Progress Update (Nr. 1)
Week ending 25th September
Programme Update - ITS
Scheme Start on Site : 14th September
Throughout the course of the two weeks we have successfully completed the below:
- Isolated and disconnected the existing mechanical and electrical building services
- Commenced internal strip out and demolitions of the existing building fabric
- Carried out the asbestos removal within the lower ground plant room
- Demolished the existing outbuilding and garage/office areas
- Commenced scaffold to the rear of the building to enable efficient waste removal
Progress Photos – External
Site Compound and external hoardings set up
Progress Photos – External
External outbuilding and
garage/office demolished
Progress Photos – External
Tree protection area set up
around Horse Chestnut Tree
Progress Photos – Internal
Internal soft strip and
demolition works
commenced
Progress Photos – Internal
Progress Photos – Internal
Existing Plant Room now
fully stripped of asbestos
Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Complete strip out of existing mechanical and electrical building services
- Complete internal soft strip and demolition works
- Remove scaffold & associated rubbish chute at the rear of the building
- Commence external drainage works (including forming new manholes)
- Commence excavation to proposed basement area
- Install temporary propping to basement to assist with excavations
Progress Update (Nr. 2)
Week ending 9th October
Programme Update - ITS
For Period : Mon 28th September – Friday 9th October
- Fully completed strip out of existing mechanical and electrical building services
- Fully completed internal soft strip, demolition and non-structural works
- Removed scaffold & associated rubbish chute at the rear of the building
- Fully completed cut and carve demolition of structures around rear of building
- Commenced external drainage works (including forming new manhole)
- Numerous trial pits excavated and waste samples collected for review off site; in
preparation for groundworks commencing
Progress Photos – Internal
Building now completely
stripped at all floor levels
Progress Photos – Internal
Building now completely
stripped at all floor levels
Progress Photos – Internal
All internal non-structural
walls now removed on each
floor level
Progress Photos – External
Trial pits now complete and
backfilled on site to
establish extent of existing
foundations
Progress Photos – External
All external demolition
works now complete
Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Commence excavations to the new basement area of the extension and muck away
- Begin excavations of new perimeter retaining walls
- Fully set out new building footprint and excavate necessary pad foundations
- Installation of associated insulation, reinforcement and temporary formwork in
preparation for concrete pours
- Commence new internal flooring infills where redundant staircases removed
- Commence first fix mechanical and electrical works within existing building
Progress Update (Nr. 3)
Week ending 23rd October
Programme Update - ITS
For Period : Mon 10th October – Friday 23rd October
- Commence excavations to the new basement area of the extension and muck away
- Begin excavations of new perimeter retaining walls
- Fully set out new building footprint and excavate necessary pad foundations
- Installation of associated insulation, reinforcement and temporary formwork in
preparation for concrete pours
- Completed new internal flooring infills where redundant staircases removed
- Commence first fix mechanical and electrical works within existing building
Progress Photos – Internal
First fix mechanical and
electrical works
commenced within the
existing buidling
Progress Photos – Internal
Damp proof membrane
applied to walls within
basement
Progress Photos – Internal
Further internal damp-
proofing works to basement
walls commenced including
re-plaster (to 1.5m) where
required
Progress Photos – External
Reduced level dig complete
to basement area with
damp proofing and
reinforcement installation
begun.
Progress Photos – External
Below ground drainage
‘pop ups’ for sinks and
toilets etc installed prior to
concrete pours
Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Complete excavations to new ground floor slab and perimeter retaining walls
- Complete installation of reinforcement to basement slab and concrete pour
- Excavate pad foundations to proposed ground floor and install associated holding
down bolts in preparation for steelwork
- Complete internal damp-proofing works to basement walls
- Commence internal builders work and remove remaining load bearing walls:
including installing required lintels and steelwork
- Continue first fix mechanical and electrical works within existing building to all floors

More Related Content

PDF
ITS building project progress update 1+2
PDF
ITS building project progress update 3
PDF
ITS Building Project - progress update 5
PDF
ITS Building Project - progress update 8
PPS
Ittina Progress
PDF
Case study - 01 Underpinning
PDF
XACTChrysalisAwardEntry042016
DOC
TOMS RESUME
ITS building project progress update 1+2
ITS building project progress update 3
ITS Building Project - progress update 5
ITS Building Project - progress update 8
Ittina Progress
Case study - 01 Underpinning
XACTChrysalisAwardEntry042016
TOMS RESUME

What's hot (12)

DOCX
Assignment (1)
PPTX
Designers Connect Presentation May 14th 2013
PDF
ste p rept 2
PPT
Renovator's Presentation for Orderline Duplex Simplifed for linked-in
PDF
Balinese residences at adora de goa
PDF
Plots for sale in electronic city
DOCX
Ici final project
PDF
Flats for Sale in whitefield, Bangalore
PPT
Big Water Visitor Center
PPTX
Directors report (2)
PPT
CDECA Toronto Chapter Presentation Feb 5, 2013
PPTX
King Street Staion: 3rd floor walls demolition
Assignment (1)
Designers Connect Presentation May 14th 2013
ste p rept 2
Renovator's Presentation for Orderline Duplex Simplifed for linked-in
Balinese residences at adora de goa
Plots for sale in electronic city
Ici final project
Flats for Sale in whitefield, Bangalore
Big Water Visitor Center
Directors report (2)
CDECA Toronto Chapter Presentation Feb 5, 2013
King Street Staion: 3rd floor walls demolition
Ad

Viewers also liked (13)

PDF
Project timeline slides v2
PDF
Mind Map- Interdepartmental Communication for Rehabbing Affordable Housing
PPTX
Project timeline v0.1
PDF
Meeting Project Schedule Compliance Standards
PPT
The project schedule and budget
PDF
January 23rd ,2017 Parkmerced Vision Update
PPT
Template for building project schedule
PPT
Planning And Managing The Project
PPTX
Project Timeline Template - Deliverable Based Consulting
PDF
Project Planning Timeline Editable ppt
PPTX
PROJECT SCHEDULE
PPTX
Business plan presentation
 
PPT
Plant layout ppt by me
Project timeline slides v2
Mind Map- Interdepartmental Communication for Rehabbing Affordable Housing
Project timeline v0.1
Meeting Project Schedule Compliance Standards
The project schedule and budget
January 23rd ,2017 Parkmerced Vision Update
Template for building project schedule
Planning And Managing The Project
Project Timeline Template - Deliverable Based Consulting
Project Planning Timeline Editable ppt
PROJECT SCHEDULE
Business plan presentation
 
Plant layout ppt by me
Ad

Similar to ITS Building Project - progress update 1 (13)

PDF
ITS Building Project - progress update 4
PPTX
ITS Bulding Project - progress update April 2016
PPTX
ITS Building Project - progress update 6
PPTX
ITS Building Project - progress update 7
PDF
PDF
buildingcvbghyuthUpdate as on Feb 2024 for .pdf
PPTX
Experiencing Construction
PPTX
CONSTRUCTION PRESENTATION
PDF
status report.pdf
PPTX
Educational opportunities Internship CIE-4-25-1.pptx
PDF
YU MIN LIU _ 2017 PORTFOLIO_FULL 11_17
PDF
Adoradegoa Brochure for real estate and purchase
PDF
OP YADAV PROJECT
ITS Building Project - progress update 4
ITS Bulding Project - progress update April 2016
ITS Building Project - progress update 6
ITS Building Project - progress update 7
buildingcvbghyuthUpdate as on Feb 2024 for .pdf
Experiencing Construction
CONSTRUCTION PRESENTATION
status report.pdf
Educational opportunities Internship CIE-4-25-1.pptx
YU MIN LIU _ 2017 PORTFOLIO_FULL 11_17
Adoradegoa Brochure for real estate and purchase
OP YADAV PROJECT

More from Institute for Transport Studies (ITS) (20)

PPT
Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
PPT
BA Geography with Transport Studies at the University of Leeds
PDF
Highways Benchmarking - Accelerating Impact
PDF
Using telematics data to research traffic related air pollution
PDF
Masters Dissertation Posters 2017
PDF
Institute for Transport Studies - Masters Open Day 2017
PPT
London's Crossrail Scheme - its evolution, governance, financing and challenges
PDF
Secretary of State Visit
PDF
Business model innovation for electrical vehicle futures
PPTX
A clustering method based on repeated trip behaviour to identify road user cl...
PDF
PDF
Annual Review 2015-16 - University of leeds
PDF
Social networks, activities, and travel - building links to understand behaviour
PPTX
Rail freight in Japan - track access
PDF
Real time traffic management - challenges and solutions
PDF
Proportionally fair scheduling for traffic light networks
PDF
Capacity maximising traffic signal control policies
PDF
Bayesian risk assessment of autonomous vehicles
PDF
Agent based car following model for heterogeneities of platoon driving with v...
PDF
A new theory of lane selection on highways
Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
BA Geography with Transport Studies at the University of Leeds
Highways Benchmarking - Accelerating Impact
Using telematics data to research traffic related air pollution
Masters Dissertation Posters 2017
Institute for Transport Studies - Masters Open Day 2017
London's Crossrail Scheme - its evolution, governance, financing and challenges
Secretary of State Visit
Business model innovation for electrical vehicle futures
A clustering method based on repeated trip behaviour to identify road user cl...
Annual Review 2015-16 - University of leeds
Social networks, activities, and travel - building links to understand behaviour
Rail freight in Japan - track access
Real time traffic management - challenges and solutions
Proportionally fair scheduling for traffic light networks
Capacity maximising traffic signal control policies
Bayesian risk assessment of autonomous vehicles
Agent based car following model for heterogeneities of platoon driving with v...
A new theory of lane selection on highways

Recently uploaded (20)

PPTX
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
PPTX
Radiologic_Anatomy_of_the_Brachial_plexus [final].pptx
PPTX
Unit 4 Skeletal System.ppt.pptxopresentatiom
PPTX
UNIT III MENTAL HEALTH NURSING ASSESSMENT
PDF
Hazard Identification & Risk Assessment .pdf
PDF
A systematic review of self-coping strategies used by university students to ...
PDF
IGGE1 Understanding the Self1234567891011
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
Trump Administration's workforce development strategy
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PPTX
Lesson notes of climatology university.
PDF
LNK 2025 (2).pdf MWEHEHEHEHEHEHEHEHEHEHE
PDF
Complications of Minimal Access Surgery at WLH
PDF
Paper A Mock Exam 9_ Attempt review.pdf.
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PPTX
UV-Visible spectroscopy..pptx UV-Visible Spectroscopy – Electronic Transition...
PPTX
Cell Types and Its function , kingdom of life
PPTX
A powerpoint presentation on the Revised K-10 Science Shaping Paper
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
Radiologic_Anatomy_of_the_Brachial_plexus [final].pptx
Unit 4 Skeletal System.ppt.pptxopresentatiom
UNIT III MENTAL HEALTH NURSING ASSESSMENT
Hazard Identification & Risk Assessment .pdf
A systematic review of self-coping strategies used by university students to ...
IGGE1 Understanding the Self1234567891011
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
Final Presentation General Medicine 03-08-2024.pptx
Trump Administration's workforce development strategy
Final Presentation General Medicine 03-08-2024.pptx
Lesson notes of climatology university.
LNK 2025 (2).pdf MWEHEHEHEHEHEHEHEHEHEHE
Complications of Minimal Access Surgery at WLH
Paper A Mock Exam 9_ Attempt review.pdf.
Chinmaya Tiranga quiz Grand Finale.pdf
Supply Chain Operations Speaking Notes -ICLT Program
UV-Visible spectroscopy..pptx UV-Visible Spectroscopy – Electronic Transition...
Cell Types and Its function , kingdom of life
A powerpoint presentation on the Revised K-10 Science Shaping Paper

ITS Building Project - progress update 1

  • 7. Progress Update (Nr. 1) Week ending 25th September
  • 8. Programme Update - ITS Scheme Start on Site : 14th September Throughout the course of the two weeks we have successfully completed the below: - Isolated and disconnected the existing mechanical and electrical building services - Commenced internal strip out and demolitions of the existing building fabric - Carried out the asbestos removal within the lower ground plant room - Demolished the existing outbuilding and garage/office areas - Commenced scaffold to the rear of the building to enable efficient waste removal
  • 9. Progress Photos – External Site Compound and external hoardings set up
  • 10. Progress Photos – External External outbuilding and garage/office demolished
  • 11. Progress Photos – External Tree protection area set up around Horse Chestnut Tree
  • 12. Progress Photos – Internal Internal soft strip and demolition works commenced
  • 14. Progress Photos – Internal Existing Plant Room now fully stripped of asbestos
  • 15. Next Few Weeks……….. A look ahead to works commencing within the next 2 weeks : - Complete strip out of existing mechanical and electrical building services - Complete internal soft strip and demolition works - Remove scaffold & associated rubbish chute at the rear of the building - Commence external drainage works (including forming new manholes) - Commence excavation to proposed basement area - Install temporary propping to basement to assist with excavations
  • 16. Progress Update (Nr. 2) Week ending 9th October
  • 17. Programme Update - ITS For Period : Mon 28th September – Friday 9th October - Fully completed strip out of existing mechanical and electrical building services - Fully completed internal soft strip, demolition and non-structural works - Removed scaffold & associated rubbish chute at the rear of the building - Fully completed cut and carve demolition of structures around rear of building - Commenced external drainage works (including forming new manhole) - Numerous trial pits excavated and waste samples collected for review off site; in preparation for groundworks commencing
  • 18. Progress Photos – Internal Building now completely stripped at all floor levels
  • 19. Progress Photos – Internal Building now completely stripped at all floor levels
  • 20. Progress Photos – Internal All internal non-structural walls now removed on each floor level
  • 21. Progress Photos – External Trial pits now complete and backfilled on site to establish extent of existing foundations
  • 22. Progress Photos – External All external demolition works now complete
  • 23. Next Few Weeks……….. A look ahead to works commencing within the next 2 weeks : - Commence excavations to the new basement area of the extension and muck away - Begin excavations of new perimeter retaining walls - Fully set out new building footprint and excavate necessary pad foundations - Installation of associated insulation, reinforcement and temporary formwork in preparation for concrete pours - Commence new internal flooring infills where redundant staircases removed - Commence first fix mechanical and electrical works within existing building
  • 24. Progress Update (Nr. 3) Week ending 23rd October
  • 25. Programme Update - ITS For Period : Mon 10th October – Friday 23rd October - Commence excavations to the new basement area of the extension and muck away - Begin excavations of new perimeter retaining walls - Fully set out new building footprint and excavate necessary pad foundations - Installation of associated insulation, reinforcement and temporary formwork in preparation for concrete pours - Completed new internal flooring infills where redundant staircases removed - Commence first fix mechanical and electrical works within existing building
  • 26. Progress Photos – Internal First fix mechanical and electrical works commenced within the existing buidling
  • 27. Progress Photos – Internal Damp proof membrane applied to walls within basement
  • 28. Progress Photos – Internal Further internal damp- proofing works to basement walls commenced including re-plaster (to 1.5m) where required
  • 29. Progress Photos – External Reduced level dig complete to basement area with damp proofing and reinforcement installation begun.
  • 30. Progress Photos – External Below ground drainage ‘pop ups’ for sinks and toilets etc installed prior to concrete pours
  • 31. Next Few Weeks……….. A look ahead to works commencing within the next 2 weeks : - Complete excavations to new ground floor slab and perimeter retaining walls - Complete installation of reinforcement to basement slab and concrete pour - Excavate pad foundations to proposed ground floor and install associated holding down bolts in preparation for steelwork - Complete internal damp-proofing works to basement walls - Commence internal builders work and remove remaining load bearing walls: including installing required lintels and steelwork - Continue first fix mechanical and electrical works within existing building to all floors