Critical Chain Project Management  - Introduction
Agenda Refresher Project Network  Critical Path  Earned Value Traditional Project Estimation Critical Chain Project Mgmt. Differences from Critical Path CCPM Principles Task & Project Buffers EVM and Buffer Management CCPM Behaviors CCPM Focus
Refresher - Project Network  A project network is a graph (flow chart) depicting the sequence in which a project's terminal elements are to be completed by showing terminal elements and their dependencies.  Float/Slack in project management is the amount of time that a terminal element in a project network can be delayed by, without causing a delay to: Subsequent terminal elements (free float)  Project completion date (total float).
Refresher - Critical Path  A Critical path is the  sequence  of project network terminal elements  with the longest overall duration , determining the shortest time to complete the project. The duration of the critical path determines the duration of the entire project. Any delay of a terminal element on the critical path directly impacts the planned project completion date (i.e.  there is no slack on the critical path ). A project can have several, parallel critical paths. An additional parallel path through the network with the total durations just shorter than the critical path is called a sub-critical path. The critical path method was invented by the DuPont corporation and originally considered only logical dependencies among terminal elements
Refresher - Earned Value Earned value (EV) compares the work finished so far with the estimates made in the beginning of the project.  Gives a measure of how far the project is from completion.  Allows PM to extrapolate to arrive at Estimate at Completion Earned Value is measured in terms of  budgeted cost of work scheduled (BCWS) or planned value: for every period the budgets of the tasks that were planned to be finished in this time unit  budgeted cost of work produced (BCWP) or earned value: for every period the budgets of the tasks that actually finished in this time unit  actual cost of work produced (ACWP) or effort spent: for every period the actual costs of the work  budget at completion (BAC): sum(BCWS), the total budget estimated to be spent to complete the project
Refresher - Earned Value Earned Value is expressed in terms of  the cost variance (CV): BCWP - ACWP, greater than 0 is good  the schedule variance (SV): BCWP - BCWS, greater than 0 is good  the cost performance index (CPI): BCWP/ACWP, greater than 1 is good  the schedule performance index (SPI): BCWP/BCWS, greater than 1 is good the estimate at completion (EAC): sum(ACWP) + (BAC - sum(BCWP)) / CPI, an estimate of the budget spent at the end of the project
Traditional Project Estimation Assume Infinite Resources Protect the whole by protecting the completion date of each step Pad each step with a lot of safety time Create a Lifecycle network using these estimates to identify the critical path Most of the safety time is taken away by: Student Syndrome Multi-tasking Delays accumulate, advances do not Critical Path  is the constraint on the project
The Limitations “ Work expands to fill (and often exceed) the time allowed.” — Parkinson’s Law “ Whatever can go wrong, will.” — Murphy’s Law “ Many people will start to fully apply themselves to a task just in the wake of a deadline” No matter how long you give students to work on something, they will start the night before. End Result – When problems are encountered deep into the project, there is no buffer to dig into.
Critical Chain Project Mgmt. CCPM was developed by Dr. Eliyahu Goldratt Application of Theory of Constraints (TOC) to Project Management TOC Presented in his Business Novel The Goal CCPM Presented in his Business Novel Critical Chain TOC suggests that all real-world systems have at least one constraint; otherwise they would be capable of infinite throughput, which is clearly impossible.  TOC claims that a real-world system with more than three constraints is extremely unlikely.  Managing a complex system can be made simpler & effective, by providing managers with a few specific focus areas on which to focus -- maximizing performance in the areas of key constraints, or "elevating" the constraint
Critical Chain Project Mgmt. Systems are Analogous to Chains Weakest Link is the System’s Constraint A System’s Optimum Performance IS NOT the Sum of Local Optima A System Has Only One Constraint at a Time Constraints Can Never Really be Eliminated Can Move From One Part of the System to Another In project management, the critical chain is the sequence of both precedence- and resource-dependent terminal elements that prevents a project from being completed in a shorter time, given finite resources.  If resource availability is not a constraint, then a project's critical chain is identical to its critical path.
Differences from Critical Path The use of (often implicit) resource dependencies. Implicit means that they are not included in the project network but have to be identified by looking at the resource requirements.  Lack of search for an optimum solution. This means that a "good enough" solution is enough because:  As far as is known, there is no analytical method of finding an absolute optimum  The inherent uncertainty in estimates is much greater than the difference between the optimum and near-optimum ("good enough" solutions).  The identification and insertion of buffers:  project buffer  feeding buffers  resource buffers.
CCPM Principles Single Integrated Schedule Eliminate   Safeties  from Each Task Management Must Not Insist on Each Task Starting & Finishing “On Time” Start  Right Jobs at Right Time  Using Prioritized Task List Focus on  Meeting Milestone Dates , Not Task Dates  Counter Parkinson’s Law Conserve Available Float/Slack on Each Task, Reduce Time Available Counter Student Syndrome.  Claim Early Finishes Immediately Start Each Task As Early As Possible Predict Milestones Based on Buffer Penetration Focus on  Task Throughput , NOT on Task Costs
Task & Project Buffers
Task & Project Buffers
EVM and Buffer Management Earned value (EV) compares the work finished so far with the estimates made in the beginning of the project.  Gives a measure of how far the project is from completion.  Allows PM to extrapolate to arrive at Estimate at Completion EVM does not distinguish between the progress on the project constraint (i.e. its critical chain) from progress on the non-constraints   Buffer Management focuses on throughput.
CCPM Behaviors Base Duration & Cost Estimates on  Average/Bare Bones  Performance When Problems Occur,  Solve the Problem vice Starting New Task   Decrease  Frequency & Duration of Meetings Resolve Conflicts Immediately at the Jobsite Eliminate  Bad Multi-tasking Resources Focus on One Job at a Time, Work to Completion Request  Only  Resources Necessary to Accommodate  Priority Work Request  Only  Overtime Necessary to  Recover Buffer on Priority Work  Move Resources When Work is Done  to Next Priority Work  Quickly  Work  Right  Jobs instead of  Easy  Jobs Plan for  New Work & Scope Changes vice  Complaining About it
Project Focus Identify the System Constraint Exploit the Constraint Subordinate Everything Else Elevate the Constraint Go back to Step 1 Senior Management Buy in Promote early finishes Focus on usage of Project Buffer Avoid evaluating of team w.r.t. task deadlines CCPM Focus
Summary and Conclusion Critical Chain Project Management can dramatically... Improve project delivery date reliability Shorten overall project duration Provide “early warning” of threats to project delivery Enable earlier, less drastic responses Reduce Costs Reduce Overtime Reduce Rework
Bibliography / Reference Wikipedia http://www.wikipedia.org   Critical Chain  Dr. Eliyahu Goldratt  Buffering Against Risk -- Risk Management and Critical Chain.  http://www.focusedperformance.com/articles/ccrisk.html   Getting Out From Between Parkinson's Rock and Murphy's Hard Place – Francis S. Patrick http://www.focusedperformance.com/articles/ccpm.html Managing an ERP project using critical chain M van Loggerenberg. EDS Enterprise Solutions
Thank You

More Related Content

PPTX
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
PPT
Scheduling-Resources-and-Costs.ppt
PPTX
CPM - Critical Path Method
PDF
An introduction to Critical Chain Project Management (CCPM)
PPTX
Project Planning and Approval Process
PPTX
Project Mangement
PPT
08. Project Time Management Upload
PPTX
Reducing Project Duration_Jagat Prasad Upadhyay.pptx
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
Scheduling-Resources-and-Costs.ppt
CPM - Critical Path Method
An introduction to Critical Chain Project Management (CCPM)
Project Planning and Approval Process
Project Mangement
08. Project Time Management Upload
Reducing Project Duration_Jagat Prasad Upadhyay.pptx

What's hot (20)

PPTX
Critical chain - Eliyahu goldratt
PPTX
Critical Chain Project Management
PPTX
Evolution of project management
PPTX
Project Management Best Practices - Tips and Techniques
PPT
09. Project Cost Management
PPT
Critical Chain Basics
PPTX
Project monitoring and control & planning for monitoring
PDF
Lean Project Management PowerPoint Presentation Slides
PPTX
project management
PPTX
project management (10).pptx
PPTX
Project management
PPTX
Critical Chain Project Management & Theory of Constraints
PPT
Project initiation
PDF
Value Stream Mapping
PDF
Value Stream Mapping: Case Studies
PPTX
Project Execution
PDF
Project Management Kickoff Meeting Template Powerpoint Presentation Slides
PPTX
Project Management Foundations Course 101 - Project Management Concepts
PPT
The Project Management Process - Week 1
PDF
Project Budget PowerPoint Presentation Slides
Critical chain - Eliyahu goldratt
Critical Chain Project Management
Evolution of project management
Project Management Best Practices - Tips and Techniques
09. Project Cost Management
Critical Chain Basics
Project monitoring and control & planning for monitoring
Lean Project Management PowerPoint Presentation Slides
project management
project management (10).pptx
Project management
Critical Chain Project Management & Theory of Constraints
Project initiation
Value Stream Mapping
Value Stream Mapping: Case Studies
Project Execution
Project Management Kickoff Meeting Template Powerpoint Presentation Slides
Project Management Foundations Course 101 - Project Management Concepts
The Project Management Process - Week 1
Project Budget PowerPoint Presentation Slides
Ad

Similar to Critical Chain Project Management (20)

DOC
Critical Chain Project Management
PDF
topic9.pdf
PDF
Crtical chain m ethod ver 2
PDF
Criticalchainprojectmanagement
PPS
Critical Chain Project Management
PPSX
Major Projects - Faster Better Cheaper
PPTX
Theory of constraints
PDF
Transition to Critical Chain Multi.pdf
PPT
Definition Of Project Management
PDF
Critical chain project management - Gary Palmer
PDF
57086 23 goldratt
PPTX
CPM AND PERT(critical path method) .pptx
PDF
CCPM using ms project 2010 and prochain implementing ppm
PDF
Critical path method(cpm)
PPSX
Critical path method & pert
PPT
1.7 Project Management basics and techniques.ppt
PPTX
Materi 08 ( Project Management for Manufacturing ).pptx
PPT
Pert & Cpm
PDF
IRJET- Critical Chain Project Management in Construction Projects
Critical Chain Project Management
topic9.pdf
Crtical chain m ethod ver 2
Criticalchainprojectmanagement
Critical Chain Project Management
Major Projects - Faster Better Cheaper
Theory of constraints
Transition to Critical Chain Multi.pdf
Definition Of Project Management
Critical chain project management - Gary Palmer
57086 23 goldratt
CPM AND PERT(critical path method) .pptx
CCPM using ms project 2010 and prochain implementing ppm
Critical path method(cpm)
Critical path method & pert
1.7 Project Management basics and techniques.ppt
Materi 08 ( Project Management for Manufacturing ).pptx
Pert & Cpm
IRJET- Critical Chain Project Management in Construction Projects
Ad

Recently uploaded (20)

PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
PPTX
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...
PPTX
Business Ethics - An introduction and its overview.pptx
PDF
COST SHEET- Tender and Quotation unit 2.pdf
PPTX
5 Stages of group development guide.pptx
PDF
Laughter Yoga Basic Learning Workshop Manual
PPTX
Amazon (Business Studies) management studies
PPTX
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
PDF
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
PPTX
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
PDF
DOC-20250806-WA0002._20250806_112011_0000.pdf
DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
PPT
Chapter four Project-Preparation material
PDF
Deliverable file - Regulatory guideline analysis.pdf
PPTX
ICG2025_ICG 6th steering committee 30-8-24.pptx
PDF
Chapter 5_Foreign Exchange Market in .pdf
PPTX
HR Introduction Slide (1).pptx on hr intro
DOCX
unit 1 COST ACCOUNTING AND COST SHEET
PPTX
Probability Distribution, binomial distribution, poisson distribution
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...
Business Ethics - An introduction and its overview.pptx
COST SHEET- Tender and Quotation unit 2.pdf
5 Stages of group development guide.pptx
Laughter Yoga Basic Learning Workshop Manual
Amazon (Business Studies) management studies
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
DOC-20250806-WA0002._20250806_112011_0000.pdf
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
Chapter four Project-Preparation material
Deliverable file - Regulatory guideline analysis.pdf
ICG2025_ICG 6th steering committee 30-8-24.pptx
Chapter 5_Foreign Exchange Market in .pdf
HR Introduction Slide (1).pptx on hr intro
unit 1 COST ACCOUNTING AND COST SHEET
Probability Distribution, binomial distribution, poisson distribution

Critical Chain Project Management

  • 1. Critical Chain Project Management - Introduction
  • 2. Agenda Refresher Project Network Critical Path Earned Value Traditional Project Estimation Critical Chain Project Mgmt. Differences from Critical Path CCPM Principles Task & Project Buffers EVM and Buffer Management CCPM Behaviors CCPM Focus
  • 3. Refresher - Project Network A project network is a graph (flow chart) depicting the sequence in which a project's terminal elements are to be completed by showing terminal elements and their dependencies. Float/Slack in project management is the amount of time that a terminal element in a project network can be delayed by, without causing a delay to: Subsequent terminal elements (free float) Project completion date (total float).
  • 4. Refresher - Critical Path A Critical path is the sequence of project network terminal elements with the longest overall duration , determining the shortest time to complete the project. The duration of the critical path determines the duration of the entire project. Any delay of a terminal element on the critical path directly impacts the planned project completion date (i.e. there is no slack on the critical path ). A project can have several, parallel critical paths. An additional parallel path through the network with the total durations just shorter than the critical path is called a sub-critical path. The critical path method was invented by the DuPont corporation and originally considered only logical dependencies among terminal elements
  • 5. Refresher - Earned Value Earned value (EV) compares the work finished so far with the estimates made in the beginning of the project. Gives a measure of how far the project is from completion. Allows PM to extrapolate to arrive at Estimate at Completion Earned Value is measured in terms of budgeted cost of work scheduled (BCWS) or planned value: for every period the budgets of the tasks that were planned to be finished in this time unit budgeted cost of work produced (BCWP) or earned value: for every period the budgets of the tasks that actually finished in this time unit actual cost of work produced (ACWP) or effort spent: for every period the actual costs of the work budget at completion (BAC): sum(BCWS), the total budget estimated to be spent to complete the project
  • 6. Refresher - Earned Value Earned Value is expressed in terms of the cost variance (CV): BCWP - ACWP, greater than 0 is good the schedule variance (SV): BCWP - BCWS, greater than 0 is good the cost performance index (CPI): BCWP/ACWP, greater than 1 is good the schedule performance index (SPI): BCWP/BCWS, greater than 1 is good the estimate at completion (EAC): sum(ACWP) + (BAC - sum(BCWP)) / CPI, an estimate of the budget spent at the end of the project
  • 7. Traditional Project Estimation Assume Infinite Resources Protect the whole by protecting the completion date of each step Pad each step with a lot of safety time Create a Lifecycle network using these estimates to identify the critical path Most of the safety time is taken away by: Student Syndrome Multi-tasking Delays accumulate, advances do not Critical Path is the constraint on the project
  • 8. The Limitations “ Work expands to fill (and often exceed) the time allowed.” — Parkinson’s Law “ Whatever can go wrong, will.” — Murphy’s Law “ Many people will start to fully apply themselves to a task just in the wake of a deadline” No matter how long you give students to work on something, they will start the night before. End Result – When problems are encountered deep into the project, there is no buffer to dig into.
  • 9. Critical Chain Project Mgmt. CCPM was developed by Dr. Eliyahu Goldratt Application of Theory of Constraints (TOC) to Project Management TOC Presented in his Business Novel The Goal CCPM Presented in his Business Novel Critical Chain TOC suggests that all real-world systems have at least one constraint; otherwise they would be capable of infinite throughput, which is clearly impossible. TOC claims that a real-world system with more than three constraints is extremely unlikely. Managing a complex system can be made simpler & effective, by providing managers with a few specific focus areas on which to focus -- maximizing performance in the areas of key constraints, or "elevating" the constraint
  • 10. Critical Chain Project Mgmt. Systems are Analogous to Chains Weakest Link is the System’s Constraint A System’s Optimum Performance IS NOT the Sum of Local Optima A System Has Only One Constraint at a Time Constraints Can Never Really be Eliminated Can Move From One Part of the System to Another In project management, the critical chain is the sequence of both precedence- and resource-dependent terminal elements that prevents a project from being completed in a shorter time, given finite resources. If resource availability is not a constraint, then a project's critical chain is identical to its critical path.
  • 11. Differences from Critical Path The use of (often implicit) resource dependencies. Implicit means that they are not included in the project network but have to be identified by looking at the resource requirements. Lack of search for an optimum solution. This means that a "good enough" solution is enough because: As far as is known, there is no analytical method of finding an absolute optimum The inherent uncertainty in estimates is much greater than the difference between the optimum and near-optimum ("good enough" solutions). The identification and insertion of buffers: project buffer feeding buffers resource buffers.
  • 12. CCPM Principles Single Integrated Schedule Eliminate Safeties from Each Task Management Must Not Insist on Each Task Starting & Finishing “On Time” Start Right Jobs at Right Time Using Prioritized Task List Focus on Meeting Milestone Dates , Not Task Dates Counter Parkinson’s Law Conserve Available Float/Slack on Each Task, Reduce Time Available Counter Student Syndrome. Claim Early Finishes Immediately Start Each Task As Early As Possible Predict Milestones Based on Buffer Penetration Focus on Task Throughput , NOT on Task Costs
  • 13. Task & Project Buffers
  • 14. Task & Project Buffers
  • 15. EVM and Buffer Management Earned value (EV) compares the work finished so far with the estimates made in the beginning of the project. Gives a measure of how far the project is from completion. Allows PM to extrapolate to arrive at Estimate at Completion EVM does not distinguish between the progress on the project constraint (i.e. its critical chain) from progress on the non-constraints Buffer Management focuses on throughput.
  • 16. CCPM Behaviors Base Duration & Cost Estimates on Average/Bare Bones Performance When Problems Occur, Solve the Problem vice Starting New Task Decrease Frequency & Duration of Meetings Resolve Conflicts Immediately at the Jobsite Eliminate Bad Multi-tasking Resources Focus on One Job at a Time, Work to Completion Request Only Resources Necessary to Accommodate Priority Work Request Only Overtime Necessary to Recover Buffer on Priority Work Move Resources When Work is Done to Next Priority Work Quickly Work Right Jobs instead of Easy Jobs Plan for New Work & Scope Changes vice Complaining About it
  • 17. Project Focus Identify the System Constraint Exploit the Constraint Subordinate Everything Else Elevate the Constraint Go back to Step 1 Senior Management Buy in Promote early finishes Focus on usage of Project Buffer Avoid evaluating of team w.r.t. task deadlines CCPM Focus
  • 18. Summary and Conclusion Critical Chain Project Management can dramatically... Improve project delivery date reliability Shorten overall project duration Provide “early warning” of threats to project delivery Enable earlier, less drastic responses Reduce Costs Reduce Overtime Reduce Rework
  • 19. Bibliography / Reference Wikipedia http://www.wikipedia.org Critical Chain Dr. Eliyahu Goldratt Buffering Against Risk -- Risk Management and Critical Chain. http://www.focusedperformance.com/articles/ccrisk.html Getting Out From Between Parkinson's Rock and Murphy's Hard Place – Francis S. Patrick http://www.focusedperformance.com/articles/ccpm.html Managing an ERP project using critical chain M van Loggerenberg. EDS Enterprise Solutions