The document discusses why an extension of time does not automatically entitle a contractor to prolongation costs (costs incurred due to delays). It explains that an extension of time only relieves the contractor of liquidated damages payments for the period of overrun. To claim prolongation costs, the contractor must prove the delay was caused by the employer in breach of contract and actually caused the costs. The document also notes differing views on concurrent delays from multiple causes and recovering costs in such situations.