SlideShare a Scribd company logo
PERT/CPM Models for Project Management
AgendaWhat is Project ManagementDiscuss PERT/CPMMotivating Case Study: The Reliable Construction CompanyWays of Finding the Critical PathConsidering Time-Cost Trade-Offs
What is Project ManagementProject management can be defined as the coordination of activities with the potential use of many organizations, both internal and external to the business, in order to conduct a large scale project from beginning to end.There are two management science techniques that are used for project management:Program and Evaluation Review Technique (PERT)Critical Path Method (CPM)
PERT/CPMPERTPERT was designed to examine projects from the standpoint of uncertainty.CPMCPM was designed to examine projects from the standpoint of costs.PERT and CPM techniques have been combined over time.PERT and CPM both rely heavily on the use of networks to help plan and display the coordination of all the activities for a project.
The Reliable Construction CompanyReliable has just secured a contract to construct a new plant for a major manufacturer.The contract is for $5.4 million to cover all costs and any profits.The plant must be finished in a year.A penalty of $300,000 will be assessed if Reliable does not complete the project within 47 weeks.A bonus of $150,000 will be paid to Reliable if the plant is completed within 40 weeks.
Needed TerminologyActivityA distinct task that needs to be performed as part of the project.Start NodeThis is a node that represents the beginning of the project.Finish NodeThis node represents the end of the project.
Needed Terminology Cont.Immediate PredecessorThese are activities that must be completed by no later than the start time of the given activity.Immediate SuccessorGiven the immediate predecessor of an activity, this activity becomes the immediate successor of each of these immediate predecessors.If an immediate successor has multiple immediate predecessors, then all must be finished before an activity can begin.
Activity List for Reliable Construction
Questions Needed to be AnsweredHow can the project be displayed graphically?How much time is required to finish the project if no delays occur?When is earliest start and finish times for each activity if no delays occur?What activities are critical bottleneck activities where delays must be avoided to finish the project on time?
Questions Needed to be Answered Cont.For non bottleneck activities, how much can an activity be delayed and yet still keep the project on time?What is the probability of completing the project by the deadline?What is the least amount of money needed to expedite the project to obtain the bonus?How should costs be monitored to keep the project within budget?
Project NetworkA project network is a network diagram that uses nodes and arcs to represent the progression of the activities is a project from start to finish.Three pieces of information needed:Activity informationPrecedence relationshipTime information
Project Network Cont.Two types of project networksActivity-on-Arc (AOA)On this diagram, the activity is represented on an arc, while a node is used to separate an activity from its immediate predecessors. Activity-on-Node (AON)On this diagram, the activity is represented by the node, while the arc is used to showed the precedence relationship between the activities.
Critical path method & pert
Microsoft Project Visual Diagram: Gantt Chart
Scheduling Using PERT/CPMA path through a project network is a route that follows a set of arcs from the start node to the finish node.The length of a path is defined as the sum of the durations of the activities of the path.What are the paths and their corresponding lengths for Reliable?
Critical PathThis is the path that has the longest length through the project.The shortest time that a project can conceivably be finished is the critical path.Why?
More TerminologyEarliest start time of an activity (ES)The time at which an activity will begin if there are no delays in a project.Earliest finish time of an activity (EF)The time at which an activity will finish if there are no delays in a project.Latest start time of an activity (LS)The latest possible time that an activity can start without delaying the project.
More Terminology Cont.Latest finish time of an activity (LF)The latest possible time that an activity can be completed without delaying the project.Forward passThe process of moving through a project from start to finish to determine the earliest start and finish times for the activities in the project.
More Terminology Cont.Backward passThe process of moving through a project from finish to start to determine the latest start and finish times for the activities in the project.Slack for an activityThe amount of time that a particular activity can be delayed without delaying the whole project.It is calculated by taking the difference between the latest finish time with the earliest finish time.
More Terminology Cont.Earliest start time ruleThe earliest start time for an activity is equal to the largest of the earliest finish times of its immediate predecessors.Latest finish time ruleThe latest finish time is equal to the smallest of the latest start times of its immediate successors.
Procedure for Obtaining Earliest TimesStep 1: For the activity that starts the project, assign an earliest start time of zero, i.e., ES=0.Step 2: For each activity whose ES has just been obtained, calculate its earliest finish time as ES plus duration of the activity.Step 3: For each new activity whose immediate predecessors have EF values, obtain its ES by using the earliest start time rule.
Procedure for Obtaining Earliest Times Cont.Step 4: Apply step 2 to calculate EF.Step 5: Repeat step 3 until ES and EF have been obtained for all activities including the finish node.
Procedure for Obtaining Latest TimesStep 1: For each of the activities that together complete the project, set its latest finish time equal to the earliest finish time of the finish node.Step 2: For each activity whose LF value has just been obtained, calculate its latest start time as LS equals LF minus the duration of the activity.
Procedure for Obtaining Latest Times Cont.Step 3: For each new activity whose immediate successors now have LS values, obtain its LF by applying the latest finish time rule.Step 4: Apply step 2 to calculate its LS.Step 5: Repeat step 3 until LF and LS have been obtained for all activities.
Critical path method & pert
Ways of Finding the Critical PathExamine all the paths and find the path with the maximum length.Calculate the slack for an activity.If the slack is zero, it is on the critical path.If the slack is positive, it is not on the critical path.
Time-Cost Trade-OffsReliable had an incentive bonus of $150,000 to finish the project in 40 weeks.Is it worth while for Reliable to speed-up the project?
CrashingCrashing an activity refers to taking on extra expenditures in order to reduce the duration of an activity below its expected value.Crashing a project refers to crashing a number of activities to reduce the duration of the project.
CPM Method of Time-Cost Trade-OffsThis is a method concerned with whether it is worthwhile to crash activities to reduce the anticipated duration of the project to a desired value.This assumes that there is a trade-off between time and cost that has an inverse relationship.
More TerminologyNormal Point is the time and cost of an activity when it is performed in a normal way.Crash point show the time and cost when the activity is fully crashed.
Graph of Normal and Crash Points
Marginal Cost AnalysisIt is a method of using the marginal cost of crashing individual activities on the current critical path to determine the least expensive way of reducing the project duration to an acceptable level.This method requires you to calculate the cost per desired time unit and compare each cost with the other costs.
Critical path method & pert
Marginal Cost Analysis Cont.Once the marginal cost for crashing each activity has been conducted, you next want to choose the crashing that has the smallest marginal cost.Next, calculate the effect that the crash has on each path.Note: Crashing can potentially cause another path to become a critical path.
Solving Crashing Problems Using LPThere are three decisions to be made:The start time of each activityThe reduction in each activity due to crashingThe finish time of the projectLP model will be examined in class.

More Related Content

PPTX
Critical Path Method/ Program Evaluation and Review Technique
PPTX
Cpm and pert
PPT
Critical path method (cpm)
PPS
The ant story
PPSX
E governance, gartner's model by bhim upadhyaya
PPS
Rebirth of the_eagle
PDF
Apj abdul kalam's vision of developed nepal nov 2008
PPSX
My nepal is great ! (mero nepal mahaan)
Critical Path Method/ Program Evaluation and Review Technique
Cpm and pert
Critical path method (cpm)
The ant story
E governance, gartner's model by bhim upadhyaya
Rebirth of the_eagle
Apj abdul kalam's vision of developed nepal nov 2008
My nepal is great ! (mero nepal mahaan)

Viewers also liked (20)

PPSX
A vision of prosperous new nepal by bhim upadhyaya 064.11.5
PDF
जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19
PDF
Workshop on Understnding E governance
PDF
E gov lecture1
PPTX
Final ppg 520 group ppt (group 5)
PDF
Electronic Transaction Act 2063 (ETA 2063)
PPT
Cyber law in nepal and implementation
PDF
FACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTAN
PPT
Lesson02_new
PDF
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
PPTX
Syam critical path cpa
PDF
Education management information system nepal
PDF
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)
PDF
Critical Path Analysis for a New Product Release
DOCX
Integrated Marketing Communications
PDF
Network Anaysis_ critical path methods
PPTX
Bpp 3213 lecture 2
PPTX
Session 4 critical path method upload
PPTX
ICT perspectives for rural development
PDF
Ict in-education-master-plan-nepal
A vision of prosperous new nepal by bhim upadhyaya 064.11.5
जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19
Workshop on Understnding E governance
E gov lecture1
Final ppg 520 group ppt (group 5)
Electronic Transaction Act 2063 (ETA 2063)
Cyber law in nepal and implementation
FACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTAN
Lesson02_new
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
Syam critical path cpa
Education management information system nepal
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)
Critical Path Analysis for a New Product Release
Integrated Marketing Communications
Network Anaysis_ critical path methods
Bpp 3213 lecture 2
Session 4 critical path method upload
ICT perspectives for rural development
Ict in-education-master-plan-nepal
Ad

Similar to Critical path method & pert (20)

PPTX
Chap 4- CPM & PERT.pptx
PDF
Cpm n pert
PPTX
CPM AND PERT(critical path method) .pptx
PPT
Chapter 12(cpm pert)
DOCX
PPT
Project Management: NETWORK ANALYSIS - CPM and PERT
PDF
project managment lesson mechanical engineering
PDF
CPM AND PERT
PDF
pert and crm examples full class course.pdf
PPT
Pert
PPTX
Project Management Techniques ( CPM & PERT Techniques )
PPT
Pert 182
PPT
PERT CPM Intro
PPT
06 pert cpm
PDF
Critical Path Explained With 7 Q&As and a Free Excel Template
PPTX
CPM, Network Analysis A-O-A, A-O-N, Resource management
PPTX
Program Evalution and Review Rechnical Path Method.pptx
PPTX
Chapter 3.pptx
PPTX
project management-cpm and pert methods for managers
PPT
time mamangement.ppt
Chap 4- CPM & PERT.pptx
Cpm n pert
CPM AND PERT(critical path method) .pptx
Chapter 12(cpm pert)
Project Management: NETWORK ANALYSIS - CPM and PERT
project managment lesson mechanical engineering
CPM AND PERT
pert and crm examples full class course.pdf
Pert
Project Management Techniques ( CPM & PERT Techniques )
Pert 182
PERT CPM Intro
06 pert cpm
Critical Path Explained With 7 Q&As and a Free Excel Template
CPM, Network Analysis A-O-A, A-O-N, Resource management
Program Evalution and Review Rechnical Path Method.pptx
Chapter 3.pptx
project management-cpm and pert methods for managers
time mamangement.ppt
Ad

More from Bhim Upadhyaya (20)

PDF
Role of engineers in infrastructure development for the prosperity of nepal ...
PDF
India's vision and roadmap for development of sanskrit report
PDF
Nepal faecal sludge management and regulatory framework 2074
PDF
Nepal- Total sanitation guidelines 2073 ministry of water supply and sanitat...
PDF
जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15
PDF
Water resources of nepal- in the context of climate change 2011 by wecs
PDF
Energy demand projection 2030 a study done by nepal investment board
PDF
Nepal Energy strategy 2013 by wecs
PDF
National Water Plan Nepal 2005 by WECS
PDF
Water Resources Strategy Nepal 2002 by WECs
PDF
Nepal - energy sector synopsis report 2010- wecs
PDF
Nepal final report on energy sectors vision 2050 ad
PDF
Andhra pradesh(india) sunrise vision 2029 draft by chandrababu naidu
PDF
Facebook sambad with naya patrika daily push 9th 2071
PDF
Ma pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भए
PDF
Gurustrotam in sanskrit and hindi
PDF
Engineering council uk guidance on security for engineers & technicians
PDF
Sankskrit and science by dr raja ramanna
PDF
Ayurveda swadeshi chikitsa- part 1 by rajiv dixit
PDF
Ayurveda aapka swasthya aap ke haath by rajiv dixit
Role of engineers in infrastructure development for the prosperity of nepal ...
India's vision and roadmap for development of sanskrit report
Nepal faecal sludge management and regulatory framework 2074
Nepal- Total sanitation guidelines 2073 ministry of water supply and sanitat...
जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15
Water resources of nepal- in the context of climate change 2011 by wecs
Energy demand projection 2030 a study done by nepal investment board
Nepal Energy strategy 2013 by wecs
National Water Plan Nepal 2005 by WECS
Water Resources Strategy Nepal 2002 by WECs
Nepal - energy sector synopsis report 2010- wecs
Nepal final report on energy sectors vision 2050 ad
Andhra pradesh(india) sunrise vision 2029 draft by chandrababu naidu
Facebook sambad with naya patrika daily push 9th 2071
Ma pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भए
Gurustrotam in sanskrit and hindi
Engineering council uk guidance on security for engineers & technicians
Sankskrit and science by dr raja ramanna
Ayurveda swadeshi chikitsa- part 1 by rajiv dixit
Ayurveda aapka swasthya aap ke haath by rajiv dixit

Recently uploaded (20)

PPTX
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
PDF
Computing-Curriculum for Schools in Ghana
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
Complications of Minimal Access Surgery at WLH
PDF
01-Introduction-to-Information-Management.pdf
PPTX
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PPTX
Cell Structure & Organelles in detailed.
PPTX
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PPTX
Pharma ospi slides which help in ospi learning
PDF
Yogi Goddess Pres Conference Studio Updates
PPTX
Pharmacology of Heart Failure /Pharmacotherapy of CHF
PPTX
GDM (1) (1).pptx small presentation for students
PPTX
Microbial diseases, their pathogenesis and prophylaxis
PDF
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
PDF
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
PDF
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
PDF
2.FourierTransform-ShortQuestionswithAnswers.pdf
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
Computing-Curriculum for Schools in Ghana
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
Final Presentation General Medicine 03-08-2024.pptx
Complications of Minimal Access Surgery at WLH
01-Introduction-to-Information-Management.pdf
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
Cell Structure & Organelles in detailed.
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
Final Presentation General Medicine 03-08-2024.pptx
Pharma ospi slides which help in ospi learning
Yogi Goddess Pres Conference Studio Updates
Pharmacology of Heart Failure /Pharmacotherapy of CHF
GDM (1) (1).pptx small presentation for students
Microbial diseases, their pathogenesis and prophylaxis
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
2.FourierTransform-ShortQuestionswithAnswers.pdf

Critical path method & pert

  • 1. PERT/CPM Models for Project Management
  • 2. AgendaWhat is Project ManagementDiscuss PERT/CPMMotivating Case Study: The Reliable Construction CompanyWays of Finding the Critical PathConsidering Time-Cost Trade-Offs
  • 3. What is Project ManagementProject management can be defined as the coordination of activities with the potential use of many organizations, both internal and external to the business, in order to conduct a large scale project from beginning to end.There are two management science techniques that are used for project management:Program and Evaluation Review Technique (PERT)Critical Path Method (CPM)
  • 4. PERT/CPMPERTPERT was designed to examine projects from the standpoint of uncertainty.CPMCPM was designed to examine projects from the standpoint of costs.PERT and CPM techniques have been combined over time.PERT and CPM both rely heavily on the use of networks to help plan and display the coordination of all the activities for a project.
  • 5. The Reliable Construction CompanyReliable has just secured a contract to construct a new plant for a major manufacturer.The contract is for $5.4 million to cover all costs and any profits.The plant must be finished in a year.A penalty of $300,000 will be assessed if Reliable does not complete the project within 47 weeks.A bonus of $150,000 will be paid to Reliable if the plant is completed within 40 weeks.
  • 6. Needed TerminologyActivityA distinct task that needs to be performed as part of the project.Start NodeThis is a node that represents the beginning of the project.Finish NodeThis node represents the end of the project.
  • 7. Needed Terminology Cont.Immediate PredecessorThese are activities that must be completed by no later than the start time of the given activity.Immediate SuccessorGiven the immediate predecessor of an activity, this activity becomes the immediate successor of each of these immediate predecessors.If an immediate successor has multiple immediate predecessors, then all must be finished before an activity can begin.
  • 8. Activity List for Reliable Construction
  • 9. Questions Needed to be AnsweredHow can the project be displayed graphically?How much time is required to finish the project if no delays occur?When is earliest start and finish times for each activity if no delays occur?What activities are critical bottleneck activities where delays must be avoided to finish the project on time?
  • 10. Questions Needed to be Answered Cont.For non bottleneck activities, how much can an activity be delayed and yet still keep the project on time?What is the probability of completing the project by the deadline?What is the least amount of money needed to expedite the project to obtain the bonus?How should costs be monitored to keep the project within budget?
  • 11. Project NetworkA project network is a network diagram that uses nodes and arcs to represent the progression of the activities is a project from start to finish.Three pieces of information needed:Activity informationPrecedence relationshipTime information
  • 12. Project Network Cont.Two types of project networksActivity-on-Arc (AOA)On this diagram, the activity is represented on an arc, while a node is used to separate an activity from its immediate predecessors. Activity-on-Node (AON)On this diagram, the activity is represented by the node, while the arc is used to showed the precedence relationship between the activities.
  • 14. Microsoft Project Visual Diagram: Gantt Chart
  • 15. Scheduling Using PERT/CPMA path through a project network is a route that follows a set of arcs from the start node to the finish node.The length of a path is defined as the sum of the durations of the activities of the path.What are the paths and their corresponding lengths for Reliable?
  • 16. Critical PathThis is the path that has the longest length through the project.The shortest time that a project can conceivably be finished is the critical path.Why?
  • 17. More TerminologyEarliest start time of an activity (ES)The time at which an activity will begin if there are no delays in a project.Earliest finish time of an activity (EF)The time at which an activity will finish if there are no delays in a project.Latest start time of an activity (LS)The latest possible time that an activity can start without delaying the project.
  • 18. More Terminology Cont.Latest finish time of an activity (LF)The latest possible time that an activity can be completed without delaying the project.Forward passThe process of moving through a project from start to finish to determine the earliest start and finish times for the activities in the project.
  • 19. More Terminology Cont.Backward passThe process of moving through a project from finish to start to determine the latest start and finish times for the activities in the project.Slack for an activityThe amount of time that a particular activity can be delayed without delaying the whole project.It is calculated by taking the difference between the latest finish time with the earliest finish time.
  • 20. More Terminology Cont.Earliest start time ruleThe earliest start time for an activity is equal to the largest of the earliest finish times of its immediate predecessors.Latest finish time ruleThe latest finish time is equal to the smallest of the latest start times of its immediate successors.
  • 21. Procedure for Obtaining Earliest TimesStep 1: For the activity that starts the project, assign an earliest start time of zero, i.e., ES=0.Step 2: For each activity whose ES has just been obtained, calculate its earliest finish time as ES plus duration of the activity.Step 3: For each new activity whose immediate predecessors have EF values, obtain its ES by using the earliest start time rule.
  • 22. Procedure for Obtaining Earliest Times Cont.Step 4: Apply step 2 to calculate EF.Step 5: Repeat step 3 until ES and EF have been obtained for all activities including the finish node.
  • 23. Procedure for Obtaining Latest TimesStep 1: For each of the activities that together complete the project, set its latest finish time equal to the earliest finish time of the finish node.Step 2: For each activity whose LF value has just been obtained, calculate its latest start time as LS equals LF minus the duration of the activity.
  • 24. Procedure for Obtaining Latest Times Cont.Step 3: For each new activity whose immediate successors now have LS values, obtain its LF by applying the latest finish time rule.Step 4: Apply step 2 to calculate its LS.Step 5: Repeat step 3 until LF and LS have been obtained for all activities.
  • 26. Ways of Finding the Critical PathExamine all the paths and find the path with the maximum length.Calculate the slack for an activity.If the slack is zero, it is on the critical path.If the slack is positive, it is not on the critical path.
  • 27. Time-Cost Trade-OffsReliable had an incentive bonus of $150,000 to finish the project in 40 weeks.Is it worth while for Reliable to speed-up the project?
  • 28. CrashingCrashing an activity refers to taking on extra expenditures in order to reduce the duration of an activity below its expected value.Crashing a project refers to crashing a number of activities to reduce the duration of the project.
  • 29. CPM Method of Time-Cost Trade-OffsThis is a method concerned with whether it is worthwhile to crash activities to reduce the anticipated duration of the project to a desired value.This assumes that there is a trade-off between time and cost that has an inverse relationship.
  • 30. More TerminologyNormal Point is the time and cost of an activity when it is performed in a normal way.Crash point show the time and cost when the activity is fully crashed.
  • 31. Graph of Normal and Crash Points
  • 32. Marginal Cost AnalysisIt is a method of using the marginal cost of crashing individual activities on the current critical path to determine the least expensive way of reducing the project duration to an acceptable level.This method requires you to calculate the cost per desired time unit and compare each cost with the other costs.
  • 34. Marginal Cost Analysis Cont.Once the marginal cost for crashing each activity has been conducted, you next want to choose the crashing that has the smallest marginal cost.Next, calculate the effect that the crash has on each path.Note: Crashing can potentially cause another path to become a critical path.
  • 35. Solving Crashing Problems Using LPThere are three decisions to be made:The start time of each activityThe reduction in each activity due to crashingThe finish time of the projectLP model will be examined in class.