Progress Update (Nr. 3)
Week ending 23rd October
Programme Update - ITS
For Period : Mon 10th October – Friday 23rd October
- Commence excavations to the new basement area of the extension and muck away
- Begin excavations of new perimeter retaining walls
- Fully set out new building footprint and excavate necessary pad foundations
- Installation of associated insulation, reinforcement and temporary formwork in
preparation for concrete pours
- Completed new internal flooring infills where redundant staircases removed
- Commence first fix mechanical and electrical works within existing building
Progress Photos – Internal
First fix mechanical and
electrical works
commenced within the
existing buidling
Progress Photos – Internal
Damp proof membrane
applied to walls within
basement
Progress Photos – Internal
Further internal damp-
proofing works to basement
walls commenced including
re-plaster (to 1.5m) where
required
Progress Photos – External
Reduced level dig complete
to basement area with
damp proofing and
reinforcement installation
begun.
Progress Photos – External
Below ground drainage
‘pop ups’ for sinks and
toilets etc installed prior to
concrete pours
Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Complete excavations to new ground floor slab and perimeter retaining walls
- Complete installation of reinforcement to basement slab and concrete pour
- Excavate pad foundations to proposed ground floor and install associated holding
down bolts in preparation for steelwork
- Complete internal damp-proofing works to basement walls
- Commence internal builders work and remove remaining load bearing walls:
including installing required lintels and steelwork
- Continue first fix mechanical and electrical works within existing building to all floors

More Related Content

PDF
ITS Building Project - progress update 1
PPTX
ITS Building Project - progress update 6
PDF
ITS Building Project - progress update 4
PPTX
ITS Building Project - progress update 7
PDF
Environmental Room
PDF
Marie Reed School Construction Project Update (April 21, 2017)
PDF
Case study - 01 Underpinning
PPT
Is low mobility an important factor in the persistence of ‘enclave’ low-incom...
ITS Building Project - progress update 1
ITS Building Project - progress update 6
ITS Building Project - progress update 4
ITS Building Project - progress update 7
Environmental Room
Marie Reed School Construction Project Update (April 21, 2017)
Case study - 01 Underpinning
Is low mobility an important factor in the persistence of ‘enclave’ low-incom...

Viewers also liked (20)

PDF
Public Opinion of Low Carbon Innovation Policy
PPTX
Air safety attitudes: preliminary insights post MH370
PPTX
Is the equity value of time really fair
PPTX
International comparisons of transport appraisal practice.
PPTX
MSc Transport Planning & MSc Sustainability (Transport)
PDF
Vehicle emissions measurement: micro-trip analysis of non-stationary time-series
PDF
Buses and the_economy_ii_main_report_july2014
PPTX
Freight transport models with logistics in data-rich and not so rich environ...
PPTX
Would predicting peoples’ choices get any easier if we understood behaviour?
PPT
Growing and understanding passenger rail demand
PPTX
Congestion pricing in Gothenburg
PDF
Annual Research Report 2014 - Institute for Transport Studies
PPTX
PDF
Déclaration sur la gouvernance démocratique politique-economique entreprises
PDF
Le japon une puissance déclinante - quelles conséquences géopolitiques
DOCX
La réorganisation géostratégique mondiale
PDF
Le système éducatif djiboutien Diagnostic sectoriel et perspectives pour la p...
PDF
Pedestrian planning and modelling
PPTX
Crossrail 2 - Planning for the Future
PDF
AUDIT ENVIRONNEMENTAL DU DÉPÔT D’HYDROCARBURES DE LA SOCIETE « HORIZON TERMIN...
Public Opinion of Low Carbon Innovation Policy
Air safety attitudes: preliminary insights post MH370
Is the equity value of time really fair
International comparisons of transport appraisal practice.
MSc Transport Planning & MSc Sustainability (Transport)
Vehicle emissions measurement: micro-trip analysis of non-stationary time-series
Buses and the_economy_ii_main_report_july2014
Freight transport models with logistics in data-rich and not so rich environ...
Would predicting peoples’ choices get any easier if we understood behaviour?
Growing and understanding passenger rail demand
Congestion pricing in Gothenburg
Annual Research Report 2014 - Institute for Transport Studies
Déclaration sur la gouvernance démocratique politique-economique entreprises
Le japon une puissance déclinante - quelles conséquences géopolitiques
La réorganisation géostratégique mondiale
Le système éducatif djiboutien Diagnostic sectoriel et perspectives pour la p...
Pedestrian planning and modelling
Crossrail 2 - Planning for the Future
AUDIT ENVIRONNEMENTAL DU DÉPÔT D’HYDROCARBURES DE LA SOCIETE « HORIZON TERMIN...
Ad

Similar to ITS building project progress update 3 (12)

PDF
ITS building project progress update 1+2
PDF
ITS Building Project - progress update 8
PDF
ITS Building Project - progress update 5
PPTX
ITS Bulding Project - progress update April 2016
PDF
SCTE Solar Story
PDF
Roosevelt High School Renovation Project SIT Meeting (January 15, 2015)
PPTX
Please click here to view the Cranmer Court Presentation
PPTX
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
PPTX
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
PPTX
Retrofitting case study of RCC structure
PPT
Protecting PHandENV Dolls place
PPT
Wellesley High School Project
ITS building project progress update 1+2
ITS Building Project - progress update 8
ITS Building Project - progress update 5
ITS Bulding Project - progress update April 2016
SCTE Solar Story
Roosevelt High School Renovation Project SIT Meeting (January 15, 2015)
Please click here to view the Cranmer Court Presentation
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Retrofitting case study of RCC structure
Protecting PHandENV Dolls place
Wellesley High School Project
Ad

More from Institute for Transport Studies (ITS) (20)

PPT
Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
PPT
BA Geography with Transport Studies at the University of Leeds
PDF
Highways Benchmarking - Accelerating Impact
PDF
Using telematics data to research traffic related air pollution
PDF
Masters Dissertation Posters 2017
PDF
Institute for Transport Studies - Masters Open Day 2017
PPT
London's Crossrail Scheme - its evolution, governance, financing and challenges
PDF
Secretary of State Visit
PDF
Business model innovation for electrical vehicle futures
PPTX
A clustering method based on repeated trip behaviour to identify road user cl...
PDF
PDF
Annual Review 2015-16 - University of leeds
PDF
Social networks, activities, and travel - building links to understand behaviour
PPTX
Rail freight in Japan - track access
PDF
Real time traffic management - challenges and solutions
PDF
Proportionally fair scheduling for traffic light networks
PDF
Capacity maximising traffic signal control policies
PDF
Bayesian risk assessment of autonomous vehicles
PDF
Agent based car following model for heterogeneities of platoon driving with v...
PDF
A new theory of lane selection on highways
Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
BA Geography with Transport Studies at the University of Leeds
Highways Benchmarking - Accelerating Impact
Using telematics data to research traffic related air pollution
Masters Dissertation Posters 2017
Institute for Transport Studies - Masters Open Day 2017
London's Crossrail Scheme - its evolution, governance, financing and challenges
Secretary of State Visit
Business model innovation for electrical vehicle futures
A clustering method based on repeated trip behaviour to identify road user cl...
Annual Review 2015-16 - University of leeds
Social networks, activities, and travel - building links to understand behaviour
Rail freight in Japan - track access
Real time traffic management - challenges and solutions
Proportionally fair scheduling for traffic light networks
Capacity maximising traffic signal control policies
Bayesian risk assessment of autonomous vehicles
Agent based car following model for heterogeneities of platoon driving with v...
A new theory of lane selection on highways

Recently uploaded (20)

PDF
MICROENCAPSULATION_NDDS_BPHARMACY__SEM VII_PCI .pdf
PDF
Skin Care and Cosmetic Ingredients Dictionary ( PDFDrive ).pdf
DOCX
Cambridge-Practice-Tests-for-IELTS-12.docx
PDF
Hazard Identification & Risk Assessment .pdf
PDF
Paper A Mock Exam 9_ Attempt review.pdf.
PPTX
Computer Architecture Input Output Memory.pptx
PPTX
What’s under the hood: Parsing standardized learning content for AI
PDF
International_Financial_Reporting_Standa.pdf
PDF
Uderstanding digital marketing and marketing stratergie for engaging the digi...
PDF
English Textual Question & Ans (12th Class).pdf
PPTX
Introduction to pro and eukaryotes and differences.pptx
PDF
David L Page_DCI Research Study Journey_how Methodology can inform one's prac...
PPTX
A powerpoint presentation on the Revised K-10 Science Shaping Paper
PDF
Environmental Education MCQ BD2EE - Share Source.pdf
PDF
medical_surgical_nursing_10th_edition_ignatavicius_TEST_BANK_pdf.pdf
PDF
AI-driven educational solutions for real-life interventions in the Philippine...
PPTX
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
PDF
What if we spent less time fighting change, and more time building what’s rig...
PDF
Complications of Minimal Access-Surgery.pdf
PPTX
Module on health assessment of CHN. pptx
MICROENCAPSULATION_NDDS_BPHARMACY__SEM VII_PCI .pdf
Skin Care and Cosmetic Ingredients Dictionary ( PDFDrive ).pdf
Cambridge-Practice-Tests-for-IELTS-12.docx
Hazard Identification & Risk Assessment .pdf
Paper A Mock Exam 9_ Attempt review.pdf.
Computer Architecture Input Output Memory.pptx
What’s under the hood: Parsing standardized learning content for AI
International_Financial_Reporting_Standa.pdf
Uderstanding digital marketing and marketing stratergie for engaging the digi...
English Textual Question & Ans (12th Class).pdf
Introduction to pro and eukaryotes and differences.pptx
David L Page_DCI Research Study Journey_how Methodology can inform one's prac...
A powerpoint presentation on the Revised K-10 Science Shaping Paper
Environmental Education MCQ BD2EE - Share Source.pdf
medical_surgical_nursing_10th_edition_ignatavicius_TEST_BANK_pdf.pdf
AI-driven educational solutions for real-life interventions in the Philippine...
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
What if we spent less time fighting change, and more time building what’s rig...
Complications of Minimal Access-Surgery.pdf
Module on health assessment of CHN. pptx

ITS building project progress update 3

  • 1. Progress Update (Nr. 3) Week ending 23rd October
  • 2. Programme Update - ITS For Period : Mon 10th October – Friday 23rd October - Commence excavations to the new basement area of the extension and muck away - Begin excavations of new perimeter retaining walls - Fully set out new building footprint and excavate necessary pad foundations - Installation of associated insulation, reinforcement and temporary formwork in preparation for concrete pours - Completed new internal flooring infills where redundant staircases removed - Commence first fix mechanical and electrical works within existing building
  • 3. Progress Photos – Internal First fix mechanical and electrical works commenced within the existing buidling
  • 4. Progress Photos – Internal Damp proof membrane applied to walls within basement
  • 5. Progress Photos – Internal Further internal damp- proofing works to basement walls commenced including re-plaster (to 1.5m) where required
  • 6. Progress Photos – External Reduced level dig complete to basement area with damp proofing and reinforcement installation begun.
  • 7. Progress Photos – External Below ground drainage ‘pop ups’ for sinks and toilets etc installed prior to concrete pours
  • 8. Next Few Weeks……….. A look ahead to works commencing within the next 2 weeks : - Complete excavations to new ground floor slab and perimeter retaining walls - Complete installation of reinforcement to basement slab and concrete pour - Excavate pad foundations to proposed ground floor and install associated holding down bolts in preparation for steelwork - Complete internal damp-proofing works to basement walls - Commence internal builders work and remove remaining load bearing walls: including installing required lintels and steelwork - Continue first fix mechanical and electrical works within existing building to all floors