Planning a Software Project From Pankaj Jalote’s book
Agenda Background Process planning Effort estimation  Schedule and resource estimation Quality Planning Risk management Configuration Management Project monitoring plans
Software Project Goal: Build a software system to meet commitments on cost, schedule, quality Worldwide - many projects fail one-third are runaways with cost or schedule overrun of more than 125%
Project Failures Major reasons for project runaways unclear objectives bad planning no project management methodology new technology insufficient staff All of these relate to project management Effective project management is key to successfully executing a project
Why improve PM? Better predictability leading to commitments that can be met Lower cost through reduced rework, better resource mgmt, better planning,.. Improved quality through proper quality planning and control Better control through change control, CM, monitoring etc.
Why improve PM …. Better visibility into project health and state leading to timely intervention Better handling of risks reducing the chances of failure All this leads to higher customer satisfaction And self and organization improvement
Two Dimensions in project execution
Process-based Project Execution Small project both engg and PM can be done informally Large projects require formality Formality: well defined processes used for each task; measurements used to control Here we focus on processes for PM only
The Project Mgmt Process Has three phases - planning, monitoring and control, and closure Planning is done before the main engineering LC (Life Cycle) and closure after the LC Monitoring phase is in parallel with LC
Project Planning Basic objective: To create a plan to meet the commitments of the project, I.e. create a path that, if followed, will lead to a successful project Planning involves defining the LC process to be followed, estimates, detailed schedule, plan for quality, etc. Main output - a project management plan and the project schedule
Key Planning Tasks Define suitable processes for executing the project  Estimate effort Define project milestones and create a schedule Define quality objectives and a quality plan Identify risks and make plans to mitigate them Define measurement plan, project-tracking procedures, training plan, team organization, etc.
Process Planning Plan how the project will be executed, I.e. the process to be followed Process will decide the tasks, their ordering, milestones Hence process planning is an important project planning task  Should plan for LC and PM processes as well as supporting processes
Life Cycle Process Various LC models - waterfall, iterative, prototyping; diff models suit different projects During planning can select the model that is best for the project This gives the overall process which has to be fine-tuned to garb the project needs Usually done by process tailoring - changing the process to suit the project Tailoring finally results in adding, deleting, modifying some process steps
Effort Estimation
Effort Estimation For a project total cost and duration has to be committed in start Requires effort estimation, often in terms of person-months Effort estimate is key to planning - schedule, cost, resources depend on it Many problems in project execution stem from improper estimation
Estimation.. No easy way, no silver bullet Estimation accuracy can improve with more information about the project Early estimates are more likely to be inaccurate than later  More uncertainties in the start With more info, estimation becomes easier
Estimation accuracy
Effort Estimation Models.. A model tries to determine the effort estimate from some parameter values A model also requires input about the project, and cannot work in vacuum So to apply a model, we should be able to extract properties about the system Two types of models - top-down and bottom-up
Effort Estimation Models
Top-down Estimation First determines the total effort, then effort for components Usually works with overall size One method is to see estimate as a function of effort; the common function used is  E = a * size  b E  (Effort) is in person-months,  size  in KLOC Constants  a  and  b  determined through regression analysis of past project data
Top down estimation Can also estimate from size and productivity Get the estimate of the total size of the software Estimate project productivity using past data and project characteristics  Obtain the overall effort estimate from productivity and size estimates Effort distribution data from similar project are used to estimate effort for different phases
Bottom-up Estimation Effort for components and phases first estimated, then the total Can use activity based costing - all activities enumerated and then each activity estimated separately Can group activities into classes - their effort estimate from past data
An Estimation Procedure Identify programs in the system and classify them as simple, medium, or complex (S/M/C) Define the average coding effort for S/M/C  Get the total coding effort. Use the effort distribution in similar projects to estimate effort for other tasks and total Refine the estimates based on project specific factors
COCOMO Model for Estimation Is a top-down approach Uses size, but adjusts using some factors Basic procedure Obtain initial estimate using size Determine a set of 15 multiplying factors from different project attributes Adjust the effort estimate by scaling it with the final multiplying factor
COCOMO.. Initial estimate: a * size  b  ; some standard values for a, b given for diff project types There are 15 cost driver attributes like reliability, complexity, application experience, capability, … Each factor is rated, and for the rating a multiplication factor is given Final effort adjustment factor is the product of the factors for all 15 attributes
COCOMO – Some cost drivers Cost Driver Very low Low Nominal High Very High Required reliability Database size Product complexity Execution time constraint Memory constraint Analyst capability Application experience Programmer capability Use of software tools Development schedule .75 .7 1.46 1.29 1.42 1.24 1.23 .88 .94 .85 1.19 1.13 1.17 1.10 1.08 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.15 1.08 1.15 1.11 1.06 .86 .91 .86 .91 1.04 1.4 1.16 1.3 1.3 1.21 .71 .82 .70 .83 1.1
COCOMO – effort distribution Effort distribution among different phases is given as a percent of effort Eg. For medium size product it is Product design – 16% Detailed design – 24% Coding and UT – 38% Integration and test – 22%
Sizing With Function Points
Sizing Effort for project depends on many factors Size is the main factor – many experiments and data analysis have validated this Size in the start is only an estimate; getting size estimates from requirement is hard Need a size unit that can be “computed” from requirements Function points attempt to do this
Function Points Is a size measure like LOC Determined from SRS Defines size in terms of “ functionality “ Why “measure” size early ? Needed for estimation and planning Five different parameters external input type external output type logical internal file type external interface file type external inquiry type
Function Points… These five parameters capture the functionality of a system within a type , an element may be simple , average or complex A weighted sum is taken External input type :   each unique input type A input type is unique if the format is different from others or if the specifications require different processing.
Function Points… Simple : a few data elements Complex : many data elements and many internal files needed for processing Only files needed by the application are counted.  ( HW/OS config. Files are are not counted ) External output type : each unique output that leave system boundary E.g.  Reports , messages to user , data to other applications Simple : few columns
Function Points… Average : many columns Complex : references many files for production Logical internal file type :   An application maintains information internally for its own processes Each logical group of data generated , used and maintained Same for simple , average and complex
Function Points… External interface file type logical files passed between application External inquiry type input , output combination Weights External Input  3 4 6 External Output 4 5 7 Logical int. file 7 10 15 External int. file 5 7 10 External inquiry 3 4 6
Function Points…   Unadjusted function point : Basic function points Adjusted for other factors 14 such factors performance objectives , transaction rate etc. Final FP is adjusted differs at most 35%
Function Points… Interest in FP  since obtained at requirements => major advantage Well correlated with size in some what interchangeable and tables exist 1 FP = 70 LOC of C Works well for MIS , but not for system type Major draw back - subjectivity not repeatable not precisely known ever for a built system  not addictive
Scheduling and Staffing
Project Schedule A project Schedule is at two levels - overall schedule and detailed schedule Overall schedule comprises of major milestones and final date Detailed schedule is the assignment of lowest level tasks to resources
Overall Schedule Depends heavily on the effort estimate For an effort estimate,  some  flexibility exists depending on resources assigned Eg a 56 PM project can be done in 8 months (7 people) or 7 months (8 people) Stretching a schedule is easy; compressing is hard and expensive
Overall Scheduling... One method is to estimate schedule S (in months) as a function of effort in PMs Can determine the fn through analysis of past data; the function is non linear COCOMO: S = 2.5 E  3.8   Often this schedule is checked and corrected for the specific project One checking method – square root check
Determining Overall Schedule from past data
Determining Milestones With effort and overall schedule decided, avg project resources are fixed Manpower ramp-up in a project decides the milestones Manpower ramp-up in a project follows a Rayleigh curve - like a normal curve In reality manpower build-up is a step function
Manpower Ramp-up
Milestones ... With manpower ramp-up and effort distribution, milestones can be decided Effort distribution and schedule distribution in phases are different Generally, the build has larger effort but not correspondingly large schedule COCOMO specifies distr of overall sched. Design – 19%, programming – 62%, integration – 18%
An Example Schedule # Task Dur. (days) Work (p-days) Start Date End Date 2 Project Init tasks 33 24 5/4 6/23 74 Training 95 49 5/8 9/29 104 Knowledge sharing 78 20 6/2 9/30 114 Elaboration iteration I 55 55 5/15 6/23 198 Construction iteration I 9 35 7/10 7/21
Detailed Scheduling To reach a milestone, many tasks have to be performed Lowest level tasks - those that can be done by a person (in less than 2-3 days) Scheduling - decide the tasks, assign them while preserving high-level schedule Is an iterative task - if cannot “fit” all tasks, must revisit high level schedule
Detailed Scheduling Detailed schedule not done completely in the start - it evolves Can use MS Project for keeping it Detailed Schedule is the most live document for managing the project Any activity to be done must get reflected in the detailed schedule
An example task in detail schedule Module Act Code Task Duration Effort History PUT Unit test # 17 1 day 7 hrs St. date End date %comp Depend. Resource 7/18 7/18 0% Nil SB
.Project Scheduling….. The scheduling process
..Project Scheduling…. Graphical notations used in software project scheduling: Tables: summary description of tasks  Bar charts : show schedule against the time Activity charts : graphs that depict dependencies between tasks and indicate the  critical path  (the longest path in the activity graph)
… Project Scheduling… Example of tabular description [Fig. 5.5, SE-7]:
… .Project Scheduling.. Example of activity chart
… ..Project Scheduling. Example of bar chart
…… Project Scheduling Staff allocation chart
Detail schedule Each task has name, date, duration, resource etc assigned % done is for tracking (tools use it) The detailed schedule has to be consistent with milestones Tasks are sub-activities of milestone level activities, so effort should add up, total schedule should be preserved
Team Structure To assign tasks in detailed schedule, need to have a clear team structure Hierarchic team org is most common Project manager has overall responsibility; also does design etc. Has programmers and testers for executing detailed tasks May have config controller, db manager, etc
Team structure.. An alternative – democratic teams Can work for small teams; leadership rotates Another one used for products A dev team led by a dev mgr, a test team led by test mgr, and a prog. Mgmt team All three report to a product mgr Allows specialization of tasks and separate career ladders for devs, tests, PMs
SCM process and planning Have discussed SCM process earlier During planning, the SCM activities are planned along with who will perform them Have discussed planning also earlier Includes defining CM items, naming scheme, directory structure, access restrictions, change control, versioning, release procedure etc
Quality Planning
Quality Planning Delivering high quality is a basic goal Quality can be defined in many ways Current industry standard -  delivered defect density  (e.g. #defects/KLOC) Defect - something that causes software to behave in an inconsistent manner Aim of a project - deliver software with low delivered defect density
Defect Injection and Removal Software development is labor intensive Defects are injected at any stage As quality goal is low delivered defect density, these defects have to be removed Done primarily by quality control (QC) activities of reviews and testing
Defect Injection and Removal
Approaches to Quality Management  Ad hoc - some testing, some reviews done as and when needed Procedural - defined procedures are followed in a project Quantitative - defect data analysis done to manage the quality process
Procedural Approach A quality plan defines what QC tasks will be undertaken and when Main QC tasks - reviews and testing Guidelines and procedures for reviews and testing are provided During project execution, adherence to the plan and procedures ensured
Quantitative Approach Goes beyond asking “has the procedure been executed” Analyzes defect data to make judgements about quality Past data is very important Key parameters - defect injection and removal rates, defect removal efficiency (DRE)
Quality Plan The quality plan drives the quality activities in the project Level of plan depends on models available Must define QC tasks that have to be performed in the project Can specify defect levels for each QC tasks (if models and data available)
Risk Management
Risk Management Any project can fail - reasons can be technical, managerial, etc. Project management aims to tackle the project management aspect Engineering life cycles aim to tackle the engineering issues A project may fail due to unforeseen events - risk management aims to tackle this
Risk Management Risk: any condition or event whose occurrence is not certain but which can cause the project to fail Aim of risk management: minimize the effect of risks on a project
Risk Management Tasks
Risk Identification To identify possible risks to a project, i.e. to those events that might occur and which might cause the project to fail No “algorithm” possible, done by “what ifs”, checklists, past experience Can have a list of “top 10” risks that projects have seen in past
Top Risk Examples Shortage of technically trained manpower Too many requirement changes Unclear requirements Not meeting performance requirements Unrealistic schedules Insufficient business knowledge Working on new technology
Risk Prioritization The number of risks might be large Must prioritize them to focus attention on the “high risk” areas For prioritization, impact of each risk must be understood In addition, probability of the risk occurring should also be understood
Risk Prioritization ... Risk exposure (RE) = probability of risk occurring * risk impact RE is the expected value of loss for a risk Prioritization can be done based on risk exposure value Plans can be made to handle high RE risks
A Simple approach to Risk Prioritization Classify risk occurrence probabilities as: Low, Medium, High Classify risk impact as: Low, Medium, High Identify those that are HH, or HM/MH Focus on these for risk mitigation Will work for most small and medium sized projects
Risk Control Can the risk be avoided? E.g. if new hardware is a risk, it can be avoided by working with proven hardware For others, risk mitigation steps need to be planned and executed Actions taken in the project such that if the risk materializes, its impact is minimal Involves extra cost
Risk Mitigation Examples Too many requirement changes Convince client that changes in requirements will have an impact on the schedule  Define a procedure for requirement changes Maintain cumulative impact of changes and make it visible to client Negotiate payment on actual effort.
Examples ... Manpower attrition Ensure that multiple resources are assigned on key project areas Have team building sessions Rotate jobs among team members Keep backup resources in the project  Maintain documentation of individual’s work Follow the CM process and guidelines strictly
Examples ... Unrealistic schedules Negotiate for better schedule Identify parallel tasks Have resources ready early Identify areas that can be  automated If the critical path is not within the schedule, negotiate with the client Negotiate payment on actual effort
Risk Mitigation Plan Risk mitigation involves steps that are to be performed (hence has extra cost) It is not a paper plan - these steps should be scheduled and executed These are different from the steps one would take if the risk materializes - they are performed only if needed Risks must be revisited periodically
Project Monitoring Plans
Background A plan is a mere document that can guide It must be executed To ensure execution goes as per plan, it must be monitored and controlled Monitoring requires measurements And methods for interpreting them Monitoring plan has to plan for all the tasks related to monitoring
Measurements Must plan for measurements in a project Without planning, measurements will not be done Main measurements – effort, size, schedule, and defects Effort – as this is the main resource; often tracked through effort reporting tools Defects – as they determine quality; often defect logging and tracking systems used During planning – what will be measured, how, tool support, and data management
Project Tracking Goal: To get visibility in project execution so corrective actions can be taken when needed to ensure project succeeds Diff types of monitoring done at projects; measurements provide data for it
Tracking… Activity-level monitoring Each activity in detailed schd is getting done Often done daily by managers A task done marked 100%; tools can determine status of higher level tasks Status reports Generally done weekly to take stock Summary of activities completed, pending Issues to be resolved
Tracking… Milestone analysis A bigger review at milestones Actual vs estimated for effort and sched is done Risks are revisited Changes to product and their impact may be analyzed Cost-schedule milestone graph is another way of doing this
Cost-schedule milestone graph
Project Management Plan The project management plan (PMP) contains outcome of all planning activities - focuses on overall project management Besides PMP, a project schedule is needed Reflects what activities get done in the project Microsoft project (MSP) can be used for this Based on project planning; is essential for day-to-day management Does not replace PMP !
PMP Structure - Example Project overview - customer, start and end date, overall effort, overall value, main contact persons, project milestones, development environment.. Project planning - process and tailoring, requirements change mgmt, effort estimation, quality goals and plan, risk management plan, ..
PMP Example ... Project tracking - data collection, analysis frequency, escalation procedures, status reporting, customer complaints, … Project team, its organization, roles and responsibility, …
Project Planning - Summary Project planning forms the foundation of project management Key aspects: effort and schedule estimation, quality planning, risk mgmt., … Outputs of all can be documented in a PMP, which carries all relevant info about project Besides PMP, a detailed project schedule maintains tasks to be done in the project

More Related Content

PPT
9 project planning
PPT
Project Cost Management
PPT
Spm unit 4
PPT
Ch 9 project monitoring & control updated
PPT
Unit 2 spm
PPT
Software Project Management Spm1176
PPTX
project management information system
PDF
Monitor and control process group part two
9 project planning
Project Cost Management
Spm unit 4
Ch 9 project monitoring & control updated
Unit 2 spm
Software Project Management Spm1176
project management information system
Monitor and control process group part two

What's hot (20)

PPTX
Software Project Scheduling Diagrams
PDF
07 project cost management
PPT
Software Engineering (Project Scheduling)
PPTX
Basic Software Effort Estimation
PPT
Chapter 07 project cost management
PPTX
SPM Evaluation
PDF
Introduction to schedule management
PDF
4. project cost management
PPTX
Project control. Management
PPTX
Project scheduling and tracking
PPT
Project performance tracking analysis and reporting
PPTX
Project Cost Management
PPT
Software Project Management
PPTX
DELPHI METHOD (COST ESTIMATION MODELT)
PPT
Project cost management
PDF
Pmbok 5th planning process group part two
PPTX
Project Cost Management
PDF
Project cost management
PDF
How to prepare recovery or revised schedule rev.2
PPTX
Managingtripleconstraint aam
Software Project Scheduling Diagrams
07 project cost management
Software Engineering (Project Scheduling)
Basic Software Effort Estimation
Chapter 07 project cost management
SPM Evaluation
Introduction to schedule management
4. project cost management
Project control. Management
Project scheduling and tracking
Project performance tracking analysis and reporting
Project Cost Management
Software Project Management
DELPHI METHOD (COST ESTIMATION MODELT)
Project cost management
Pmbok 5th planning process group part two
Project Cost Management
Project cost management
How to prepare recovery or revised schedule rev.2
Managingtripleconstraint aam
Ad

Viewers also liked (10)

PDF
Schedule Integrity - The Key to Successful Project Management
PPTX
Better Bidding for Facilities Management Contracts
PDF
Schedule Design AACE
PPTX
Episode 28 : Project Management Contract
PPTX
Types of contracts
PPTX
Tendering Bidding & Award of Contract Final Draft
PPTX
Tendering process, Bid Evaluation & Award Process
PPTX
The Basics of Tendering & Bidding
PPTX
CONTRACTS AND ITS TYPES
PPTX
Types of contract
Schedule Integrity - The Key to Successful Project Management
Better Bidding for Facilities Management Contracts
Schedule Design AACE
Episode 28 : Project Management Contract
Types of contracts
Tendering Bidding & Award of Contract Final Draft
Tendering process, Bid Evaluation & Award Process
The Basics of Tendering & Bidding
CONTRACTS AND ITS TYPES
Types of contract
Ad

Similar to 8 project planning (20)

PPTX
Software Engineering Fundamentals in Computer Science
PPTX
CS8494 SOFTWARE ENGINEERING Unit-5
PPTX
Software Engineering Chapter 4 Part 1 Euu
PPT
Project-Planning
PPT
Project Planning
PPT
Project Management
PDF
Software Project Management
PPT
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
PPT
Planning.ppt
PPT
5-ProjPlanning.ppt
PPT
5-ProjPlanning.ppthhjjjjhhhjjjjhgyhhjhggg
PPT
4-ProjectPlanning.ppt
PPT
Software cost estimation project
PDF
APznzaZSEwUJhKEim-rOA-Svk6nc1xZygCeBBAW4QZluPqM0dLSELK_S9YNDE8po44L2LgB6Is5VJ...
PPTX
Project Scheduling and Tracking in Software Engineering.pptx
PPTX
Lec_6_Sosssssftwaaaaaare_Estimation.pptx
PPT
Chapter 3- Software Project Management(Reduced).ppt
PPTX
Software project plannings
PPTX
Software project plannings
PPTX
3. Lect 29_ 30_ 32 Project Planning.pptx
Software Engineering Fundamentals in Computer Science
CS8494 SOFTWARE ENGINEERING Unit-5
Software Engineering Chapter 4 Part 1 Euu
Project-Planning
Project Planning
Project Management
Software Project Management
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
Planning.ppt
5-ProjPlanning.ppt
5-ProjPlanning.ppthhjjjjhhhjjjjhgyhhjhggg
4-ProjectPlanning.ppt
Software cost estimation project
APznzaZSEwUJhKEim-rOA-Svk6nc1xZygCeBBAW4QZluPqM0dLSELK_S9YNDE8po44L2LgB6Is5VJ...
Project Scheduling and Tracking in Software Engineering.pptx
Lec_6_Sosssssftwaaaaaare_Estimation.pptx
Chapter 3- Software Project Management(Reduced).ppt
Software project plannings
Software project plannings
3. Lect 29_ 30_ 32 Project Planning.pptx

More from randhirlpu (13)

PPT
system software
PPT
16 user interfacedesign
PPT
15 object orienteddesign
PPT
14 functional design
PPT
13 configuration management
PPT
12 couplingand cohesion-student
PPT
7(srs template)
PPT
5(re dfd-erd-data dictionay)
PPTX
Cocomo m odel
system software
16 user interfacedesign
15 object orienteddesign
14 functional design
13 configuration management
12 couplingand cohesion-student
7(srs template)
5(re dfd-erd-data dictionay)
Cocomo m odel

Recently uploaded (20)

PDF
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
PDF
Per capita expenditure prediction using model stacking based on satellite ima...
PPTX
Digital-Transformation-Roadmap-for-Companies.pptx
PPTX
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
PDF
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
PDF
Shreyas Phanse Resume: Experienced Backend Engineer | Java • Spring Boot • Ka...
PDF
Advanced methodologies resolving dimensionality complications for autism neur...
PDF
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
PDF
Electronic commerce courselecture one. Pdf
PPTX
PA Analog/Digital System: The Backbone of Modern Surveillance and Communication
PDF
Agricultural_Statistics_at_a_Glance_2022_0.pdf
PDF
Reach Out and Touch Someone: Haptics and Empathic Computing
PDF
Dropbox Q2 2025 Financial Results & Investor Presentation
PDF
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
PDF
Peak of Data & AI Encore- AI for Metadata and Smarter Workflows
PDF
Unlocking AI with Model Context Protocol (MCP)
PDF
Machine learning based COVID-19 study performance prediction
PDF
Building Integrated photovoltaic BIPV_UPV.pdf
PDF
TokAI - TikTok AI Agent : The First AI Application That Analyzes 10,000+ Vira...
PDF
cuic standard and advanced reporting.pdf
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
Per capita expenditure prediction using model stacking based on satellite ima...
Digital-Transformation-Roadmap-for-Companies.pptx
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
Shreyas Phanse Resume: Experienced Backend Engineer | Java • Spring Boot • Ka...
Advanced methodologies resolving dimensionality complications for autism neur...
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
Electronic commerce courselecture one. Pdf
PA Analog/Digital System: The Backbone of Modern Surveillance and Communication
Agricultural_Statistics_at_a_Glance_2022_0.pdf
Reach Out and Touch Someone: Haptics and Empathic Computing
Dropbox Q2 2025 Financial Results & Investor Presentation
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
Peak of Data & AI Encore- AI for Metadata and Smarter Workflows
Unlocking AI with Model Context Protocol (MCP)
Machine learning based COVID-19 study performance prediction
Building Integrated photovoltaic BIPV_UPV.pdf
TokAI - TikTok AI Agent : The First AI Application That Analyzes 10,000+ Vira...
cuic standard and advanced reporting.pdf

8 project planning

  • 1. Planning a Software Project From Pankaj Jalote’s book
  • 2. Agenda Background Process planning Effort estimation Schedule and resource estimation Quality Planning Risk management Configuration Management Project monitoring plans
  • 3. Software Project Goal: Build a software system to meet commitments on cost, schedule, quality Worldwide - many projects fail one-third are runaways with cost or schedule overrun of more than 125%
  • 4. Project Failures Major reasons for project runaways unclear objectives bad planning no project management methodology new technology insufficient staff All of these relate to project management Effective project management is key to successfully executing a project
  • 5. Why improve PM? Better predictability leading to commitments that can be met Lower cost through reduced rework, better resource mgmt, better planning,.. Improved quality through proper quality planning and control Better control through change control, CM, monitoring etc.
  • 6. Why improve PM …. Better visibility into project health and state leading to timely intervention Better handling of risks reducing the chances of failure All this leads to higher customer satisfaction And self and organization improvement
  • 7. Two Dimensions in project execution
  • 8. Process-based Project Execution Small project both engg and PM can be done informally Large projects require formality Formality: well defined processes used for each task; measurements used to control Here we focus on processes for PM only
  • 9. The Project Mgmt Process Has three phases - planning, monitoring and control, and closure Planning is done before the main engineering LC (Life Cycle) and closure after the LC Monitoring phase is in parallel with LC
  • 10. Project Planning Basic objective: To create a plan to meet the commitments of the project, I.e. create a path that, if followed, will lead to a successful project Planning involves defining the LC process to be followed, estimates, detailed schedule, plan for quality, etc. Main output - a project management plan and the project schedule
  • 11. Key Planning Tasks Define suitable processes for executing the project Estimate effort Define project milestones and create a schedule Define quality objectives and a quality plan Identify risks and make plans to mitigate them Define measurement plan, project-tracking procedures, training plan, team organization, etc.
  • 12. Process Planning Plan how the project will be executed, I.e. the process to be followed Process will decide the tasks, their ordering, milestones Hence process planning is an important project planning task Should plan for LC and PM processes as well as supporting processes
  • 13. Life Cycle Process Various LC models - waterfall, iterative, prototyping; diff models suit different projects During planning can select the model that is best for the project This gives the overall process which has to be fine-tuned to garb the project needs Usually done by process tailoring - changing the process to suit the project Tailoring finally results in adding, deleting, modifying some process steps
  • 15. Effort Estimation For a project total cost and duration has to be committed in start Requires effort estimation, often in terms of person-months Effort estimate is key to planning - schedule, cost, resources depend on it Many problems in project execution stem from improper estimation
  • 16. Estimation.. No easy way, no silver bullet Estimation accuracy can improve with more information about the project Early estimates are more likely to be inaccurate than later More uncertainties in the start With more info, estimation becomes easier
  • 18. Effort Estimation Models.. A model tries to determine the effort estimate from some parameter values A model also requires input about the project, and cannot work in vacuum So to apply a model, we should be able to extract properties about the system Two types of models - top-down and bottom-up
  • 20. Top-down Estimation First determines the total effort, then effort for components Usually works with overall size One method is to see estimate as a function of effort; the common function used is E = a * size b E (Effort) is in person-months, size in KLOC Constants a and b determined through regression analysis of past project data
  • 21. Top down estimation Can also estimate from size and productivity Get the estimate of the total size of the software Estimate project productivity using past data and project characteristics Obtain the overall effort estimate from productivity and size estimates Effort distribution data from similar project are used to estimate effort for different phases
  • 22. Bottom-up Estimation Effort for components and phases first estimated, then the total Can use activity based costing - all activities enumerated and then each activity estimated separately Can group activities into classes - their effort estimate from past data
  • 23. An Estimation Procedure Identify programs in the system and classify them as simple, medium, or complex (S/M/C) Define the average coding effort for S/M/C Get the total coding effort. Use the effort distribution in similar projects to estimate effort for other tasks and total Refine the estimates based on project specific factors
  • 24. COCOMO Model for Estimation Is a top-down approach Uses size, but adjusts using some factors Basic procedure Obtain initial estimate using size Determine a set of 15 multiplying factors from different project attributes Adjust the effort estimate by scaling it with the final multiplying factor
  • 25. COCOMO.. Initial estimate: a * size b ; some standard values for a, b given for diff project types There are 15 cost driver attributes like reliability, complexity, application experience, capability, … Each factor is rated, and for the rating a multiplication factor is given Final effort adjustment factor is the product of the factors for all 15 attributes
  • 26. COCOMO – Some cost drivers Cost Driver Very low Low Nominal High Very High Required reliability Database size Product complexity Execution time constraint Memory constraint Analyst capability Application experience Programmer capability Use of software tools Development schedule .75 .7 1.46 1.29 1.42 1.24 1.23 .88 .94 .85 1.19 1.13 1.17 1.10 1.08 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.15 1.08 1.15 1.11 1.06 .86 .91 .86 .91 1.04 1.4 1.16 1.3 1.3 1.21 .71 .82 .70 .83 1.1
  • 27. COCOMO – effort distribution Effort distribution among different phases is given as a percent of effort Eg. For medium size product it is Product design – 16% Detailed design – 24% Coding and UT – 38% Integration and test – 22%
  • 29. Sizing Effort for project depends on many factors Size is the main factor – many experiments and data analysis have validated this Size in the start is only an estimate; getting size estimates from requirement is hard Need a size unit that can be “computed” from requirements Function points attempt to do this
  • 30. Function Points Is a size measure like LOC Determined from SRS Defines size in terms of “ functionality “ Why “measure” size early ? Needed for estimation and planning Five different parameters external input type external output type logical internal file type external interface file type external inquiry type
  • 31. Function Points… These five parameters capture the functionality of a system within a type , an element may be simple , average or complex A weighted sum is taken External input type : each unique input type A input type is unique if the format is different from others or if the specifications require different processing.
  • 32. Function Points… Simple : a few data elements Complex : many data elements and many internal files needed for processing Only files needed by the application are counted. ( HW/OS config. Files are are not counted ) External output type : each unique output that leave system boundary E.g. Reports , messages to user , data to other applications Simple : few columns
  • 33. Function Points… Average : many columns Complex : references many files for production Logical internal file type : An application maintains information internally for its own processes Each logical group of data generated , used and maintained Same for simple , average and complex
  • 34. Function Points… External interface file type logical files passed between application External inquiry type input , output combination Weights External Input 3 4 6 External Output 4 5 7 Logical int. file 7 10 15 External int. file 5 7 10 External inquiry 3 4 6
  • 35. Function Points… Unadjusted function point : Basic function points Adjusted for other factors 14 such factors performance objectives , transaction rate etc. Final FP is adjusted differs at most 35%
  • 36. Function Points… Interest in FP since obtained at requirements => major advantage Well correlated with size in some what interchangeable and tables exist 1 FP = 70 LOC of C Works well for MIS , but not for system type Major draw back - subjectivity not repeatable not precisely known ever for a built system not addictive
  • 38. Project Schedule A project Schedule is at two levels - overall schedule and detailed schedule Overall schedule comprises of major milestones and final date Detailed schedule is the assignment of lowest level tasks to resources
  • 39. Overall Schedule Depends heavily on the effort estimate For an effort estimate, some flexibility exists depending on resources assigned Eg a 56 PM project can be done in 8 months (7 people) or 7 months (8 people) Stretching a schedule is easy; compressing is hard and expensive
  • 40. Overall Scheduling... One method is to estimate schedule S (in months) as a function of effort in PMs Can determine the fn through analysis of past data; the function is non linear COCOMO: S = 2.5 E 3.8 Often this schedule is checked and corrected for the specific project One checking method – square root check
  • 42. Determining Milestones With effort and overall schedule decided, avg project resources are fixed Manpower ramp-up in a project decides the milestones Manpower ramp-up in a project follows a Rayleigh curve - like a normal curve In reality manpower build-up is a step function
  • 44. Milestones ... With manpower ramp-up and effort distribution, milestones can be decided Effort distribution and schedule distribution in phases are different Generally, the build has larger effort but not correspondingly large schedule COCOMO specifies distr of overall sched. Design – 19%, programming – 62%, integration – 18%
  • 45. An Example Schedule # Task Dur. (days) Work (p-days) Start Date End Date 2 Project Init tasks 33 24 5/4 6/23 74 Training 95 49 5/8 9/29 104 Knowledge sharing 78 20 6/2 9/30 114 Elaboration iteration I 55 55 5/15 6/23 198 Construction iteration I 9 35 7/10 7/21
  • 46. Detailed Scheduling To reach a milestone, many tasks have to be performed Lowest level tasks - those that can be done by a person (in less than 2-3 days) Scheduling - decide the tasks, assign them while preserving high-level schedule Is an iterative task - if cannot “fit” all tasks, must revisit high level schedule
  • 47. Detailed Scheduling Detailed schedule not done completely in the start - it evolves Can use MS Project for keeping it Detailed Schedule is the most live document for managing the project Any activity to be done must get reflected in the detailed schedule
  • 48. An example task in detail schedule Module Act Code Task Duration Effort History PUT Unit test # 17 1 day 7 hrs St. date End date %comp Depend. Resource 7/18 7/18 0% Nil SB
  • 49. .Project Scheduling….. The scheduling process
  • 50. ..Project Scheduling…. Graphical notations used in software project scheduling: Tables: summary description of tasks Bar charts : show schedule against the time Activity charts : graphs that depict dependencies between tasks and indicate the critical path (the longest path in the activity graph)
  • 51. … Project Scheduling… Example of tabular description [Fig. 5.5, SE-7]:
  • 52. … .Project Scheduling.. Example of activity chart
  • 53. … ..Project Scheduling. Example of bar chart
  • 54. …… Project Scheduling Staff allocation chart
  • 55. Detail schedule Each task has name, date, duration, resource etc assigned % done is for tracking (tools use it) The detailed schedule has to be consistent with milestones Tasks are sub-activities of milestone level activities, so effort should add up, total schedule should be preserved
  • 56. Team Structure To assign tasks in detailed schedule, need to have a clear team structure Hierarchic team org is most common Project manager has overall responsibility; also does design etc. Has programmers and testers for executing detailed tasks May have config controller, db manager, etc
  • 57. Team structure.. An alternative – democratic teams Can work for small teams; leadership rotates Another one used for products A dev team led by a dev mgr, a test team led by test mgr, and a prog. Mgmt team All three report to a product mgr Allows specialization of tasks and separate career ladders for devs, tests, PMs
  • 58. SCM process and planning Have discussed SCM process earlier During planning, the SCM activities are planned along with who will perform them Have discussed planning also earlier Includes defining CM items, naming scheme, directory structure, access restrictions, change control, versioning, release procedure etc
  • 60. Quality Planning Delivering high quality is a basic goal Quality can be defined in many ways Current industry standard - delivered defect density (e.g. #defects/KLOC) Defect - something that causes software to behave in an inconsistent manner Aim of a project - deliver software with low delivered defect density
  • 61. Defect Injection and Removal Software development is labor intensive Defects are injected at any stage As quality goal is low delivered defect density, these defects have to be removed Done primarily by quality control (QC) activities of reviews and testing
  • 63. Approaches to Quality Management Ad hoc - some testing, some reviews done as and when needed Procedural - defined procedures are followed in a project Quantitative - defect data analysis done to manage the quality process
  • 64. Procedural Approach A quality plan defines what QC tasks will be undertaken and when Main QC tasks - reviews and testing Guidelines and procedures for reviews and testing are provided During project execution, adherence to the plan and procedures ensured
  • 65. Quantitative Approach Goes beyond asking “has the procedure been executed” Analyzes defect data to make judgements about quality Past data is very important Key parameters - defect injection and removal rates, defect removal efficiency (DRE)
  • 66. Quality Plan The quality plan drives the quality activities in the project Level of plan depends on models available Must define QC tasks that have to be performed in the project Can specify defect levels for each QC tasks (if models and data available)
  • 68. Risk Management Any project can fail - reasons can be technical, managerial, etc. Project management aims to tackle the project management aspect Engineering life cycles aim to tackle the engineering issues A project may fail due to unforeseen events - risk management aims to tackle this
  • 69. Risk Management Risk: any condition or event whose occurrence is not certain but which can cause the project to fail Aim of risk management: minimize the effect of risks on a project
  • 71. Risk Identification To identify possible risks to a project, i.e. to those events that might occur and which might cause the project to fail No “algorithm” possible, done by “what ifs”, checklists, past experience Can have a list of “top 10” risks that projects have seen in past
  • 72. Top Risk Examples Shortage of technically trained manpower Too many requirement changes Unclear requirements Not meeting performance requirements Unrealistic schedules Insufficient business knowledge Working on new technology
  • 73. Risk Prioritization The number of risks might be large Must prioritize them to focus attention on the “high risk” areas For prioritization, impact of each risk must be understood In addition, probability of the risk occurring should also be understood
  • 74. Risk Prioritization ... Risk exposure (RE) = probability of risk occurring * risk impact RE is the expected value of loss for a risk Prioritization can be done based on risk exposure value Plans can be made to handle high RE risks
  • 75. A Simple approach to Risk Prioritization Classify risk occurrence probabilities as: Low, Medium, High Classify risk impact as: Low, Medium, High Identify those that are HH, or HM/MH Focus on these for risk mitigation Will work for most small and medium sized projects
  • 76. Risk Control Can the risk be avoided? E.g. if new hardware is a risk, it can be avoided by working with proven hardware For others, risk mitigation steps need to be planned and executed Actions taken in the project such that if the risk materializes, its impact is minimal Involves extra cost
  • 77. Risk Mitigation Examples Too many requirement changes Convince client that changes in requirements will have an impact on the schedule Define a procedure for requirement changes Maintain cumulative impact of changes and make it visible to client Negotiate payment on actual effort.
  • 78. Examples ... Manpower attrition Ensure that multiple resources are assigned on key project areas Have team building sessions Rotate jobs among team members Keep backup resources in the project Maintain documentation of individual’s work Follow the CM process and guidelines strictly
  • 79. Examples ... Unrealistic schedules Negotiate for better schedule Identify parallel tasks Have resources ready early Identify areas that can be automated If the critical path is not within the schedule, negotiate with the client Negotiate payment on actual effort
  • 80. Risk Mitigation Plan Risk mitigation involves steps that are to be performed (hence has extra cost) It is not a paper plan - these steps should be scheduled and executed These are different from the steps one would take if the risk materializes - they are performed only if needed Risks must be revisited periodically
  • 82. Background A plan is a mere document that can guide It must be executed To ensure execution goes as per plan, it must be monitored and controlled Monitoring requires measurements And methods for interpreting them Monitoring plan has to plan for all the tasks related to monitoring
  • 83. Measurements Must plan for measurements in a project Without planning, measurements will not be done Main measurements – effort, size, schedule, and defects Effort – as this is the main resource; often tracked through effort reporting tools Defects – as they determine quality; often defect logging and tracking systems used During planning – what will be measured, how, tool support, and data management
  • 84. Project Tracking Goal: To get visibility in project execution so corrective actions can be taken when needed to ensure project succeeds Diff types of monitoring done at projects; measurements provide data for it
  • 85. Tracking… Activity-level monitoring Each activity in detailed schd is getting done Often done daily by managers A task done marked 100%; tools can determine status of higher level tasks Status reports Generally done weekly to take stock Summary of activities completed, pending Issues to be resolved
  • 86. Tracking… Milestone analysis A bigger review at milestones Actual vs estimated for effort and sched is done Risks are revisited Changes to product and their impact may be analyzed Cost-schedule milestone graph is another way of doing this
  • 88. Project Management Plan The project management plan (PMP) contains outcome of all planning activities - focuses on overall project management Besides PMP, a project schedule is needed Reflects what activities get done in the project Microsoft project (MSP) can be used for this Based on project planning; is essential for day-to-day management Does not replace PMP !
  • 89. PMP Structure - Example Project overview - customer, start and end date, overall effort, overall value, main contact persons, project milestones, development environment.. Project planning - process and tailoring, requirements change mgmt, effort estimation, quality goals and plan, risk management plan, ..
  • 90. PMP Example ... Project tracking - data collection, analysis frequency, escalation procedures, status reporting, customer complaints, … Project team, its organization, roles and responsibility, …
  • 91. Project Planning - Summary Project planning forms the foundation of project management Key aspects: effort and schedule estimation, quality planning, risk mgmt., … Outputs of all can be documented in a PMP, which carries all relevant info about project Besides PMP, a detailed project schedule maintains tasks to be done in the project