SlideShare a Scribd company logo
Program Evaluation Review Technique (PERT) Report by: Raymund N. Sanchez
Content of the Presentation Definition Differences between PERT & CPM Purpose Historical Perspective Terminologies Creating a PERT/CPM diagram Schedule Duration Crash Probabilistic Time Estimates uncertainty of activities and paths path probabilities Problem Exercises
Definition A method to analyze the tasks involved in completing a given project. Focus is paid to the time needed to complete each task, and identifying the minimum time needed to complete the total project.
Purpose To simplify the planning and scheduling of large and complex projects. To incorporate uncertainty in the sense that it was possible to schedule a project not knowing precisely the details and duration's of all the activities. Event-oriented technique rather than start- and completion-oriented. Used more in R&D-type projects where Cost is not a major factor but Time is.
PERT & CPM Similarities Both follow the same steps and use network diagrams Both are used to plan the scheduling of individual activities that make up a project They can be used to determine the earliest/latest start and finish times for each activity
PERT & CPM Differences PERT is probabilistic whereas CPM is deterministic In CPM, estimates of activity duration are based on historical data In PERT, estimates are uncertain and we talk of ranges of duration and the probability that an activity duration will fall into that range CPM concentrates on Time/Cost trade off.
Historical Background PERT  was invented by Booz Allen Hamilton, Inc. under contract to the United States Department of Defense's US Navy Special Projects Office in 1958  A part of the Polaris mobile submarine-launched ballistic missile project. This project was a direct response to the Sputnik crisis CPM was developed by the dupont company & Remington-Rand-Univac Used for large construction projects Each were unaware of the others existence until the 1960’s
Terminologies PERT event :  is a point that marks the start or completion of one (or more) tasks. It consumes  no time , and uses  no resources . It marks the completion of one (or more) tasks.  It is not “reached” until  all  of the activities leading to that event have been completed.  P redecessor event :  an event (or events) that immediately precedes some other event without any other events intervening. It may be the consequence of more than one activity.  Successor event :  an event (or events) that immediately follows some other event without any other events intervening. It may be the consequence of more than one activity.
Terminologies PERT activity :  is the actual performance of a task. It consumes  time , it requires  resources  (such as labor, materials, space, machinery), and it can be understood as representing the time, effort, and resources required to move from one event to another. A PERT activity cannot be completed until the event preceding it has occurred.   Optimistic time  (O):  the minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected  Pessimistic time  (P):  the maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes).
Terminologies Most likely time  (M):  the best estimate of the time required to accomplish a task, assuming everything proceeds as normal.  Expected time  (T E ):  the best estimate of the time required to accomplish a task, assuming everything proceeds as normal (the implication being that the expected time is the average time the task would require if the task were repeated on a number of occasions over an extended period of time).  Critical Path :  the longest possible continuous pathway taken from the initial event to the terminal event. It determines the total calendar time required for the project; and, therefore, any time delays along the critical path will delay the reaching of the terminal event by at least the same amount.
Terminologies Lead time :  the time by which a  predecessor event  must be completed in order to allow sufficient time for the activities that must elapse before a specific PERT event is reached to be completed.  Lag time :  the earliest time by which a  successor event  can follow a specific PERT event.  Slack :  the  slack  of an event is a measure of the excess time and resources available in achieving this event.  Positive slack  would indicate  ahead of schedule ;  negative slack  would indicate  behind schedule ; and  zero slack  would indicate  on schedule .
Terminologies Early Start (ES):  maximum EF of all predecessor activities, unless the activity in question is the the first activity, wherein ES is 0 Early Finish (EF):  ES plus task duration Late Start (LS):  LF minus task duration Late Finish (LF):  minimum LS on all successor activities, unless the activity is the last activity, wherein LF equals EF Activity on Arrow (AOA):  a type of PERT diagram wherein the activities are written on the arrows Activity on Node (AON):  a type of PERT diagram wherein the activities are written on the nodes
Creating a PERT Diagram STEPS 1: Determine the tasks that the project requires and the order in which they must be completed Determine the optimistic, most likely, and pessimistic time of each task Compute for the Expected time using the formula Te=(O+4M+P)/6 Determine whether to use AOA or AON diagrams
 
Start F C G E D B A Finish
Creating a PERT Diagram STEPS 2: Determine the ES & EF of each activity by: Start at the beginning moving towards the end ES & EF for the start activity is always 0 since they are milestones Use the EF of the predecessor activity as the ES of the current activity EF of an activity is computed by adding its ES with its duration For activities with 2 or more predecessor activities, use the predecessor with the higher EF as the ES of the current activity
Start ES:0 EF:0 F D:4.5 ES:10.33 EF:14.83 C D:5.17 ES:4 EF:9.17 G D:5.17 ES:14.34 EF:19.51 E D:5.17 ES:9.17 EF:14.34 D D:6.33 ES:4 EF:10.33 B D:5.33 ES:0 EF:5.33 A D:4 ES:0 EF:4 Finish D:0 ES:19.51 EF:19.51
Creating a PERT Diagram STEPS 3: Determine the LS & LF of each activity by: Start at the end and work towards the beginning The LF for the finish activity is equal to EF since it is the last activity in the project. Since duration is 0, LS is equal to LF Use the LS of the successor activity as the LF of the current activity LS of an activity is computed by subtracting its LF with its duration For activities with 2 or more successor activities, use the successor with the lower LS as the LF of the current activity
Start D:0 ES:0 EF:0 LS:0 LF:0 F D:4.5 ES:10.33 EF:14.83 LS:15.01 LF:19.51 C D:5.17 ES:4 EF:9.17 LS:4 LF:9.17 G D:5.17 ES:14.34 EF:19.51 LS:14.34 LF:19.51 E D:5.17 ES:9.17 EF:14.34 LS:9.17 LF:14.34 D D:6.33 ES:4 EF:10.33 LS:8.68 LF:15.01 B D:5.33 ES:0 EF:5.33 LS:3.84 LF:9.17 A D:4 ES:0 EF:4 LS:0 LF:4 Finish D:0 ES:19.51 EF:19.51 LS:19.51 LF:19.51
Creating a PERT Diagram STEPS 4: Compute for the critical path by adding the duration's of various paths for all activities Determine if any activities have slack by subtracting the activity’s LF & EF
Critical Path Critical Path: A-C-E-G Path A-D-F  = 14.83 work days Path A-C-E-G  = 19.51 work days Path B-E-G  = 15.67 work days
Slack
Gantt Chart
Schedule Duration Crash Crash :  an effort to reduce the overall time duration of a project by employing one or all of the following techniques Adding resources (human or otherwise) Increasing work hours (overtime or weekends) Lessening quality A trade-off between shorter task duration and higher task costs  If the cost savings on a delay penalty are higher than the incremental cost of reducing the project duration, then the crashing is justified.
Activity Uncertainty Standard Deviation of an activity is estimated as one sixth of the difference between the pessimistic and optimistic time estimates Variance is determined by squaring the standard deviation The size of the variance reflects the degree of uncertainty associated with the activity’s time.  The larger the variance, the greater the uncertainty. Standard Deviation =  t p  - t o    6
Path Uncertainty Standard Deviation of a path can also be computed to know the uncertainty of a particular path.   SD of Path=   variances of activities on  a path
Path Probability The probability that a given path will be completed in a specified length of time can be determined using the following formula: Z = Specified Time - Path Mean   Path Standard Deviation If the value of Z is 2.50 more, treat the path probability as 100%.  If the value of Z is less than 2.50, use the table of values under the standardized normal curve.
Sample Problem
- END -

More Related Content

PPTX
Program evaluation review technique (pert)
PPT
Critical path method (cpm)
PPTX
Critical path method
PPTX
Pert cpm
PPTX
Reducing Project Duration_Jagat Prasad Upadhyay.pptx
PPTX
CPM/PERT and Gantt charts
PPTX
Project Management PERT and CPM
PPTX
PROJECT-SCHEDULING-pptx.pptx
Program evaluation review technique (pert)
Critical path method (cpm)
Critical path method
Pert cpm
Reducing Project Duration_Jagat Prasad Upadhyay.pptx
CPM/PERT and Gantt charts
Project Management PERT and CPM
PROJECT-SCHEDULING-pptx.pptx

What's hot (20)

PPTX
Program Evaluation and Review Technique (PERT)
PPT
Pert
PPTX
Project Management - Critical path method
PPTX
Pert and gantt chart
PPTX
Planning and Steps in Planning ppt by Arun Joseph MLISc
PPTX
Coordination as a management function
PPTX
Supervision
PPTX
Programme Evaluation and Review Technique
PPTX
DOCX
Gantt chart
PPTX
Pert- program evaluation and review technique
PPTX
The Gantt Chart
PPTX
PERT & Gantt Chart
PDF
Programme evaluation review technique
PPTX
Brief introduction to project management and project management tools
DOCX
PERT (Program evaluation review technique)
PPTX
MATERIALS MANAGEMENT
PPTX
CPM - Critical Path Method
PPTX
Seminar on pert
PPTX
Programme evaluation and review technique &Gantt Chart
Program Evaluation and Review Technique (PERT)
Pert
Project Management - Critical path method
Pert and gantt chart
Planning and Steps in Planning ppt by Arun Joseph MLISc
Coordination as a management function
Supervision
Programme Evaluation and Review Technique
Gantt chart
Pert- program evaluation and review technique
The Gantt Chart
PERT & Gantt Chart
Programme evaluation review technique
Brief introduction to project management and project management tools
PERT (Program evaluation review technique)
MATERIALS MANAGEMENT
CPM - Critical Path Method
Seminar on pert
Programme evaluation and review technique &Gantt Chart
Ad

Viewers also liked (20)

PPTX
Planning Nursing Administration
PPTX
Planning for nursing service
PPTX
Planning new venture
PPTX
introduction to management and planning
PPT
Internal Auditing - Performance Standards
PPT
Eindtermen en leerplannen wo natuur - Walter Dons
DOCX
Advantages of swot analysis
PPTX
Critical path method
PPT
P E R T
PPTX
Swot analysis , its importance and limitations
PPT
Cpm (critical path method)
PDF
Establishing performance standards
PPTX
Critical Path Method presentation.
PPTX
Pert and its applications
PDF
Cpm (critical path method)
PPTX
Critical Path Method
PPTX
5 strategic and operational planning
PPT
Chapter 12(cpm pert)
PPTX
Management and it's functions
Planning Nursing Administration
Planning for nursing service
Planning new venture
introduction to management and planning
Internal Auditing - Performance Standards
Eindtermen en leerplannen wo natuur - Walter Dons
Advantages of swot analysis
Critical path method
P E R T
Swot analysis , its importance and limitations
Cpm (critical path method)
Establishing performance standards
Critical Path Method presentation.
Pert and its applications
Cpm (critical path method)
Critical Path Method
5 strategic and operational planning
Chapter 12(cpm pert)
Management and it's functions
Ad

Similar to Program Evaluation and Review Technique (20)

PPTX
Pert and mbo
PPTX
Pb602 operation management chapter 7
PPTX
Project management. Module 4 ktu sem 6.pptx
PPTX
PERT.pptx pert is a model devised to complete the under the content.
PDF
Program Evaluation And Review Technique
PPT
Pert Cpm Nis
PPTX
or-pert
PPTX
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
PDF
PERT AND CPM PROJECT MANAGEMENT
PPTX
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
PPT
3...06 pert cpm
PPT
Project management
PPTX
Cpm and pert
PPSX
Critical path method & pert
PPTX
Chap 4- CPM & PERT.pptx
PPTX
Project Management.pptx
PPT
06 pert cpm
PPT
S pert cpm
PPTX
Unit v mha project evaluation review technique (pert)
PPTX
Cpm pert
Pert and mbo
Pb602 operation management chapter 7
Project management. Module 4 ktu sem 6.pptx
PERT.pptx pert is a model devised to complete the under the content.
Program Evaluation And Review Technique
Pert Cpm Nis
or-pert
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
PERT AND CPM PROJECT MANAGEMENT
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
3...06 pert cpm
Project management
Cpm and pert
Critical path method & pert
Chap 4- CPM & PERT.pptx
Project Management.pptx
06 pert cpm
S pert cpm
Unit v mha project evaluation review technique (pert)
Cpm pert

More from Raymund Sanchez (20)

ODP
Csr presentation
PPT
HRM Presentation
PPT
Pcierd Report
PPT
Doing Business God’S Way
PPT
Marxism & Business
PPT
micro finance
PPT
Investment Banking
DOCX
Genghis Khan, the Modern Manager
PPT
Consumer Protection
PPS
Big servings
PPS
My Birthday Party
PPS
Letter Written In 2070
PPT
Change Management
PPT
Oral Communication
PPT
Visual Communication as used in a Business Context
PPT
Classification and Purpose of Production and Operations Management
PPT
Introduction to Market Segmentation
PPT
Communications and Human Rights Education
PPT
Human Rights in Philippine Schools
PPT
Media and Human RIghts Education
Csr presentation
HRM Presentation
Pcierd Report
Doing Business God’S Way
Marxism & Business
micro finance
Investment Banking
Genghis Khan, the Modern Manager
Consumer Protection
Big servings
My Birthday Party
Letter Written In 2070
Change Management
Oral Communication
Visual Communication as used in a Business Context
Classification and Purpose of Production and Operations Management
Introduction to Market Segmentation
Communications and Human Rights Education
Human Rights in Philippine Schools
Media and Human RIghts Education

Recently uploaded (20)

PDF
Chapter 5_Foreign Exchange Market in .pdf
PDF
MSPs in 10 Words - Created by US MSP Network
PPTX
Lecture (1)-Introduction.pptx business communication
PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
PPT
340036916-American-Literature-Literary-Period-Overview.ppt
PPTX
Principles of Marketing, Industrial, Consumers,
PDF
DOC-20250806-WA0002._20250806_112011_0000.pdf
PPT
Data mining for business intelligence ch04 sharda
PDF
Training And Development of Employee .pdf
PPTX
Probability Distribution, binomial distribution, poisson distribution
PPTX
5 Stages of group development guide.pptx
PDF
Ôn tập tiếng anh trong kinh doanh nâng cao
DOCX
Euro SEO Services 1st 3 General Updates.docx
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
PDF
Outsourced Audit & Assurance in USA Why Globus Finanza is Your Trusted Choice
PPTX
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
PDF
Nidhal Samdaie CV - International Business Consultant
PPTX
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...
Chapter 5_Foreign Exchange Market in .pdf
MSPs in 10 Words - Created by US MSP Network
Lecture (1)-Introduction.pptx business communication
Belch_12e_PPT_Ch18_Accessible_university.pptx
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
340036916-American-Literature-Literary-Period-Overview.ppt
Principles of Marketing, Industrial, Consumers,
DOC-20250806-WA0002._20250806_112011_0000.pdf
Data mining for business intelligence ch04 sharda
Training And Development of Employee .pdf
Probability Distribution, binomial distribution, poisson distribution
5 Stages of group development guide.pptx
Ôn tập tiếng anh trong kinh doanh nâng cao
Euro SEO Services 1st 3 General Updates.docx
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
Outsourced Audit & Assurance in USA Why Globus Finanza is Your Trusted Choice
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
Nidhal Samdaie CV - International Business Consultant
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...

Program Evaluation and Review Technique

  • 1. Program Evaluation Review Technique (PERT) Report by: Raymund N. Sanchez
  • 2. Content of the Presentation Definition Differences between PERT & CPM Purpose Historical Perspective Terminologies Creating a PERT/CPM diagram Schedule Duration Crash Probabilistic Time Estimates uncertainty of activities and paths path probabilities Problem Exercises
  • 3. Definition A method to analyze the tasks involved in completing a given project. Focus is paid to the time needed to complete each task, and identifying the minimum time needed to complete the total project.
  • 4. Purpose To simplify the planning and scheduling of large and complex projects. To incorporate uncertainty in the sense that it was possible to schedule a project not knowing precisely the details and duration's of all the activities. Event-oriented technique rather than start- and completion-oriented. Used more in R&D-type projects where Cost is not a major factor but Time is.
  • 5. PERT & CPM Similarities Both follow the same steps and use network diagrams Both are used to plan the scheduling of individual activities that make up a project They can be used to determine the earliest/latest start and finish times for each activity
  • 6. PERT & CPM Differences PERT is probabilistic whereas CPM is deterministic In CPM, estimates of activity duration are based on historical data In PERT, estimates are uncertain and we talk of ranges of duration and the probability that an activity duration will fall into that range CPM concentrates on Time/Cost trade off.
  • 7. Historical Background PERT was invented by Booz Allen Hamilton, Inc. under contract to the United States Department of Defense's US Navy Special Projects Office in 1958 A part of the Polaris mobile submarine-launched ballistic missile project. This project was a direct response to the Sputnik crisis CPM was developed by the dupont company & Remington-Rand-Univac Used for large construction projects Each were unaware of the others existence until the 1960’s
  • 8. Terminologies PERT event : is a point that marks the start or completion of one (or more) tasks. It consumes no time , and uses no resources . It marks the completion of one (or more) tasks. It is not “reached” until all of the activities leading to that event have been completed. P redecessor event : an event (or events) that immediately precedes some other event without any other events intervening. It may be the consequence of more than one activity. Successor event : an event (or events) that immediately follows some other event without any other events intervening. It may be the consequence of more than one activity.
  • 9. Terminologies PERT activity : is the actual performance of a task. It consumes time , it requires resources (such as labor, materials, space, machinery), and it can be understood as representing the time, effort, and resources required to move from one event to another. A PERT activity cannot be completed until the event preceding it has occurred. Optimistic time (O): the minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected Pessimistic time (P): the maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes).
  • 10. Terminologies Most likely time (M): the best estimate of the time required to accomplish a task, assuming everything proceeds as normal. Expected time (T E ): the best estimate of the time required to accomplish a task, assuming everything proceeds as normal (the implication being that the expected time is the average time the task would require if the task were repeated on a number of occasions over an extended period of time). Critical Path : the longest possible continuous pathway taken from the initial event to the terminal event. It determines the total calendar time required for the project; and, therefore, any time delays along the critical path will delay the reaching of the terminal event by at least the same amount.
  • 11. Terminologies Lead time : the time by which a predecessor event must be completed in order to allow sufficient time for the activities that must elapse before a specific PERT event is reached to be completed. Lag time : the earliest time by which a successor event can follow a specific PERT event. Slack : the slack of an event is a measure of the excess time and resources available in achieving this event. Positive slack would indicate ahead of schedule ; negative slack would indicate behind schedule ; and zero slack would indicate on schedule .
  • 12. Terminologies Early Start (ES): maximum EF of all predecessor activities, unless the activity in question is the the first activity, wherein ES is 0 Early Finish (EF): ES plus task duration Late Start (LS): LF minus task duration Late Finish (LF): minimum LS on all successor activities, unless the activity is the last activity, wherein LF equals EF Activity on Arrow (AOA): a type of PERT diagram wherein the activities are written on the arrows Activity on Node (AON): a type of PERT diagram wherein the activities are written on the nodes
  • 13. Creating a PERT Diagram STEPS 1: Determine the tasks that the project requires and the order in which they must be completed Determine the optimistic, most likely, and pessimistic time of each task Compute for the Expected time using the formula Te=(O+4M+P)/6 Determine whether to use AOA or AON diagrams
  • 14.  
  • 15. Start F C G E D B A Finish
  • 16. Creating a PERT Diagram STEPS 2: Determine the ES & EF of each activity by: Start at the beginning moving towards the end ES & EF for the start activity is always 0 since they are milestones Use the EF of the predecessor activity as the ES of the current activity EF of an activity is computed by adding its ES with its duration For activities with 2 or more predecessor activities, use the predecessor with the higher EF as the ES of the current activity
  • 17. Start ES:0 EF:0 F D:4.5 ES:10.33 EF:14.83 C D:5.17 ES:4 EF:9.17 G D:5.17 ES:14.34 EF:19.51 E D:5.17 ES:9.17 EF:14.34 D D:6.33 ES:4 EF:10.33 B D:5.33 ES:0 EF:5.33 A D:4 ES:0 EF:4 Finish D:0 ES:19.51 EF:19.51
  • 18. Creating a PERT Diagram STEPS 3: Determine the LS & LF of each activity by: Start at the end and work towards the beginning The LF for the finish activity is equal to EF since it is the last activity in the project. Since duration is 0, LS is equal to LF Use the LS of the successor activity as the LF of the current activity LS of an activity is computed by subtracting its LF with its duration For activities with 2 or more successor activities, use the successor with the lower LS as the LF of the current activity
  • 19. Start D:0 ES:0 EF:0 LS:0 LF:0 F D:4.5 ES:10.33 EF:14.83 LS:15.01 LF:19.51 C D:5.17 ES:4 EF:9.17 LS:4 LF:9.17 G D:5.17 ES:14.34 EF:19.51 LS:14.34 LF:19.51 E D:5.17 ES:9.17 EF:14.34 LS:9.17 LF:14.34 D D:6.33 ES:4 EF:10.33 LS:8.68 LF:15.01 B D:5.33 ES:0 EF:5.33 LS:3.84 LF:9.17 A D:4 ES:0 EF:4 LS:0 LF:4 Finish D:0 ES:19.51 EF:19.51 LS:19.51 LF:19.51
  • 20. Creating a PERT Diagram STEPS 4: Compute for the critical path by adding the duration's of various paths for all activities Determine if any activities have slack by subtracting the activity’s LF & EF
  • 21. Critical Path Critical Path: A-C-E-G Path A-D-F = 14.83 work days Path A-C-E-G = 19.51 work days Path B-E-G = 15.67 work days
  • 22. Slack
  • 24. Schedule Duration Crash Crash : an effort to reduce the overall time duration of a project by employing one or all of the following techniques Adding resources (human or otherwise) Increasing work hours (overtime or weekends) Lessening quality A trade-off between shorter task duration and higher task costs If the cost savings on a delay penalty are higher than the incremental cost of reducing the project duration, then the crashing is justified.
  • 25. Activity Uncertainty Standard Deviation of an activity is estimated as one sixth of the difference between the pessimistic and optimistic time estimates Variance is determined by squaring the standard deviation The size of the variance reflects the degree of uncertainty associated with the activity’s time. The larger the variance, the greater the uncertainty. Standard Deviation = t p - t o 6
  • 26. Path Uncertainty Standard Deviation of a path can also be computed to know the uncertainty of a particular path. SD of Path=  variances of activities on a path
  • 27. Path Probability The probability that a given path will be completed in a specified length of time can be determined using the following formula: Z = Specified Time - Path Mean Path Standard Deviation If the value of Z is 2.50 more, treat the path probability as 100%. If the value of Z is less than 2.50, use the table of values under the standardized normal curve.