Resources measurement and
its utilization
By
SELVAPRAKASH
INTRODUCTION
A resource is any entity that contributes to the accomplishment of project
activities like
Personnel
Equipment
Materials
Money
Time
WHAT AND WHY WE NEED RESOURCE
IDENTIFACTION
Once the Work Breakdown Structure (WBS) has
been applied and the project activities have been
identified, you are ready to identify the types (labor,
equipment, material) and quantities of the resources
needed to implement the project.
STEPS FOR IDENTIFICATION OFSTEPS FOR IDENTIFICATION OF
RESOURCERESOURCE
In order to identify the resource requirements the following steps should be
followed:
Review the project scope and activities/ tasks list
In order to identify the project’s requirements for people, equipment
and material resources.
Gather historical information
from old project files, databases and from people who have worked
on similar projects, regarding what types and numbers of resources were
required for performing similar work on previous projects, as well as the
duration of the relative tasks.
IDENTIFY THE RESOURCE TYPES AND
QUANTITIES NEEDED.
Once you have collected all the necessary information, identify the
types of resources and the quantities needed for each.
The duration of most tasks is also influenced by the capabilities
and experience of the resources assigned to them.
As you collect information about the project in hand and other
similar projects, continue to refine the duration estimates for the project
tasks. The accuracy of the duration estimates is closely related to the
accuracy of your resource requirements
Measurement of resources
LABOUR:
 The quantity of a labour resources is measured by
using the term Full Time Equivalent.
One FTE indicates one person that will work 8hrs per
day for 5 days per week.
Respectively 0.5 indicates one person that will spent
half of the full time in the project.
MATERIAL AND EQUIPMENT
The quantity of material resources is defined using
the appropriate measurement units for each material.
For example, 50 m of cable, 5 tn of cement, 50 kg of
plastic paint, etc., and the equipments are measured in
numbers. Example :2 dozers,2 cranes.
UTILISATION OF RESOURCES
Resource allocation
Resource leveling
Time-limited resource consideration
Resource-limited resource consideration
RESOURCE ALLOCATION
Resource allocation, also called resource loading, is
concerned with assigning the required number of
those resources identified in the previous step to each
activity identified in the plan.
 More than one type of resource may be attributed to
a specific activity
RESOURCE LEVELLING
Resource leveling is the process that ensures resource
demand does not exceed resource availability.
The ideal scenario would be a build up of resource usage at
the beginning of the project and a reduction at the end of the
project.
However, the approach to resource leveling will also depend
on whether resources are dedicated to a particular project or
shared across several projects and whether there is a need to
keep all resources fully utilized.
10.resources measurement and its utilization
TIME-LIMITED RESOURCE CONSIDERATION
In this case emphasis will be placed on completing
the project within a specified time.
This time will usually have been determined by
network analysis.
Adjustments in the timing of any activity,and the
resources required at a given time,must be
undertaken within the float available.
RESOURCE-LIMITED RESOURCE
CONSIDERATION
In this case the project must be completed with the
resources available even if this means extending the
project duration.
If the total resource demand exceeds the resource
availability at any time then some of the activities
must be delayed until there is sufficient resource
availability.
For level resources EST,LST and SLACK will be used.
10.resources measurement and its utilization

More Related Content

PPT
8. (lecture 6) Project Cost Control.ppt
PPTX
Role and Responsibilities of Project Manager
PPTX
Project cost control
PPTX
7.4 Earned Value Analysis
PPTX
Construction Cost Control
PPT
Project Planning and Development
PDF
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
PPTX
03 Construction Project Planning and Scheduling
8. (lecture 6) Project Cost Control.ppt
Role and Responsibilities of Project Manager
Project cost control
7.4 Earned Value Analysis
Construction Cost Control
Project Planning and Development
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
03 Construction Project Planning and Scheduling

What's hot (20)

PPTX
Construction Management & Equipments
PPTX
Earned value management (EVM)
PPT
Linear scheduling LSM
PPTX
Work breakdown structure ppt
PDF
Project cost management
PPTX
Water Requirements
PPTX
project monitoring and control
PPTX
What is construction management & its Benefits?
PPT
labour management
PPTX
Construction Planning
PPTX
Project Planning, Design and Management
PDF
Earned Value Management
PPTX
Construction planning - Construction Technology and Project Management
PDF
Construction Project Management
PPT
Earned Value Analysis
PPTX
Construction Documents
PDF
PPT on Construction Costing
PDF
Lecture 8 monitoring & controlling (1)
PDF
Introduction-construction management_Construction Management (2180611) (Semes...
PPTX
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
Construction Management & Equipments
Earned value management (EVM)
Linear scheduling LSM
Work breakdown structure ppt
Project cost management
Water Requirements
project monitoring and control
What is construction management & its Benefits?
labour management
Construction Planning
Project Planning, Design and Management
Earned Value Management
Construction planning - Construction Technology and Project Management
Construction Project Management
Earned Value Analysis
Construction Documents
PPT on Construction Costing
Lecture 8 monitoring & controlling (1)
Introduction-construction management_Construction Management (2180611) (Semes...
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
Ad

Viewers also liked (20)

PPTX
Fast track construction of elvated roads in metro
PPT
MAINTENANCE AND REPAIR STRATEGIES
PPTX
Productivity of human resources
PPT
04.development & operation of human resources
PPTX
Impact strength in concrete test
PPT
Advanced concrete technology 3
PPT
SERVICEABILITY OF CONCRETE
PPTX
Final review ppt project EFFECTIVENESS OF USING RECYCLED COARSE AGGREGATES IN...
PDF
Predicting 28 Days Compressive Strength of Concrete from 7 Days Test Result
PPT
Construction Management Project
PPTX
Flexural strength in concrete test
PDF
Project management in construction.
PPTX
Safety management for construction machines & equipments
PPTX
Engineering drawing
PPTX
Compressive strength of the concrete
PPTX
Durability of concrete
PPT
Split tensile strength in concrete
PPTX
The Ultimate Review of Construction Project Management Methodologies
PPTX
Chemical attack on concrete
PDF
Concrete durability
Fast track construction of elvated roads in metro
MAINTENANCE AND REPAIR STRATEGIES
Productivity of human resources
04.development & operation of human resources
Impact strength in concrete test
Advanced concrete technology 3
SERVICEABILITY OF CONCRETE
Final review ppt project EFFECTIVENESS OF USING RECYCLED COARSE AGGREGATES IN...
Predicting 28 Days Compressive Strength of Concrete from 7 Days Test Result
Construction Management Project
Flexural strength in concrete test
Project management in construction.
Safety management for construction machines & equipments
Engineering drawing
Compressive strength of the concrete
Durability of concrete
Split tensile strength in concrete
The Ultimate Review of Construction Project Management Methodologies
Chemical attack on concrete
Concrete durability
Ad

Similar to 10.resources measurement and its utilization (20)

PPT
project_management and its adoption_10.ppt
PPTX
Project Resource Allocation
PPTX
Allocating resources
PPTX
Resource planning and resource allocation
PPT
Resource-Allocation.ppt
PPT
Managing Project Resources
PPTX
Project Management
PPTX
Foro #1 integrative project lll
PPT
ch09s.ppt
PPT
Module :-5 project scheduling and resource levelling
PPT
Planning and scheduling Techniques.ppt
PDF
A brief on project time management
PPTX
Ch09 (1).pptx
PPTX
CE427-Chp6-Resource-Allocation-24Apr2019.pptx
PPTX
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
PPTX
PMNM101 Lesson 2 2022.pptx
PPTX
Part II: Planning Time: Determining When and How Much
PDF
PMP CAPM Study Guide Time Management
DOCX
MGT 3302, Introduction to Project Management 1 Cou.docx
PPTX
Pert,cpm, resource allocation and gert
project_management and its adoption_10.ppt
Project Resource Allocation
Allocating resources
Resource planning and resource allocation
Resource-Allocation.ppt
Managing Project Resources
Project Management
Foro #1 integrative project lll
ch09s.ppt
Module :-5 project scheduling and resource levelling
Planning and scheduling Techniques.ppt
A brief on project time management
Ch09 (1).pptx
CE427-Chp6-Resource-Allocation-24Apr2019.pptx
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
PMNM101 Lesson 2 2022.pptx
Part II: Planning Time: Determining When and How Much
PMP CAPM Study Guide Time Management
MGT 3302, Introduction to Project Management 1 Cou.docx
Pert,cpm, resource allocation and gert

More from Selva Prakash (17)

PDF
Design of-steel-structures bhavakkati- by easy engineering.net
PPT
Road Construction Work Zone Safety
PPT
safety and health programs
PPT
staffing ,recruitment and selection
PPS
Bandra worli sealink
PPT
DESIGN METHODLOGY
PPT
Green Technologies for Buildings
PPT
Detailed project report
PPTX
Burj khalifa
PPT
Engineering drawing graphics
PPT
Compressive strength in concrete test
PPT
Bond strenth
DOCX
Comparision of is 10262 1982 & 2009
PPTX
Advanced concrete technology 2
PPTX
Advanced concrete technology
PPTX
Hydraulics & hydraulic machinery
PPT
Organisation information
Design of-steel-structures bhavakkati- by easy engineering.net
Road Construction Work Zone Safety
safety and health programs
staffing ,recruitment and selection
Bandra worli sealink
DESIGN METHODLOGY
Green Technologies for Buildings
Detailed project report
Burj khalifa
Engineering drawing graphics
Compressive strength in concrete test
Bond strenth
Comparision of is 10262 1982 & 2009
Advanced concrete technology 2
Advanced concrete technology
Hydraulics & hydraulic machinery
Organisation information

Recently uploaded (20)

PPT
Project quality management in manufacturing
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
CH1 Production IntroductoryConcepts.pptx
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PPTX
Geodesy 1.pptx...............................................
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
DOCX
573137875-Attendance-Management-System-original
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PPTX
UNIT 4 Total Quality Management .pptx
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PDF
Well-logging-methods_new................
PPTX
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
PPTX
Strings in CPP - Strings in C++ are sequences of characters used to store and...
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
Lesson 3_Tessellation.pptx finite Mathematics
PPTX
Sustainable Sites - Green Building Construction
Project quality management in manufacturing
Operating System & Kernel Study Guide-1 - converted.pdf
CH1 Production IntroductoryConcepts.pptx
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
Geodesy 1.pptx...............................................
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Model Code of Practice - Construction Work - 21102022 .pdf
573137875-Attendance-Management-System-original
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
UNIT 4 Total Quality Management .pptx
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
Well-logging-methods_new................
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
Strings in CPP - Strings in C++ are sequences of characters used to store and...
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Lesson 3_Tessellation.pptx finite Mathematics
Sustainable Sites - Green Building Construction

10.resources measurement and its utilization

  • 1. Resources measurement and its utilization By SELVAPRAKASH
  • 2. INTRODUCTION A resource is any entity that contributes to the accomplishment of project activities like Personnel Equipment Materials Money Time
  • 3. WHAT AND WHY WE NEED RESOURCE IDENTIFACTION Once the Work Breakdown Structure (WBS) has been applied and the project activities have been identified, you are ready to identify the types (labor, equipment, material) and quantities of the resources needed to implement the project.
  • 4. STEPS FOR IDENTIFICATION OFSTEPS FOR IDENTIFICATION OF RESOURCERESOURCE In order to identify the resource requirements the following steps should be followed: Review the project scope and activities/ tasks list In order to identify the project’s requirements for people, equipment and material resources. Gather historical information from old project files, databases and from people who have worked on similar projects, regarding what types and numbers of resources were required for performing similar work on previous projects, as well as the duration of the relative tasks.
  • 5. IDENTIFY THE RESOURCE TYPES AND QUANTITIES NEEDED. Once you have collected all the necessary information, identify the types of resources and the quantities needed for each. The duration of most tasks is also influenced by the capabilities and experience of the resources assigned to them. As you collect information about the project in hand and other similar projects, continue to refine the duration estimates for the project tasks. The accuracy of the duration estimates is closely related to the accuracy of your resource requirements
  • 6. Measurement of resources LABOUR:  The quantity of a labour resources is measured by using the term Full Time Equivalent. One FTE indicates one person that will work 8hrs per day for 5 days per week. Respectively 0.5 indicates one person that will spent half of the full time in the project.
  • 7. MATERIAL AND EQUIPMENT The quantity of material resources is defined using the appropriate measurement units for each material. For example, 50 m of cable, 5 tn of cement, 50 kg of plastic paint, etc., and the equipments are measured in numbers. Example :2 dozers,2 cranes.
  • 8. UTILISATION OF RESOURCES Resource allocation Resource leveling Time-limited resource consideration Resource-limited resource consideration
  • 9. RESOURCE ALLOCATION Resource allocation, also called resource loading, is concerned with assigning the required number of those resources identified in the previous step to each activity identified in the plan.  More than one type of resource may be attributed to a specific activity
  • 10. RESOURCE LEVELLING Resource leveling is the process that ensures resource demand does not exceed resource availability. The ideal scenario would be a build up of resource usage at the beginning of the project and a reduction at the end of the project. However, the approach to resource leveling will also depend on whether resources are dedicated to a particular project or shared across several projects and whether there is a need to keep all resources fully utilized.
  • 12. TIME-LIMITED RESOURCE CONSIDERATION In this case emphasis will be placed on completing the project within a specified time. This time will usually have been determined by network analysis. Adjustments in the timing of any activity,and the resources required at a given time,must be undertaken within the float available.
  • 13. RESOURCE-LIMITED RESOURCE CONSIDERATION In this case the project must be completed with the resources available even if this means extending the project duration. If the total resource demand exceeds the resource availability at any time then some of the activities must be delayed until there is sufficient resource availability. For level resources EST,LST and SLACK will be used.