How to manage agile fixed-price projects?
Tassilo Kubitz
10.04.2017
Tassilo Kubitz
• 1969 / Berlin
• Meteorologist
• 20 years – IT / Software development / Team lead / Project lead
• Head of Competence Center Project Management akquinet tech@spree GmbH
akquinet tech@spree GmbH
• Part of the akquinet AG (IT consultancy)
• Individual software development projects
• Across the industry
• Industry 4.0 / Enterprise Mobility, e.g.
• Production planning (knitting machines)
• Remote maintenance (glove boxes)
• Fleet management (forklift)
• Flexible project management (from traditional to agile)
Who has experiences with…
• …the classical / traditional approach?
• …agile methods?
• …both „worlds“?
Agenda
• Agile meets classic – Can one combine that?
• Why is only the product owner to be strangled?
• How to manage agile fixed-price projects?
• Pitfalls
• Conclusion
Agenda
• Agile meets classic – Can one combine that?
• Why is only the product owner to be strangled?
• How to manage agile fixed-price projects?
• Pitfalls
• Conclusion
The agile fixed-price…
Is that a contradiction?
Why?
Agile meets classic – Can one combine that?
Yegor Bugayenko
12 Mistakes in agile manifesto
The Manifesto doesn't say anything
about the cost of development
and that's probably because it was
written by those who make money
(programmers),
not those who spend it (customers).
Agile meets classic – Can one combine that?
Individuals and interactions over processes and tools
Working software over comprehensive documentation
Customer collaboration over contract negotiation
Responding to change over following a plan
So why not combine?Over does not mean instead!
Agile meets classic – Can one combine that?
• There is no generally correct procedure - there is always only appropriate procedure
• The border from traditional to
agile is fluent…
• So why not combine?
by Baf Kurtulaj
Agile meets classic – Can one combine that?
• The Requirements of our customers
• Compliance with a budget limit
• Plannability of deadline and costs
• Flexibility throughout the project
• Lightweight change management
• So why not combine?
– agile
– agile
– traditional
– traditional
Agile meets classic – can one combine that?
The agile fixed-price project
is possible!
The agile fixed-price project…
• Where is the agility?
• User Story
• Iterations
• New feature requests
• Where is the streering?
• Preliminary planning
• Choosing the next story
• Adaption of the roadmap
• Where is the fixed price?
• Budget frame
• Implementation in fixed-price
Agenda
• Agile meets classic – Can one combine that?
• Why is only the product owner to be strangled?
• How to manage agile fixed-price projects?
• Pitfalls
• Conclusion
Why is only the product owner to be strangled?
• The „traditional“ PM says about controlling/steering…
=> To keep time and cost, you have to change scope/quality…
Quality
Time Cost
Scope
Why is only the product owner to be strangled?
• The product owner…
• represents the client and thus all stakeholders
• attends the daily scrums to get informed (passively)
• is ready to answer the questions of the team
• maintains the product backlog
• prioritizes the product backlog items so that the business value of the product is maximized
and the possibility of early releases of core functionality to achieve a rapid return on
investment
Why is only the product owner to be strangled?
• The product owner is responsible for
• ensuring that the correct requirements are in the product backlog
=> Very high business domain knowledge
• for the fact that they are processed in a meaningful order
=> Technology decisions require architectural knowledge
• And now he has to be responsible for dates and budget…
Agenda
• Agile meets classic – Can one combine that?
• Why is only the product owner to be strangled?
• How to manage agile fixed-price projects?
• Pitfalls
• Conclusion
How to manage agile fixed-price projects?
• Effective control means…
• …always know where you are and where you want to go
• …make changes to the plan possible at any time to get where you want to go
Where you want to go to?
• If the project is cut right from the beginning, then it
will be easier to control…
• Setup with the benefit of a requirement with
an impact map
• Structuring the roadmap with
the story map
• Adjust the roadmap with
the Kano model
By Craigwbrown - Own work, CC BY-SA 3.0
www.impactmapping.org
Winnipeg Agilist
Make changes to the plan possible
„parallelize the waterfall“ - time2market
Analysis/Design Implementation Acceptance
Feature 1
Feature 2
Feature 3
Earlier releases
Make changes to the plan possible
Prioritize with Lean Management – design2cost
Analysis/Design Implementation
Feature 1
Feature 2
Feature 3
Reduced costs and earlier releases
Acceptance
How to manage agile fixed-price projects?
• Premilinary Planning
• Big Picture
• Impact Map
• Story Map
• First roadmap
• Rough estimate
• Pick a story
• User Stories
• Estimation
• Use the roadmap
• Implementation
• Priorization
• Omitting
• Adding
• Estimation
Continuous recording and
evaluation of budget and deadlines!!
Agenda
• Agile meets classic – Can one combine that?
• Why is only the product owner to be strangled?
• How to manage agile fixed-price projects?
• Pitfalls
• Conclusion
Pitfalls…
• The project must fit!
 This method is not suitable for any project
• Communication expenditure (for changing the plan)
 Flexibility costs and needs a separate cost center!
• Understanding and trust for the process (the agile mindset) does not come about the
paper called "contract"
 Simulation of the procedure in a workshop (don‘t forget the role purchase)
 Start with smaller budgets or define exit points after each release
Agenda
• Agile meets classic – Can one combine that?
• Why is only the product owner to be strangled?
• How to manage agile fixed-price projects?
• Pitfalls
• Conclusion
Conclusion
• Agility is controllable when the project is set up accordingly
• benefit and value (Impact Mapping…)
• Method is suitable for traditional thinking customers
• time2market
• design2cost
• Applicable when trust is present
• internal projects
• further development projects
This is the end…
Thank you!
The final discussion is open 
Sources
• http://agilemanifesto.org
• https://dzone.com/articles/twelve-mistakes-in-agile-manifesto
• https://www.linkedin.com/pulse/why-stacey-matrix-model-can-help-understand-agile-baf-kurtulaj-mba
• https://www.impactmapping.org/
• http://winnipegagilist.blogspot.de/2012/03/how-to-create-user-story-map.html
• https://commons.wikimedia.org/w/index.php?curid=23262780
• https://de.slideshare.net/iku165/d42-ma2015-tassilokubitzagilefestpreisprojekte

More Related Content

PPTX
Agile fixed-price-slide share
PDF
Scaling Agile With SAFe (Scaled Agile Framework)
PDF
Agile transformation 1.3
PPTX
The Agile PMO
PPTX
Business Agility 2017 (final)
PPTX
Rick Austin - Portfolio mangement in an agile world [Agile DC]
PPTX
Scrum Master Interview Questions SlideShare
PDF
Agile Transformation Defined
Agile fixed-price-slide share
Scaling Agile With SAFe (Scaled Agile Framework)
Agile transformation 1.3
The Agile PMO
Business Agility 2017 (final)
Rick Austin - Portfolio mangement in an agile world [Agile DC]
Scrum Master Interview Questions SlideShare
Agile Transformation Defined

What's hot (20)

PDF
Agile Transformation at Scale
PDF
Certified Scrum Product Owner: class desk, posters and photos
PPTX
What is Agile Project Management? | Agile Project Management | Invensis Learn...
PDF
SAFe® PI Planning - 4 locations - but how?
PDF
Agile Transformation
PDF
10 steps to a successsful enterprise agile transformation global scrum 2018
PPTX
Introduction to SAFe, the Scaled Agile Framework
PPTX
Agile Transformation Journey on Large Scale Projects
PDF
Agile Transformation Explained
PDF
10 Essential SAFe(tm) patterns you should focus on when scaling Agile
PDF
Creating Valuable PI objectives v1.1.2 - OLD VERSION
PPTX
Never Miss An Opportunity: How ISO 56000 Enables an Innovative Organization
PPTX
Scrum Training (One Day)
PDF
Agile transformation Explanined
PDF
Scrum guide presentation (Scrum Guide in easy to read PPT format)
PPTX
Agile 101
PPTX
What is Value Stream Management and why do you need it?
PDF
Agile & Scrum Training
PPT
Agile Project Management for IT Projects
PPTX
Agile Principles, Agile People
Agile Transformation at Scale
Certified Scrum Product Owner: class desk, posters and photos
What is Agile Project Management? | Agile Project Management | Invensis Learn...
SAFe® PI Planning - 4 locations - but how?
Agile Transformation
10 steps to a successsful enterprise agile transformation global scrum 2018
Introduction to SAFe, the Scaled Agile Framework
Agile Transformation Journey on Large Scale Projects
Agile Transformation Explained
10 Essential SAFe(tm) patterns you should focus on when scaling Agile
Creating Valuable PI objectives v1.1.2 - OLD VERSION
Never Miss An Opportunity: How ISO 56000 Enables an Innovative Organization
Scrum Training (One Day)
Agile transformation Explanined
Scrum guide presentation (Scrum Guide in easy to read PPT format)
Agile 101
What is Value Stream Management and why do you need it?
Agile & Scrum Training
Agile Project Management for IT Projects
Agile Principles, Agile People
Ad

Similar to How to manage agile fixed-price projects? (20)

PPTX
Андрій Просов “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
PPTX
Андрій Просов "Fixed Price Agile Projects: Challenges for Project Manager" Kh...
PDF
Planning for Fixed Price Agile projects. Second step_Problem investigation.
PPTX
Agile Projects Estimations and Planning
PDF
An Agile Twist: Fixed-Bid Pricing
PPTX
Agile Projects Estimation and Planning
PPTX
Agile, PMI and PMBOK
PDF
Working With Agile Suppliers Toby Mckenzie
PPTX
Agile fix cost_pecha_kucha
PPT
Using Agile Approach with Fixed Budget Projects
PPTX
Agile and fixed budget projects
PPT
Agile softwareengineering
PPTX
Андрій Просов “Управління очікуваннями клієнтів в проектах з використанням гн...
PPTX
Андрій Просов: Managing Client Expectations in Fixed Price Agile Projects by ...
PDF
How to successfully execute fixed price agile projects
PDF
Lean & Agile Project Manaagement: Its Leadership Considerations
PPTX
Importance of Adaptive Planning in Agile
PDF
Business Value of Agile Methods: Its Leadership Considerations
PDF
Agile pmo brussels 2012
PDF
Introduction to Agile Methods
Андрій Просов “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
Андрій Просов "Fixed Price Agile Projects: Challenges for Project Manager" Kh...
Planning for Fixed Price Agile projects. Second step_Problem investigation.
Agile Projects Estimations and Planning
An Agile Twist: Fixed-Bid Pricing
Agile Projects Estimation and Planning
Agile, PMI and PMBOK
Working With Agile Suppliers Toby Mckenzie
Agile fix cost_pecha_kucha
Using Agile Approach with Fixed Budget Projects
Agile and fixed budget projects
Agile softwareengineering
Андрій Просов “Управління очікуваннями клієнтів в проектах з використанням гн...
Андрій Просов: Managing Client Expectations in Fixed Price Agile Projects by ...
How to successfully execute fixed price agile projects
Lean & Agile Project Manaagement: Its Leadership Considerations
Importance of Adaptive Planning in Agile
Business Value of Agile Methods: Its Leadership Considerations
Agile pmo brussels 2012
Introduction to Agile Methods
Ad

More from Tassilo Kubitz (12)

PPTX
Modern-RE_Tassilo_Kubitz-Von_der_Impact_Map_zur_User_Story-20170920.pptx
PPTX
Modern-RE_Tassilo_Kubitz-Der_Beitrag_von_RE_zur_Steuerung_Agiler_Festpreispro...
PDF
2018 06-20-agile-leadership-meetup#2
PDF
Step aside I am certifed
PDF
Manage agile skills-der-handelnden-personen-im-agilen-festpreisprojekt-ein-pe...
PDF
Der Beitrag von Requirements Engineering zur Steuerung Agiler Festpreisprojekte
PDF
Von der Impact Map zur User Story - Anforderungsanalyse in einem langlaufende...
PDF
Sind Agile Festpreisprojekte steuerbar?
PDF
D4.2 ma2015 tassilo-kubitz_agile-festpreisprojekte
PDF
20150701 agile contracts_tassilo-kubitz_agile-festpreisprojekte
PDF
20150508 sea con_tassilo-kubitz_agile-festpreisprojekte
PDF
Manage Agile 2014 - Agile Festpreisprojekte - Risiko oder Chance?
Modern-RE_Tassilo_Kubitz-Von_der_Impact_Map_zur_User_Story-20170920.pptx
Modern-RE_Tassilo_Kubitz-Der_Beitrag_von_RE_zur_Steuerung_Agiler_Festpreispro...
2018 06-20-agile-leadership-meetup#2
Step aside I am certifed
Manage agile skills-der-handelnden-personen-im-agilen-festpreisprojekt-ein-pe...
Der Beitrag von Requirements Engineering zur Steuerung Agiler Festpreisprojekte
Von der Impact Map zur User Story - Anforderungsanalyse in einem langlaufende...
Sind Agile Festpreisprojekte steuerbar?
D4.2 ma2015 tassilo-kubitz_agile-festpreisprojekte
20150701 agile contracts_tassilo-kubitz_agile-festpreisprojekte
20150508 sea con_tassilo-kubitz_agile-festpreisprojekte
Manage Agile 2014 - Agile Festpreisprojekte - Risiko oder Chance?

Recently uploaded (20)

PPTX
Strategic Plan 2023-2024 Presentation.pptx
PDF
Case study -Uber strategic plan and management
PDF
Timeless Leadership Principles from History’s Greatest Figures by Alfonso Ken...
PPTX
Mangeroal Finance for Strategic Management
PPTX
_ISO_Presentation_ISO 9001 and 45001.pptx
PPTX
The Sustainable Site: Boosting Productivity in Construction – Pipe Dream or P...
PDF
MANAGEMENT LESSONS FROM ANCIENT KNOWLEDGE SYSTEM-ARTHASHASTRA AND THIRUKKURAL...
PDF
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
PPTX
Human resources management -job perception concept
PDF
Air India AI-171 Crash in Ahmedabad A Tragic Wake-Up Call.
PDF
Maintaining a Quality Culture - Performance Metrics, Best Practices and QMS E...
PPTX
2. CYCLE OF FUNCTIONING RIFLE -PP Presentation..pptx
PPTX
Course Overview of the Course Titled.pptx
PPTX
BASIC H2S TRAINING for oil and gas industries
PPTX
Effective_communication._(strategy).pptx
PDF
CHAPTER 15- Manageement of Nursing Educational Institutions- Staffing and st...
PPTX
Course Overview of the Course Titled.pptx
PDF
CISSP Domain 5: Identity and Access Management (IAM)
PPTX
Five S Training Program - Principles of 5S
PPTX
Project Management Methods PERT-and-CPM.pptx
Strategic Plan 2023-2024 Presentation.pptx
Case study -Uber strategic plan and management
Timeless Leadership Principles from History’s Greatest Figures by Alfonso Ken...
Mangeroal Finance for Strategic Management
_ISO_Presentation_ISO 9001 and 45001.pptx
The Sustainable Site: Boosting Productivity in Construction – Pipe Dream or P...
MANAGEMENT LESSONS FROM ANCIENT KNOWLEDGE SYSTEM-ARTHASHASTRA AND THIRUKKURAL...
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
Human resources management -job perception concept
Air India AI-171 Crash in Ahmedabad A Tragic Wake-Up Call.
Maintaining a Quality Culture - Performance Metrics, Best Practices and QMS E...
2. CYCLE OF FUNCTIONING RIFLE -PP Presentation..pptx
Course Overview of the Course Titled.pptx
BASIC H2S TRAINING for oil and gas industries
Effective_communication._(strategy).pptx
CHAPTER 15- Manageement of Nursing Educational Institutions- Staffing and st...
Course Overview of the Course Titled.pptx
CISSP Domain 5: Identity and Access Management (IAM)
Five S Training Program - Principles of 5S
Project Management Methods PERT-and-CPM.pptx

How to manage agile fixed-price projects?

  • 1. How to manage agile fixed-price projects? Tassilo Kubitz 10.04.2017
  • 2. Tassilo Kubitz • 1969 / Berlin • Meteorologist • 20 years – IT / Software development / Team lead / Project lead • Head of Competence Center Project Management akquinet tech@spree GmbH
  • 3. akquinet tech@spree GmbH • Part of the akquinet AG (IT consultancy) • Individual software development projects • Across the industry • Industry 4.0 / Enterprise Mobility, e.g. • Production planning (knitting machines) • Remote maintenance (glove boxes) • Fleet management (forklift) • Flexible project management (from traditional to agile)
  • 4. Who has experiences with… • …the classical / traditional approach? • …agile methods? • …both „worlds“?
  • 5. Agenda • Agile meets classic – Can one combine that? • Why is only the product owner to be strangled? • How to manage agile fixed-price projects? • Pitfalls • Conclusion
  • 6. Agenda • Agile meets classic – Can one combine that? • Why is only the product owner to be strangled? • How to manage agile fixed-price projects? • Pitfalls • Conclusion
  • 7. The agile fixed-price… Is that a contradiction? Why?
  • 8. Agile meets classic – Can one combine that? Yegor Bugayenko 12 Mistakes in agile manifesto The Manifesto doesn't say anything about the cost of development and that's probably because it was written by those who make money (programmers), not those who spend it (customers).
  • 9. Agile meets classic – Can one combine that? Individuals and interactions over processes and tools Working software over comprehensive documentation Customer collaboration over contract negotiation Responding to change over following a plan So why not combine?Over does not mean instead!
  • 10. Agile meets classic – Can one combine that? • There is no generally correct procedure - there is always only appropriate procedure • The border from traditional to agile is fluent… • So why not combine? by Baf Kurtulaj
  • 11. Agile meets classic – Can one combine that? • The Requirements of our customers • Compliance with a budget limit • Plannability of deadline and costs • Flexibility throughout the project • Lightweight change management • So why not combine? – agile – agile – traditional – traditional
  • 12. Agile meets classic – can one combine that? The agile fixed-price project is possible!
  • 13. The agile fixed-price project… • Where is the agility? • User Story • Iterations • New feature requests • Where is the streering? • Preliminary planning • Choosing the next story • Adaption of the roadmap • Where is the fixed price? • Budget frame • Implementation in fixed-price
  • 14. Agenda • Agile meets classic – Can one combine that? • Why is only the product owner to be strangled? • How to manage agile fixed-price projects? • Pitfalls • Conclusion
  • 15. Why is only the product owner to be strangled? • The „traditional“ PM says about controlling/steering… => To keep time and cost, you have to change scope/quality… Quality Time Cost Scope
  • 16. Why is only the product owner to be strangled? • The product owner… • represents the client and thus all stakeholders • attends the daily scrums to get informed (passively) • is ready to answer the questions of the team • maintains the product backlog • prioritizes the product backlog items so that the business value of the product is maximized and the possibility of early releases of core functionality to achieve a rapid return on investment
  • 17. Why is only the product owner to be strangled? • The product owner is responsible for • ensuring that the correct requirements are in the product backlog => Very high business domain knowledge • for the fact that they are processed in a meaningful order => Technology decisions require architectural knowledge • And now he has to be responsible for dates and budget…
  • 18. Agenda • Agile meets classic – Can one combine that? • Why is only the product owner to be strangled? • How to manage agile fixed-price projects? • Pitfalls • Conclusion
  • 19. How to manage agile fixed-price projects? • Effective control means… • …always know where you are and where you want to go • …make changes to the plan possible at any time to get where you want to go
  • 20. Where you want to go to? • If the project is cut right from the beginning, then it will be easier to control… • Setup with the benefit of a requirement with an impact map • Structuring the roadmap with the story map • Adjust the roadmap with the Kano model By Craigwbrown - Own work, CC BY-SA 3.0 www.impactmapping.org Winnipeg Agilist
  • 21. Make changes to the plan possible „parallelize the waterfall“ - time2market Analysis/Design Implementation Acceptance Feature 1 Feature 2 Feature 3 Earlier releases
  • 22. Make changes to the plan possible Prioritize with Lean Management – design2cost Analysis/Design Implementation Feature 1 Feature 2 Feature 3 Reduced costs and earlier releases Acceptance
  • 23. How to manage agile fixed-price projects? • Premilinary Planning • Big Picture • Impact Map • Story Map • First roadmap • Rough estimate • Pick a story • User Stories • Estimation • Use the roadmap • Implementation • Priorization • Omitting • Adding • Estimation Continuous recording and evaluation of budget and deadlines!!
  • 24. Agenda • Agile meets classic – Can one combine that? • Why is only the product owner to be strangled? • How to manage agile fixed-price projects? • Pitfalls • Conclusion
  • 25. Pitfalls… • The project must fit!  This method is not suitable for any project • Communication expenditure (for changing the plan)  Flexibility costs and needs a separate cost center! • Understanding and trust for the process (the agile mindset) does not come about the paper called "contract"  Simulation of the procedure in a workshop (don‘t forget the role purchase)  Start with smaller budgets or define exit points after each release
  • 26. Agenda • Agile meets classic – Can one combine that? • Why is only the product owner to be strangled? • How to manage agile fixed-price projects? • Pitfalls • Conclusion
  • 27. Conclusion • Agility is controllable when the project is set up accordingly • benefit and value (Impact Mapping…) • Method is suitable for traditional thinking customers • time2market • design2cost • Applicable when trust is present • internal projects • further development projects
  • 28. This is the end… Thank you! The final discussion is open 
  • 29. Sources • http://agilemanifesto.org • https://dzone.com/articles/twelve-mistakes-in-agile-manifesto • https://www.linkedin.com/pulse/why-stacey-matrix-model-can-help-understand-agile-baf-kurtulaj-mba • https://www.impactmapping.org/ • http://winnipegagilist.blogspot.de/2012/03/how-to-create-user-story-map.html • https://commons.wikimedia.org/w/index.php?curid=23262780 • https://de.slideshare.net/iku165/d42-ma2015-tassilokubitzagilefestpreisprojekte