Nisqually 2018 Grant Round
& New Project List
Nisqually River Council, May 2018
A few grant round details..
2018 SRFB allocation: estimated $400,000
2019-2021 PSAR planning year: estimated $1.4 million
8 pre-applications submitted
Total Request: $2,945,297
Total Match: $524,563
Project Grand Total: $3,469,860
Site Visits with the SRFB Review Panel
2018 SRFB PSAR Project List for
McKenna Reach Protection and
Restoration
• Sponsor: Nisqually Land Trust
• Amount Requested: $528,689
• Acquisition of 65 acres along mainstem, including .7 miles of
shoreline
• Stewardship activities are planned throughout, including invasive
vegetation control and plantings
• Site specific information unavailable at this time
• Amount Requested: $237,362
• Acquisition of 6.4 undeveloped acres along the northern
shoreline of the Nisqually mainstem
• This project would protect 4 of 15 parcels that are at risk
for future development near the town of McKenna
Nisqually River Wilcox Reach Restoration Design
SRFB Funding awarded in 2014 to
look at conceptual designs for
assessing restoration
opportunities RM 26.2 and 27.8 of
the mainstem. This project seeks
to further the design
• Removal of up to 2,730ft
of levees/berms
• Re-engage up to 100 acres
of forested floodplain, side
channels, wetlands
• Restoration
approval/alternative
selection from Wilcox
Family is pending
Sponsor: South Puget Sound Salmon
Enhancement Group
Amount Requested: $510,000
• Amount Requested:
$505,428
• Acquisition of 49.5 acres
along Lackamas Creek
• Planting of this site,
along with enhancement
of 185-acre Lackamas
Creek Protected Area
• Amount Requested: $289,874
• Acquisition of 60 acres along
the mainstem at RM 33
• Initial planting of the site, along
with the downstream North
Powell Pastures property
• Amount Requested:
$469,844
• Acquisition of 90 acres
for future restoration
opportunity
• .65 miles of shoreline
• Implementation of
additional stewardship
activities in riparian
area along Lower Ohop
Creek (Restoration
Phases 1-3)
• Amount Requested:
$219,138
• Conservation easement on
35 acres along 2,000 feet of
middle Ohop Creek
• Project will enhance a 6-acre
riparian planting done by NIT
in 2005, along with planting
an additional 3 acres
• Amount Requested:
$148,162
• Acquisition of 25.3
acres in the Upper
Ohop Creek Valley,
including .4 miles of
Ohop Creek
• 23 acre planting
planned for this
parcel, with
additional plantings
on the downstream
NLT site
2018 timeline
January 31 Nisqually Four Year Work Plan approved/submitted 
April 23 Draft applications due in PRISM 
May 14 Project site visits with SRFB Review Panel 
June 15 Present ranking criteria update to NRC for consideration
July 11 NSHWG develops ranked project list for approval
July 20 Present ranked project list to NRC for approval
August 9 Final applications due
Aug/Nov Review panel provides project comments
November 7 Final ranked list due
December 5/6 SRFB funds awarded
July 1, 2019 PSAR funds awarded

More Related Content

PDF
DURBAN PORT COMMITTEE - 20 April
PPTX
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
PPTX
Bee Creek Sewer Line
PPT
TBRR Workshop, University of Washington
PDF
Addison Capital Projects Update
PPTX
Interlocal Agreement with Wellborn SUD
PPTX
Jeff Polenik, Robindale Energy,"Leanor GFCC - A Positive Impact
PDF
Victorias Waste Infrastructure Planning Framework
DURBAN PORT COMMITTEE - 20 April
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bee Creek Sewer Line
TBRR Workshop, University of Washington
Addison Capital Projects Update
Interlocal Agreement with Wellborn SUD
Jeff Polenik, Robindale Energy,"Leanor GFCC - A Positive Impact
Victorias Waste Infrastructure Planning Framework

What's hot (20)

PDF
Garretson site tentative tract 36764
PDF
AH CCM 07.23.18 Item #8 Harrigan Ct Sewer Rehab
PDF
ORGANICS3 Municipal Site Development: Life Beyond the Landfill, Dan Barrett
PPTX
SLRD - Bralorne Sewer Upgrade: Project Update (June 28, 2018)
PDF
Iwcm green_expo
PPTX
Lick Creek Trail Restoration
PPTX
SH 6 Waterline Easements
PPTX
2014 Economic Summit - City of Norman
PDF
A New Reservoir Project 30 Years in the Making - Tom Kula and Mike Rickman
PPTX
FY17 Budget Amendment No. 1
PDF
PPTX
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
PDF
Cape Cod Commission 208 plan update
PDF
Columbus lpoe slides 9 8-20
PPTX
Njf redevelopment forum 2018 dodge ignite
PDF
Annual report 2015 edited
PDF
Bear River Development Project
PPT
Northeast Gordon Estates NCP
PDF
Fy 19 PPT Public Works and Utilities
PPTX
Lick Creek Wastewater Treatment Plant Expansion
Garretson site tentative tract 36764
AH CCM 07.23.18 Item #8 Harrigan Ct Sewer Rehab
ORGANICS3 Municipal Site Development: Life Beyond the Landfill, Dan Barrett
SLRD - Bralorne Sewer Upgrade: Project Update (June 28, 2018)
Iwcm green_expo
Lick Creek Trail Restoration
SH 6 Waterline Easements
2014 Economic Summit - City of Norman
A New Reservoir Project 30 Years in the Making - Tom Kula and Mike Rickman
FY17 Budget Amendment No. 1
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Cape Cod Commission 208 plan update
Columbus lpoe slides 9 8-20
Njf redevelopment forum 2018 dodge ignite
Annual report 2015 edited
Bear River Development Project
Northeast Gordon Estates NCP
Fy 19 PPT Public Works and Utilities
Lick Creek Wastewater Treatment Plant Expansion
Ad

Similar to 2018 SRFB PSAR Project List for (20)

PPTX
2018 SRFB PSAR Project Ranked List
PPTX
Nisqually 2015 Ranked Project List
PDF
2014 Enbridge Day - Major Projects
PDF
Williams Slide Presentation for Northeast Supply Enhancement Project
PDF
Santomenna great marshnov13v2
PDF
Water Management Strategies - Ryan Kelso
PPTX
Elizabeth Hughes, Earth Conservancy, “Lessons Learned from 25 Years of Recove...
PPT
K.1 turkey point units 6 & 7 project
PPT
Land & Environmental Claims Report
PPTX
Eric. E. Cavazza P.E., Director PA DEP Bureau of Abandoned Mine Reclamation -...
PDF
Andrea Collier, MDNR, Water Resources Center Regional Planning Projects, Miss...
PDF
Honeycutt farm 2014 farm bill
PPT
2015 Nisqually New Project List
PPTX
Barnack Drive Outfall Restoration Project Completion
PDF
DEP Ecosystem Water Quality Initiatives Update May 7 2025 JBTF.pdf
PPT
Kansas Water Vision Implementation - A Regional Approach
PPTX
A Regulatory Update Of Stormwater Requirements.Km
PPTX
Water presentation port of corpus christi
PPT
Honey Brook Townshop Saving Farms Saving Water
PDF
Idaho champion RTO (CSE:ITKO) Aka "The Champ"
2018 SRFB PSAR Project Ranked List
Nisqually 2015 Ranked Project List
2014 Enbridge Day - Major Projects
Williams Slide Presentation for Northeast Supply Enhancement Project
Santomenna great marshnov13v2
Water Management Strategies - Ryan Kelso
Elizabeth Hughes, Earth Conservancy, “Lessons Learned from 25 Years of Recove...
K.1 turkey point units 6 & 7 project
Land & Environmental Claims Report
Eric. E. Cavazza P.E., Director PA DEP Bureau of Abandoned Mine Reclamation -...
Andrea Collier, MDNR, Water Resources Center Regional Planning Projects, Miss...
Honeycutt farm 2014 farm bill
2015 Nisqually New Project List
Barnack Drive Outfall Restoration Project Completion
DEP Ecosystem Water Quality Initiatives Update May 7 2025 JBTF.pdf
Kansas Water Vision Implementation - A Regional Approach
A Regulatory Update Of Stormwater Requirements.Km
Water presentation port of corpus christi
Honey Brook Townshop Saving Farms Saving Water
Idaho champion RTO (CSE:ITKO) Aka "The Champ"
Ad

More from Nisqually River Council (20)

PDF
Yil Me Hu Summer 2023 Edition - Nisqually Salmon Recovery Newsletter
PDF
Yil Me Hu Spring 2024 - Nisqually Salmon Recovery Newsletter
PDF
Yil Me Hu Summer 2022
PDF
Yil Me Hu Winter 2021
PPTX
I-5 Study Report 2020
PDF
Nisqually Watershed Stewardship Report 8.16.19
PPTX
Nisqually River Education Project - NOAA ELG Presentation 2019
PPTX
Kayak Nisqually
PPTX
Dynamic Habitat Models for Estuary-Dependent Species
PPTX
Tacoma Metro Parks Public Engagement
PDF
Nisqually Watershed Management Plan 2019 Addendum - Appendices
PDF
Nisqually Watershed Management Plan 2019 Addendum - Figures
PDF
Nisqually Watershed Management Plan 2019 Addendum
PDF
2018 Nisqually Water Planning Unit Working Agreement
PDF
Yil Me Hu Winter 2018-19
PPTX
Remembering Medicine Creek
PPTX
Evaluating Biodiversity in the Salish Sea at Two Levels
PDF
Nisqually Stream Stewards Map 2018
PPTX
Nisqually Watershed Stewardship Plan: Status Report 2018 Draft Presentation
PPTX
Nisqually Indian Tribe Food Sovereignty Assessment
Yil Me Hu Summer 2023 Edition - Nisqually Salmon Recovery Newsletter
Yil Me Hu Spring 2024 - Nisqually Salmon Recovery Newsletter
Yil Me Hu Summer 2022
Yil Me Hu Winter 2021
I-5 Study Report 2020
Nisqually Watershed Stewardship Report 8.16.19
Nisqually River Education Project - NOAA ELG Presentation 2019
Kayak Nisqually
Dynamic Habitat Models for Estuary-Dependent Species
Tacoma Metro Parks Public Engagement
Nisqually Watershed Management Plan 2019 Addendum - Appendices
Nisqually Watershed Management Plan 2019 Addendum - Figures
Nisqually Watershed Management Plan 2019 Addendum
2018 Nisqually Water Planning Unit Working Agreement
Yil Me Hu Winter 2018-19
Remembering Medicine Creek
Evaluating Biodiversity in the Salish Sea at Two Levels
Nisqually Stream Stewards Map 2018
Nisqually Watershed Stewardship Plan: Status Report 2018 Draft Presentation
Nisqually Indian Tribe Food Sovereignty Assessment

Recently uploaded (20)

PPTX
Plant Production 7.pptx in grade 7 students
PPT
Environmental pollution for educational study
PDF
The European Green Deal (EU Green Deal)
PPTX
RadiationSafetyPt120252026nucchemis.pptx
DOCX
The Ripple Effect: Understanding Extreme Weather Patterns and Geomagnetic Dyn...
PDF
FMM Slides For OSH Management Requirement
DOCX
Double Membrane Roofs for Biogas Tanks Securely store produced biogas.docx
PPTX
NSTP1 NSTP1NSTP1NSTP1NSTP1NSTP1NSTP1NSTP
PPTX
sustainable-development in tech-ppt[1].pptx
PPTX
Unit 1 - Environmental management, politics and.pptx
PPT
MATERI - LABORATORY - SAFETY.ppt
PDF
Cave Diggers Simplified cave survey methods and mapping
PPTX
Biodiversity.udfnfndrijfreniufrnsiufnriufrenfuiernfuire
PPTX
IMPACTS OF CHEMICAL FERTILIZERS -CHEMPROJ (11).pptx
DOCX
Double Membrane Roofs for Bio-gas Tanks Reliable containment for biofuel gas....
PDF
Tree Biomechanics, a concise presentation
PPTX
Microbial-Pathogens-and-Parasites-Their-Impact-on-Plant-Health.pptx
PPTX
TERI-Lighting-the-Way-to-a-Sustainable-Future.pptx
PPTX
Air_Pollution_Thesis_Presentation (1).pptx
DOCX
Double Membrane Roofs for Digester Tank Wastewater Treatment Integral to biog...
Plant Production 7.pptx in grade 7 students
Environmental pollution for educational study
The European Green Deal (EU Green Deal)
RadiationSafetyPt120252026nucchemis.pptx
The Ripple Effect: Understanding Extreme Weather Patterns and Geomagnetic Dyn...
FMM Slides For OSH Management Requirement
Double Membrane Roofs for Biogas Tanks Securely store produced biogas.docx
NSTP1 NSTP1NSTP1NSTP1NSTP1NSTP1NSTP1NSTP
sustainable-development in tech-ppt[1].pptx
Unit 1 - Environmental management, politics and.pptx
MATERI - LABORATORY - SAFETY.ppt
Cave Diggers Simplified cave survey methods and mapping
Biodiversity.udfnfndrijfreniufrnsiufnriufrenfuiernfuire
IMPACTS OF CHEMICAL FERTILIZERS -CHEMPROJ (11).pptx
Double Membrane Roofs for Bio-gas Tanks Reliable containment for biofuel gas....
Tree Biomechanics, a concise presentation
Microbial-Pathogens-and-Parasites-Their-Impact-on-Plant-Health.pptx
TERI-Lighting-the-Way-to-a-Sustainable-Future.pptx
Air_Pollution_Thesis_Presentation (1).pptx
Double Membrane Roofs for Digester Tank Wastewater Treatment Integral to biog...

2018 SRFB PSAR Project List for

  • 1. Nisqually 2018 Grant Round & New Project List Nisqually River Council, May 2018
  • 2. A few grant round details.. 2018 SRFB allocation: estimated $400,000 2019-2021 PSAR planning year: estimated $1.4 million 8 pre-applications submitted Total Request: $2,945,297 Total Match: $524,563 Project Grand Total: $3,469,860
  • 3. Site Visits with the SRFB Review Panel
  • 5. McKenna Reach Protection and Restoration • Sponsor: Nisqually Land Trust • Amount Requested: $528,689 • Acquisition of 65 acres along mainstem, including .7 miles of shoreline • Stewardship activities are planned throughout, including invasive vegetation control and plantings • Site specific information unavailable at this time
  • 6. • Amount Requested: $237,362 • Acquisition of 6.4 undeveloped acres along the northern shoreline of the Nisqually mainstem • This project would protect 4 of 15 parcels that are at risk for future development near the town of McKenna
  • 7. Nisqually River Wilcox Reach Restoration Design SRFB Funding awarded in 2014 to look at conceptual designs for assessing restoration opportunities RM 26.2 and 27.8 of the mainstem. This project seeks to further the design • Removal of up to 2,730ft of levees/berms • Re-engage up to 100 acres of forested floodplain, side channels, wetlands • Restoration approval/alternative selection from Wilcox Family is pending Sponsor: South Puget Sound Salmon Enhancement Group Amount Requested: $510,000
  • 8. • Amount Requested: $505,428 • Acquisition of 49.5 acres along Lackamas Creek • Planting of this site, along with enhancement of 185-acre Lackamas Creek Protected Area
  • 9. • Amount Requested: $289,874 • Acquisition of 60 acres along the mainstem at RM 33 • Initial planting of the site, along with the downstream North Powell Pastures property
  • 10. • Amount Requested: $469,844 • Acquisition of 90 acres for future restoration opportunity • .65 miles of shoreline • Implementation of additional stewardship activities in riparian area along Lower Ohop Creek (Restoration Phases 1-3)
  • 11. • Amount Requested: $219,138 • Conservation easement on 35 acres along 2,000 feet of middle Ohop Creek • Project will enhance a 6-acre riparian planting done by NIT in 2005, along with planting an additional 3 acres
  • 12. • Amount Requested: $148,162 • Acquisition of 25.3 acres in the Upper Ohop Creek Valley, including .4 miles of Ohop Creek • 23 acre planting planned for this parcel, with additional plantings on the downstream NLT site
  • 13. 2018 timeline January 31 Nisqually Four Year Work Plan approved/submitted  April 23 Draft applications due in PRISM  May 14 Project site visits with SRFB Review Panel  June 15 Present ranking criteria update to NRC for consideration July 11 NSHWG develops ranked project list for approval July 20 Present ranked project list to NRC for approval August 9 Final applications due Aug/Nov Review panel provides project comments November 7 Final ranked list due December 5/6 SRFB funds awarded July 1, 2019 PSAR funds awarded