The progress update details the advancements made between December 7th and December 18th, including the completion of external steelwork installation and ground floor slab installation. Ongoing internal work is highlighted, consisting of plastering and wiring in the existing building. Upcoming tasks for the next two weeks include scaffolding completion, brickwork, and additional internal finishing work.