminates large heavy top side measurement equipment. - In multiple subsea systems, will reduce down time due to testing. - Allows measurement before commingling subsea wells
  • 28. Operations Training(RTC) Surface Casing Landing Base Conductor Casing Production Casing Slip and seal assembly Production Tubing VR Plug Valve Removal Tubing Hanger Spool Tubing Hanger SC-SSSV Hydraulic Control Line Drive Pipe Hanger Pins Guide Pins Christmas Tree
  • 30. Operations Training(RTC) Typical Solid Block (OCS) Tree Tree Cap Wireline Valve SSV Master Valve Tubing Hanger Spool Casing Valve Choke Body Needle Valve Wing Valve
  • 31. Subsea Tree •Choke •POD (Subsea Control Module) •Tree Valves •Production •Chemical •Annulus Tree Wellhead ROV Access Panel POD (Control Module)
  • 32. Subsea Tree Tubing Head Assembly Tree Cap Tubing Hanger Tubing Hanger
  • 33. ROV Tree Cap ROV Tree Cap Insert Choke Insert Choke Tree Assembly Tree Assembly Tubing Hanger Tubing Hanger Vertical Hub Vertical Hub for Well Jumper for Well Jumper Tubing Head Tubing Head Assembly Assembly
  • 34. Operations Training(RTC) After a well has produced for a time, mechanical may develop. Problems may include: A. Damaged Tubing •Collapsed and plugged •Holes and split •Parted and corroded •Leaking Packers B. Damaged gravel pack screens • Collapsed • Washed out C. Damaged Casing • Collapsed • Split • Eroded • Parted • Corroded
  • 35. Remedial Well Operations Remedial well work will be required at some point in the life of a well. Re-completions requires a workover rig. If the job does not require pulling of the tubing, through tubing equipment may be used. Problems may include: •The reservoir is depleted •Excessive gas or water production •Mechanical problems •The well is plugged up
  • 36. Operations Training(RTC) Mechanical problems (Tubular Damage) usually require pulling the tubing string and its components, necessary repair’s or replacement made and the well returned to production. With this type of workover, the well continues to produce from the same reservoir. Examples of non-mechanical well problems: 1. Excessive water production (expected or unexpected) 2. Excessive gas production 3. Restricted production due to formation damage 4. Increase/decrease in reservoir pressure 5. Depleted reservoir
  • 37. Operations Training(RTC) Conventional Workover/Intervention Methods: • Require removal of Christmas tree, tubing, and other mechanical components in the well • In many instances, workover/intervention on a well with reservoir problems will require completing the well in a different reservoir These projects must be justified, cost to do the work is estimated, economics of the project are then determined. Based upon this evaluation, the project is approved or rejected. After completion, the well is turned over to production for unloading and bringing to full potential.
  • 38. Coiled Tubing Units A continuous small diameter tubing (generally on the order of 1/2” to 1 1/4”/12.5mm to 31.25 mm in diameter) which is inserted into and removed from the well bore by means of a tubing injector and BOP which is mounted on the christmas tree. Designed to do remedial work on wells without removing the christmas tree or production tubing from the well. They are limited in the following ways: •Depth and pulling capabilities •Pressure handling capabilities •Inability to rotate the work string •They must use down hole mud motors to drill •Do not work well in highly deviated wells •Not well suited for minor drilling or fishing operations Courtesy of Halliburton Energy Services Courtesy of Halliburton Energy Services
  • 39. Snubbing Units Designed to do remedial work on a well without removal of the Christmas tree or production tubing. This kind of a project is called a through tubing job. Pipe, generally about 1”/ 25 mm in diameter is inserted into and removed from the well by means of a hydraulic ram. A small BOP is placed on top of the tree to ensure proper well control while working is being conducted. Snubbing operations are suited for work on fairly deep high pressure wells. Snubbers are capable of: •Acidizing wells •Drilling or washing sanded out of the tubing •Fishing operations including milling •Minor drilling operations by means of a hydraulic rotating system or a down hole mud motor. •Operating in deviated wells. •Unloading wells by means of gas injection •Spotting cement and doing minor squeeze jobs Courtesy of Halliburton Energy Services Down Hole Mud Motor
  • 40. To recomplete this well to another zone: •A workover rig would be moved on location •The well would be killed and prepared for the workover •The tubing would be removed •If the zone to be completed were below the existing zone, the gravel pack would have to be removed using typical fishing techniques to clean out the hole. •The perforations would be squeeze cemented •The new zone would be perforated and gravel packed •Production tubulars would be run in the well •The christmas tree installed and the well would be turned over to production personnel to be put on production
  • 41. If the zone to be completed were above the existing zone, the gravel pack would be squeeze cemented and abandoned using typical cementing techniques. The new zone located above the original zone would be perforated and gravel packed •Production tubulars would be run in the well •The christmas tree installed and the well would be turned over to production personnel to be put on production
  • 42. Squeeze Tool Packer Mill and Spear Box and Tapered Taps Junk and Tapered Mills Rotary Shoe
  • 43. Surface Controlled Subsurface Safety Valve System SC-SSSV
  • 44. Surface Controlled Subsurface Safety Valve System • Surface controlled subsurface safety valves are controlled (opened & closed) from the surface by applying and releasing hydraulic pressure to the valve.
  • 45. Surface Controlled Subsurface Safety Valve System • The Surface Controlled Subsurface Safety Valve is a device installed in a well to prevent uncontrolled well flow when actuated. • This type valve can be tubing or wireline retrievable.
  • 46. Surface Controlled Subsurface Safety Valve System • Each well has both a surface safety valve (SSV) and a surface controlled subsurface safety valve (SC-SSSV) • The SSV is the primary means of shutting in the well • The SC-SSSV is the secondary means of shut in
  • 47. Surface Controlled Subsurface Safety Valve System Regulations concerning subsurface valves • All tubing installations open to hydrocarbon- bearing zones shall be equipped with subsurface safety valves • All tubing installations which are capable of natural flow shall be equipped with a surface control SSSV
  • 48. Surface Controlled Subsurface Safety Valve System • Test frequencies: Every six months • Leakage rates: 200 cc’s liquid per min. or 5 scfm gas • The SC-SSSV shall close in not more than 2 minutes after the shut in signal has closed the SSV
  • 51. Subsurface Safety Valve Subsurface Controlled Subsurface Safety Valves SSSV
  • 52. Subsurface Safety Valve The subsurface controlled subsurface safety valve (SSCSV) is a device installed in a well, below the well-head, with the designed function to prevent uncontrolled well flow when actuated.
  • 53. Subsurface Safety Valve • These devices can be installed and retrieved by wire-line (wire-line retrievable) and/or pump down methods (TFL Thru-Flowline) or be an integral part of the tubing string (Tubing retrievable).
  • 54. Subsurface Safety Valve • The most common type in our operation is the wire-line retrievable, which is set in a landing nipple or on a slip lock device. The landing nipple is generally used. The subsurface safety valve is attached to a mandrel which is located, locked, and sealed inside the landing nipple. A flow coupling should extend a min. of 3 feet above and below the landing nipple.
  • 55. Subsurface Safety Valve • Other names given this valve are “storm choke” or “velocity valve”. The general principle of operation is an increased pressure drop across the choke or decreased tubing pressure that will cause the valve to shut.
  • 56. Subsurface Safety Valve • These valves are set to close on velocities higher than normal production rates. This is generally done by installing spacers and chokes in the valve. If improper spacers or chokes are installed, the valve will not close at the desired velocity.
  • 57. Subsurface Safety Valve • Leakage Rates: 200 cc liquid or 5 scfm • Test Frequency: Every six months if not installed in a landing and once a year for those valves that are installed in a landing nipple.