Operations Research
“
”
CES Activity On LLP and Transportation
Problems
Made By :- ADITYA ARORA
Roll No. :- 0141mba009
Class :- MBA 3A
Linear Programming
Problems
Graphic Method
Product Platinum Required/unit
(gms)
Gold Required/unit
(gms)
Profit/Unit (Rs.)
A 2 3 500
B 4 2 600
Q1) A company manufactures two types of parts which use precious metals platinum &
gold. Due to shortage of these precious metals, the government regulates the amount that
may be used per day. The relevant data with respect to supply, requirements and profits are
summarized in the table as follows:
Daily allotment of platinum & gold are 160 gm and 120 gm respectively. How should the
company divide the supply of scarce precious metals. Formulate as a LPP.
Solution Q1)
After reading the question we know this is a maximization question as we have a limited
supply of Gold and Platinum for 2 product which required the item to produce the product
Let us assume product A is x1 and product B is x2
Therefor,
Zmax = 500 x1 + 600x2
For the equation we know that Gold and Platinum daily allotment is 120gm and 160gm .
Now, for equation-1 we will take all the requirement of platinum per unit of all product witch will be
multiplied with the units to be allotted to a product (i.e., x1 and x2) and then add them with each other witch
will be less then or equal to zero(0)
i.e., 2x1+ 4x2≤ 160
Now, for equation-2 we will take all the requirement of gold per unit of all product witch will be multiplied
with the units to be allotted to a product (i.e., x1 and x2) and then add them with each other witch will be less
then or equal to zero(0)
i.e., 3x1+ 2x2≤ 120
Also a non-negativity restriction for preventing negative values i.e., x1 ,x2 ≥ 0
By the help of eq. 1 we will find out the coordinates
2x1+ 4x2≤ 160
Let take x1 =0
0+ 4x2= 160
x2= 40
Therefor, coordinates are (0,40)
Let take x2 =0
2x1+ 0 = 160
x1= 80
Therefor, coordinates are (80,0)
x1 x2
0 40
80 0
By the help of eq. 2 we will find out the coordinates
3x1+ 2x2≤ 120
Let take x1 =0
0+ 2x2= 120
x2= 60
Therefor, coordinates are (0,60)
Let take x2 =0
3x1+ 0 = 120
x1= 40
Therefor, coordinates are (40,0)
x1 x2
0 60
40 0
0
10
20
30
40
50
60
70
0 10 20 30 40 50 60 70 80 90
A
B
C
FEASIBLE AREA
From the graph we got the fishable area OABC and thehe coordinate are
We will use equation of zmax to find the quantity per product
Zmax = 500 x1 + 600x2
• For O
Zmax = 0
• For A
Zmax = 0x1 + (600*40)
Zmax = 24000
• For B
Zmax = (500*20) + (600*30)
Zmax = 28000
x1 x2
O 0 0
A 0 40
B 20 30
C 40 0
• For C
Zmax = 500*40 + 0x2
Zmax = 20000
As the value of coordinate C is the maximum, therefor, the producer should use
• For product A = 20 units of Platinum and 20 unit of Gold and
• For product B = 30 units of Platinum and 30 units of Gold
Therefor, making total of 140 units of Platinum and 120units of Gold
Any Questions
Relating To LLP
Transportation Problem
Q2) A company is producing three product P1, P2 and P3 at two of its plant situated in cities A and B. The
company plans to start a new plant in city C or in city D. the unit profits from the various plants are listed
in the table, along with the demand for various products and capacity available in each of the plants.
Plant
Product
Capacity
P1 P2 P3
A 35 24 20 600
B 30 28 25 1000
C 20 25 37 800
D 24 32 28 800
Demand 500 800 600 1900 3200
The company would set up the new plant on the bases of maximising aggregate profits from the three
cities plants. Using the transportation method determine in witch city would the plant be set up and
what would the corresponding profit be.
Solution Q2)
Step1: To check if the demand and supply are balanced
As the demand and supply are not equal we will introduce dummy column in the table to get
Supply = Demand
Plant
Product
Capacity
P1 P2 P3 Dummy
A 35 24 20 0 600
B 30 28 25 0 1000
C 20 25 37 0 800
D 24 32 28 0 800
Demand 500 800 600 1300 3200
Step2: To see if the given matrix is minimisation matrix o not
As we can see in the question it was clearly mention that the matrix given is the profit from the product
from different plant, Hence, it’s a maximisation matrix so to convert it in to minimisation matrix we have
to select the biggest profit and subtract it from every other profit to get the new matrix
Plant
Product
Capacity
P1 P2 P3 Dummy
A 35 24 20 0 600
B 30 28 25 0 1000
C 20 25 37 0 800
D 24 32 28 0 800
Demand 500 800 600 1300 3200
The biggest
profit given in
the table
Plant
Product
Capacity
P1 P2 P3 Dummy
A 2 13 17 37 600
B 7 9 12 37 1000
C 17 12 0 37 800
D 13 5 9 37 800
Demand 500 800 600 1300 3200
Step3: Using VAM method to solve
Plant
Product
Capacity Penalties
P1 P2 P3 Dummy
A 2 13 17 37 600 11
B 7 9 12 37 1000 2
C 17 12 0(600) 37 800 200 12
D 13 5 9 37 800 4
Demand 500 800 600 1300
3200
Penalties
5 4 9 0
Step3: Using VAM method to solve
Plant
Product
Capacity Penalties
P1 P2 P3 Dummy
A 2(500) 13 17 37 600 100 11 11
B 7 9 12 37 1000 2 2
C 17 12 0(600) 37 800 200 12 5
D 13 5 9 37 800 4 8
Demand 500 800 600 1300
3200
Penalties
5 4 9 0
5 4 X 0
Step3: Using VAM method to solve
Plant
Product
Capacity Penalties
P1 P2 P3 Dummy
A 2(500) 13 17 37 600 100 11 11 24
B 7 9 12 37 1000 2 2 28
C 17 12 0(600) 37 800 200 12 5 25
D 13 5(800) 9 37 800 4 8 32
Demand 500 800 600 1300
3200
Penalties
5 4 9 0
5 4 X 0
X 4 X 0
Step3: Using VAM method to solve
Plant
Product Capacit
y
Penalties
P1 P2 P3 Dummy
A 2(500) 13 17 37 600 100 11 11 24 37
B 7 9 12 37(1000) 1000 2 2 28 37
C 17 12 0(600) 37 800 200 12 5 25 37
D 13 5(800) 9 37 800 4 8 32 X
Demand 500 800 600 1300 300
3200
Penalties
5 4 9 0
5 4 X 0
X 4 X 0
X X X 0
Step3: Using VAM method to solve
Plant
Product Capacit
y
Penalties
P1 P2 P3 Dummy
A 2(500) 13 17 37(100) 600 100 11 11 24 37
B 7 9 12 37(1000) 1000 2 2 28 37
C 17 12 0(600) 37(200) 800 200 12 5 25 37
D 13 5(800) 9 37 800 4 8 32 X
Demand 500 800 600 1300 300
3200
Penalties
5 4 9 0
5 4 X 0
X 4 X 0
X X X 0
Step3: Using VAM method to solve
Plant
Product
Capacity
P1 P2 P3 Dummy
A 2(500) 13 17 37(100) 600
B 7 9 12 37(1000) 1000
C 17 12 0(600) 37(200) 800
D 13 5(800) 9 37 800
Demand 500 800 600 1300 3200
Step4(a) : Feasibility test to check if the matrix is feasible or not
The test id done by using formula No. of occupied cells = m+n-1
Where, m = no. of rows and n = no. of columns
No. of occupied cells = 4+4-1=7
But there are only 6 occupied cells. Hence the matrix is not feasible.
Plant
Product
Capacity
P1 P2 P3 Dummy
A 2(500) 13 17 37(100) 600
B 7 9 12 37(1000) 1000
C 17 12 0(600) 37(200) 800
D 13 5(800) 9 37 800
Demand 500 800 600 1300 3200
Step4(b) : Introducing EPSILON (e)
Epsilon is used to make a unoccupied cell into occupied cells and its vale is near to zero or nil
It is placed on lowest value in the matrix by keeping in mind 2 things
i) It should be introduced at least coast unoccupied cell
ii) It should not form a loop with other occupied sell. If it form a loop at the least cost then move to the
second least cost .
Plant
Product
Capacity
P1 P2 P3 Dummy
A 2(500) 13 17 37(100) 600
B 7 9(e) 12 37(1000) 1000
C 17 12 0(600) 37(200) 800
D 13 5(800) 9 37 800
Demand 500 800 600 1300 3200
Step5: Finding the value of Ui and Vj
The formula for finding them is Cij = Ui + Vj
Let us assume U1 = 0
Plant
Product
Capacity
P1 P2 P3 Dummy
A 2(500) 13 17 37(100) 600 U1=0
B 7 9(e) 12 37(1000) 1000 U2=0
C 17 12 0(600) 37(200) 800 U3=0
D 13 5(800) 9 37 800 U4=-4
Demand
500 800 600 1300
3200
V1=2 V2=9 V3=0 V4=37
Step6: Optimal Test
Formula for this test is
Unoccupied cells = Ui + Vj - Cij
• C12(13) = U1 + V2 – C13 = 0+9-13=(-4)
• C13(17) = U1 + V3 – C13 = 0+0-17=(-17)
• C21(7) = U2 + V1 – C21 = 0+2-7=(-5)
• C23(12) = U2 + V3 – C23 = 0+0-12=(-12)
• C31(17) = U3 + V1 – C31 = 0+2-17=(-15)
• C32(12) = U3 + V2 – C32 = 0+9-12=(-3)
• C41 (13) = U4 + V1 – C41 = (-4)+2-13=(-15)
Step6: Optimal Test
Formula for this test is
Unoccupied cells = Ui + Vj - Cij
• C43 (9) = U4 + V3 – C43 = (-4)+0-9=(-13)
• C44 (37) = U4 + V4 – C44 = (-4)+37-37=(-4)
As all the values of optimal cost is negative
or zero, Therefor, the new shold be set up
in
If we take cities A,B and C the profit will be
Total profit (ABC) = (35*500)+(0*100)+(28*e)+(0*1000)+(37*600)+(0*200)= 17500+0+0+0+22200+0 =39700
If we take cities A,B and D the profit will be
Total profit (ABD) = (35*500)+(0*100)+(28*e)+(0*1000)+(32*800)= 17500+0+0+0+25600 =43100
• As the Profit earned is more in cities ABD then in cities ABC i.e., 43100 and
39700 respectively
• Therefor, the new plant should be setup in city D rather then in City C
Thank You
Any Questions

More Related Content

PPTX
Special Cases in Simplex Method
PPTX
Lpp simplex method
PPT
FINAL PROJECT PRSENTATION2
PPTX
Leadership Qualities of Elon Musk and Learnings
PDF
Industrial Relations in Nepal : An Institutional Analysis
PPTX
Corporate Social Responsibility Case Study: Coca Cola India
PPTX
Be final ppt
PPTX
Whistle blowing
Special Cases in Simplex Method
Lpp simplex method
FINAL PROJECT PRSENTATION2
Leadership Qualities of Elon Musk and Learnings
Industrial Relations in Nepal : An Institutional Analysis
Corporate Social Responsibility Case Study: Coca Cola India
Be final ppt
Whistle blowing

What's hot (20)

PDF
Coca-Cola India Case Study
PPTX
A study on recruitment & selection process
PPTX
LEAST COST METHOD
PPT
Bba 3274 qm week 9 transportation and assignment models
PPTX
Difference between CSR and Corporate Philanthropy
DOC
Procedure Of Simplex Method
PPT
Business Training Strategies
PDF
3. linear programming senstivity analysis
PPTX
Cement industry Pakistan
DOC
Performance appraisal & employee satisfaction in pharmaceutical industry in b...
PPTX
Transportation Problem- Stepping Stone Method
PPTX
Ethical principles in business
PPTX
Transportation problems
PPTX
Developing an Effective Ethics Program
DOCX
Impact of incentives on motivation level of employee (2)
PPTX
Human Resource Management COCA COLA
PPTX
Game theory
PDF
Ethical decision making in business
PPTX
Organizational values and their impact on strategy
PPTX
Engro foods
Coca-Cola India Case Study
A study on recruitment & selection process
LEAST COST METHOD
Bba 3274 qm week 9 transportation and assignment models
Difference between CSR and Corporate Philanthropy
Procedure Of Simplex Method
Business Training Strategies
3. linear programming senstivity analysis
Cement industry Pakistan
Performance appraisal & employee satisfaction in pharmaceutical industry in b...
Transportation Problem- Stepping Stone Method
Ethical principles in business
Transportation problems
Developing an Effective Ethics Program
Impact of incentives on motivation level of employee (2)
Human Resource Management COCA COLA
Game theory
Ethical decision making in business
Organizational values and their impact on strategy
Engro foods
Ad

Viewers also liked (10)

PPTX
Assignment Problem
DOCX
Half + half 1000 acre community forest
PDF
Lesson 35: Game Theory and Linear Programming
PPTX
Operation research and its application
PPTX
Solving Transportation Problem in Operations Research
PPTX
PPT on types of solution
PPTX
Transportation Problem in Operational Research
PPTX
Linear programming - Model formulation, Graphical Method
PPTX
Transportation Problem
PPTX
applications of operation research in business
Assignment Problem
Half + half 1000 acre community forest
Lesson 35: Game Theory and Linear Programming
Operation research and its application
Solving Transportation Problem in Operations Research
PPT on types of solution
Transportation Problem in Operational Research
Linear programming - Model formulation, Graphical Method
Transportation Problem
applications of operation research in business
Ad

Similar to LLP and Transportation problems solution (20)

DOCX
Ejercicios y problemas sobre maximización y minimización por el método gráfico
PDF
Chapter 13 solutions_to_exercises (engineering circuit analysis 7th)
PDF
Transportation And Assignment Problems - Operations Research
 
PDF
Optimización de recursos en la confección de overoles
DOCX
Practice topic 9 - answers (1)
PPT
VAM and MODI Method in Solving Transportation Problems
PDF
Transportation and transshipment problems
PPTX
Transportation Problem
PPTX
Episode 39 : Hopper Design
PPT
Production scheduling
PDF
Barkha gupta 010012_mms.docx
PDF
Copy of mpc 22-04-2018 jee adv-p-1 _ 2_cc_ans _ sol
PDF
Time series Forecasting
DOCX
Ejerciciooo3
PPTX
Coefficient of variation
PDF
Eee498 assignment
PPTX
Vogel's Approximation Method
PPTX
uses of Modi Method in operation research
DOCX
Supply Chain Optimization Projects
Ejercicios y problemas sobre maximización y minimización por el método gráfico
Chapter 13 solutions_to_exercises (engineering circuit analysis 7th)
Transportation And Assignment Problems - Operations Research
 
Optimización de recursos en la confección de overoles
Practice topic 9 - answers (1)
VAM and MODI Method in Solving Transportation Problems
Transportation and transshipment problems
Transportation Problem
Episode 39 : Hopper Design
Production scheduling
Barkha gupta 010012_mms.docx
Copy of mpc 22-04-2018 jee adv-p-1 _ 2_cc_ans _ sol
Time series Forecasting
Ejerciciooo3
Coefficient of variation
Eee498 assignment
Vogel's Approximation Method
uses of Modi Method in operation research
Supply Chain Optimization Projects

Recently uploaded (20)

PDF
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PPTX
Pharma ospi slides which help in ospi learning
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
Insiders guide to clinical Medicine.pdf
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PPTX
human mycosis Human fungal infections are called human mycosis..pptx
PDF
TR - Agricultural Crops Production NC III.pdf
PPTX
Renaissance Architecture: A Journey from Faith to Humanism
PPTX
Pharmacology of Heart Failure /Pharmacotherapy of CHF
PDF
2.FourierTransform-ShortQuestionswithAnswers.pdf
PPTX
Institutional Correction lecture only . . .
PPTX
Lesson notes of climatology university.
PPTX
Microbial diseases, their pathogenesis and prophylaxis
PPTX
PPH.pptx obstetrics and gynecology in nursing
PDF
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PDF
Complications of Minimal Access Surgery at WLH
PDF
Computing-Curriculum for Schools in Ghana
PDF
Anesthesia in Laparoscopic Surgery in India
PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
Pharma ospi slides which help in ospi learning
Final Presentation General Medicine 03-08-2024.pptx
Insiders guide to clinical Medicine.pdf
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
human mycosis Human fungal infections are called human mycosis..pptx
TR - Agricultural Crops Production NC III.pdf
Renaissance Architecture: A Journey from Faith to Humanism
Pharmacology of Heart Failure /Pharmacotherapy of CHF
2.FourierTransform-ShortQuestionswithAnswers.pdf
Institutional Correction lecture only . . .
Lesson notes of climatology university.
Microbial diseases, their pathogenesis and prophylaxis
PPH.pptx obstetrics and gynecology in nursing
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
Supply Chain Operations Speaking Notes -ICLT Program
Complications of Minimal Access Surgery at WLH
Computing-Curriculum for Schools in Ghana
Anesthesia in Laparoscopic Surgery in India
Chapter 2 Heredity, Prenatal Development, and Birth.pdf

LLP and Transportation problems solution

  • 2. “ ” CES Activity On LLP and Transportation Problems Made By :- ADITYA ARORA Roll No. :- 0141mba009 Class :- MBA 3A
  • 4. Product Platinum Required/unit (gms) Gold Required/unit (gms) Profit/Unit (Rs.) A 2 3 500 B 4 2 600 Q1) A company manufactures two types of parts which use precious metals platinum & gold. Due to shortage of these precious metals, the government regulates the amount that may be used per day. The relevant data with respect to supply, requirements and profits are summarized in the table as follows: Daily allotment of platinum & gold are 160 gm and 120 gm respectively. How should the company divide the supply of scarce precious metals. Formulate as a LPP.
  • 5. Solution Q1) After reading the question we know this is a maximization question as we have a limited supply of Gold and Platinum for 2 product which required the item to produce the product Let us assume product A is x1 and product B is x2 Therefor, Zmax = 500 x1 + 600x2
  • 6. For the equation we know that Gold and Platinum daily allotment is 120gm and 160gm . Now, for equation-1 we will take all the requirement of platinum per unit of all product witch will be multiplied with the units to be allotted to a product (i.e., x1 and x2) and then add them with each other witch will be less then or equal to zero(0) i.e., 2x1+ 4x2≤ 160 Now, for equation-2 we will take all the requirement of gold per unit of all product witch will be multiplied with the units to be allotted to a product (i.e., x1 and x2) and then add them with each other witch will be less then or equal to zero(0) i.e., 3x1+ 2x2≤ 120 Also a non-negativity restriction for preventing negative values i.e., x1 ,x2 ≥ 0
  • 7. By the help of eq. 1 we will find out the coordinates 2x1+ 4x2≤ 160 Let take x1 =0 0+ 4x2= 160 x2= 40 Therefor, coordinates are (0,40) Let take x2 =0 2x1+ 0 = 160 x1= 80 Therefor, coordinates are (80,0) x1 x2 0 40 80 0
  • 8. By the help of eq. 2 we will find out the coordinates 3x1+ 2x2≤ 120 Let take x1 =0 0+ 2x2= 120 x2= 60 Therefor, coordinates are (0,60) Let take x2 =0 3x1+ 0 = 120 x1= 40 Therefor, coordinates are (40,0) x1 x2 0 60 40 0
  • 9. 0 10 20 30 40 50 60 70 0 10 20 30 40 50 60 70 80 90 A B C FEASIBLE AREA
  • 10. From the graph we got the fishable area OABC and thehe coordinate are We will use equation of zmax to find the quantity per product Zmax = 500 x1 + 600x2 • For O Zmax = 0 • For A Zmax = 0x1 + (600*40) Zmax = 24000 • For B Zmax = (500*20) + (600*30) Zmax = 28000 x1 x2 O 0 0 A 0 40 B 20 30 C 40 0 • For C Zmax = 500*40 + 0x2 Zmax = 20000
  • 11. As the value of coordinate C is the maximum, therefor, the producer should use • For product A = 20 units of Platinum and 20 unit of Gold and • For product B = 30 units of Platinum and 30 units of Gold Therefor, making total of 140 units of Platinum and 120units of Gold
  • 14. Q2) A company is producing three product P1, P2 and P3 at two of its plant situated in cities A and B. The company plans to start a new plant in city C or in city D. the unit profits from the various plants are listed in the table, along with the demand for various products and capacity available in each of the plants. Plant Product Capacity P1 P2 P3 A 35 24 20 600 B 30 28 25 1000 C 20 25 37 800 D 24 32 28 800 Demand 500 800 600 1900 3200 The company would set up the new plant on the bases of maximising aggregate profits from the three cities plants. Using the transportation method determine in witch city would the plant be set up and what would the corresponding profit be.
  • 15. Solution Q2) Step1: To check if the demand and supply are balanced As the demand and supply are not equal we will introduce dummy column in the table to get Supply = Demand Plant Product Capacity P1 P2 P3 Dummy A 35 24 20 0 600 B 30 28 25 0 1000 C 20 25 37 0 800 D 24 32 28 0 800 Demand 500 800 600 1300 3200
  • 16. Step2: To see if the given matrix is minimisation matrix o not As we can see in the question it was clearly mention that the matrix given is the profit from the product from different plant, Hence, it’s a maximisation matrix so to convert it in to minimisation matrix we have to select the biggest profit and subtract it from every other profit to get the new matrix Plant Product Capacity P1 P2 P3 Dummy A 35 24 20 0 600 B 30 28 25 0 1000 C 20 25 37 0 800 D 24 32 28 0 800 Demand 500 800 600 1300 3200 The biggest profit given in the table
  • 17. Plant Product Capacity P1 P2 P3 Dummy A 2 13 17 37 600 B 7 9 12 37 1000 C 17 12 0 37 800 D 13 5 9 37 800 Demand 500 800 600 1300 3200
  • 18. Step3: Using VAM method to solve Plant Product Capacity Penalties P1 P2 P3 Dummy A 2 13 17 37 600 11 B 7 9 12 37 1000 2 C 17 12 0(600) 37 800 200 12 D 13 5 9 37 800 4 Demand 500 800 600 1300 3200 Penalties 5 4 9 0
  • 19. Step3: Using VAM method to solve Plant Product Capacity Penalties P1 P2 P3 Dummy A 2(500) 13 17 37 600 100 11 11 B 7 9 12 37 1000 2 2 C 17 12 0(600) 37 800 200 12 5 D 13 5 9 37 800 4 8 Demand 500 800 600 1300 3200 Penalties 5 4 9 0 5 4 X 0
  • 20. Step3: Using VAM method to solve Plant Product Capacity Penalties P1 P2 P3 Dummy A 2(500) 13 17 37 600 100 11 11 24 B 7 9 12 37 1000 2 2 28 C 17 12 0(600) 37 800 200 12 5 25 D 13 5(800) 9 37 800 4 8 32 Demand 500 800 600 1300 3200 Penalties 5 4 9 0 5 4 X 0 X 4 X 0
  • 21. Step3: Using VAM method to solve Plant Product Capacit y Penalties P1 P2 P3 Dummy A 2(500) 13 17 37 600 100 11 11 24 37 B 7 9 12 37(1000) 1000 2 2 28 37 C 17 12 0(600) 37 800 200 12 5 25 37 D 13 5(800) 9 37 800 4 8 32 X Demand 500 800 600 1300 300 3200 Penalties 5 4 9 0 5 4 X 0 X 4 X 0 X X X 0
  • 22. Step3: Using VAM method to solve Plant Product Capacit y Penalties P1 P2 P3 Dummy A 2(500) 13 17 37(100) 600 100 11 11 24 37 B 7 9 12 37(1000) 1000 2 2 28 37 C 17 12 0(600) 37(200) 800 200 12 5 25 37 D 13 5(800) 9 37 800 4 8 32 X Demand 500 800 600 1300 300 3200 Penalties 5 4 9 0 5 4 X 0 X 4 X 0 X X X 0
  • 23. Step3: Using VAM method to solve Plant Product Capacity P1 P2 P3 Dummy A 2(500) 13 17 37(100) 600 B 7 9 12 37(1000) 1000 C 17 12 0(600) 37(200) 800 D 13 5(800) 9 37 800 Demand 500 800 600 1300 3200
  • 24. Step4(a) : Feasibility test to check if the matrix is feasible or not The test id done by using formula No. of occupied cells = m+n-1 Where, m = no. of rows and n = no. of columns No. of occupied cells = 4+4-1=7 But there are only 6 occupied cells. Hence the matrix is not feasible. Plant Product Capacity P1 P2 P3 Dummy A 2(500) 13 17 37(100) 600 B 7 9 12 37(1000) 1000 C 17 12 0(600) 37(200) 800 D 13 5(800) 9 37 800 Demand 500 800 600 1300 3200
  • 25. Step4(b) : Introducing EPSILON (e) Epsilon is used to make a unoccupied cell into occupied cells and its vale is near to zero or nil It is placed on lowest value in the matrix by keeping in mind 2 things i) It should be introduced at least coast unoccupied cell ii) It should not form a loop with other occupied sell. If it form a loop at the least cost then move to the second least cost . Plant Product Capacity P1 P2 P3 Dummy A 2(500) 13 17 37(100) 600 B 7 9(e) 12 37(1000) 1000 C 17 12 0(600) 37(200) 800 D 13 5(800) 9 37 800 Demand 500 800 600 1300 3200
  • 26. Step5: Finding the value of Ui and Vj The formula for finding them is Cij = Ui + Vj Let us assume U1 = 0 Plant Product Capacity P1 P2 P3 Dummy A 2(500) 13 17 37(100) 600 U1=0 B 7 9(e) 12 37(1000) 1000 U2=0 C 17 12 0(600) 37(200) 800 U3=0 D 13 5(800) 9 37 800 U4=-4 Demand 500 800 600 1300 3200 V1=2 V2=9 V3=0 V4=37
  • 27. Step6: Optimal Test Formula for this test is Unoccupied cells = Ui + Vj - Cij • C12(13) = U1 + V2 – C13 = 0+9-13=(-4) • C13(17) = U1 + V3 – C13 = 0+0-17=(-17) • C21(7) = U2 + V1 – C21 = 0+2-7=(-5) • C23(12) = U2 + V3 – C23 = 0+0-12=(-12) • C31(17) = U3 + V1 – C31 = 0+2-17=(-15) • C32(12) = U3 + V2 – C32 = 0+9-12=(-3) • C41 (13) = U4 + V1 – C41 = (-4)+2-13=(-15)
  • 28. Step6: Optimal Test Formula for this test is Unoccupied cells = Ui + Vj - Cij • C43 (9) = U4 + V3 – C43 = (-4)+0-9=(-13) • C44 (37) = U4 + V4 – C44 = (-4)+37-37=(-4) As all the values of optimal cost is negative or zero, Therefor, the new shold be set up in
  • 29. If we take cities A,B and C the profit will be Total profit (ABC) = (35*500)+(0*100)+(28*e)+(0*1000)+(37*600)+(0*200)= 17500+0+0+0+22200+0 =39700 If we take cities A,B and D the profit will be Total profit (ABD) = (35*500)+(0*100)+(28*e)+(0*1000)+(32*800)= 17500+0+0+0+25600 =43100
  • 30. • As the Profit earned is more in cities ABD then in cities ABC i.e., 43100 and 39700 respectively • Therefor, the new plant should be setup in city D rather then in City C