PERT/CPM Network Rules of Network Construction with Emphasis on Dummy Activities Redundancy in Precedence Relationships Scheduling the Activities: Earliest and Latest Times Determination of Critical Path Determination of Floats: Total, Free, Interfering and Independent PERT Resource Analysis and Resource Allocation Time-cost Tradeoff: Crashing the Project Resource Leveling Resource Allocation
Each activity is represented by one arrow An activity can begin only when all its  predecessors are done Length and bearing of arrows is of no consequence Arrow direction indicates general progression in time – tail events represent start while head events represent end of activities Events are identified by numbers while activities are represented by their starting and ending events A network should have only one initial and one final node Introduce as few dummy activities as may be necessary Looping is not permitted
Activity Imm. Pred. A - B - C - D A, B E B F B Activity Imm. Pred. G C, F H B I E, H J E, H K C, D, F, J L K
A C B E H F D G I J K L 1 2 3 4 5 6 7 8 9 Activity Imm. Pred. A - B - C - D A, B E B F B Activity Imm. Pred. G C, F H B I E, H J E, H K C, D, F, J L K
Critical path refers to the longest path of a given project network Duration of a project is given by the length of the critical path Activities on a critical path are called  critical activities  while remaining activities are  non-critical A project can have more than one critical path as well Critical activities are so called because their timely completion is critical to the completion of the project in time Critical activities can not be delayed while non-critical activities have some cushion available
Information on the activities required for a project is as follows:  Draw the network and calculate the earliest start(ES), earliest finish(EF), latest start(LS), and latest finish(LF) times of each of the activities. Name A B C D E F G H I J K Activities Node 1-2 1-3 1-4 2-5 3-5 3-6 3-7 4-6 5-7 6-8 7-8 Duration (Days) 2 7 8 3 6 10 4 6 2 5 6
 
Critical Path: 1-3-6-8 Critical Activities: B F J Project Duration: 22 days Non-critical Activities: A C E G H I K A 2 B 7 C 8 D 3 E 6 G 4 H 6 F 10 I 2 K 6 J 5 1 2 3 4 5 6 7 8
Total float  is the amount of time by which an activity may be delayed without delaying the project completion Caution:  interpret total floats of activities carefully - all can not be used independently  Free float  is that part of total float which can be used without affecting floats of the succeeding activities The part of total float which is not free is called  interfering float Independent float  is the amount of time which can be used without affecting the head and the tail events Total Float ≥ Free Float ≥ Independent Float
Total float   = Latest start time of the activity – Earliest start time of the activity  Free float = Total float – Head event slack = Earliest start time of the next activity – Earliest completion time of the activity Interfering float = Total float – Free float Independent float  =   Earliest start time of the next activity – Latest finish time of the preceding activity – Duration of the activity = Free float – Tail event slack, or zero, whichever is higher
i - j t  ES EF LS LF TF IF FF lnF 1-2 2 0 2 9 11 9 9 0 0 1-3 7 0 7 0 7 0 0 0 0 1-4 8 0 8 3 11 3 3 0 0 2-5 3 2 5 11 14 9 1 8 0 3-5 6 7 13 8 14 1 1 0 0 3-6 10 7 17 7 17 0 0 0 0 3-7 4 7 11 12 16 5 1 4 4 4-6 6 8 14 11 17 3 0 3 0 5-7 2 13 1 14 16 1 1 0 0 6-8 5 17 22 17 22 0 0 0 0 7-8 6 15 21 16 22 1 0 1 0
Problems related to resources include Time-cost trade-off , called  crashing  Completion time of the project is systematically reduced considering cost Resource Levelling:  An attempt is made to smoothen the resources requirements by systematically scheduling the activities  Resource Allocation:  Allocation of limited availability of resources in a manner that the project is completed in minimum time
Involves use of additional resources with a view to reduce the project duration Crashing increases direct cost of doing activities but reduces overhead, which is usually a function of time It may also help to reap any benefits of early completion It needs information on cost of reduction of every activity per unit of time In crashing, always consider the critical path and choose the activity that can be crashed at least cost In case of multiple critical paths, all of them should be considered for crashing simultaneously Time-cost schedule is prepared to get information on normal time and the cost, the minimum time to complete project and the cost, and optimal duration of the project
Resource leveling refers to scheduling the activities of a project in such a manner that the requirement of resources may be leveled to the extent possible without delaying the completion of the project To begin with every activity is scheduled at the earliest and the requirement of the resource involved is assessed on a daily basis Since the activities are scheduled on early days, the demand for the resource, say labour, is likely to be large in earlier days of the project and small in the later days
Attempt is then made to shift the performance of non-critical activities depending on the floats available so that demand for the resource is reduced somewhat in the early days and increased in later days. Adjustments are made in such a way that the resource demand becomes as uniform as possible Thus, attempt is made to level the resource demand without adversely affecting the project duration
Uses three time estimates for every activity:  optimistic (a ) ,   most likely  ( m ) and  pessimistic  ( b ) They are used to obtain expected times and their variances  Expected time = ( a +4× m + b )/6;  and  Variance = [( b  –  a  )/6] 2 Obtain critical path using expected times and identify critical activities Add variances for critical activities to get variance for completion time and find its square root to get standard deviation With expected duration and standard deviation, calculate probabilities of project completion using normal distribution
The owner of a chain of fast-food restaurants is considering a new computer system for accounting and inventory control. A computer company sent the following information about the system installation: Activity Immediate Predecessor Most Optimistic Most likely Most Pessimistic A - 4 6 8 B A 5 7 15 C A 4 8 12 D B 15 20 25 E B 10 18 26 F C 8 9 16 G E 4 8 12 H D,F 1 2 3 I G,H 6 7 8
 
Critical activities: A B E G I Project duration = 6+8+18+8+7 = 47 days Project variance = 4/9 + 25/9 + 64/9 + 16/9 + 1/9 = 110/9 Project standard deviation = √(110/9) = 3.496 Example  Activity a  m  b  t e σ 2 A 4 6 8 6 4/9* B 5 7 15 8 25/9* C 4 8 12 8 16/9 D 15 20 25 20 25/9 E 10 18 26 18 64/9* F 8 9 16 10 16/9 G 4 8 12 8 16/9* H 1 2 3 2 1/9 I 6 7 8 7 1/9*
For Pr (completion in 55 days):   Z  = ( X  -  µ)/ σ   Z = (55 – 47)/3.496 = 2.29.  Now, Area to the left of Z = 2.29 is 0.5+0.4890 =  0.9890 For Pr (completion with 0.90 chance): Z  corresponding to area 0.40 (between µ and  X ) is 1.28.  Thus, 1.28 = ( X  – 47)/3.496 and  X  = 51.47 or 52 app.  The project should start 52 days before due date Project Network A B C E F D H G I
A modification of PERT which allows planning, monitoring and controlling of project cost and duration Budgeting process allows to determine how much money is to be spent every time unit (week/month) over planned duration of project Budgets are prepared on the basis of earliest and latest start times of activities Comparisons are made continuously between the actual costs and budgeted amounts  Comparisons are also made between percentage of work done and percentage of budgeted amount spent: if former is smaller than the later, we have  budget overrun
CPM is: Critical Project Management. Critical Path Management. Critical Path Method. Crash Project Method.
Which of these is not correct? PERT is probabilistic in nature. CPM is deterministic in nature. CPM is event-oriented. CPM and PERT use similar terminology, but were developed independently.
Mark the wrong statement:  A project is a set of activities, which can be performed in a certain logical sequence. A network is a graphic portrayal of interdependency relationship among the activities of a project. An arrow representing an activity can have any length and shape. An activity cannot be represented by more than one arrow but an arrow can represent one or more activities.
Point out what is not required. While considering precedence relationships, all the predecessor(s) of an activity should be focussed on. only immediate predecessor(s) should be focussed on. redundant predecessors should be dropped. care must be taken that there is no logical fault it as may result in formation of a loop.
Mark the correct statement:  The head event of an activity also represents tail event of its predecessor activity. Nodes should be numbered in such a way that, for every activity, the initial node bears a lower number while final node bears a higher number. The event marking start of an activity is called head event and the event marking the end is termed as tail-event. In drawing a network, it may happen that A precedes B, B precedes C and C precedes A.
Which of the following is not a rule of network construction? Each defined activity is represented by one and only one arrow. A network should have only initial and one terminal node. Identical initial and final nodes can identify two activities. Only as few dummy activities should be included as is warranted.
Mark the wrong statement: Forward pass calculations yield the earliest and latest start & finish times of various activities. The difference between latest and earliest finish times of an activity is its total float. Free float of an activity cannot exceed its total float. Determination of earliest and latest start time of various activities of a project is useful for proper planning of their execution.
It is known that in a project, an activity 4-6 has duration of 6 days and total float of 3 days. The E and L times at node 4 are 8 and 11 respectively while at node 6, both are equal to 17. Which of the following is not a true statement about 4-6? Its free float is 3 days. Its independent float is 0. It is a critical activity. The ES of this activity is 8.
Mark the wrong statement:  All activities on a critical path are critical activities. A project network may have none, one or more critical paths. A delay in a critical activity surely delays the completion of project. Each critical activity has identical earliest and latest start times.
Pick the wrong relationship: Interfering Float = Total Float – Free Float . Total Float = Free Float + Independent Float . Total Float    Free Float    Independent Float. Free Float = Total Float – Head Event Slack.
Which of the following is not correct in respect of PERT calculations? Expected time of an activity is a weighted average of three time estimates,  a, m , and  b  with respective weights of 1, 4 and 1. The completion time of an activity is assumed to follow normal distribution. The standard deviation of activity completion time is one-sixth of the excess of pessimistic over optimistic time. The sum total of variances of critical activity times gives the variance of the overall project completion time.
Given, expected duration of project = 47 days, variance = 9 days. What is the probability of not completing the project in 50 days? 0.6293 0.8413 0.1587 0.3707 Z 0.33 1.00 Area 0.1293 0.3413
In the previous Question, what is the probability of completing the project within 3 days more or less than the expected time? 0.5000 0.6826 0.2586 0.3174
Which of the following is not true about crashing? Always focus on critical path and choose between critical activities only. Crashing cost per day = (Crash cost – Normal cost)/(Normal time – Crash time). Of all activities of the project, choose the activity with least crashing cost. If there are multiple critical paths, crash them all.
Mark the wrong statement:  An event, which represents the initiation of more than one activity, is called the burst event. The longest path of a given project gives the maximum duration while its shortest path indicates shortest duration. The resource allocation programmes aim to allocate the given resources in a manner that the project completes in minimum time. A non-critical activity may or may not have any free float.
 

More Related Content

PPTX
Reducing Project Duration_Jagat Prasad Upadhyay.pptx
PDF
Lect-6&7: Network Diagrams, PERT and CPM
PPTX
PROJECT-SCHEDULING-pptx.pptx
PPT
08. Project Time Management Upload
PPT
Chapter-5-Scheduling-and-Resource-Allocation.ppt
PPTX
Resource Scheduling
PPTX
CPM - Critical Path Method
PDF
Project scheduling and resource levelling_Construction Management
Reducing Project Duration_Jagat Prasad Upadhyay.pptx
Lect-6&7: Network Diagrams, PERT and CPM
PROJECT-SCHEDULING-pptx.pptx
08. Project Time Management Upload
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Resource Scheduling
CPM - Critical Path Method
Project scheduling and resource levelling_Construction Management

What's hot (20)

PPT
Pert & Cpm
PDF
Critical path method(cpm)
PPTX
Pert & cpm project management
PPTX
Critical Path Method: Activities And Events, Float/Slacks
PPTX
INTRODUCTION TO COST ESTIMATION
PPT
Project Management: NETWORK ANALYSIS - CPM and PERT
PDF
Critical Path Method
PDF
Float in Projects
PPTX
Project Management Techniques ( CPM & PERT Techniques )
PPTX
Pert cpm
PPTX
Network Problem CPM & PERT
PPTX
Rules for Network Construction
PPTX
Per tand project crashing
PPTX
Pert and CPM
PDF
time cost trade off
PPTX
Pert Analysis
PPTX
Project Management - Critical path method
PPT
Critical path method (cpm)
PPTX
Project Management PERT and CPM
Pert & Cpm
Critical path method(cpm)
Pert & cpm project management
Critical Path Method: Activities And Events, Float/Slacks
INTRODUCTION TO COST ESTIMATION
Project Management: NETWORK ANALYSIS - CPM and PERT
Critical Path Method
Float in Projects
Project Management Techniques ( CPM & PERT Techniques )
Pert cpm
Network Problem CPM & PERT
Rules for Network Construction
Per tand project crashing
Pert and CPM
time cost trade off
Pert Analysis
Project Management - Critical path method
Critical path method (cpm)
Project Management PERT and CPM
Ad

Viewers also liked (20)

PDF
Project management cpm-pert
PPT
PERT CPM Intro
PDF
Pert & cpm
PPT
Critical path and pert
PDF
Cpm n pert
PPT
Production Management Introduction
PDF
Numerical assignment
PPTX
Operational research- main techniques PERT and CPM
PPTX
Modern management techniques part 1
PPTX
graphical method
PPT
Graphical Method
PPTX
Linear programming - Model formulation, Graphical Method
PPTX
Materials management ppt
PPT
Inventory Control ABC Analysis
PPTX
Network Diagrams
PPTX
Program Evaluation and Review Technique (PERT)
PPT
Pert
PPTX
Bar chart
Project management cpm-pert
PERT CPM Intro
Pert & cpm
Critical path and pert
Cpm n pert
Production Management Introduction
Numerical assignment
Operational research- main techniques PERT and CPM
Modern management techniques part 1
graphical method
Graphical Method
Linear programming - Model formulation, Graphical Method
Materials management ppt
Inventory Control ABC Analysis
Network Diagrams
Program Evaluation and Review Technique (PERT)
Pert
Bar chart
Ad

Similar to Chapter 12(cpm pert) (20)

PPTX
Project management
PPT
Critical Path Method
PPT
Pert cpm
PPT
Pert cpm
PDF
Back to basics scheduling Webinar
PPTX
CPM.pptx
PPTX
Project evaluation and review techniques and cpm basics
PPTX
Unit2 network optimization
PPT
A760535773_16727_28_2018_u6.ppt
PPT
Chapter 6 project management
PPTX
Chap 4- CPM & PERT.pptx
PDF
Management Network Lec 3
PPT
Program Evaluation and Review Technique
PPT
Ovi project
PPTX
PertGanttchart
PPT
Chapter-2 Solved examples.ppt
PPTX
Pb602 operation management chapter 7
PPTX
Critical path method (CPM).pptx
PPTX
Network problem cpm and pert BY MITESH KUMAR
PPT
III - UNIT PERT-CPM.pptnnnnnnnnnnnnnnnnnnnnnnnnnn
Project management
Critical Path Method
Pert cpm
Pert cpm
Back to basics scheduling Webinar
CPM.pptx
Project evaluation and review techniques and cpm basics
Unit2 network optimization
A760535773_16727_28_2018_u6.ppt
Chapter 6 project management
Chap 4- CPM & PERT.pptx
Management Network Lec 3
Program Evaluation and Review Technique
Ovi project
PertGanttchart
Chapter-2 Solved examples.ppt
Pb602 operation management chapter 7
Critical path method (CPM).pptx
Network problem cpm and pert BY MITESH KUMAR
III - UNIT PERT-CPM.pptnnnnnnnnnnnnnnnnnnnnnnnnnn

Recently uploaded (20)

PDF
Building Integrated photovoltaic BIPV_UPV.pdf
PPTX
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
PPTX
Cloud computing and distributed systems.
PDF
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
PPTX
Digital-Transformation-Roadmap-for-Companies.pptx
PPT
Teaching material agriculture food technology
PDF
Reach Out and Touch Someone: Haptics and Empathic Computing
PPTX
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
PPTX
sap open course for s4hana steps from ECC to s4
PDF
Network Security Unit 5.pdf for BCA BBA.
PDF
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
PPT
“AI and Expert System Decision Support & Business Intelligence Systems”
PDF
Review of recent advances in non-invasive hemoglobin estimation
PPTX
ACSFv1EN-58255 AWS Academy Cloud Security Foundations.pptx
PPTX
Big Data Technologies - Introduction.pptx
PDF
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
PDF
Machine learning based COVID-19 study performance prediction
PDF
Advanced methodologies resolving dimensionality complications for autism neur...
PDF
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
PDF
Chapter 3 Spatial Domain Image Processing.pdf
Building Integrated photovoltaic BIPV_UPV.pdf
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
Cloud computing and distributed systems.
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
Digital-Transformation-Roadmap-for-Companies.pptx
Teaching material agriculture food technology
Reach Out and Touch Someone: Haptics and Empathic Computing
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
sap open course for s4hana steps from ECC to s4
Network Security Unit 5.pdf for BCA BBA.
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
“AI and Expert System Decision Support & Business Intelligence Systems”
Review of recent advances in non-invasive hemoglobin estimation
ACSFv1EN-58255 AWS Academy Cloud Security Foundations.pptx
Big Data Technologies - Introduction.pptx
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
Machine learning based COVID-19 study performance prediction
Advanced methodologies resolving dimensionality complications for autism neur...
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
Chapter 3 Spatial Domain Image Processing.pdf

Chapter 12(cpm pert)

  • 1.  
  • 2. PERT/CPM Network Rules of Network Construction with Emphasis on Dummy Activities Redundancy in Precedence Relationships Scheduling the Activities: Earliest and Latest Times Determination of Critical Path Determination of Floats: Total, Free, Interfering and Independent PERT Resource Analysis and Resource Allocation Time-cost Tradeoff: Crashing the Project Resource Leveling Resource Allocation
  • 3. Each activity is represented by one arrow An activity can begin only when all its predecessors are done Length and bearing of arrows is of no consequence Arrow direction indicates general progression in time – tail events represent start while head events represent end of activities Events are identified by numbers while activities are represented by their starting and ending events A network should have only one initial and one final node Introduce as few dummy activities as may be necessary Looping is not permitted
  • 4. Activity Imm. Pred. A - B - C - D A, B E B F B Activity Imm. Pred. G C, F H B I E, H J E, H K C, D, F, J L K
  • 5. A C B E H F D G I J K L 1 2 3 4 5 6 7 8 9 Activity Imm. Pred. A - B - C - D A, B E B F B Activity Imm. Pred. G C, F H B I E, H J E, H K C, D, F, J L K
  • 6. Critical path refers to the longest path of a given project network Duration of a project is given by the length of the critical path Activities on a critical path are called critical activities while remaining activities are non-critical A project can have more than one critical path as well Critical activities are so called because their timely completion is critical to the completion of the project in time Critical activities can not be delayed while non-critical activities have some cushion available
  • 7. Information on the activities required for a project is as follows: Draw the network and calculate the earliest start(ES), earliest finish(EF), latest start(LS), and latest finish(LF) times of each of the activities. Name A B C D E F G H I J K Activities Node 1-2 1-3 1-4 2-5 3-5 3-6 3-7 4-6 5-7 6-8 7-8 Duration (Days) 2 7 8 3 6 10 4 6 2 5 6
  • 8.  
  • 9. Critical Path: 1-3-6-8 Critical Activities: B F J Project Duration: 22 days Non-critical Activities: A C E G H I K A 2 B 7 C 8 D 3 E 6 G 4 H 6 F 10 I 2 K 6 J 5 1 2 3 4 5 6 7 8
  • 10. Total float is the amount of time by which an activity may be delayed without delaying the project completion Caution: interpret total floats of activities carefully - all can not be used independently Free float is that part of total float which can be used without affecting floats of the succeeding activities The part of total float which is not free is called interfering float Independent float is the amount of time which can be used without affecting the head and the tail events Total Float ≥ Free Float ≥ Independent Float
  • 11. Total float = Latest start time of the activity – Earliest start time of the activity Free float = Total float – Head event slack = Earliest start time of the next activity – Earliest completion time of the activity Interfering float = Total float – Free float Independent float = Earliest start time of the next activity – Latest finish time of the preceding activity – Duration of the activity = Free float – Tail event slack, or zero, whichever is higher
  • 12. i - j t ES EF LS LF TF IF FF lnF 1-2 2 0 2 9 11 9 9 0 0 1-3 7 0 7 0 7 0 0 0 0 1-4 8 0 8 3 11 3 3 0 0 2-5 3 2 5 11 14 9 1 8 0 3-5 6 7 13 8 14 1 1 0 0 3-6 10 7 17 7 17 0 0 0 0 3-7 4 7 11 12 16 5 1 4 4 4-6 6 8 14 11 17 3 0 3 0 5-7 2 13 1 14 16 1 1 0 0 6-8 5 17 22 17 22 0 0 0 0 7-8 6 15 21 16 22 1 0 1 0
  • 13. Problems related to resources include Time-cost trade-off , called crashing Completion time of the project is systematically reduced considering cost Resource Levelling: An attempt is made to smoothen the resources requirements by systematically scheduling the activities Resource Allocation: Allocation of limited availability of resources in a manner that the project is completed in minimum time
  • 14. Involves use of additional resources with a view to reduce the project duration Crashing increases direct cost of doing activities but reduces overhead, which is usually a function of time It may also help to reap any benefits of early completion It needs information on cost of reduction of every activity per unit of time In crashing, always consider the critical path and choose the activity that can be crashed at least cost In case of multiple critical paths, all of them should be considered for crashing simultaneously Time-cost schedule is prepared to get information on normal time and the cost, the minimum time to complete project and the cost, and optimal duration of the project
  • 15. Resource leveling refers to scheduling the activities of a project in such a manner that the requirement of resources may be leveled to the extent possible without delaying the completion of the project To begin with every activity is scheduled at the earliest and the requirement of the resource involved is assessed on a daily basis Since the activities are scheduled on early days, the demand for the resource, say labour, is likely to be large in earlier days of the project and small in the later days
  • 16. Attempt is then made to shift the performance of non-critical activities depending on the floats available so that demand for the resource is reduced somewhat in the early days and increased in later days. Adjustments are made in such a way that the resource demand becomes as uniform as possible Thus, attempt is made to level the resource demand without adversely affecting the project duration
  • 17. Uses three time estimates for every activity: optimistic (a ) , most likely ( m ) and pessimistic ( b ) They are used to obtain expected times and their variances Expected time = ( a +4× m + b )/6; and Variance = [( b – a )/6] 2 Obtain critical path using expected times and identify critical activities Add variances for critical activities to get variance for completion time and find its square root to get standard deviation With expected duration and standard deviation, calculate probabilities of project completion using normal distribution
  • 18. The owner of a chain of fast-food restaurants is considering a new computer system for accounting and inventory control. A computer company sent the following information about the system installation: Activity Immediate Predecessor Most Optimistic Most likely Most Pessimistic A - 4 6 8 B A 5 7 15 C A 4 8 12 D B 15 20 25 E B 10 18 26 F C 8 9 16 G E 4 8 12 H D,F 1 2 3 I G,H 6 7 8
  • 19.  
  • 20. Critical activities: A B E G I Project duration = 6+8+18+8+7 = 47 days Project variance = 4/9 + 25/9 + 64/9 + 16/9 + 1/9 = 110/9 Project standard deviation = √(110/9) = 3.496 Example Activity a m b t e σ 2 A 4 6 8 6 4/9* B 5 7 15 8 25/9* C 4 8 12 8 16/9 D 15 20 25 20 25/9 E 10 18 26 18 64/9* F 8 9 16 10 16/9 G 4 8 12 8 16/9* H 1 2 3 2 1/9 I 6 7 8 7 1/9*
  • 21. For Pr (completion in 55 days): Z = ( X - µ)/ σ Z = (55 – 47)/3.496 = 2.29. Now, Area to the left of Z = 2.29 is 0.5+0.4890 = 0.9890 For Pr (completion with 0.90 chance): Z corresponding to area 0.40 (between µ and X ) is 1.28. Thus, 1.28 = ( X – 47)/3.496 and X = 51.47 or 52 app. The project should start 52 days before due date Project Network A B C E F D H G I
  • 22. A modification of PERT which allows planning, monitoring and controlling of project cost and duration Budgeting process allows to determine how much money is to be spent every time unit (week/month) over planned duration of project Budgets are prepared on the basis of earliest and latest start times of activities Comparisons are made continuously between the actual costs and budgeted amounts Comparisons are also made between percentage of work done and percentage of budgeted amount spent: if former is smaller than the later, we have budget overrun
  • 23. CPM is: Critical Project Management. Critical Path Management. Critical Path Method. Crash Project Method.
  • 24. Which of these is not correct? PERT is probabilistic in nature. CPM is deterministic in nature. CPM is event-oriented. CPM and PERT use similar terminology, but were developed independently.
  • 25. Mark the wrong statement: A project is a set of activities, which can be performed in a certain logical sequence. A network is a graphic portrayal of interdependency relationship among the activities of a project. An arrow representing an activity can have any length and shape. An activity cannot be represented by more than one arrow but an arrow can represent one or more activities.
  • 26. Point out what is not required. While considering precedence relationships, all the predecessor(s) of an activity should be focussed on. only immediate predecessor(s) should be focussed on. redundant predecessors should be dropped. care must be taken that there is no logical fault it as may result in formation of a loop.
  • 27. Mark the correct statement: The head event of an activity also represents tail event of its predecessor activity. Nodes should be numbered in such a way that, for every activity, the initial node bears a lower number while final node bears a higher number. The event marking start of an activity is called head event and the event marking the end is termed as tail-event. In drawing a network, it may happen that A precedes B, B precedes C and C precedes A.
  • 28. Which of the following is not a rule of network construction? Each defined activity is represented by one and only one arrow. A network should have only initial and one terminal node. Identical initial and final nodes can identify two activities. Only as few dummy activities should be included as is warranted.
  • 29. Mark the wrong statement: Forward pass calculations yield the earliest and latest start & finish times of various activities. The difference between latest and earliest finish times of an activity is its total float. Free float of an activity cannot exceed its total float. Determination of earliest and latest start time of various activities of a project is useful for proper planning of their execution.
  • 30. It is known that in a project, an activity 4-6 has duration of 6 days and total float of 3 days. The E and L times at node 4 are 8 and 11 respectively while at node 6, both are equal to 17. Which of the following is not a true statement about 4-6? Its free float is 3 days. Its independent float is 0. It is a critical activity. The ES of this activity is 8.
  • 31. Mark the wrong statement: All activities on a critical path are critical activities. A project network may have none, one or more critical paths. A delay in a critical activity surely delays the completion of project. Each critical activity has identical earliest and latest start times.
  • 32. Pick the wrong relationship: Interfering Float = Total Float – Free Float . Total Float = Free Float + Independent Float . Total Float  Free Float  Independent Float. Free Float = Total Float – Head Event Slack.
  • 33. Which of the following is not correct in respect of PERT calculations? Expected time of an activity is a weighted average of three time estimates, a, m , and b with respective weights of 1, 4 and 1. The completion time of an activity is assumed to follow normal distribution. The standard deviation of activity completion time is one-sixth of the excess of pessimistic over optimistic time. The sum total of variances of critical activity times gives the variance of the overall project completion time.
  • 34. Given, expected duration of project = 47 days, variance = 9 days. What is the probability of not completing the project in 50 days? 0.6293 0.8413 0.1587 0.3707 Z 0.33 1.00 Area 0.1293 0.3413
  • 35. In the previous Question, what is the probability of completing the project within 3 days more or less than the expected time? 0.5000 0.6826 0.2586 0.3174
  • 36. Which of the following is not true about crashing? Always focus on critical path and choose between critical activities only. Crashing cost per day = (Crash cost – Normal cost)/(Normal time – Crash time). Of all activities of the project, choose the activity with least crashing cost. If there are multiple critical paths, crash them all.
  • 37. Mark the wrong statement: An event, which represents the initiation of more than one activity, is called the burst event. The longest path of a given project gives the maximum duration while its shortest path indicates shortest duration. The resource allocation programmes aim to allocate the given resources in a manner that the project completes in minimum time. A non-critical activity may or may not have any free float.
  • 38.