4. Project Cost Management
-

Cost is one of 3 Triple constraints of the project. Managing costs of the project is
very crucial and hardest part of the project. It spans across all phases of the project
right from conception to closure of the project.

-

Cost Management is not just controlling “Costs”; it involves definitive planning and
preparing budgets. Collecting cost associated data. Comparing the data to prepared
budgets and taking appropriate actions when needed.

-

The process involved in estimating, budgeting, and controlling cost so that the
project can be completed within approved budget.
Value analysis (value engineering)
ď‚· Looking at less costly way to do the same work within the same scope
Following table lists all 3 Processes in this Knowledge Area, spread across '2 out of 5
Process Groups'

-

5 Process
Groups

Initiation

Planning

Executi
on

Monitoring and
control

Closing

4.1. Cost Estimating
Processes

4.3. Cost Control
4.2. Cost Budgeting

4.1 Estimate Cost
- The process of developing approximation of the monetary resources needed to complete
project activities
ď‚· Cost trade-offs & risk must be considered
ď‚·

Cost estimates should be refined

Inputs

-

-

Scope baseline
Project schedule
Human resource plan
Risk register
Enterprise
environmental
factors
Organizational
process assets

Tools

-

Expert judgment
Analogous estimating
Parametric estimating
Bottom-up estimating
Three-point estimates
Reserve analysis
Cost of quality
Project management
estimating software
Vendor bid analysis

Outputs

- Activity cost estimates
- Basis of estimates
- Project document updates

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
There are 3 different types of estimation techniques listed over here under Tools section of Cost
Estimation.
- Analogous Estimation techniques
- Bottom-up approach technique
- Parametric approach technique
Analogous estimation
-It is mainly based on Expert Judgment or based on similar previous Projects. This approach is
very useful in early stages of the project where WBS and work packets are completely defined.
The expert judgment success factor depends on similarity of previous projects too. The main
disadvantage is that it is good for ball-park figures but not for precise project cost.
Parametric Estimation
- It considers different project characteristics to calculate total costs of the project. For example,
in the Telephone wire digging project, if we know cost per meter we can estimate it to whole
project. For a house construction, if we know cost to construct per square feet, we can estimate
total house project. For complex projects there will be multi dimensional parameters involved.
When historic information is available these parametric estimation will be more accurate.
Bottom-up approach
- It is elaborative estimation technique. We start estimating from the bottom most part of WBS
hierarchy which is work package. Work packages are divided into activities. Summing up work
packages to modules or groups, summing up different modules to stages, summing up different
stages to project is the bottom-up approach method. The people who will actually do this work
should create the estimates.
Types of Cost;

-

-

Variable Costs
ď‚· Change with the amount of production/work
ď‚· e.g. material, supplies, wages
Fixed Costs
ď‚· Do not change as production change
ď‚·

-

Direct Costs
ď‚· Directly attributable to the work of project
ď‚·

-

e.g. set-up, rental

e.g. team travel, recognition, team wages

Indirect Costs
ď‚· overhead or cost incurred for benefit of more than one project
ď‚·

e.g. taxes, fringe benefit, janitorial services

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
-

It is very important to understand “Cost Variability” that focuses on changing of
cost over time as well as over volume;
ď‚·

Inflation; cost of some items increase over time.

ď‚·

Deflation; cost of technology items decrease over time.

Direct Costs vs. Indirect Costs

-

when talking about “a new project team member”, the direct cost will be his salary
while the indirect costs may be the insurance premiums given to him, the paid pill
for his telephone calls, computer internet access cost, his disk or disk space that have
been given to him.

-

When talking about “a specific material needed”, the direct cost will be its price
while the indirect cost will be the transportation cost paid to receive such material as
well as the storing cost...etc.

Fixed Costs vs. Variable Costs

-

A fixed cost is like the cost of a unit has a certain nature which maybe a resource
such as a specific material or equipment used for the project. If you need to buy a
piece of equipment to allow the project to continue, that is simply a fixed cost
regardless it will be used for once or hundreds of times.

-

Variable costs are directly related to the level of work with each and every element
of the WBS. It is like the cost of water needed to drink or Gasoline needed to some
machinery.

Quality/Accuracy of Cost Estimation

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
4.2 Determine Budget
- Process of aggregating the estimated cost of individual activities or work packages to
establish an authorized cost baseline.
Inputs

- Activity cost estimates
- Basis of estimates
- Scope baselines
- Project schedule
- Resource calendars
- Contracts
- Organizational process
assets

Tools

-

Cost aggregation
Reserve analysis
Expert judgment
Historical relationship
Funding limit
reconciliation

Outputs

-

Cost performance
baseline
Project funding
requirements
Project document
updates

- The main goal of this process is to develop Cost Baseline. At the starting point of this Process,
you should have finished Project Cost Estimation and have a complete list of estimates of
individual
activities.
Cost Aggregation;
-

We use Cost Aggregation tools to sum up those low level activity costs to Work package to
higher levels of WBS hierarchy.

-

Reserves & risk management are important while estimating!

ď‚·

Contingency reserves/Cost Baseline (the cost impacts of the remaining risk)

ď‚·

Management reserves/Cost Budget (extra fund to cover surprising risks or
changes to the project).

The cost baseline
-

It is a reference point for the project to compare time to time. You will monitor and control
project costs comparing to the baseline and report any variations. Costs at work package
level are tied to financial systems using Chart of Accounts. Chart of accounts show cost
allocation categories.

Project manager is allowed to allocate extra resources (time or money) as a buffer for known
unknowns; we call it as Contingency Reserve.
Determines Budget: Other considerations

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
- High level parametric estimate as a rule of thumb
ď‚· E.g. testing cost 50% of development cost
- Funding limit reconciliation = checking cash flow
ď‚· When the money will be available?
- Reconciliation needed before proposed cost baseline and cost budget become final
ď‚· Such reconciliation is part of integration management

4.3 Control Cost
- The process of monitoring the status of the project to update the project budget and
managing changes to the cost baseline.
Inputs

- Project management
plan
- Project funding
requirement
- Work performance
information
- Organizational process
assets

Tools

-

Earned value
management
Forecasting
To-complete
performance index
Performance reviews
Variance analysis
Project management
software

Outputs

-

Work performance
measurement
Budget forecast
Organizational process
updates
Change requests
Project management plan
updates
Project document updates

Cost control:
Once you estimate Project costs as well as cost baseline and prepare a Budget, you will
be on cruise mode to control the costs. That doesn’t mean it is easy thereafter. No not at
all. You have to monitor your cost so closely. Your work performance information is key
input for this process. You should have clear set templates to report the work progress.
Otherwise all unwanted junk data might ruin the soup.

How to control cost?

-

Follow the cost management plan

-

Look at any organizational process asset that are available

-

Manage change
ď‚·

Recording all appropriate change

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
ď‚·
ď‚·

Ensuring requested changes are agreed upon

ď‚·
-

Preventing incorrect change

Managing the actual changes when and as they occur

Measure and measure and measure (monitoring)

Project performance review is another Tools & Techniques provided. You will review

project progress with your baseline plans and will provide what you’ve earned against
what you have planned. This is known as Earned Value Analysis and helps you to track
your day to day progress. 3 possible scenarios are: you are progressing ahead of plan that
means you are getting more than what you have planned, or progress is as per the plan or
not getting enough worth for your investment. Based on these 3 scenarios you can take
according corrective actions. Corrective actions are what you are supposed to do in this
process.

You can use Project Management software of your choice to help you in this regard. MS
Project is popular one or even you can simply use well planned out Excel sheets to track
those costs.

First you will find variances and report those using Variance analysis. The terms you use
over here are Cost Variance (CV) and Schedule Variance (SV). From that point you
might required to forecast rest of the project. This involves estimating rest of the work.
You use terms like Estimation to Completion (ETC) and Estimate at Complete (EAC).
Those names are telling what you have to Estimate.
Other terms you use here are Cost Performance Index (CPI) and SPI (Schedule
Performance Index)

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Earned Value Technique
Ex;

Cont. Earned Value Technique

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Earned Value Management
-

Method to measure project performance against scope, schedule and cost baseline
(performance measurement baseline).

-

Interpretation of basic EVM performance measures

ď‚·

Cost Performance Index (CPI)

ď‚·

Schedule Performance Index (SPI)

Exercise;

-

You have a project to build a box. The box is six sided. Each side is to take one day to
build and is budgeted for $1000 per side. The sides are planned to be completed one
after the other. Today is the end of day three.

-

Using the following project status chart, calculate PV, EV, AC, BAC, CV, CPI, SV,
SPI, EAC, ETC, VAC.

-

Describe your interpretation based on the calculation!

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Solution;

Hence, based on the result table;
• Over budget, getting 0.88 dollar for every spent dollar,
• Ahead schedule, progressing 101% of the rate planned,
• Probably will spend $6818 at the end (estimation),
• need $3368 to complete,
• Over budget at the end for about $818 (estimation)
Performance Metrics;

-

Budget At Completion (BAC) “Total cost of the project.”

-

Budgeted Cost for Work Scheduled (BCWS) / Planned Value (PV)
ď‚·
ď‚·

-

The amount expressed in Pounds (or hours) of work to be performed as
per the schedule plan.
PV = BAC * % of planned work.

Budgeted Cost for Work Performed (BCWP) / Earned Value (EV)
ď‚·
ď‚·

-

The amount expressed in Pounds (or hours) on the actual worked
performed.
EV = BAC * % of Actual work

Actual Cost of Work Performed (ACWP) / Actual Cost (AC)

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Cost Forecasting:

-

Estimate At Completion (EAC)

-

The expected TOTAL cost required to finish complete work.

-

EAC = BAC / CPI
= AC + (BAC - EV) (at typical case)
= AC + ((BAC - EV) / CPI) (The same performance will remain)
= AC + (BAC - EV) / (CPI* SPI) (The same performance will remain +
Extra loss due to delay in time)

* Here “typical” means it is assumed that similar variances will not occur in the future.

-

Estimate to complete (ETC)

-

The expected cost required to finish all the Remaining work.

-

ETC

= EAC - AC
= (BAC - EV) / CPI

Variances:
ď‚·

Cost Variances (CV)
Determine “How much under or over budget?”
CV = EV-AC
NEGATIVE is over budget, POSITIVE is under budget.

ď‚·

Schedule Variances (SV)
Determine “How much ahead or behind schedule?”.
SV = EV-PV
NEGATIVE is behind schedule, POSITIVE is ahead of schedule.

ď‚·

Variance At Completion (VAC)
Variance of “TOTAL” cost of the work and expected cost.
VAC = BAC - EAC

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Performance Indices:
ď‚·

Cost Performance Index
CPI = EV / AC
“Over (< 1) or under (> 1) budget”.

ď‚·

Schedule Performance Index
SPI = EV / PV
“Ahead (> 1) or behind (< 1) schedule”.

To-Complete Performance Index (TCPI)

-

Helps the team determine the efficiency that must be achieved on the remaining
work for a project to meet a specified endpoint, such as BAC or the team’s revised
EAC.
TCPI = Remaining Work (BAC – EV) / Funds Remaining (EAC - AC)

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Problem: A project has a budget of ÂŁ10M and schedule for 10 months. It is assumed that

the total budget will be spent equally each month until the 10th month is reached. After 2
months the project manager finds that only 5% of the work is finished and a total of ÂŁ1M
spent.
Solution:
PV = ÂŁ2M
EV = ÂŁ10M * 0.05 = ÂŁ0.5M
AV = ÂŁ1M
CV = EV-AC = 0.5-1 = -0.5M
CV% = 100 * (CV/EV) = 100*(-0.5/0.5) = -100% overrun
SV = EV-PV = 0.5-2 = -1.5 months
SV% = 100 * (SV/PV) = 100*(-1.5/2) = -75% behind
CPI = EV/AC = 0.5/1 = 0.5
SPI = EV/PV = 0.5/2 = 0.25
EAC = BAC/CPI = 10/0.5 = ÂŁ20M
ETC = (BAC-EV) / CPI = (10-0.5)/0.5 = ÂŁ19M
Time to compete = (10-0.5)/0.25 = 38 Months

This project will take TOTAL ÂŁ20M (19+1) and 40 (38+2) Months to complete.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Hints to remember;
-

EV comes in most of formulas specially regarding “Variance” & “Index”

-

If it’s variance, the formula is EV – something.

-

If it’s index, EV / something.

-

If it relates to cost, use Actual Cost.

-

If it relates to schedule, use PV.

-

Negative numbers are bad, positive is good.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD

More Related Content

PPTX
Project Cost Management
PPS
An Introduction To Project Management
PPT
Project cost management-slides
PDF
A brief on project cost management
PPTX
PROJECT CONTROL PROCESS
PPTX
Project Management Life Cycle
 
PDF
Methodologies of Project Progress Measurement
PPT
09. Project Cost Management
Project Cost Management
An Introduction To Project Management
Project cost management-slides
A brief on project cost management
PROJECT CONTROL PROCESS
Project Management Life Cycle
 
Methodologies of Project Progress Measurement
09. Project Cost Management

What's hot (20)

PPS
Critical Chain Project Management
PPT
Estimating Cost & Time.ppt
PPT
Project planning and Scheduling
PPTX
Project Management Best Practices - Tips and Techniques
PPT
Project Manangement Introduction
 
PPTX
Earned value analysis (1)
PPT
Project management
PDF
Project Quality Management - PMBOK
PPTX
Project Cost Management
PPTX
Project cost & control
PPTX
Project management
PPTX
Earned Value Analysis
PPTX
2. project initiation
PPT
Project management planning
PDF
4.Cost management
PPTX
Elements of Project Management
PPTX
10- PMP Training - Risk Management
PPTX
What are the Basic Principles of Project Management | AIMS, UK
PPT
05. Project And Organizational Structure
PPTX
Project management life cycle
Critical Chain Project Management
Estimating Cost & Time.ppt
Project planning and Scheduling
Project Management Best Practices - Tips and Techniques
Project Manangement Introduction
 
Earned value analysis (1)
Project management
Project Quality Management - PMBOK
Project Cost Management
Project cost & control
Project management
Earned Value Analysis
2. project initiation
Project management planning
4.Cost management
Elements of Project Management
10- PMP Training - Risk Management
What are the Basic Principles of Project Management | AIMS, UK
05. Project And Organizational Structure
Project management life cycle
Ad

Similar to 4. project cost management (20)

PPT
Cost management
PPTX
Software Project Cost Management and estimation
PDF
Constructiion cost estimating 2017
PDF
Project Management A Managerial Approach 9th Edition Meredith Solutions Manual
PDF
Project cost management
PDF
Project Management A Managerial Approach 9th Edition Meredith Solutions Manual
PDF
Project Management A Managerial Approach 9th Edition Meredith Solutions Manual
PDF
Project Management A Managerial Approach 9th Edition Meredith Solutions Manual
DOCX
Term paper spm
PPT
Project_cost_managment definition and tools
PPT
con_mangt-lec4-project_costppt.ppt
PPT
con_mangt-lec4-project_costppt.ppt
PPT
con_mangt-lec4cxxxxxxxxxx-project_costppt.ppt
 
PPTX
Project Estimation Project Estimation Project Estimation
PDF
Project Management A Managerial Approach 9th Edition Meredith Solutions Manual
PPTX
engineering economics lect 8-10 final.pptx
PPT
Project Cost Management
PDF
Project Management A Managerial Approach 9th Edition Meredith Solutions Manual
PDF
Project Management A Managerial Approach 9th Edition Meredith Solutions Manual
Cost management
Software Project Cost Management and estimation
Constructiion cost estimating 2017
Project Management A Managerial Approach 9th Edition Meredith Solutions Manual
Project cost management
Project Management A Managerial Approach 9th Edition Meredith Solutions Manual
Project Management A Managerial Approach 9th Edition Meredith Solutions Manual
Project Management A Managerial Approach 9th Edition Meredith Solutions Manual
Term paper spm
Project_cost_managment definition and tools
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4cxxxxxxxxxx-project_costppt.ppt
 
Project Estimation Project Estimation Project Estimation
Project Management A Managerial Approach 9th Edition Meredith Solutions Manual
engineering economics lect 8-10 final.pptx
Project Cost Management
Project Management A Managerial Approach 9th Edition Meredith Solutions Manual
Project Management A Managerial Approach 9th Edition Meredith Solutions Manual
Ad

More from Mohamed Salah Eldien Mohamed Ali (12)

PDF
Series_Certificate
PDF
Business Management Cert.
PDF
Business Management Cert.
PDF
9. project procurement management
PDF
8. project risk management
PDF
7. project communications management
PDF
6. project human resource management
PDF
5. project quality management
PDF
2. project scope management
PDF
3. project time management
PDF
1. project integration management
PDF
0. project management framework (fundamentals)
Series_Certificate
Business Management Cert.
Business Management Cert.
9. project procurement management
8. project risk management
7. project communications management
6. project human resource management
5. project quality management
2. project scope management
3. project time management
1. project integration management
0. project management framework (fundamentals)

Recently uploaded (20)

PDF
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
PDF
Business model innovation report 2022.pdf
PPTX
Probability Distribution, binomial distribution, poisson distribution
PDF
How to Get Funding for Your Trucking Business
PPT
340036916-American-Literature-Literary-Period-Overview.ppt
PPT
Data mining for business intelligence ch04 sharda
PPTX
Amazon (Business Studies) management studies
DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
PDF
Dr. Enrique Segura Ense Group - A Self-Made Entrepreneur And Executive
PDF
Unit 1 Cost Accounting - Cost sheet
PDF
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
PPTX
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
PDF
Types of control:Qualitative vs Quantitative
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PDF
Chapter 5_Foreign Exchange Market in .pdf
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PDF
Reconciliation AND MEMORANDUM RECONCILATION
PDF
Training And Development of Employee .pdf
PDF
IFRS Notes in your pocket for study all the time
DOCX
Euro SEO Services 1st 3 General Updates.docx
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
Business model innovation report 2022.pdf
Probability Distribution, binomial distribution, poisson distribution
How to Get Funding for Your Trucking Business
340036916-American-Literature-Literary-Period-Overview.ppt
Data mining for business intelligence ch04 sharda
Amazon (Business Studies) management studies
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
Dr. Enrique Segura Ense Group - A Self-Made Entrepreneur And Executive
Unit 1 Cost Accounting - Cost sheet
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
Types of control:Qualitative vs Quantitative
Power and position in leadershipDOC-20250808-WA0011..pdf
Chapter 5_Foreign Exchange Market in .pdf
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
Reconciliation AND MEMORANDUM RECONCILATION
Training And Development of Employee .pdf
IFRS Notes in your pocket for study all the time
Euro SEO Services 1st 3 General Updates.docx

4. project cost management

  • 1. 4. Project Cost Management - Cost is one of 3 Triple constraints of the project. Managing costs of the project is very crucial and hardest part of the project. It spans across all phases of the project right from conception to closure of the project. - Cost Management is not just controlling “Costs”; it involves definitive planning and preparing budgets. Collecting cost associated data. Comparing the data to prepared budgets and taking appropriate actions when needed. - The process involved in estimating, budgeting, and controlling cost so that the project can be completed within approved budget. Value analysis (value engineering) ď‚· Looking at less costly way to do the same work within the same scope Following table lists all 3 Processes in this Knowledge Area, spread across '2 out of 5 Process Groups' - 5 Process Groups Initiation Planning Executi on Monitoring and control Closing 4.1. Cost Estimating Processes 4.3. Cost Control 4.2. Cost Budgeting 4.1 Estimate Cost - The process of developing approximation of the monetary resources needed to complete project activities ď‚· Cost trade-offs & risk must be considered ď‚· Cost estimates should be refined Inputs - - Scope baseline Project schedule Human resource plan Risk register Enterprise environmental factors Organizational process assets Tools - Expert judgment Analogous estimating Parametric estimating Bottom-up estimating Three-point estimates Reserve analysis Cost of quality Project management estimating software Vendor bid analysis Outputs - Activity cost estimates - Basis of estimates - Project document updates By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 2. There are 3 different types of estimation techniques listed over here under Tools section of Cost Estimation. - Analogous Estimation techniques - Bottom-up approach technique - Parametric approach technique Analogous estimation -It is mainly based on Expert Judgment or based on similar previous Projects. This approach is very useful in early stages of the project where WBS and work packets are completely defined. The expert judgment success factor depends on similarity of previous projects too. The main disadvantage is that it is good for ball-park figures but not for precise project cost. Parametric Estimation - It considers different project characteristics to calculate total costs of the project. For example, in the Telephone wire digging project, if we know cost per meter we can estimate it to whole project. For a house construction, if we know cost to construct per square feet, we can estimate total house project. For complex projects there will be multi dimensional parameters involved. When historic information is available these parametric estimation will be more accurate. Bottom-up approach - It is elaborative estimation technique. We start estimating from the bottom most part of WBS hierarchy which is work package. Work packages are divided into activities. Summing up work packages to modules or groups, summing up different modules to stages, summing up different stages to project is the bottom-up approach method. The people who will actually do this work should create the estimates. Types of Cost; - - Variable Costs ď‚· Change with the amount of production/work ď‚· e.g. material, supplies, wages Fixed Costs ď‚· Do not change as production change ď‚· - Direct Costs ď‚· Directly attributable to the work of project ď‚· - e.g. set-up, rental e.g. team travel, recognition, team wages Indirect Costs ď‚· overhead or cost incurred for benefit of more than one project ď‚· e.g. taxes, fringe benefit, janitorial services By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 3. - It is very important to understand “Cost Variability” that focuses on changing of cost over time as well as over volume; ď‚· Inflation; cost of some items increase over time. ď‚· Deflation; cost of technology items decrease over time. Direct Costs vs. Indirect Costs - when talking about “a new project team member”, the direct cost will be his salary while the indirect costs may be the insurance premiums given to him, the paid pill for his telephone calls, computer internet access cost, his disk or disk space that have been given to him. - When talking about “a specific material needed”, the direct cost will be its price while the indirect cost will be the transportation cost paid to receive such material as well as the storing cost...etc. Fixed Costs vs. Variable Costs - A fixed cost is like the cost of a unit has a certain nature which maybe a resource such as a specific material or equipment used for the project. If you need to buy a piece of equipment to allow the project to continue, that is simply a fixed cost regardless it will be used for once or hundreds of times. - Variable costs are directly related to the level of work with each and every element of the WBS. It is like the cost of water needed to drink or Gasoline needed to some machinery. Quality/Accuracy of Cost Estimation By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 4. 4.2 Determine Budget - Process of aggregating the estimated cost of individual activities or work packages to establish an authorized cost baseline. Inputs - Activity cost estimates - Basis of estimates - Scope baselines - Project schedule - Resource calendars - Contracts - Organizational process assets Tools - Cost aggregation Reserve analysis Expert judgment Historical relationship Funding limit reconciliation Outputs - Cost performance baseline Project funding requirements Project document updates - The main goal of this process is to develop Cost Baseline. At the starting point of this Process, you should have finished Project Cost Estimation and have a complete list of estimates of individual activities. Cost Aggregation; - We use Cost Aggregation tools to sum up those low level activity costs to Work package to higher levels of WBS hierarchy. - Reserves & risk management are important while estimating! ď‚· Contingency reserves/Cost Baseline (the cost impacts of the remaining risk) ď‚· Management reserves/Cost Budget (extra fund to cover surprising risks or changes to the project). The cost baseline - It is a reference point for the project to compare time to time. You will monitor and control project costs comparing to the baseline and report any variations. Costs at work package level are tied to financial systems using Chart of Accounts. Chart of accounts show cost allocation categories. Project manager is allowed to allocate extra resources (time or money) as a buffer for known unknowns; we call it as Contingency Reserve. Determines Budget: Other considerations By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 5. - High level parametric estimate as a rule of thumb ď‚· E.g. testing cost 50% of development cost - Funding limit reconciliation = checking cash flow ď‚· When the money will be available? - Reconciliation needed before proposed cost baseline and cost budget become final ď‚· Such reconciliation is part of integration management 4.3 Control Cost - The process of monitoring the status of the project to update the project budget and managing changes to the cost baseline. Inputs - Project management plan - Project funding requirement - Work performance information - Organizational process assets Tools - Earned value management Forecasting To-complete performance index Performance reviews Variance analysis Project management software Outputs - Work performance measurement Budget forecast Organizational process updates Change requests Project management plan updates Project document updates Cost control: Once you estimate Project costs as well as cost baseline and prepare a Budget, you will be on cruise mode to control the costs. That doesn’t mean it is easy thereafter. No not at all. You have to monitor your cost so closely. Your work performance information is key input for this process. You should have clear set templates to report the work progress. Otherwise all unwanted junk data might ruin the soup. How to control cost? - Follow the cost management plan - Look at any organizational process asset that are available - Manage change ď‚· Recording all appropriate change By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 6. ď‚· ď‚· Ensuring requested changes are agreed upon ď‚· - Preventing incorrect change Managing the actual changes when and as they occur Measure and measure and measure (monitoring) Project performance review is another Tools & Techniques provided. You will review project progress with your baseline plans and will provide what you’ve earned against what you have planned. This is known as Earned Value Analysis and helps you to track your day to day progress. 3 possible scenarios are: you are progressing ahead of plan that means you are getting more than what you have planned, or progress is as per the plan or not getting enough worth for your investment. Based on these 3 scenarios you can take according corrective actions. Corrective actions are what you are supposed to do in this process. You can use Project Management software of your choice to help you in this regard. MS Project is popular one or even you can simply use well planned out Excel sheets to track those costs. First you will find variances and report those using Variance analysis. The terms you use over here are Cost Variance (CV) and Schedule Variance (SV). From that point you might required to forecast rest of the project. This involves estimating rest of the work. You use terms like Estimation to Completion (ETC) and Estimate at Complete (EAC). Those names are telling what you have to Estimate. Other terms you use here are Cost Performance Index (CPI) and SPI (Schedule Performance Index) By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 7. Earned Value Technique Ex; Cont. Earned Value Technique By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 8. Earned Value Management - Method to measure project performance against scope, schedule and cost baseline (performance measurement baseline). - Interpretation of basic EVM performance measures ď‚· Cost Performance Index (CPI) ď‚· Schedule Performance Index (SPI) Exercise; - You have a project to build a box. The box is six sided. Each side is to take one day to build and is budgeted for $1000 per side. The sides are planned to be completed one after the other. Today is the end of day three. - Using the following project status chart, calculate PV, EV, AC, BAC, CV, CPI, SV, SPI, EAC, ETC, VAC. - Describe your interpretation based on the calculation! By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 9. Solution; Hence, based on the result table; • Over budget, getting 0.88 dollar for every spent dollar, • Ahead schedule, progressing 101% of the rate planned, • Probably will spend $6818 at the end (estimation), • need $3368 to complete, • Over budget at the end for about $818 (estimation) Performance Metrics; - Budget At Completion (BAC) “Total cost of the project.” - Budgeted Cost for Work Scheduled (BCWS) / Planned Value (PV) ď‚· ď‚· - The amount expressed in Pounds (or hours) of work to be performed as per the schedule plan. PV = BAC * % of planned work. Budgeted Cost for Work Performed (BCWP) / Earned Value (EV) ď‚· ď‚· - The amount expressed in Pounds (or hours) on the actual worked performed. EV = BAC * % of Actual work Actual Cost of Work Performed (ACWP) / Actual Cost (AC) By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 10. Cost Forecasting: - Estimate At Completion (EAC) - The expected TOTAL cost required to finish complete work. - EAC = BAC / CPI = AC + (BAC - EV) (at typical case) = AC + ((BAC - EV) / CPI) (The same performance will remain) = AC + (BAC - EV) / (CPI* SPI) (The same performance will remain + Extra loss due to delay in time) * Here “typical” means it is assumed that similar variances will not occur in the future. - Estimate to complete (ETC) - The expected cost required to finish all the Remaining work. - ETC = EAC - AC = (BAC - EV) / CPI Variances: ď‚· Cost Variances (CV) Determine “How much under or over budget?” CV = EV-AC NEGATIVE is over budget, POSITIVE is under budget. ď‚· Schedule Variances (SV) Determine “How much ahead or behind schedule?”. SV = EV-PV NEGATIVE is behind schedule, POSITIVE is ahead of schedule. ď‚· Variance At Completion (VAC) Variance of “TOTAL” cost of the work and expected cost. VAC = BAC - EAC By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 11. Performance Indices: ď‚· Cost Performance Index CPI = EV / AC “Over (< 1) or under (> 1) budget”. ď‚· Schedule Performance Index SPI = EV / PV “Ahead (> 1) or behind (< 1) schedule”. To-Complete Performance Index (TCPI) - Helps the team determine the efficiency that must be achieved on the remaining work for a project to meet a specified endpoint, such as BAC or the team’s revised EAC. TCPI = Remaining Work (BAC – EV) / Funds Remaining (EAC - AC) By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 12. Problem: A project has a budget of ÂŁ10M and schedule for 10 months. It is assumed that the total budget will be spent equally each month until the 10th month is reached. After 2 months the project manager finds that only 5% of the work is finished and a total of ÂŁ1M spent. Solution: PV = ÂŁ2M EV = ÂŁ10M * 0.05 = ÂŁ0.5M AV = ÂŁ1M CV = EV-AC = 0.5-1 = -0.5M CV% = 100 * (CV/EV) = 100*(-0.5/0.5) = -100% overrun SV = EV-PV = 0.5-2 = -1.5 months SV% = 100 * (SV/PV) = 100*(-1.5/2) = -75% behind CPI = EV/AC = 0.5/1 = 0.5 SPI = EV/PV = 0.5/2 = 0.25 EAC = BAC/CPI = 10/0.5 = ÂŁ20M ETC = (BAC-EV) / CPI = (10-0.5)/0.5 = ÂŁ19M Time to compete = (10-0.5)/0.25 = 38 Months This project will take TOTAL ÂŁ20M (19+1) and 40 (38+2) Months to complete. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 13. Hints to remember; - EV comes in most of formulas specially regarding “Variance” & “Index” - If it’s variance, the formula is EV – something. - If it’s index, EV / something. - If it relates to cost, use Actual Cost. - If it relates to schedule, use PV. - Negative numbers are bad, positive is good. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD