CRANE DEMOBILIZATION
CRANEDEMOBILIZATION
Location
Sattahip, Thailand
Duration
1 day
Crane Specifications Base Unit
Length 			8.36m
Width			6.7m
Height			3.82m
Weight incl. base boom	 41t
Weight excl. base boom	 38t
Boom & Boom Top
Length			44m
Width			2m
Height			2.1m
Weight 			7.92t
Equipment/Services Used
220 Ton mobile crane
4 Flat bed trailers
2 Low loader trailers
Lifting slings
Shackles
Police escort
SCOPE
To provide demobilization of a KOBELCO CKE1800
Crawler crane from an operations barge at Sattahip
Port,Thailand. CEA also provided transportation to
their facility in Laem Chabang and consolidation of
the cargo until ready for shipping to Singapore.
PROCEDURE
A CEA 220 Ton crane moved into position alongside the barge.
Counterweights for the crane were installed. Operatives removed
the hook block and unfastened the bridle section from the main
boom. The crawler cranes 10 counter weights were lifted and
removed one at a time and placed on three CEA flatbed trailers.
The next crane section removed was the counter weight holder
this was loaded on to a CEA low loader.
The CEA crane was moved further along the barge to lift the main
boom. The main boom comprised of five sections, four insert
booms and one boom top. Lifting slings were secured in four key
lift points to compensate for the heavy boom top section. The
crane lifted the complete boom and lowered it on to the port.
CEA operatives removed the boom pins and dismantled the
boom into five sections. The boom top was secured in place on a
low loader trailer, each of the four insert booms were placed and
secured on separate flatbed trailers.
CASE STUDY		 CS006
Crane Demobilization 1/2
CRANEDEMOBILIZATION
CEA PROJECT LOGISTICS
41/13 M1 AO-UDOM ROAD
TUNGSUNGKHLA
SRI RACHA
CHONBURI 20230
THAILAND
+66 38 354 019
www.ceaprojects.com
The crane was once again moved to facilitate the demobilization,
both tracks on the crawler section were unpinned and lifted on
to a low loader trailer and secured. Walkway steps attached to the
crawler section were removed and secured on a flatbed truck.
The only section remaining on the barge was the crane base with
boom base attached. Operatives retracted and lowered the main
bridle section and slings were attached to the lift points. The CEA
crane lifted the base  boom on to the port floor below. The cranes
operative then retracted all supports and lowered the boom base
ready for transportation. The crane base section was lifted on to
a low loader trailer and secured in place. The trailer with police
escort made the journey to CEA’s Cargo Consolidation Facility in
Laem Chabang to await shipping to Singapore.
CASE STUDY		 CS006
Crane Demobilization 2/2
COMPLETE BOOM LIFTED ON TO PORT
CEA TEAM DISMANTLE THE BOOM SECTIONS
BRIDLE UNFASTENED FROM MAIN BOOM
TRACKS FROM THE CRAWLER SECTION
CRANE BASE WITH BOOM BASE ATTACHED AND BRIDLE RETRACTED
CRANE BASE WITH BOOM LOWERED SECURED AND READY FOR TRANSPORTATION

More Related Content

PDF
Specialized Lifting
PDF
2009 Face Conference Orosha Cranes Wooley
PPTX
selection operation and maintainance of mobile cranes ( for education purpose...
PDF
Safe use of Mobile Cranes
PDF
Seahawk Helicopter Transportation
PPTX
Forklift Training General
PPT
Fork Lift Training
DOCX
Paul CV 2017-2
Specialized Lifting
2009 Face Conference Orosha Cranes Wooley
selection operation and maintainance of mobile cranes ( for education purpose...
Safe use of Mobile Cranes
Seahawk Helicopter Transportation
Forklift Training General
Fork Lift Training
Paul CV 2017-2

What's hot (17)

PPT
Forklift training
PPTX
Crane Incident Handbook
PPTX
2016 CRW - An inside look at Kiewit's Crane & Rigging Management System
PPSX
RusselSmith Group Service Portfolio
DOCX
Emmanuel Uchenna Isiwu - Acergy Polaris
PPT
presentation on mobile cranes
DOCX
Rake maintenance (C&W Depot AGC ) Indian Railways
PPTX
Mobile crane safety rules
PPTX
Basic load out methodologies introduction
PPTX
Safe operating of forklift
PDF
2009 Face Conference Wa Crane Rules Sjostrom
PPT
Crane safety
PDF
Hi Rail Safety Alert Issue 023
PPT
Truck crane training bill brown
DOC
Gennadiy CV
PPT
Forklift training - refresher course
PDF
Paul French Resume 1
Forklift training
Crane Incident Handbook
2016 CRW - An inside look at Kiewit's Crane & Rigging Management System
RusselSmith Group Service Portfolio
Emmanuel Uchenna Isiwu - Acergy Polaris
presentation on mobile cranes
Rake maintenance (C&W Depot AGC ) Indian Railways
Mobile crane safety rules
Basic load out methodologies introduction
Safe operating of forklift
2009 Face Conference Wa Crane Rules Sjostrom
Crane safety
Hi Rail Safety Alert Issue 023
Truck crane training bill brown
Gennadiy CV
Forklift training - refresher course
Paul French Resume 1
Ad

Similar to Crane Demobilization (20)

PDF
Dual Penetrator Catamaran Launch
PDF
Technical Installation
PDF
Injection Mould Demob & Export
PDF
CEA Myanmar - Bottle Washer Relocation
PDF
Power Plant Demobilisation
PDF
Catamaran Transport & Export
PPTX
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
PPTX
Types of cranes
PDF
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
PPT
Liftingproedure
PPT
Tower Crane PPT (Lite Version).ppt To be utilized after taking permission fro...
PDF
Heliotrope 65 Catamaran Launch
PPT
Lifting & procedure
PPT
Industrial safety of lifting & procedure
PDF
Syncrolift (shiplift)
PDF
Types of cranes
PPTX
Construction Equipment -Crane - Hoisting equipment
PPTX
Crane 123
PDF
heavylift and rigging.pdf
PPTX
lifting device & tackles.pptx
Dual Penetrator Catamaran Launch
Technical Installation
Injection Mould Demob & Export
CEA Myanmar - Bottle Washer Relocation
Power Plant Demobilisation
Catamaran Transport & Export
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
Types of cranes
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
Liftingproedure
Tower Crane PPT (Lite Version).ppt To be utilized after taking permission fro...
Heliotrope 65 Catamaran Launch
Lifting & procedure
Industrial safety of lifting & procedure
Syncrolift (shiplift)
Types of cranes
Construction Equipment -Crane - Hoisting equipment
Crane 123
heavylift and rigging.pdf
lifting device & tackles.pptx
Ad

More from CEA Project Logistics (20)

PDF
CEA & Fagioli Italy
PDF
Drill Rig Transportation
PDF
Bottle Blower Installation
PDF
CEA Project Logistics Brochure 2016
PDF
Bottle Manufacturing Plant, Assembly & Installation
PDF
Drill Pipe Storage & Transportation
PDF
CEA Ao-Udom Facility
PDF
Steel Handling & Consolidation
PDF
CEA SURELIFT Brochure 2015
PDF
CEA Project Logistics News Articles
PDF
Technical Lifting
PDF
Warehousing & Storage
PDF
Fleet & Equipment
PDF
Break Bulk Consolidation
PDF
DAFF/AQIS Quarantine Project
PDF
CEA Project Logistics Myanmar
PDF
VpCI Cortec Preservation
PDF
Cleaning & Quarantine
PDF
The Asian Marshalling Yard
PDF
CEA Quarantine Management
CEA & Fagioli Italy
Drill Rig Transportation
Bottle Blower Installation
CEA Project Logistics Brochure 2016
Bottle Manufacturing Plant, Assembly & Installation
Drill Pipe Storage & Transportation
CEA Ao-Udom Facility
Steel Handling & Consolidation
CEA SURELIFT Brochure 2015
CEA Project Logistics News Articles
Technical Lifting
Warehousing & Storage
Fleet & Equipment
Break Bulk Consolidation
DAFF/AQIS Quarantine Project
CEA Project Logistics Myanmar
VpCI Cortec Preservation
Cleaning & Quarantine
The Asian Marshalling Yard
CEA Quarantine Management

Recently uploaded (20)

PDF
Kishore Vora - Best CFO in India to watch in 2025.pdf
PDF
Susan Semmelmann: Enriching the Lives of others through her Talents and Bless...
DOCX
Center Enamel Powering Innovation and Resilience in the Italian Chemical Indu...
DOCX
Center Enamel A Strategic Partner for the Modernization of Georgia's Chemical...
PPTX
Understanding Procurement Strategies.pptx Your score increases as you pick a ...
PPTX
IITM - FINAL Option - 01 - 12.08.25.pptx
PPTX
Chapter 2 strategic Presentation (6).pptx
PPTX
IMM marketing mix of four ps give fjcb jjb
PPTX
Market and Demand Analysis.pptx for Management students
PDF
Satish NS: Fostering Innovation and Sustainability: Haier India’s Customer-Ce...
PDF
Vinod Bhatt - Most Inspiring Supply Chain Leader in India 2025.pdf
PPTX
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
PDF
Middle East's Most Impactful Business Leaders to Follow in 2025
PDF
#1 Safe and Secure Verified Cash App Accounts for Purchase.pdf
PDF
income tax laws notes important pakistan
PDF
Tortilla Mexican Grill 发射点犯得上发射点发生发射点犯得上发生
PPTX
33ABJFA6556B1ZP researhchzfrsdfasdfsadzd
PDF
Engaging Stakeholders in Policy Discussions: A Legal Framework (www.kiu.ac.ug)
PDF
Robin Fischer: A Visionary Leader Making a Difference in Healthcare, One Day ...
PDF
Value-based IP Management at Siemens: A Cross-Divisional Analysis
Kishore Vora - Best CFO in India to watch in 2025.pdf
Susan Semmelmann: Enriching the Lives of others through her Talents and Bless...
Center Enamel Powering Innovation and Resilience in the Italian Chemical Indu...
Center Enamel A Strategic Partner for the Modernization of Georgia's Chemical...
Understanding Procurement Strategies.pptx Your score increases as you pick a ...
IITM - FINAL Option - 01 - 12.08.25.pptx
Chapter 2 strategic Presentation (6).pptx
IMM marketing mix of four ps give fjcb jjb
Market and Demand Analysis.pptx for Management students
Satish NS: Fostering Innovation and Sustainability: Haier India’s Customer-Ce...
Vinod Bhatt - Most Inspiring Supply Chain Leader in India 2025.pdf
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
Middle East's Most Impactful Business Leaders to Follow in 2025
#1 Safe and Secure Verified Cash App Accounts for Purchase.pdf
income tax laws notes important pakistan
Tortilla Mexican Grill 发射点犯得上发射点发生发射点犯得上发生
33ABJFA6556B1ZP researhchzfrsdfasdfsadzd
Engaging Stakeholders in Policy Discussions: A Legal Framework (www.kiu.ac.ug)
Robin Fischer: A Visionary Leader Making a Difference in Healthcare, One Day ...
Value-based IP Management at Siemens: A Cross-Divisional Analysis

Crane Demobilization

  • 1. CRANE DEMOBILIZATION CRANEDEMOBILIZATION Location Sattahip, Thailand Duration 1 day Crane Specifications Base Unit Length 8.36m Width 6.7m Height 3.82m Weight incl. base boom 41t Weight excl. base boom 38t Boom & Boom Top Length 44m Width 2m Height 2.1m Weight 7.92t Equipment/Services Used 220 Ton mobile crane 4 Flat bed trailers 2 Low loader trailers Lifting slings Shackles Police escort SCOPE To provide demobilization of a KOBELCO CKE1800 Crawler crane from an operations barge at Sattahip Port,Thailand. CEA also provided transportation to their facility in Laem Chabang and consolidation of the cargo until ready for shipping to Singapore. PROCEDURE A CEA 220 Ton crane moved into position alongside the barge. Counterweights for the crane were installed. Operatives removed the hook block and unfastened the bridle section from the main boom. The crawler cranes 10 counter weights were lifted and removed one at a time and placed on three CEA flatbed trailers. The next crane section removed was the counter weight holder this was loaded on to a CEA low loader. The CEA crane was moved further along the barge to lift the main boom. The main boom comprised of five sections, four insert booms and one boom top. Lifting slings were secured in four key lift points to compensate for the heavy boom top section. The crane lifted the complete boom and lowered it on to the port. CEA operatives removed the boom pins and dismantled the boom into five sections. The boom top was secured in place on a low loader trailer, each of the four insert booms were placed and secured on separate flatbed trailers. CASE STUDY CS006 Crane Demobilization 1/2
  • 2. CRANEDEMOBILIZATION CEA PROJECT LOGISTICS 41/13 M1 AO-UDOM ROAD TUNGSUNGKHLA SRI RACHA CHONBURI 20230 THAILAND +66 38 354 019 www.ceaprojects.com The crane was once again moved to facilitate the demobilization, both tracks on the crawler section were unpinned and lifted on to a low loader trailer and secured. Walkway steps attached to the crawler section were removed and secured on a flatbed truck. The only section remaining on the barge was the crane base with boom base attached. Operatives retracted and lowered the main bridle section and slings were attached to the lift points. The CEA crane lifted the base boom on to the port floor below. The cranes operative then retracted all supports and lowered the boom base ready for transportation. The crane base section was lifted on to a low loader trailer and secured in place. The trailer with police escort made the journey to CEA’s Cargo Consolidation Facility in Laem Chabang to await shipping to Singapore. CASE STUDY CS006 Crane Demobilization 2/2 COMPLETE BOOM LIFTED ON TO PORT CEA TEAM DISMANTLE THE BOOM SECTIONS BRIDLE UNFASTENED FROM MAIN BOOM TRACKS FROM THE CRAWLER SECTION CRANE BASE WITH BOOM BASE ATTACHED AND BRIDLE RETRACTED CRANE BASE WITH BOOM LOWERED SECURED AND READY FOR TRANSPORTATION