SORIYA MITESHKUMAR. A. 
Mobile: +91‐8128308997 ~ Res.: +91 265 2710 914 
E‐Mail: miteshsoriya@yahoo.com / miteshsoriya@gmail.com 
 
 
SENIOR PROJECT MANAGEMENT PROFESSIONAL 
“Exhibits a strong and firm approach to sustaining & encouraging safe work environments and a demonstrated ability to 
streamline operations. Applies continuous improvement principles to increase process, systems, efficiency and company profits. 
Expertise in handling project execution, implementing plans & schedules for EPC Projects with focus on optimum utilisation of 
manpower and materials.” 
Project Management ~ Cost & Schedule Control ~ Risk 
Industry Preference: Oil & Gas/ Construction 
Location Preference: International   
PROFILE SUMMARY 
 
Dynamic professional offering 24 years of rich expertise in: 
Project Management      Site / Construction Management      Procurement Operations   
Detailed Engineering Operations    Planning, Monitoring & Control, Coordination  Risk / Cost Management 
Contract Management      Supplier/ Vendor Management       Installation & Commissioning  
• Proficient  in  handling  site  operations  and  accountable  for  quality  service,  timely 
completion & within budget of the projects 
• Hands  on  experience  in  overseeing  project  activities  from  conceptualization  to 
execution including details of engineering, procurement and construction phases for  
various stages as initiation, planning, execution, monitoring and control, closing 
• Proven  track  record  in  implementing  cost  saving  measures  to  achieve  substantial 
reduction in terms of resources as materials, manpower and machine 
• Expertise in managing challenging project to keep on track by root cause analysis and 
corrective actions with improving productivity of manpower, optimum utilization of 
machines. Implementing effective, efficient and result oriented project management 
• Adept at carrying out various checks for required procurement and tests / inspection 
for various processes to assure the quality 
• An effective communicator with excellent relationship management skills and strong 
analytical, leadership, decision making, problem solving & organizational abilities 
 
MAJOR ACCOMPLISHMENTS ACROSS CAREER        CORE SKILLS 
 
• Demonstrated excellence in: 
o Improving  projects  trends,  controlling  critical  path 
activities,  implementing  project  control  systems, 
management presentation and action plan 
o Controlling  a  3  months  delayed  challenging  pipeline 
project in UAE  
o Developing  project  control  systems,  dashboard  for 
management in Oil & Gas Project, Iran 
• Actively took part in 3 days construction schedule alignment 
workshop  with  SADARA,  DOW  chemical  USA  and  baseline 
construction  schedule  with  extra  3  months  from  contact 
period in KSA 
• Adroitly full implemented use of SAP Oracle for uploading 
budget  cost  data  for  28  projects  under  Industrial  Facility 
group in Head office Kharafi National, Kuwait 
• Successfully  lowered  all  bottlenecks  of  3  months  delayed  
not  started  projects  by  in‐house  developing  drawings,  setting‐up  fabrication  shop  and  special  rolling  requirement  for 
fabrication of Thermocompressor 10 Nos. for SIDEM Power Project, Qatar 
• Stellar in: 
o Implementation of CMMS for constructed 4 Nos. projects & Project Control System of LDPE construction projects in Iran 
o Launching 6 Nos. of contracting job under single contract for operations & maintenance of bagging and shipping for 
bulk material handling in Iran  
o Successfully coordinated and controlled Co‐Generation, Ammonia, Melamine, Nylon Projects in Baroda, India. 
 
WORK EXPERIENCE 
 
Sep’14‐Jun’16    Etimaad Qatar LLC, as Project Manager                    
Roles:  
• EPIC of New LGO Tanks at QP Refinery, Mesaieed, Qatar of  US$ 110 Millions  
• Leading, organizing, Planning, monitoring, controlling all activities of project execution.  
• Carrying out the project plan in order to achieve the project objectives.  
• Managing critical interfaces with project team and stakeholders 
• Exercise the "soft skills." Skills such as communicating clearly, team motivation, and conflict resolution. 
• Leading projects by Setting team direction, coordinating activities across different departments, Motivating,  Assigning work 
• Organizing by Determine the organizational structure of the project team, Identify roles and positions, Identify services to 
be provided by external companies, Staff project positions 
• Planning by define and clarify project scope, develop the project plan, develop the project schedule, develop policies and 
procedures to support the achievement of the project objectives 
• Project controlling by defining baselines, tracking progress, status reporting, determining and taking corrective actions 
• Keeping the project on track through project control and performed process like Measuring, Evaluating, Correcting 
• Presentation  for  management,  attended  client  progress  review  meetings,  construction  strategy,  risk  management  and  
other management requirements 
• Led a team members and conducted joint workshop for Risk of project to prepare and finalize the risk register 
• Continuous  Improvement  in  performance,  productivity  and  progress  for  client  satisfaction  and  profitability  to  achieve 
agreed milestones 
 
Dec’13‐Aug’14    Essar Projects 
• Essar Projects Mauritania SARL, Mauritania, as Lead Project Control (Jun’14‐Aug’14) functioning from HO 
Mumbai and Engineering office, Hazira, Gujarat, India 
• Planning,  monitoring  and  control  of  7.5  MTPA  Iron  Ore  Beneficiation  EPC  Project  at  Askaf  site  near 
Zeurate in Mauritania for Spear Mauritania (Subsidiaries of Glencore, Switzerland) of US$ 600 Millions 
• Schedule development and approval of procedures, planning packages for functioning project control 
• Established DPR, WPR, MPR, MOM reporting systems and meeting management 
• Implementing new software requirement like ACONEX, WRENCH and integration with existing software 
• Boost up the engineering required deliverable to create a work front for procurement team 
• Follow up to approve immediate required engineering deliverable and procurement for pre construction activities 
• Mobilization of equipments in lot wise as per plan and requirement 
• Mobilization of Manpower as per plan and requirement 
• Planned, monitored & controlled of project for timely delivery of project deliverables 
• Essar Construction Overseas Ltd, Abu Dhabi, UAE as Project Control Manager (Dec’13‐May’14)   
• Managed the replacement of EPC 16” Condensate Pipeline 110 KM from Habshan to Ruwais for GASCO EPC Project & PMC 
by EIL – Engineers India Limited 
• Planned, monitored & controlled of project for timely delivery of project deliverables 
• Implemented recovery plan in Primavera schedule with supporting elements of Project Control Package and development of 
detailed schedule for construction to control project timeline 
• Developed  of  schedule  analysis  report,  delay  analysis  report  and  action  plan  to  recover  progress.  Update  schedule 
assumptions 
• Presentation  for  management,  attended  client  progress  review  meetings,  construction  strategy,  risk  management  and  
other management requirements 
• Handled the Earn Value Management (EVM), conducted delay analysis, implemented value engineering and validation of 
project schedules and progress reports 
• Led a team members and conducted joint workshop for Risk of project to prepare and finalize the risk register 
 
Mar’13‐Nov’13    National Iranian Oil Company, Assaluyeh, Iran for Lead Project Management Team            
Key Result Areas 
• Managed South Pars Gas Field Development Project Phase‐22, 23, 24 at Asaluyeh, Iran of US$ 2.9 Billions
• Strengthening PMT – Project Management Team to control 1 part (Refinery) of onshore and 3 parts (Wells, Platforms, Sub 
sea pipelines) of offshore project 
• Prepared strategy for project execution plan and manages contractors for various requirements at site for all phases like 
mobilization, execution, scope change and close out 
• Schedule  control  for  Drilling,  Casings, Platforms  fabrication,  transportation,  Installation,  Jacket  installation, Flow  Line, 
Pipeline,  Well  Heads,  Umbilical,  Sub  sea  systems,  HIPPS,  Sub  sea  pipeline  by  advanced  pipeline  laying  barge,  Pig 
launcher/receiver etc. 
• Chasing to complete balance scope for construction execution and control schedule variance to meet project timeline 
• Offered  special  consultation  for  Implementation  of  IOR  –  Improved  Oil  Recovery  requirement  by  installation  CDS,  RDS, 
MSMs, MPFMs, Tie‐ins, utilities and support facilities, gas dehydration unit, pumps and new gas Lift Network in ongoing 
operation of NIOC 
• Handled a team of 10 members                                                                
                                                                                                                                    
May’12‐Feb’13        Larsen &Toubro, Hydrocarbon, Jubail, Saudi Arabia as Planning Manager                                   
Key Result Areas 
• Led Project Controller for EPC Project for SADARA (A Joint Venture of ARAMCO with DOW Chemical, USA) for Solution 
Polyethylene Train‐1, 2 and  4 Project of value US $ 180 Million & 20 Millions Man‐Hours 
• Interacted with client project management team from JACOB, USA as well as conducted engineering package release & 
deliverables alignment workshop with DOW Chemical, USA. 
• Assured  timely  development  of  Primavera  schedule  with  resource  (Labour  &  Material)  loading,  levelling  to  calculate 
manpower & material requirement in time phase in concern with engineering, procurement and construction team 
• Assisted  project management team during  verification  and  preparation  of  physical progress on monthly  basis to  enable 
payments, etc. 
 
Aug’10‐Apr’12:     Kharafi National, Kuwait as Sr. Cost & Planning Engineer   
Key Result Areas 
• Prepared WBS, L4 detailed schedule, assignment, levelling in Primavera P6. 
• Updated the project progress in PMS & P6 schedule to prepare 3WLA & 4 MLA schedule 
• Prepared detailed manpower, equipments utilization report for PM, MP and OM 
• Analyzed cost variances of cost performance against budget to provide recommendations to PM & PCM 
• Handled a team of 12 employees 
 
PREVIOUS EXPERIENCE 
May’09‐Jun’10   : Descon Engineering Company, Doha, Qatar as In‐charge of Planning Department 
Sep’06‐Apr’09   : Amir Kabir Petrochemicals Company, Mahshahr, Iran as Specialist Planning 
Jul’04‐Apr’06     : Pithawala Engineering & Construction Company, Mahshahr, Iran as Assistant Project Manager 
Oct’93‐Jul’04     : Gujarat State Fertilizer & Chemical Limited, Vadodara as Senior Mechanical Engineer 
                                                 
   
 
 
 
 
EDUCATION 
 
1992      BE (Mechanical) from Regional Engineering College, Rourkela, India                                
      (Now NIT National Institute of Technology, Rourkela, India)        
 
 
IT SKILLS  
• Well versed with  
o Microsoft Project / P3 / Primavera P6 Version 7.0/8.2 
o MS‐Office (Word/Excel/Access, PowerPoint) 
o CMMS of Nazm Afrin & CMMS of IMPACT 
o SAP Oracle and AutoCAD‐2007 
o Acumen Fuse to improve quality of Primavera Schedule  
o PRA – Primavera Risk Analysis 
o ACONEX for documents flow 
o WRENCH for progress monitoring & control 
 
PERSONAL DETAILS 
Date of Birth         : 28th
 June, 1971 
Language          : English, Hindi, Gujarati 
Address     : 33, Madhuvan Society, Abhilasha Crossing, New Sama Road, Vadodara‐390008, Gujarat, India 
Nationality    : Indian 
Marital Status    : Married 
No. of dependants  : Two  
Driving Details    : Kuwait 271062804228 till 25‐May‐21, Qatar till 2020, India : GJ06 19930065021 Valid till 27‐Jun‐21 
Passport No.    : Z1885432 Valid till 02‐Nov‐2020 
ANNEXURE 
 
MAJOR PROJECTS EXECUTED 
 
• EPIC of New LGO Tanks at QP Refinery, Mesaieed, Qatar  
• 7.5 MTPA Iron Ore Beneficiation EPC Project at Askaf site near Zeurate in Mauritania for Spear Mauritania (Subsidiaries of 
Glencore, Switzerland 
• Replacement of 16” Condensate Pipeline from Habshan to Ruwais, Abu Dhabi, UAE 
• South Pars Gas Field Development Project Phase‐22,23,24 at Asaluyeh, Iran 
• EPC Solution Polyethylene Project, Jubail, Saudi Arabia, SADARA (A Joint Venture of ARAMCO with DOW Chemical, USA) 
• EPC Mishrif Pumping Station Project, MEW Ministry of Electricity and Water, Kuwait. 
• Petrofac ‐ KOC Pipeline 125 KM & Facilities Works Construction Project, Kuwait 
• EPC Regeneration Gas Heater Train‐1 & 3, Qatar Gas, Qatar 
• Repairing of Cyclone line of 4000 MTPD at Qatar National Cement Company, Qatar 
• Flare Gas Piping Construction Project, Chiyoda Technip Joint Venture, Qatar 
• Storage Tank Piping Construction Project, Ras Gas, Qatar 
• Annual Shutdown 2010 for Train‐3 & 4, Qatar Gas, Qatar 
• Annual Shutdown 2010, Qatar Fertilizers Company, Qatar 
• LDPE Project, Amir Kabir Petrochemical Company, Iran 
• Combined Cycle Co‐Generation Power Plant, Phase‐III 25MW, Gujarat State Fertilizers Company Ltd., Baroda 
• Linde Ammonia‐IV 1,350 MTPD Project, Gujarat State Fertilizers Company Ltd., Baroda 
• Melamine‐II 10,000 MTPA Project, Gujarat State Fertilizers Company Ltd., Baroda 
• Nylone‐6 15,000 MTPA Project, Gujarat State Fertilizers Company Ltd., Baroda 
 
At Essar Projects Groups : 
• Essar  Projects  Mauritania  SARL,  Mauritania  as  Lead  Project  Control  (Jun’14‐Aug’14)  functioning  from  HO  Mumbai  and 
Engineering office, Hazira, Gujarat, India 
7.5 MTPA Iron Ore Beneficiation EPC Project at Askaf site near Zeurate in Mauritania for Spear Mauritania (Subsidiaries of 
Glencore, Switzerland 
• Essar Construction Overseas Limited, Abu Dhabi, UAE as Project Control Manager  
Replacement of 16” Condensate Pipeline 110 KM from Habshan to Ruwais for GASCO & PMC EIL – Engineers India Limited 
 
At National Iranian Oil Company 
• Leading in project management activities for successful delivery of project deliverables. 
• Involved to arranges all resources like materials, subcontractors, manpower and equipments to control schedule variance 
and control schedule and resources for project requirement.  
• Alignment of departments and project team with clear forward path and detailed plan for corrective actions with target 
time.  
• EVM, root cause analysis reports, trend analysis, forecast timeline report, consultation and recommendations for all 4 parts 
of project like: 
o Onshore Refinery Project 
o Offshore Drilling 38 wells 
o Subsea Pipeline 4 Nos. 130 KM each (2 Nos. 32” & 4.5” 130KM each & additional 1 Nos. 18” 6KM & 20” 8KM) 
o Fabrication and Installation of Unmanned Platforms ‐ 4 Nos. 
 
At Larsen &Toubro, Hydrocarbon, Jubail, Saudi Arabia  
• Solution Polyethylene Train‐1 Project 
 
At Kharafi National, Kuwait  
• Lead Project Controller for MEW Mishrif Pumping Station EPC Project for various clients requirements 
• Lead Project Controller for Petrofac ‐ KOC Pipeline : 125 KM & Facilities Works Project for 42/52” FG pipeline 60KM, 24” GO 
Pipeline 60KM, 10”/16” GO pipeline 5KM,  Pumping stations, Pigging facility 12 Units, Sectionalizing  Valve  Stations 8 Nos., 
Metering and Control facility 4 Nos., Instrument Air package‐5 Nos., Metering Packages 11 Nos., Tie‐ins, Shelters, Analyzer 
House 5 Nos., FGBS Fuel Gas Booster Stations, CM/BP/OW Pits etc. 
• Lead Project Controller role at PCD Project Control Department, Head Office for Cost Controlling of FM Facility Maintenance 
Projects (Industrial, Sewage & Water) of KNPC, KOC, EQUATE, MEP 
• Site Manpower regular dealing ‐ 34 Nos. Manpower reporting ‐ 3 Nos. 
 
 
 
 
At Descon Engineering Company, Doha 
• EPC Projects :       
Qatar Gas        EPC Jobs for Regeneration Gas Heater Train‐1 & 3 
QNCC        Repairing of Cyclone line of 4000 MTPD Jobs at Cement Plant 
• Construction Projects :      
 CTJV       Flare Gas Piping Job 
  Ras Gas          Storage Tank Piping Job 
• Shutdown Projects :     
  Qatar Gas       Annual Shutdown 2010 for Train‐3 & 4 
  QAFCO      Annual Shutdown 2010 
 
At Amir Kabir Petrochemicals Company, Mahshahr, Iran 
• LDPE – Low Density Polyethylene Project 
 
At Gujarat State Fertilizer & Chemical Limited, Vadodara 
• Combined Cycle Co‐Generation Power Plant, Phase‐III 25MW 
• Ammonia‐IV 1,350 MTPD Project, Linde 
• Melamine‐II 10,000 MTPA Project 
• Nylone‐6 15,000 MTPA Project 
 
EXTRAMURAL ENGAGEMENTS 
 
• Holds the merit of being  recognised as winner for Table Tennis in 1994 & 1995, GSFC, Vadodara, India 
• Actively took part in Indian Folk Dance in 1990 at “Spring Time” Festival in Regional Engineering College, Rourkela, India 
• Merit of winning: 
o Chess Competition in 1995, GSFC, Vadodara, India 
o 5th
 position in chess in 2007 & recognised as winner for Group Chess in 2009 in AKPC, IRAN 
• Successfully Served as a member for Toast Masters Club, KSA 
 
TRAININGS ATTENDED 
 
• PRA – Primavera Risk Analysis training and workshop on schedule for quarterly risk review 
• PMP – Project Management Professional online training through Knowledge Woods, India in Nov’13 
• Team Building Management Program by L&T 
• In‐house Training for Planning & Project Control at Kharafi National, Kuwait 
• integrated management system & project management system at Descon Engineering 
• Training for safety induction and H2S at CTJV & Qatar Gas 
• Certificate course for PRIMAVERA, Sure Track Project Manager 2.0 in Apr‐May 2007 
• Microsoft Project in training centre of AKPC, Iran 
• Industrial Hydraulic Systems at Vickers International hydraulic school in Bombay 
• Heavy Mobile Equipments by TATA, VOLTAS & SAN Locomotives 
• Maintenance Machinery, Spare Parts Planning, Safety Standard, ISO‐9000, ISO‐9002, ISO‐14000 in GSFC, Baroda  
• Mysore Kirloskar Ltd., Harihar, Karnataka in May’91 
• Research Design & Standard Organization, Lucknow in May’90 
 
WORKSHOP ATTENDED 
 
• “Workshop on Shutdown Management” by The Institute of Engineers (India) Qatar in 2010 
 
 

More Related Content

PDF
Resume Expediting & Inspection Engineer (Oil & Gas)
DOCX
Planning Engineer CV
PDF
Mech. Engr. Resume
DOCX
CV- Sr. Procurement Engineer
PDF
my CV Hashim project/Site engineer
PDF
MEP procurement engineer
PDF
MEP Manager CV)
PDF
Muhammad Asif - Procurement Quality Supervisor CV (2)
Resume Expediting & Inspection Engineer (Oil & Gas)
Planning Engineer CV
Mech. Engr. Resume
CV- Sr. Procurement Engineer
my CV Hashim project/Site engineer
MEP procurement engineer
MEP Manager CV)
Muhammad Asif - Procurement Quality Supervisor CV (2)

What's hot (20)

DOCX
ANKUSH NEW CURRICULAM VITAE
PDF
Iftekhar Civil Engineer CV
DOCX
Adnan Resume revised
DOCX
Karthikeyan CIVIL Engg Resume (1)
PDF
Civil Engineer & Inspector
DOC
civil engineer Cv
DOC
Resume-Civil - QC Engineer - Gowrijayashankar
PDF
Precast Concrete QA/QC CV
PDF
Curriculum vitae of civil engineer for construction manager or Sr. project en...
PDF
Cv site civil engineer
PDF
CV CIVIL ENGINEER
DOC
Raja kumar Resume (Senior Civil Engineer)
DOCX
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
DOC
Civil engineer
PDF
CV Piping Supervisor
DOCX
QA/QC Civil Engineer
DOCX
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
PDF
Amjad CV Pipeing sup 2016
PDF
CIVIL SUPERVISOR-CV-abdul shukoor
PDF
QA/QC Manager-Civil
ANKUSH NEW CURRICULAM VITAE
Iftekhar Civil Engineer CV
Adnan Resume revised
Karthikeyan CIVIL Engg Resume (1)
Civil Engineer & Inspector
civil engineer Cv
Resume-Civil - QC Engineer - Gowrijayashankar
Precast Concrete QA/QC CV
Curriculum vitae of civil engineer for construction manager or Sr. project en...
Cv site civil engineer
CV CIVIL ENGINEER
Raja kumar Resume (Senior Civil Engineer)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
Civil engineer
CV Piping Supervisor
QA/QC Civil Engineer
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
Amjad CV Pipeing sup 2016
CIVIL SUPERVISOR-CV-abdul shukoor
QA/QC Manager-Civil
Ad

Similar to CV - Mitesh Soriya - Project Manager (20)

DOC
CV_SUMAN MUKHERJEE- JULY-16
DOCX
CV ISMAIL SHAIKH-31.10.2015
PDF
C.V. OF Mr.Arindam Guha.
DOCX
Latest Resume
DOCX
SamGhoshProjectmanagement7
DOC
Resume- Project Management Analyst
DOC
CV (Revised)
DOC
Project Senior resume
PPTX
Career Portfolio
DOCX
SFK_ Resume-jobchange_dec2016
DOC
October 2015 resume kingshook
DOC
ac (1)
DOC
Naresh Resume
DOC
Senior resume
DOCX
Resume_Omkar Palit
DOC
Resume 2016
DOCX
SG_Resume
DOCX
Arun Sahu_ Project Management _ Oil & Gas _ Petrochemical
DOCX
Resume
PDF
Resume
CV_SUMAN MUKHERJEE- JULY-16
CV ISMAIL SHAIKH-31.10.2015
C.V. OF Mr.Arindam Guha.
Latest Resume
SamGhoshProjectmanagement7
Resume- Project Management Analyst
CV (Revised)
Project Senior resume
Career Portfolio
SFK_ Resume-jobchange_dec2016
October 2015 resume kingshook
ac (1)
Naresh Resume
Senior resume
Resume_Omkar Palit
Resume 2016
SG_Resume
Arun Sahu_ Project Management _ Oil & Gas _ Petrochemical
Resume
Resume
Ad

CV - Mitesh Soriya - Project Manager

  • 1. SORIYA MITESHKUMAR. A.  Mobile: +91‐8128308997 ~ Res.: +91 265 2710 914  E‐Mail: miteshsoriya@yahoo.com / miteshsoriya@gmail.com      SENIOR PROJECT MANAGEMENT PROFESSIONAL  “Exhibits a strong and firm approach to sustaining & encouraging safe work environments and a demonstrated ability to  streamline operations. Applies continuous improvement principles to increase process, systems, efficiency and company profits.  Expertise in handling project execution, implementing plans & schedules for EPC Projects with focus on optimum utilisation of  manpower and materials.”  Project Management ~ Cost & Schedule Control ~ Risk  Industry Preference: Oil & Gas/ Construction  Location Preference: International    PROFILE SUMMARY    Dynamic professional offering 24 years of rich expertise in:  Project Management      Site / Construction Management      Procurement Operations    Detailed Engineering Operations    Planning, Monitoring & Control, Coordination  Risk / Cost Management  Contract Management      Supplier/ Vendor Management       Installation & Commissioning   • Proficient  in  handling  site  operations  and  accountable  for  quality  service,  timely  completion & within budget of the projects  • Hands  on  experience  in  overseeing  project  activities  from  conceptualization  to  execution including details of engineering, procurement and construction phases for   various stages as initiation, planning, execution, monitoring and control, closing  • Proven  track  record  in  implementing  cost  saving  measures  to  achieve  substantial  reduction in terms of resources as materials, manpower and machine  • Expertise in managing challenging project to keep on track by root cause analysis and  corrective actions with improving productivity of manpower, optimum utilization of  machines. Implementing effective, efficient and result oriented project management  • Adept at carrying out various checks for required procurement and tests / inspection  for various processes to assure the quality  • An effective communicator with excellent relationship management skills and strong  analytical, leadership, decision making, problem solving & organizational abilities    MAJOR ACCOMPLISHMENTS ACROSS CAREER        CORE SKILLS    • Demonstrated excellence in:  o Improving  projects  trends,  controlling  critical  path  activities,  implementing  project  control  systems,  management presentation and action plan  o Controlling  a  3  months  delayed  challenging  pipeline  project in UAE   o Developing  project  control  systems,  dashboard  for  management in Oil & Gas Project, Iran  • Actively took part in 3 days construction schedule alignment  workshop  with  SADARA,  DOW  chemical  USA  and  baseline  construction  schedule  with  extra  3  months  from  contact  period in KSA  • Adroitly full implemented use of SAP Oracle for uploading  budget  cost  data  for  28  projects  under  Industrial  Facility  group in Head office Kharafi National, Kuwait  • Successfully  lowered  all  bottlenecks  of  3  months  delayed   not  started  projects  by  in‐house  developing  drawings,  setting‐up  fabrication  shop  and  special  rolling  requirement  for  fabrication of Thermocompressor 10 Nos. for SIDEM Power Project, Qatar  • Stellar in:  o Implementation of CMMS for constructed 4 Nos. projects & Project Control System of LDPE construction projects in Iran  o Launching 6 Nos. of contracting job under single contract for operations & maintenance of bagging and shipping for  bulk material handling in Iran   o Successfully coordinated and controlled Co‐Generation, Ammonia, Melamine, Nylon Projects in Baroda, India. 
  • 2.   WORK EXPERIENCE    Sep’14‐Jun’16    Etimaad Qatar LLC, as Project Manager                     Roles:   • EPIC of New LGO Tanks at QP Refinery, Mesaieed, Qatar of  US$ 110 Millions   • Leading, organizing, Planning, monitoring, controlling all activities of project execution.   • Carrying out the project plan in order to achieve the project objectives.   • Managing critical interfaces with project team and stakeholders  • Exercise the "soft skills." Skills such as communicating clearly, team motivation, and conflict resolution.  • Leading projects by Setting team direction, coordinating activities across different departments, Motivating,  Assigning work  • Organizing by Determine the organizational structure of the project team, Identify roles and positions, Identify services to  be provided by external companies, Staff project positions  • Planning by define and clarify project scope, develop the project plan, develop the project schedule, develop policies and  procedures to support the achievement of the project objectives  • Project controlling by defining baselines, tracking progress, status reporting, determining and taking corrective actions  • Keeping the project on track through project control and performed process like Measuring, Evaluating, Correcting  • Presentation  for  management,  attended  client  progress  review  meetings,  construction  strategy,  risk  management  and   other management requirements  • Led a team members and conducted joint workshop for Risk of project to prepare and finalize the risk register  • Continuous  Improvement  in  performance,  productivity  and  progress  for  client  satisfaction  and  profitability  to  achieve  agreed milestones    Dec’13‐Aug’14    Essar Projects  • Essar Projects Mauritania SARL, Mauritania, as Lead Project Control (Jun’14‐Aug’14) functioning from HO  Mumbai and Engineering office, Hazira, Gujarat, India  • Planning,  monitoring  and  control  of  7.5  MTPA  Iron  Ore  Beneficiation  EPC  Project  at  Askaf  site  near  Zeurate in Mauritania for Spear Mauritania (Subsidiaries of Glencore, Switzerland) of US$ 600 Millions  • Schedule development and approval of procedures, planning packages for functioning project control  • Established DPR, WPR, MPR, MOM reporting systems and meeting management  • Implementing new software requirement like ACONEX, WRENCH and integration with existing software  • Boost up the engineering required deliverable to create a work front for procurement team  • Follow up to approve immediate required engineering deliverable and procurement for pre construction activities  • Mobilization of equipments in lot wise as per plan and requirement  • Mobilization of Manpower as per plan and requirement  • Planned, monitored & controlled of project for timely delivery of project deliverables  • Essar Construction Overseas Ltd, Abu Dhabi, UAE as Project Control Manager (Dec’13‐May’14)    • Managed the replacement of EPC 16” Condensate Pipeline 110 KM from Habshan to Ruwais for GASCO EPC Project & PMC  by EIL – Engineers India Limited  • Planned, monitored & controlled of project for timely delivery of project deliverables  • Implemented recovery plan in Primavera schedule with supporting elements of Project Control Package and development of  detailed schedule for construction to control project timeline  • Developed  of  schedule  analysis  report,  delay  analysis  report  and  action  plan  to  recover  progress.  Update  schedule  assumptions  • Presentation  for  management,  attended  client  progress  review  meetings,  construction  strategy,  risk  management  and   other management requirements  • Handled the Earn Value Management (EVM), conducted delay analysis, implemented value engineering and validation of  project schedules and progress reports  • Led a team members and conducted joint workshop for Risk of project to prepare and finalize the risk register    Mar’13‐Nov’13    National Iranian Oil Company, Assaluyeh, Iran for Lead Project Management Team             Key Result Areas  • Managed South Pars Gas Field Development Project Phase‐22, 23, 24 at Asaluyeh, Iran of US$ 2.9 Billions • Strengthening PMT – Project Management Team to control 1 part (Refinery) of onshore and 3 parts (Wells, Platforms, Sub  sea pipelines) of offshore project  • Prepared strategy for project execution plan and manages contractors for various requirements at site for all phases like  mobilization, execution, scope change and close out  • Schedule  control  for  Drilling,  Casings, Platforms  fabrication,  transportation,  Installation,  Jacket  installation, Flow  Line,  Pipeline,  Well  Heads,  Umbilical,  Sub  sea  systems,  HIPPS,  Sub  sea  pipeline  by  advanced  pipeline  laying  barge,  Pig  launcher/receiver etc.  • Chasing to complete balance scope for construction execution and control schedule variance to meet project timeline 
  • 3. • Offered  special  consultation  for  Implementation  of  IOR  –  Improved  Oil  Recovery  requirement  by  installation  CDS,  RDS,  MSMs, MPFMs, Tie‐ins, utilities and support facilities, gas dehydration unit, pumps and new gas Lift Network in ongoing  operation of NIOC  • Handled a team of 10 members                                                                                                                                                                                                      May’12‐Feb’13        Larsen &Toubro, Hydrocarbon, Jubail, Saudi Arabia as Planning Manager                                    Key Result Areas  • Led Project Controller for EPC Project for SADARA (A Joint Venture of ARAMCO with DOW Chemical, USA) for Solution  Polyethylene Train‐1, 2 and  4 Project of value US $ 180 Million & 20 Millions Man‐Hours  • Interacted with client project management team from JACOB, USA as well as conducted engineering package release &  deliverables alignment workshop with DOW Chemical, USA.  • Assured  timely  development  of  Primavera  schedule  with  resource  (Labour  &  Material)  loading,  levelling  to  calculate  manpower & material requirement in time phase in concern with engineering, procurement and construction team  • Assisted  project management team during  verification  and  preparation  of  physical progress on monthly  basis to  enable  payments, etc.    Aug’10‐Apr’12:     Kharafi National, Kuwait as Sr. Cost & Planning Engineer    Key Result Areas  • Prepared WBS, L4 detailed schedule, assignment, levelling in Primavera P6.  • Updated the project progress in PMS & P6 schedule to prepare 3WLA & 4 MLA schedule  • Prepared detailed manpower, equipments utilization report for PM, MP and OM  • Analyzed cost variances of cost performance against budget to provide recommendations to PM & PCM  • Handled a team of 12 employees    PREVIOUS EXPERIENCE  May’09‐Jun’10   : Descon Engineering Company, Doha, Qatar as In‐charge of Planning Department  Sep’06‐Apr’09   : Amir Kabir Petrochemicals Company, Mahshahr, Iran as Specialist Planning  Jul’04‐Apr’06     : Pithawala Engineering & Construction Company, Mahshahr, Iran as Assistant Project Manager  Oct’93‐Jul’04     : Gujarat State Fertilizer & Chemical Limited, Vadodara as Senior Mechanical Engineer                                                                EDUCATION    1992      BE (Mechanical) from Regional Engineering College, Rourkela, India                                       (Now NIT National Institute of Technology, Rourkela, India)             IT SKILLS   • Well versed with   o Microsoft Project / P3 / Primavera P6 Version 7.0/8.2  o MS‐Office (Word/Excel/Access, PowerPoint)  o CMMS of Nazm Afrin & CMMS of IMPACT  o SAP Oracle and AutoCAD‐2007  o Acumen Fuse to improve quality of Primavera Schedule   o PRA – Primavera Risk Analysis  o ACONEX for documents flow  o WRENCH for progress monitoring & control    PERSONAL DETAILS  Date of Birth         : 28th  June, 1971  Language          : English, Hindi, Gujarati  Address     : 33, Madhuvan Society, Abhilasha Crossing, New Sama Road, Vadodara‐390008, Gujarat, India  Nationality    : Indian  Marital Status    : Married  No. of dependants  : Two   Driving Details    : Kuwait 271062804228 till 25‐May‐21, Qatar till 2020, India : GJ06 19930065021 Valid till 27‐Jun‐21  Passport No.    : Z1885432 Valid till 02‐Nov‐2020 
  • 4. ANNEXURE    MAJOR PROJECTS EXECUTED    • EPIC of New LGO Tanks at QP Refinery, Mesaieed, Qatar   • 7.5 MTPA Iron Ore Beneficiation EPC Project at Askaf site near Zeurate in Mauritania for Spear Mauritania (Subsidiaries of  Glencore, Switzerland  • Replacement of 16” Condensate Pipeline from Habshan to Ruwais, Abu Dhabi, UAE  • South Pars Gas Field Development Project Phase‐22,23,24 at Asaluyeh, Iran  • EPC Solution Polyethylene Project, Jubail, Saudi Arabia, SADARA (A Joint Venture of ARAMCO with DOW Chemical, USA)  • EPC Mishrif Pumping Station Project, MEW Ministry of Electricity and Water, Kuwait.  • Petrofac ‐ KOC Pipeline 125 KM & Facilities Works Construction Project, Kuwait  • EPC Regeneration Gas Heater Train‐1 & 3, Qatar Gas, Qatar  • Repairing of Cyclone line of 4000 MTPD at Qatar National Cement Company, Qatar  • Flare Gas Piping Construction Project, Chiyoda Technip Joint Venture, Qatar  • Storage Tank Piping Construction Project, Ras Gas, Qatar  • Annual Shutdown 2010 for Train‐3 & 4, Qatar Gas, Qatar  • Annual Shutdown 2010, Qatar Fertilizers Company, Qatar  • LDPE Project, Amir Kabir Petrochemical Company, Iran  • Combined Cycle Co‐Generation Power Plant, Phase‐III 25MW, Gujarat State Fertilizers Company Ltd., Baroda  • Linde Ammonia‐IV 1,350 MTPD Project, Gujarat State Fertilizers Company Ltd., Baroda  • Melamine‐II 10,000 MTPA Project, Gujarat State Fertilizers Company Ltd., Baroda  • Nylone‐6 15,000 MTPA Project, Gujarat State Fertilizers Company Ltd., Baroda    At Essar Projects Groups :  • Essar  Projects  Mauritania  SARL,  Mauritania  as  Lead  Project  Control  (Jun’14‐Aug’14)  functioning  from  HO  Mumbai  and  Engineering office, Hazira, Gujarat, India  7.5 MTPA Iron Ore Beneficiation EPC Project at Askaf site near Zeurate in Mauritania for Spear Mauritania (Subsidiaries of  Glencore, Switzerland  • Essar Construction Overseas Limited, Abu Dhabi, UAE as Project Control Manager   Replacement of 16” Condensate Pipeline 110 KM from Habshan to Ruwais for GASCO & PMC EIL – Engineers India Limited    At National Iranian Oil Company  • Leading in project management activities for successful delivery of project deliverables.  • Involved to arranges all resources like materials, subcontractors, manpower and equipments to control schedule variance  and control schedule and resources for project requirement.   • Alignment of departments and project team with clear forward path and detailed plan for corrective actions with target  time.   • EVM, root cause analysis reports, trend analysis, forecast timeline report, consultation and recommendations for all 4 parts  of project like:  o Onshore Refinery Project  o Offshore Drilling 38 wells  o Subsea Pipeline 4 Nos. 130 KM each (2 Nos. 32” & 4.5” 130KM each & additional 1 Nos. 18” 6KM & 20” 8KM)  o Fabrication and Installation of Unmanned Platforms ‐ 4 Nos.    At Larsen &Toubro, Hydrocarbon, Jubail, Saudi Arabia   • Solution Polyethylene Train‐1 Project    At Kharafi National, Kuwait   • Lead Project Controller for MEW Mishrif Pumping Station EPC Project for various clients requirements  • Lead Project Controller for Petrofac ‐ KOC Pipeline : 125 KM & Facilities Works Project for 42/52” FG pipeline 60KM, 24” GO  Pipeline 60KM, 10”/16” GO pipeline 5KM,  Pumping stations, Pigging facility 12 Units, Sectionalizing  Valve  Stations 8 Nos.,  Metering and Control facility 4 Nos., Instrument Air package‐5 Nos., Metering Packages 11 Nos., Tie‐ins, Shelters, Analyzer  House 5 Nos., FGBS Fuel Gas Booster Stations, CM/BP/OW Pits etc.  • Lead Project Controller role at PCD Project Control Department, Head Office for Cost Controlling of FM Facility Maintenance  Projects (Industrial, Sewage & Water) of KNPC, KOC, EQUATE, MEP  • Site Manpower regular dealing ‐ 34 Nos. Manpower reporting ‐ 3 Nos.       
  • 5.   At Descon Engineering Company, Doha  • EPC Projects :        Qatar Gas        EPC Jobs for Regeneration Gas Heater Train‐1 & 3  QNCC        Repairing of Cyclone line of 4000 MTPD Jobs at Cement Plant  • Construction Projects :        CTJV       Flare Gas Piping Job    Ras Gas          Storage Tank Piping Job  • Shutdown Projects :        Qatar Gas       Annual Shutdown 2010 for Train‐3 & 4    QAFCO      Annual Shutdown 2010    At Amir Kabir Petrochemicals Company, Mahshahr, Iran  • LDPE – Low Density Polyethylene Project    At Gujarat State Fertilizer & Chemical Limited, Vadodara  • Combined Cycle Co‐Generation Power Plant, Phase‐III 25MW  • Ammonia‐IV 1,350 MTPD Project, Linde  • Melamine‐II 10,000 MTPA Project  • Nylone‐6 15,000 MTPA Project    EXTRAMURAL ENGAGEMENTS    • Holds the merit of being  recognised as winner for Table Tennis in 1994 & 1995, GSFC, Vadodara, India  • Actively took part in Indian Folk Dance in 1990 at “Spring Time” Festival in Regional Engineering College, Rourkela, India  • Merit of winning:  o Chess Competition in 1995, GSFC, Vadodara, India  o 5th  position in chess in 2007 & recognised as winner for Group Chess in 2009 in AKPC, IRAN  • Successfully Served as a member for Toast Masters Club, KSA    TRAININGS ATTENDED    • PRA – Primavera Risk Analysis training and workshop on schedule for quarterly risk review  • PMP – Project Management Professional online training through Knowledge Woods, India in Nov’13  • Team Building Management Program by L&T  • In‐house Training for Planning & Project Control at Kharafi National, Kuwait  • integrated management system & project management system at Descon Engineering  • Training for safety induction and H2S at CTJV & Qatar Gas  • Certificate course for PRIMAVERA, Sure Track Project Manager 2.0 in Apr‐May 2007  • Microsoft Project in training centre of AKPC, Iran  • Industrial Hydraulic Systems at Vickers International hydraulic school in Bombay  • Heavy Mobile Equipments by TATA, VOLTAS & SAN Locomotives  • Maintenance Machinery, Spare Parts Planning, Safety Standard, ISO‐9000, ISO‐9002, ISO‐14000 in GSFC, Baroda   • Mysore Kirloskar Ltd., Harihar, Karnataka in May’91  • Research Design & Standard Organization, Lucknow in May’90    WORKSHOP ATTENDED    • “Workshop on Shutdown Management” by The Institute of Engineers (India) Qatar in 2010